Uninterrupted Temporary Ventilation dust pelletizing system during a kind of nuclear island safety shell construction of hydropower
Technical field
The present invention relates to during nuclear island safety shell technical field of construction more particularly to a kind of nuclear island safety shell construction of hydropower not
Being interrupted Temporary Ventilation dust pelletizing system pacifies nuclear island for fully ensuring that each region and room fresh air convection current at the construction field (site)
Full shell workshop improves air quality.
Background technique
Currently, the Temporary Ventilation dust pelletizing system used when Project Cooperation nuclear power site operation, is that the common ventilation in market is set
Standby, protective cloth circular duct, localized metallic air hose composition are not able to satisfy the 24 hours uninterrupted ventilation needs in scene.According to nuclear power
It stands construction feature, after nuclear island safety shell cover head is in place, civil engineering, installation concurrent construction, main structure is in construction, to having been formed
The region in room is required to carry out the installation (cutting, polishing, welding) of wall polishing, equipment and large material and paint application,
Respectively there are 2 gate holes in for example same bulk container of nuclear island safety shell at this time, upper and lower part, respectively top equipment gate hole, on
Portion access lock hole and lower part equipment gate hole, top access lock hole, there are also other techniques and electrical penetration hole.
The practical wind turbine layout and ventilation situation of construction site are as follows: 1, blower, air hose, power supply line arrangement are in disorder, hinder
Channel and construction working face, and there are security risks;2, reflected by field worker, when operation side rotation, usually pause is supplied
Wind causes fresh air volume in nuclear island factory building to be unable to satisfy worker's breathing needs, so worker when can't stand, will run out of cubicle
It breathes freely out;3, it is reconnoitred by construction site, although arranging enough blowers, effect is undesirable always, nuclear island safety shell
Dust is inside diffused, also results in very big health effect to the construction worker protected has been, is also protected to live civilized construction and finished product
Shield causes very big influence.
Therefore, it is badly in need of designing novel or improvement ventilating and purifying air system.
Summary of the invention
The technical problem to be solved in the present invention is to provide 24 hours during a kind of nuclear island safety shell construction of hydropower uninterruptedly to face
When ventilating and purifying air system, can fully ensure that at the construction field (site) between each region and each room fresh air convection current ventilation time
Number makes nuclear island safety shell workshop room improve air quality, does not influence civilized construction and finished product protection, ensure that good scene is applied
Work environment and meet correlated quality requirement.
In order to solve the above-mentioned technical problem, the technical solution of the present invention is to provide during a kind of nuclear island safety shell construction of hydropower
Uninterrupted Temporary Ventilation dust pelletizing system, it is characterised in that: including the air hose root module being set in nuclear island safety shell workshop and be set to
The blower fan module of nuclear island safety shell workshop two sides, two ports of air hose root module are separately connected the air inlet of the blower fan module of two sides
Mouthful, the air outlet of blower fan module connects exhaust outlet;
The blower fan module includes at least two first blowers and at least one second blower, after each first fan parallel-connection again
With the second fans in series;The import of first blower connects the air hose root module, the second blower of outlet connection of the first blower
The outlet of import, the second blower connects exhaust outlet.
Preferably, the air hose root module is constituted by several metal bellows are detachably connected, is set on the metal bellows
There is air-valve.
Preferably, first blower and the second blower are mounted in frame, and framework upper is equipped with rain-proof shelter.
It is highly preferred that the base of frame is equipped with foundation bolt and/or spring shockproof device.
It is highly preferred that the rain-proof shelter is " people " shape structure of steel truss girder composition.
It is highly preferred that the frame, rain-proof shelter are made of channel steel, angle steel or iron plate.
Preferably, the exhaust outlet includes plenum chamber, is equipped with multiple deflectors in plenum chamber, it is logical to constitute labyrinth type air
Road.
It is highly preferred that the plenum chamber bottom is formed to the inclined inclined-plane in air inlet direction, the bottom of the slope passes through bracket branch
Support.
It is highly preferred that cleaning operation door of the plenum chamber bottom end setting convenient for cleaning flue dust.
Preferably, the air outlet and air inlet of the blower fan module are respectively provided with flange, two ends of the air hose root module
Mouth is respectively provided with flange, and flange is arranged in the import of the exhaust outlet, and the air inlet and air hose root module of the blower fan module pass through method
Orchid connection, the air outlet and exhaust outlet of the blower fan module pass through flanged joint.
The present invention is designed the Temporary Ventilation dust pelletizing system of construction period, secures the fan in frame module, then
It is installed by foundation bolt, rain-proof shelter is installed on rack, reduce the risk that blower is corroded, maintenance is convenient;Using
Block structure splicing, is easily portable and installs;It is connected between blower fan module using Demountable metallic air hose section, compared with sundry item
Protective cloth circle pneumatic hose has the characteristics that uninterrupted air draft in 24 hours, and ventilation quantity is big, and good dedusting effect at the construction field (site) can
It fully ensures that each region and space air convection current, makes nuclear island safety shell workplace air Quality advance, reduce noise in shell, improve
The working environment of construction personnel.
Detailed description of the invention
Fig. 1 uninterrupted Temporary Ventilation dust pelletizing system signal during being nuclear island safety shell construction of hydropower provided in this embodiment
Figure;
Fig. 2 is blower fan module schematic diagram;
Fig. 3 is exhaust outlet schematic diagram.
Specific embodiment
Present invention will be further explained below with reference to specific examples.
Fig. 1 uninterrupted Temporary Ventilation dust pelletizing system signal during being nuclear island safety shell construction of hydropower provided in this embodiment
Figure, during the nuclear island safety shell construction of hydropower uninterrupted Temporary Ventilation dust pelletizing system by 2 blower fan modules, 2 exhaust outlets,
Multiple air-valves and several air hose sections composition.
In conjunction with Fig. 2, two the first blowers 4 and second blower 5 constitute one group, are installed in frame 6, constitute blower mould
Block 2.Two the first blowers 4 are arranged in parallel connects with the second blower 5 again, i.e., the outlet of two the first blowers 4 is all connected with the second wind
The import of machine 5.
Wherein, the first blower 4 and the second blower 5 can choose commercially available high-power and Wind Volume blower.
In Fig. 2, the rain-proof of girder steel framework is arranged in 6 bottom mounting foot bolt of frame and spring shockproof device, 6 top of frame
Canopy 7.Rain-proof shelter 7 is soldered on frame 6, and steel truss girder forms " people " shape, is prevented rainwater from wandering in blower fan module 2, is reduced wind
The danger that machine is corroded, maintenance are convenient.
A blower fan module 2 is respectively set in the two sides of nuclear island safety shell workshop, and two exhaust outlets 1 are respectively arranged at blower mould
The air opening end of block 2.The air hose section of several interconnections of setting gives air hose according to air quantity demand in nuclear island safety shell workshop
Section specification, according to convenient setting air-valve 3 of constructing in air hose section.Two ports of air hose section are separately connected in nuclear island safety shell workshop
The second blower 5 outlet of 4 import of the first blower of the blower fan module 2 of two sides, the blower fan module 2 of two sides is separately connected corresponding row
Air port 1.
Exhaust outlet 1 uses the form air draft of labyrinth type plenum chamber, as shown in figure 3, exhaust outlet 1 is by deflector 8, plenum chamber 9
And bracket 10 forms, and is equipped with the deflector 8 of multilayer parallel in plenum chamber 9, deflector 8 be welded in 9 inner upper of plenum chamber and/or
Left and right inside constitutes labyrinth type air duct, increases contaminated path, increases flue dust settling amount, makes containing weldering dirt
Air is by precipitating heel row to atmosphere.9 bottom of plenum chamber is formed to the inclined inclined-plane in air inlet direction, and the bottom of the slope passes through bracket
10 supports.Cleaning operation door 11 is set in 9 bottom end of plenum chamber, to clean flue dust.
In Fig. 1, Fig. 2, the structure and shape of frame 6 be it is schematical, specific size and more detailed structure can be
It adds or changes on the basis of it.
Flange can be correspondingly arranged in the air outlet and air inlet of the first blower 4 and the second blower 5 in frame 6, in frame 6
Each side reinforcement structure can also be correspondingly set.
Frame 6 and 7 making material of rain-proof shelter can be regular troughs steel and angle steel and sheet iron, and shop sweeping can also be used and add
Work.
In addition to left and right assembled arrangement as shown in Figure 2 in blower fan module 2, can in frame 6 according to airflow pressure demand,
Increase blower quantity in parallel or in series, is arranged in extension aforementioned combinatorial up and down.
10-50cm, side clearance 50-100cm, underclearance 100- are divided between adjacent baffle 8
200cm。
5 ° -30 ° of 9 bottom bevel inclination angle of plenum chamber.
The size of cleaning operation door 11 are as follows: wide 50-100cm, long 30-200cm.
The present invention is designed the Temporary Ventilation dust pelletizing system of construction period, secures the fan in frame module, then
It is installed by foundation bolt, rain-proof shelter is installed on rack, reduced blower and be corroded, maintenance is convenient, using block structure
Splicing, is easily portable and installs;It is connected between 2 Fans modules using Demountable metallic air hose section, compared with the three of sundry item
Anti- cloth circle pneumatic hose has the characteristics that uninterrupted air draft in 24 hours, and ventilation quantity is big, good dedusting effect, in containment noise have compared with
It is big to improve.
Although it should be understood that herein may usage amount term " first ", " second " etc. each unit is described,
But these units should not be limited by these terms.The use of these items is only for by a unit and another unit
It distinguishes.For example, without departing substantially from the range of exemplary embodiment, it is single that first unit can be referred to as second
Member, and similarly second unit can be referred to as first unit.
It mentions in the present specification or up, down, left, right, before and after, front, the back side, top, the bottom that may mention etc.
Positional terms are defined relative to each construction shown in the drawings, they are opposite concepts, and it is therefore possible to can root
Correspondingly changed according to different location locating for it, different use states.So also should not be by these or others side
Position term is construed to restricted term.
The above, only presently preferred embodiments of the present invention, not to the present invention in any form with substantial limitation,
It should be pointed out that under the premise of not departing from the method for the present invention, can also be made for those skilled in the art
Several improvement and supplement, these are improved and supplement also should be regarded as protection scope of the present invention.All those skilled in the art,
Without departing from the spirit and scope of the present invention, when made using disclosed above technology contents it is a little more
Dynamic, modification and the equivalent variations developed, are equivalent embodiment of the invention;Meanwhile all substantial technologicals pair according to the present invention
The variation, modification and evolution of any equivalent variations made by above-described embodiment, still fall within the range of technical solution of the present invention
It is interior.