Nothing Special   »   [go: up one dir, main page]

CN109653213B - A kind of construction method of ground connection wall forming groove - Google Patents

A kind of construction method of ground connection wall forming groove Download PDF

Info

Publication number
CN109653213B
CN109653213B CN201811621065.2A CN201811621065A CN109653213B CN 109653213 B CN109653213 B CN 109653213B CN 201811621065 A CN201811621065 A CN 201811621065A CN 109653213 B CN109653213 B CN 109653213B
Authority
CN
China
Prior art keywords
groove
mud
grab
holes
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811621065.2A
Other languages
Chinese (zh)
Other versions
CN109653213A (en
Inventor
李世太
吴世红
黄世华
王新龙
赵宇康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201811621065.2A priority Critical patent/CN109653213B/en
Publication of CN109653213A publication Critical patent/CN109653213A/en
Application granted granted Critical
Publication of CN109653213B publication Critical patent/CN109653213B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F5/00Dredgers or soil-shifting machines for special purposes
    • E02F5/02Dredgers or soil-shifting machines for special purposes for digging trenches or ditches
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F5/00Dredgers or soil-shifting machines for special purposes
    • E02F5/02Dredgers or soil-shifting machines for special purposes for digging trenches or ditches
    • E02F5/025Dredgers or soil-shifting machines for special purposes for digging trenches or ditches with scraper-buckets, dippers or shovels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

本发明涉及地连墙施工领域,更具体而言,涉及一种“三抓九孔与二抓五孔”地连墙成槽施工方法,一期槽先采用一台成槽机抓槽,每副一期槽采用“三抓法”抓槽,后采用2台冲桩机同时冲孔,每副一期槽采用“九孔法”冲孔;闭合槽也采用一台成槽机抓槽,每副闭合槽采用“二抓法”抓槽,后采用2台冲桩机同时冲孔,每副闭合槽段采用“五孔法”冲孔,一期槽和闭合槽抓槽和冲孔完成后,采用圆锤和方锤依次修槽。本方法既发挥了成槽机在软土地层抓槽的高效率的特点,更好的发挥地连墙的优势,也满足了冲桩机能够在强度高的岩层中发挥其优势的特点,有效避免了地连墙在上软下硬特殊地层中施工进度慢、质量控制难的风险。

Figure 201811621065

The invention relates to the field of ground-connecting wall construction, and more particularly, to a method for forming a groove for a ground-connected wall with "three grasps of nine holes and two grasps of five holes". For the first-stage groove, a groove forming machine is used to grasp the groove, and each groove The secondary first-stage groove adopts the "three-grabbing method" to grasp the groove, and then two pile punching machines are used to punch holes at the same time. Each pair of closed grooves adopts the "two grasping method" to grasp the grooves, and then use two pile punching machines to punch holes at the same time, and each pair of closed grooves adopts the "five-hole method" to punch the holes. Afterwards, use a round hammer and a square hammer to trim the grooves in turn. This method not only gives full play to the high efficiency of the grooving machine in the soft soil stratum, and better exerts the advantages of the ground connection wall, but also satisfies the characteristics that the pile puncher can exert its advantages in the high-strength rock stratum, and effectively It avoids the risk of slow construction progress and difficult quality control of the ground connecting wall in the special stratum with soft upper and lower hard layers.

Figure 201811621065

Description

一种地连墙成槽施工方法A kind of construction method of ground connection wall forming groove

技术领域technical field

本发明涉及地连墙施工技术领域,更具体而言,涉及一种“三抓九孔与二抓五孔”地连墙成槽施工方法。The invention relates to the technical field of ground connecting wall construction, and more particularly, to a construction method of "three holes with nine holes and two holes with two holes" to form grooves for ground connecting walls.

背景技术Background technique

近年国内地连墙施工发展迅速,随之各种成槽机应运而生,使得地连墙在地下工程应用日益广泛,地连墙作为土坝、尾矿坝、水闸、基坑围护墙等构筑物的挡土、防渗结构,是非常安全和经济的。地连墙施工具有工效高、工期短、安全质量可靠、经济效益高的特点,非常使用于在城市施工,由于施工方法的不断改进,使地下连续墙几乎不透水。但是同样有不足之处,如果施工方法不当或施工地质条件复杂特殊,会导致地连墙成槽进度慢且质量难以保证,可能出现相邻地连墙接缝错开或夹泥,影响地连墙结构的安全性和实用性。In recent years, the construction of connecting walls in China has developed rapidly, with the emergence of various trough forming machines, making the ground connecting walls more and more widely used in underground engineering. The retaining and anti-seepage structure of structures is very safe and economical. Ground connecting wall construction has the characteristics of high work efficiency, short construction period, reliable safety and quality, and high economic benefit. It is very used in urban construction. Due to the continuous improvement of construction methods, the underground continuous wall is almost impermeable. However, there are also shortcomings. If the construction method is inappropriate or the construction geological conditions are complex and special, it will lead to slow progress of forming the groove of the ground connecting wall and difficult to guarantee the quality. Safety and practicality of the structure.

在上软下硬特殊的地质环境下,成槽机很难在岩层中进行抓槽作业,该地质环境给地连墙施工造成了很大的障碍,势必在上软下硬特殊地质环境下,提高地连墙的成槽施工进度和质量,是施工中重点关注的问题。Under the special geological environment where the upper part is soft and the lower part is hard, it is difficult for the grooving machine to carry out grooving operation in the rock formation. This geological environment has caused great obstacles to the construction of the ground connecting wall. Improving the construction progress and quality of the trough formation of the ground connecting wall is a key concern in the construction.

发明内容SUMMARY OF THE INVENTION

为了克服现有技术中所存在的不足,本发明提供一种“三抓九孔与二抓五孔”地连墙成槽施工方法,解决现有技术中地连墙成槽进度和质量的问题。In order to overcome the deficiencies existing in the prior art, the present invention provides a construction method for connecting walls to form grooves with "three holes with nine holes and two holes with two holes", so as to solve the problems of the progress and quality of grooves formed by connecting walls in the prior art .

为了解决上述技术问题,本发明所采用的技术方案为:In order to solve the above-mentioned technical problems, the technical scheme adopted in the present invention is:

一种“三抓九孔与二抓五孔”地连墙成槽施工方法,包括以下步骤:A construction method for forming a groove by connecting a wall with three holes and two holes with five holes, comprising the following steps:

(1)导墙施工,施工场地沿地连墙方向地面标高有纵坡,在施工导墙时,按照每副地连墙或相邻几副地连墙划分导墙标高,将导墙外放15cm,净空加大6cm。(1) For the construction of the guide wall, the construction site has a longitudinal slope along the ground elevation along the ground connecting wall. During the construction of the guide wall, the guide wall elevation shall be divided according to each pair of ground connecting walls or several adjacent ground connecting walls, and the guide wall shall be placed outside. 15cm, the headroom is increased by 6cm.

(2)在导墙施工中,同步进行泥浆池制作和新泥浆配制,在施工场地合理选择泥浆池的位置;(2) During the construction of the guide wall, the production of the mud pool and the preparation of new mud shall be carried out simultaneously, and the position of the mud pool shall be reasonably selected at the construction site;

泥浆池包括新浆池、循环池、废浆池。新浆池用来制备新浆,满足成槽时,槽段泥浆不合格时备用;循环池用来成槽结束后,清空过程中置换泥浆,使泥浆满足钢筋笼吊装下放前和混凝土浇筑前的要求;废浆池用来满足混凝土地连墙混凝土浇筑过程中,储存泥浆和再次重新经过泥浆处理器在利用泥浆。The mud pool includes new mud pool, circulating pool and waste mud pool. The new slurry tank is used to prepare new slurry, and it is used for standby when the slurry in the groove section is unqualified when the tank is formed; Requirements; the waste slurry pool is used to meet the requirements of the concrete floor-to-wall concrete pouring process, storing the mud and re-using the mud through the mud processor again.

(3)导墙混凝土强度达到75%及新浆制备完成后,地连墙采用一台液压成槽机施工一期槽成槽;(3) After the concrete strength of the guide wall reaches 75% and the preparation of the new slurry is completed, a hydraulic grooving machine is used for the construction of the first-stage groove forming groove for the ground connecting wall;

(4)按照步骤(3)逐步施工相邻地连墙4到6副;(4) According to step (3), gradually construct 4 to 6 pairs of adjacent connecting walls;

(5)待相邻一期槽地连墙施工4到6副且混凝土强度满足75%后,进行闭合槽成槽施工;(5) After 4 to 6 pairs of adjacent first-phase trough-ground connecting walls are constructed and the concrete strength meets 75%, the closed trough-to-trough construction shall be carried out;

(6)按照步骤(5)逐步施工闭合地连墙;(6) According to step (5), gradually construct the closed ground connecting wall;

(7)按照步骤(3)、步骤(4)、步骤(5)顺序施工一期槽段和闭合槽段,形成流水作业。(7) Construct the first-phase trough section and the closed trough section in the order of step (3), step (4) and step (5) to form a flow operation.

进一步地,所述步骤(3)中一期槽成槽具体包括以下步骤:Further, in the step (3), the first-stage slot formation specifically includes the following steps:

(3a)土层成槽:每副一期槽段划分为6米,在导墙上放样做出标记,一期槽混凝土浇筑时,两端采用锁口管封闭,槽段两侧各外扩870mm,采用“三抓法”抓槽施工,先施工第一抓,采用一台液压抓斗成槽机成槽,落斗时两侧斗齿应同时插入土中进行抓槽安排,成槽机定位时,机械履带应与槽段平行,抓斗每抓一次,应根据垂线观察抓斗的垂直度及位置情况,使抓斗中心与槽段中心一致,然后下斗直到土面,若土质较硬则提起抓斗约0.8m,冲击数次再抓土,起斗时应缓慢,在抓斗出泥浆面时应及时回灌泥浆,保证泥浆液面不低于导墙脚以上0.50m且高于地下水位0.50m以上;待抓至岩层地质时抓槽作业停止,依次按照标记开始第二抓、第三抓施工,方法同第一抓;(3a) Formation of soil layer grooves: The first-phase groove section of each pair is divided into 6 meters, and marks are set out on the guide wall. When the first-phase groove concrete is poured, both ends are closed with locking pipes, and each side of the groove section is expanded outward. 870mm, using the "three-grab method" for the construction of the grab grooves, the first grab is constructed first, and a hydraulic grab groove forming machine is used to form the grooves. When dropping the bucket, the bucket teeth on both sides should be inserted into the soil at the same time to arrange the grab grooves, and the groove forming machine When positioning, the mechanical crawler should be parallel to the groove section. Every time the grab bucket is grabbed, the verticality and position of the grab bucket should be observed according to the vertical line, so that the center of the grab bucket is consistent with the center of the groove section, and then the bucket is lowered to the soil surface. If it is hard, lift the grab bucket about 0.8m, and then grab the soil after impacting several times. The bucket should be lifted slowly. When the grab bucket comes out of the mud surface, the mud should be refilled in time to ensure that the mud level is not lower than 0.50m above the foot of the guide wall and high When the groundwater level is above 0.50m; the grooving operation is stopped when the rock formation is reached, and the second and third grooving constructions are started according to the markings in sequence, and the method is the same as that of the first grouting;

(3b)岩层冲孔:土层成槽完成后,每副槽段采用两台冲桩机冲孔,一期槽段采用“九孔法”冲孔施工,先施工K1孔和K2孔,而后依次施工K3孔和K4孔、K5孔和K6孔、K7孔和K8孔、K9孔,在冲孔过程中,采用短冲程的方式;若冲孔时岩面为斜坡岩,需回填片石后再冲孔;(3b) Rock stratum punching: After the soil trough is completed, two pile punching machines are used for each trough section. The first stage trough section adopts the "nine-hole method" punching construction. Holes K3 and K4, holes K5 and K6, holes K7, K8, and K9 are constructed in sequence. During the punching process, a short stroke method is adopted; if the rock surface is slope rock during punching, it needs to be backfilled with schist and then punched. hole;

(3c)圆锤修孔:岩层冲孔完成后,用一台冲桩机采用圆锤修孔,从槽段一侧开始,顺序完成孔与孔之间的岩石;(3c) Round hammer repairing: After the rock formation is punched, a pile puncher is used to repair the hole with a round hammer, starting from the side of the groove section, and completing the rock between the holes in sequence;

(3d)圆锤修孔完成后,用一台冲桩机采用方锤修剩余岩石,从槽段一侧开始,顺序修完槽壁内所有岩石,避免钢精笼下放受阻。(3d) After the hole repair with the round hammer is completed, use a pile puncher to repair the remaining rock with a square hammer, starting from one side of the groove section, and repair all the rocks in the groove wall in sequence to avoid the obstruction of the steel cage.

进一步地,所述步骤(5)中闭合槽成槽包括以下步骤:Further, in the step (5), closing the groove to form a groove includes the following steps:

(5a)土层成槽:每副闭合槽段划分为6米,在导墙上放样做出标记,一期槽段成槽时,两侧各外扩870mm,闭合槽段实际成槽4300mm,采用“二抓法”抓槽施工,先施工第一抓,采用一台液压抓斗成槽机成槽,落斗时两侧斗齿应同时插入土中进行抓槽安排,成槽机定位时,机械履带应与槽段平行,抓斗每抓一次,应根据垂线观察抓斗的垂直度及位置情况,使抓斗中心与槽段中心一致,然后下斗直到土面,若土质较硬则提起抓斗约0.8m,冲击数次再抓土,起斗时应缓慢,在抓斗出泥浆面时应及时回灌泥浆,保证泥浆液面不低于导墙脚以上0.50m且高于地下水位0.50m以上;待抓至岩层地质时抓槽作业停止,按照标记进行第二抓施工,方法同第一抓;(5a) Formation of soil layer grooves: Each closed groove section is divided into 6 meters, and marks are set out on the guide wall. When the first-stage groove section is formed into a groove, each side is expanded by 870mm, and the closed groove section is actually formed into a groove of 4300mm. The "two grab method" is adopted for the construction of the grab groove. The first grab is constructed first, and a hydraulic grab groove forming machine is used to form the groove. When the bucket is dropped, the bucket teeth on both sides should be inserted into the soil at the same time to arrange the grab groove. When the groove forming machine is positioned , The mechanical crawler belt should be parallel to the groove section. Each time the grab bucket is grabbed, the verticality and position of the grab bucket should be observed according to the vertical line, so that the center of the grab bucket is consistent with the center of the groove section, and then the bucket is lowered to the soil surface. If the soil is hard Then lift the grab bucket for about 0.8m, impact several times and then grab the soil. The bucket should be lifted slowly. When the grab bucket comes out of the mud surface, the mud should be refilled in time to ensure that the mud level is not lower than 0.50m above the foot of the guide wall and higher than the groundwater. The position is above 0.50m; the grooving operation is stopped when the rock formation is reached, and the second grabbing construction is carried out according to the mark, and the method is the same as the first grabbing;

(5b)岩层成孔:土层成槽完成后,每副闭合槽2采用两台冲桩机冲孔,闭合槽段采用“五孔法”冲孔施工,先施工K1孔和K2孔,而后依次施工K3孔和K4孔、K5孔,在冲孔过程中,采用短冲程的方式;若冲孔时岩面为斜坡岩,需回填片石后再冲孔;(5b) Hole formation in the rock layer: After the soil layer formation is completed, two pile punching machines are used for each closed slot 2, and the “five-hole method” is used for punching the closed slot section. Holes K3, K4, and K5 are constructed in sequence. During the punching process, a short stroke method is adopted; if the rock surface is slope rock during punching, it is necessary to backfill schist and then punch;

(5c)岩层冲孔完成后,用一台冲桩机采用圆锤修孔,从槽段一侧开始,顺序完成孔与孔之间的岩石;(5c) After the rock formation is punched, use a pile punching machine to repair the hole with a round hammer, starting from the side of the groove section, and complete the rock between the holes in sequence;

(5d)圆锤修孔完成后,用一台冲桩机采用方锤修剩余岩石,从槽段一侧开始,顺序修完槽壁内所有岩石,避免钢精笼下放受阻。(5d) After the hole repair with the round hammer is completed, use a pile puncher to repair the remaining rock with a square hammer, starting from one side of the groove section, and repair all the rocks in the groove wall in sequence to avoid the obstruction of the steel cage.

与现有技术相比,本发明所具有的有益效果为:Compared with the prior art, the present invention has the following beneficial effects:

本发明提供了一种“三抓九孔与二抓五孔”地连墙成槽施工方法,一期槽先采用一台成槽机抓槽,每副一期槽采用 “三抓法”抓槽,后采用2台冲桩机同时冲孔,每副一期槽采用“九孔法”冲孔;闭合槽也采用一台成槽机抓槽,每副闭合槽采用 “二抓法”抓槽,后采用2台冲桩机同时冲孔,每副闭合槽段采用“五孔法”冲孔,一期槽和闭合槽抓槽和冲孔完成后,采用圆锤和方锤依次修槽。本方法既发挥了成槽机在软土地层抓槽的高效率的特点,更好的发挥地连墙的优势,也满足了冲桩机能够在强度高的岩层中发挥其优势的特点,有效避免了地连墙在上软下硬特殊地层中施工进度慢、质量控制难的风险。本发明提供了一种工艺简单、方法新颖、技术先进、工序衔接连续性好、安全质量可控的“三抓九孔与二抓五孔”地连墙施工方法。The invention provides a construction method of "three grasps with nine holes and two grasps with five holes" to form a groove on the ground connecting the wall. The first-stage groove is firstly grasped by a groove-forming machine, and each pair of the first-stage groove is grasped by the "three grasping method". For the grooves, two pile punching machines are used to punch holes at the same time, and the "nine-hole method" is used for punching the first-stage grooves of each pair; After the groove, two pile punching machines are used to punch holes at the same time, and each closed groove section is punched by the "five-hole method". . This method not only gives full play to the high efficiency of the grooving machine in the soft soil stratum, and better exerts the advantages of the ground connection wall, but also satisfies the characteristics that the pile puncher can exert its advantages in the high-strength rock stratum, and effectively It avoids the risk of slow construction progress and difficult quality control of the ground connecting wall in the special stratum with soft upper and lower hard layers. The invention provides a ground connecting wall construction method with simple process, novel method, advanced technology, good process connection continuity and controllable safety and quality.

附图说明Description of drawings

图1为本发明的地连墙划分示意图;Fig. 1 is a schematic diagram of the division of a ground connecting wall of the present invention;

图2为本发明施工方法步骤(3a)俯视图;Figure 2 is a top view of step (3a) of the construction method of the present invention;

图3为本发明施工方法步骤(3a)示意图;3 is a schematic diagram of step (3a) of the construction method of the present invention;

图4为本发明施工方法步骤(3b)俯视图;4 is a top view of step (3b) of the construction method of the present invention;

图5为本发明施工方法步骤(3b)示意图;5 is a schematic diagram of step (3b) of the construction method of the present invention;

图6为本发明施工方法步骤(3c)俯视图;6 is a top view of step (3c) of the construction method of the present invention;

图7为本发明施工方法步骤(3c)示意图;7 is a schematic diagram of step (3c) of the construction method of the present invention;

图8为本发明施工方法步骤(3d)俯视图;8 is a top view of step (3d) of the construction method of the present invention;

图9为本发明施工方法步骤(3d)示意图;9 is a schematic diagram of step (3d) of the construction method of the present invention;

图10为本发明施工方法步骤(5a)俯视图;10 is a top view of step (5a) of the construction method of the present invention;

图11为本发明施工方法步骤(5a)示意图;Figure 11 is a schematic diagram of step (5a) of the construction method of the present invention;

图12为本发明施工方法步骤(5b)俯视图;12 is a top view of step (5b) of the construction method of the present invention;

图13为本发明施工方法步骤(5b)示意图;13 is a schematic diagram of step (5b) of the construction method of the present invention;

图14为本发明施工方法步骤(5c)俯视图;14 is a top view of step (5c) of the construction method of the present invention;

图15为本发明施工方法步骤(5c)示意图;15 is a schematic diagram of step (5c) of the construction method of the present invention;

图16为本发明施工方法步骤(5d)俯视图;16 is a top view of step (5d) of the construction method of the present invention;

图17为本发明施工方法步骤(5d)示意图。Fig. 17 is a schematic diagram of step (5d) of the construction method of the present invention.

图中:1-一期槽;2-闭合槽;3-液压成槽机;4-圆锤;5-方锤。In the picture: 1- first-stage groove; 2- closed groove; 3- hydraulic groove forming machine; 4- round hammer; 5- square hammer.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

如图1~图9所示的“三抓九孔与二抓五孔”地连墙施工方法适用于所有上软下硬的地连墙结构施工,既满足可工期要求,又能满足地连墙质量要求。所述施工方法包括以下步骤:As shown in Figure 1~Figure 9, the construction method of the "three grasps nine holes and two grasps five holes" ground connection wall construction method is suitable for the construction of all the ground connection wall structures with the upper soft and the lower hard, which not only meets the requirements of the construction period, but also meets the ground connection wall structure. Wall quality requirements. The construction method includes the following steps:

(1)导墙施工,施工场地沿地连墙方向地面标高有纵坡,在施工导墙时,按照每副地连墙或相邻几副地连墙划分导墙标高,方便后期冲桩机架设冲孔和钢筋笼标高有效控制。为保证结构限界、 墙体厚度以及成槽的宽度,将导墙外放15cm,净空加大6cm。(1) For the construction of the guide wall, the construction site has a longitudinal slope along the ground elevation along the ground connecting wall. During the construction of the guide wall, the guide wall elevation shall be divided according to each pair of ground connecting walls or several adjacent ground connecting walls, which is convenient for the pile punching machine in the later stage. Erection punching and reinforcement cage elevation are effectively controlled. In order to ensure the structural limit, the thickness of the wall and the width of the groove, the guide wall is placed 15cm outside, and the clearance is increased by 6cm.

(2)在导墙施工中,同步进行泥浆池制作和新泥浆配制,在施工场地合理选择泥浆池的位置,方便所有地连墙施工的使用,泥浆池包括新浆池、循环池、废浆池。新浆池用来制备新浆,满足成槽时,槽段泥浆不合格时备用;循环池用来成槽结束后,清空过程中置换泥浆,使泥浆满足钢筋笼吊装下放前和混凝土浇筑前的要求;废浆池用来满足混凝土地连墙混凝土浇筑过程中,储存泥浆和再次重新经过泥浆处理器在利用泥浆。(2) During the construction of the guide wall, the production of the mud pool and the preparation of the new mud should be carried out simultaneously, and the position of the mud pool should be reasonably selected on the construction site to facilitate the use of all the ground connecting walls. The mud pool includes new mud pool, circulation pool, and waste slurry. pool. The new slurry tank is used to prepare new slurry, and it is used for standby when the slurry in the groove section is unqualified when the tank is formed; Requirements; the waste slurry pool is used to meet the requirements of the concrete floor-to-wall concrete pouring process, storing the mud and re-using the mud through the mud processor again.

(3)导墙混凝土强度达到75%及新浆制备完成后,地连墙采用一台液压成槽机3抓槽,先施工一期槽1。一期槽1先采用“三抓法”抓槽,再用两台冲桩机采用“九孔法”冲孔,再先后采用圆锤4和方锤5修槽。(3) After the concrete strength of the guide wall reaches 75% and the preparation of the new slurry is completed, a hydraulic grooving machine 3 is used for the ground connecting wall to grasp the groove, and the first-stage groove 1 is constructed first. In the first phase, groove 1 first adopts the "three grasping method" to grasp the groove, and then uses two pile punching machines to punch the hole using the "nine hole method", and then successively uses the round hammer 4 and the square hammer 5 to repair the groove.

所述一期槽1成槽包括以下步骤:Said first-phase slot 1 forming slot includes the following steps:

(3a)土层成槽。每副一期槽1划分为6米,在导墙上放样做出标记,作为后期施工的依据,一期槽1混凝土浇筑时,两端采用锁口管封闭,故采用液压成槽机抓槽时,槽段两侧各外扩870mm,采用“三抓法”抓槽施工,先施工第一抓,采用一台液压抓斗成槽机3成槽,落斗时两侧斗齿应同时插入土中进行抓槽安排,成槽机定位时,机械履带应与槽段平行,抓斗每抓一次,应根据垂线观察抓斗的垂直度及位置情况,使抓斗中心与槽段中心一致,然后下斗直到土面,若土质较硬则提起抓斗约0.8m,冲击数次再抓土,起斗时应缓慢,在抓斗出泥浆面时应及时回灌泥浆,保证泥浆液面不低于导墙脚以上0.50m且高于地下水位0.50m以上。待抓至岩层地质时抓槽作业停止,依次按照标记开始第二抓、第三抓施工,方法同第一抓,如图2-3所示。(3a) The soil layer is grooved. The first-phase groove 1 of each pair is divided into 6 meters, and marks are set out on the guide wall as the basis for later construction. When the first-phase groove 1 is concreted, both ends are closed with locking pipes, so a hydraulic groove forming machine is used to grasp the groove. At the same time, the two sides of the groove section are expanded by 870mm, and the "three-grip method" is used for the construction of the grab groove. The first grab is constructed first, and a hydraulic grab groove machine is used to form 3 grooves. Arrange the grab grooves in the soil. When positioning the groove forming machine, the mechanical crawler should be parallel to the groove section. Every time the grab bucket is grabbed, the verticality and position of the grab bucket should be observed according to the vertical line, so that the center of the grab bucket is consistent with the center of the groove section. , and then lower the bucket until the soil surface. If the soil is hard, lift the grab bucket for about 0.8m, impact several times and then grab the soil. The bucket should be lifted slowly. When the grab bucket comes out of the mud surface, the mud should be refilled in time to ensure the mud level. Not lower than 0.50m above the foot of the guide wall and 0.50m above the groundwater level. When the grooving reaches the rock formation, the grooving operation is stopped, and the second and third grooving constructions are started according to the marks in turn. The method is the same as that of the first grooving, as shown in Figure 2-3.

(3b)岩层成孔。土层成槽完成后,确保槽段内泥浆比重符合要求,以防槽段塌孔,每副槽段采用两台冲桩机冲孔,一期槽1采用“九孔法”冲孔施工,先施工K1孔和K2孔,而后依次施工K3孔和K4孔、K5孔和K6孔、K7孔和K8孔、K9孔,在冲孔过程中,采用短冲程的方式,避免因冲力太大偏孔。影响冲孔进度和成孔质量。若冲孔时发现岩面为斜坡岩,需回填片石后再冲孔,如图4-5所示。(3b) Pore formation in rock formations. After the soil layer is troughed, ensure that the specific gravity of the mud in the trough section meets the requirements to prevent the trough section from collapsing. Each trough section is punched by two pile punching machines. First construct the K1 and K2 holes, then construct the K3 and K4 holes, K5 and K6 holes, K7 and K8 holes, and K9 holes in sequence. During the punching process, a short stroke is used to avoid excessive force. hole. Affects punching progress and hole quality. If the rock surface is found to be slope rock during punching, it needs to be backfilled with schist and then punched, as shown in Figure 4-5.

(3c)岩层冲孔完成后,用一台冲桩机采用圆锤4修孔,从槽段一侧开始,顺序完成孔与孔之间的岩石,如图6-7所示。(3c) After the rock formation is punched, use a pile puncher to repair the hole with a round hammer 4, starting from the side of the groove section, and sequentially complete the rock between the holes, as shown in Figure 6-7.

(3d)圆锤4修孔完成后,用一台冲桩机采用方锤5修剩余岩石,从槽段一侧开始,顺序修完槽壁内所有岩石,避免钢精笼下放受阻,如图8-9所示。(3d) After the hole repair with round hammer 4 is completed, use a pile puncher and square hammer 5 to repair the remaining rocks, starting from one side of the groove section, and repair all the rocks in the groove wall in sequence, so as to prevent the steel cage from being blocked, as shown in the figure 8-9.

(4)按照步骤(3)逐步施工相邻地连墙4到6副。(4) According to step (3), gradually construct 4 to 6 pairs of adjacent connecting walls.

(5)待相邻一期槽1地连墙施工4到6副且混凝土强度满足75%后,施工闭合槽2。闭合槽2先采用“二抓法”抓槽,再用两台冲桩机采用“五孔法”冲孔,再先后采用圆锤4和方锤5修槽。(5) After 4 to 6 sets of connecting walls are constructed in the adjacent first-phase groove 1 and the concrete strength meets 75%, the closed groove 2 is constructed. The closed groove 2 first adopts the "two grasping method" to grasp the groove, and then uses two pile punches to punch the hole by the "five hole method", and then successively uses the round hammer 4 and the square hammer 5 to repair the groove.

所述闭合槽2成槽包括以下步骤:The said closed groove 2 into a groove comprises the following steps:

(5a)土层成槽。每副闭合槽2划分为6米,在导墙上放样做出标记,作为后期施工的依据,一期槽1成槽时,因两侧各外扩870mm,故闭合槽2实际成槽4300mm,采用“二抓法”抓槽施工,依次施工第一抓、第二抓,成槽方法同一期槽1,如图10-11所示。(5a) The soil layer is grooved. Each pair of closed grooves 2 is divided into 6 meters, and marks are set out on the guide wall as a basis for later construction. When groove 1 is formed into a groove in the first phase, since the two sides are expanded by 870mm, the closed groove 2 is actually formed into a groove of 4300mm. Adopt the "two grasping method" to grasp the groove construction, construct the first grasping and the second grasping in sequence, and the groove forming method is the same as the groove 1, as shown in Figure 10-11.

(5b)岩层成孔。土层成槽完成后,确保槽段内泥浆比重符合要求,以防槽段塌孔,每副闭合槽2采用两台冲桩机冲孔,闭合槽1采用“五孔法”冲孔施工,先施工K1孔和K2孔,而后依次施工K3孔和K4孔、K5孔,冲孔方法同一期槽1,如图12-13所示。(5b) Pore formation in rock formations. After the soil layer is troughed, make sure that the specific gravity of the mud in the trough section meets the requirements to prevent the trough section from collapsing. Two pile punching machines are used for each pair of closed trough 2, and the closed trough 1 is punched by the "five-hole method". First construct K1 and K2 holes, and then construct K3 holes, K4 holes, and K5 holes in sequence. The punching method is the same as slot 1, as shown in Figure 12-13.

(5c)岩层冲孔完成后,用一台冲桩机采用圆锤4修孔,从槽段一侧开始,顺序完成孔与孔之间的岩石,如图14-15所示。(5c) After the rock formation is punched, use a pile puncher to repair the hole with a round hammer 4, starting from the side of the groove section, and sequentially complete the rock between the holes, as shown in Figure 14-15.

(5d)圆锤4修孔完成后,用一台冲桩机采用方锤5修剩余岩石,从槽段一侧开始,顺序修完槽壁内所有岩石,避免钢精笼下放受阻,如图16-17所示。(5d) After the hole repair with round hammer 4 is completed, use a pile punching machine and square hammer 5 to repair the remaining rocks, starting from one side of the groove section, and repair all the rocks in the groove wall in sequence, so as to prevent the steel cage from being blocked, as shown in the figure 16-17.

(6)按照步骤(5)逐步施工闭合地连墙。(6) Follow step (5) to gradually construct the closed ground connecting wall.

(7)按照步骤(3)、步骤(4)、步骤(5)顺序施工一期槽1和闭合槽2,形成流水作业。(7) Construct the first-phase tank 1 and the closed tank 2 in the order of step (3), step (4) and step (5) to form a flow operation.

上面仅对本发明的较佳实施例作了详细说明,但是本发明并不限于上述实施例,在本领域普通技术人员所具备的知识范围内,还可以在不脱离本发明宗旨的前提下作出各种变化,各种变化均应包含在本发明的保护范围之内。Only the preferred embodiments of the present invention have been described in detail above, but the present invention is not limited to the above-mentioned embodiments, and within the scope of knowledge possessed by those of ordinary skill in the art, various aspects can also be made without departing from the purpose of the present invention. Various changes should be included within the protection scope of the present invention.

Claims (2)

1.一种“三抓九孔与二抓五孔”地连墙成槽施工方法,其特征在于,包括以下步骤:1. a kind of "three catches nine holes and two catches five holes" ground connection wall forming groove construction method, is characterized in that, comprises the following steps: (1)导墙施工,施工场地沿地连墙方向地面标高有纵坡,在施工导墙时,按照每副地连墙或相邻几副地连墙划分导墙标高,将导墙外放15cm,净空加大6cm;(1) For the construction of the guide wall, the construction site has a longitudinal slope along the ground elevation along the ground connecting wall. During the construction of the guide wall, the guide wall elevation shall be divided according to each pair of ground connecting walls or several adjacent ground connecting walls, and the guide wall shall be placed outside. 15cm, the headroom is increased by 6cm; (2)在导墙施工中,同步进行泥浆池制作和新泥浆配制,在施工场地合理选择泥浆池的位置;(2) During the construction of the guide wall, the production of the mud pool and the preparation of new mud shall be carried out simultaneously, and the position of the mud pool shall be reasonably selected at the construction site; 泥浆池包括新浆池、循环池、废浆池;新浆池用来制备新浆,满足成槽时,槽段泥浆不合格时备用;循环池用来成槽结束后,清空过程中置换泥浆,使泥浆满足钢筋笼吊装下放前和混凝土浇筑前的要求;废浆池用来满足混凝土地连墙混凝土浇筑过程中,储存泥浆和再次重新经过泥浆处理器在利用泥浆;The mud pool includes a new mud pool, a circulating pool, and a waste mud pool; the new mud pool is used to prepare new pulp, and it is used for standby when the mud in the groove section is unqualified when the groove is formed; the circulating pool is used to replace the mud during the emptying process after the groove is formed , so that the mud can meet the requirements before the steel cage is hoisted and lowered and before the concrete is poured; the waste slurry pool is used to store the mud and reuse the mud through the mud processor again during the concrete pouring process of the concrete floor connecting wall; (3)导墙混凝土强度达到75%及新浆制备完成后,地连墙采用一台液压成槽机施工一期槽成槽;(3) After the concrete strength of the guide wall reaches 75% and the preparation of the new slurry is completed, a hydraulic grooving machine is used for the construction of the first-stage groove forming groove for the ground connecting wall; (4)按照步骤(3)逐步施工相邻地连墙4到6副;(4) According to step (3), gradually construct 4 to 6 pairs of adjacent connecting walls; (5)待相邻一期槽地连墙施工4到6副且混凝土强度满足75%后,进行闭合槽成槽施工;(5) After 4 to 6 pairs of adjacent first-phase trough-ground connecting walls are constructed and the concrete strength meets 75%, the closed trough-to-trough construction shall be carried out; (6)按照步骤(5)逐步施工闭合地连墙;(6) According to step (5), gradually construct the closed ground connecting wall; (7)按照步骤(3)、步骤(4)、步骤(5)顺序施工一期槽段和闭合槽段,形成流水作业;(7) Construct the first-phase trough section and closed trough section in the order of step (3), step (4), and step (5) to form flow operation; 所述步骤(5)中闭合槽成槽包括以下步骤:In the step (5), closing the groove to form a groove includes the following steps: (5a)土层成槽:每副闭合槽段划分为6米,在导墙上放样做出标记,一期槽段成槽时,两侧各外扩870mm,闭合槽段实际成槽4300mm,采用“二抓法”抓槽施工,先施工第一抓,采用一台液压抓斗成槽机成槽,落斗时两侧斗齿应同时插入土中进行抓槽安排,成槽机定位时,机械履带应与槽段平行,抓斗每抓一次,应根据垂线观察抓斗的垂直度及位置情况,使抓斗中心与槽段中心一致,然后下斗直到土面,若土质较硬则提起抓斗0.8m,冲击数次再抓土,起斗时应缓慢,在抓斗出泥浆面时应及时回灌泥浆,保证泥浆液面不低于导墙脚0.50m且高于地下水位0.50m;待抓至岩层地质时抓槽作业停止,按照标记进行第二抓施工,方法同第一抓;(5a) Formation of soil layer grooves: Each closed groove section is divided into 6 meters, and marks are set out on the guide wall. When the first-stage groove section is formed into a groove, each side is expanded by 870mm, and the closed groove section is actually formed into a groove of 4300mm. The "two grab method" is adopted for the construction of the grab groove. The first grab is constructed first, and a hydraulic grab groove forming machine is used to form the groove. When the bucket is dropped, the bucket teeth on both sides should be inserted into the soil at the same time to arrange the grab groove. When the groove forming machine is positioned , The mechanical crawler belt should be parallel to the groove section. Each time the grab bucket is grabbed, the verticality and position of the grab bucket should be observed according to the vertical line, so that the center of the grab bucket is consistent with the center of the groove section, and then the bucket is lowered to the soil surface. If the soil is hard Then lift the grab bucket 0.8m, impact several times and then grab the soil. The bucket should be lifted slowly. When the grab bucket comes out of the mud surface, the mud should be refilled in time to ensure that the mud level is not lower than 0.50m below the foot of the guide wall and 0.50m above the groundwater level. m; The grooving operation is stopped when the rock formation is reached, and the second grooving construction is carried out according to the mark, and the method is the same as that of the first grooving; (5b)岩层成孔:土层成槽完成后,每副闭合槽2采用两台冲桩机冲孔,闭合槽段采用“五孔法”冲孔施工,先施工K1孔和K2孔,而后依次施工K3孔和K4孔、K5孔,在冲孔过程中,采用短冲程的方式;若冲孔时岩面为斜坡岩,需回填片石后再冲孔;(5b) Hole formation in the rock layer: After the soil layer formation is completed, two pile punching machines are used for each closed slot 2, and the “five-hole method” is used for punching the closed slot section. Holes K3, K4, and K5 are constructed in sequence. During the punching process, a short stroke method is adopted; if the rock surface is slope rock during punching, it is necessary to backfill schist and then punch; (5c)岩层冲孔完成后,用一台冲桩机采用圆锤修孔,从槽段一侧开始,顺序完成孔与孔之间的岩石;(5c) After the rock formation is punched, use a pile punching machine to repair the hole with a round hammer, starting from the side of the groove section, and complete the rock between the holes in sequence; (5d)圆锤修孔完成后,用一台冲桩机采用方锤修剩余岩石,从槽段一侧开始,顺序修完槽壁内所有岩石,避免钢精笼下放受阻。(5d) After the hole repair with the round hammer is completed, use a pile puncher to repair the remaining rock with a square hammer, starting from one side of the groove section, and repair all the rocks in the groove wall in sequence to avoid the obstruction of the steel cage. 2.根据权利要求1所述的一种“三抓九孔与二抓五孔”地连墙成槽施工方法,其特征在于,所述步骤(3)中一期槽成槽具体包括以下步骤:2. The construction method for forming a groove into a ground connection wall with "three grasping nine holes and two grasping five holes" according to claim 1, characterized in that, in the step (3), the first-stage groove forming specifically comprises the following steps : (3a)土层成槽:每副一期槽段划分为6米,在导墙上放样做出标记,一期槽混凝土浇筑时,两端采用锁口管封闭,槽段两侧各外扩870mm,采用“三抓法”抓槽施工,先施工第一抓,采用一台液压抓斗成槽机成槽,落斗时两侧斗齿应同时插入土中进行抓槽安排,成槽机定位时,机械履带应与槽段平行,抓斗每抓一次,应根据垂线观察抓斗的垂直度及位置情况,使抓斗中心与槽段中心一致,然后下斗直到土面,若土质较硬则提起抓斗0.8m,冲击数次再抓土,起斗时应缓慢,在抓斗出泥浆面时应及时回灌泥浆,保证泥浆液面不低于导墙脚0.50m且高于地下水位0.50m;待抓至岩层地质时抓槽作业停止,依次按照标记开始第二抓、第三抓施工,方法同第一抓;(3a) Formation of soil layer grooves: The first-phase groove section of each pair is divided into 6 meters, and marks are set out on the guide wall. When the first-phase groove concrete is poured, both ends are closed with locking pipes, and each side of the groove section is expanded outward. 870mm, using the "three-grab method" for the construction of the grab grooves, the first grab is constructed first, and a hydraulic grab groove forming machine is used to form the grooves. When dropping the bucket, the bucket teeth on both sides should be inserted into the soil at the same time to arrange the grab grooves, and the groove forming machine When positioning, the mechanical crawler should be parallel to the groove section. Every time the grab bucket is grabbed, the verticality and position of the grab bucket should be observed according to the vertical line, so that the center of the grab bucket is consistent with the center of the groove section, and then the bucket is lowered to the soil surface. If it is hard, lift the grab bucket 0.8m, and then grab the soil after impacting several times. The bucket should be lifted slowly. When the grab bucket comes out of the mud surface, the mud should be refilled in time to ensure that the mud level is not lower than 0.50m below the foot of the guide wall and higher than the groundwater. The position is 0.50m; the grooving operation is stopped when the rock formation is reached, and the second and third grooving constructions are started according to the marks in sequence, and the method is the same as that of the first grooving; (3b)岩层冲孔:土层成槽完成后,每副槽段采用两台冲桩机冲孔,一期槽段采用“九孔法”冲孔施工,先施工K1孔和K2孔,而后依次施工K3孔和K4孔、K5孔和K6孔、K7孔和K8孔、K9孔,在冲孔过程中,采用短冲程的方式;若冲孔时岩面为斜坡岩,需回填片石后再冲孔;(3b) Rock stratum punching: After the soil trough is completed, two pile punching machines are used for each trough section. The first stage trough section adopts the "nine-hole method" punching construction. Holes K3 and K4, holes K5 and K6, holes K7, K8, and K9 are constructed in sequence. During the punching process, a short stroke method is adopted; if the rock surface is slope rock during punching, it needs to be backfilled with schist and then punched. hole; (3c)圆锤修孔:岩层冲孔完成后,用一台冲桩机采用圆锤修孔,从槽段一侧开始,顺序完成孔与孔之间的岩石;(3c) Round hammer repairing: After the rock formation is punched, a pile puncher is used to repair the hole with a round hammer, starting from the side of the groove section, and completing the rock between the holes in sequence; (3d)圆锤修孔完成后,用一台冲桩机采用方锤修剩余岩石,从槽段一侧开始,顺序修完槽壁内所有岩石,避免钢精笼下放受阻。(3d) After the hole repair with the round hammer is completed, use a pile puncher to repair the remaining rock with a square hammer, starting from one side of the groove section, and repair all the rocks in the groove wall in sequence to avoid the obstruction of the steel cage.
CN201811621065.2A 2018-12-28 2018-12-28 A kind of construction method of ground connection wall forming groove Active CN109653213B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811621065.2A CN109653213B (en) 2018-12-28 2018-12-28 A kind of construction method of ground connection wall forming groove

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811621065.2A CN109653213B (en) 2018-12-28 2018-12-28 A kind of construction method of ground connection wall forming groove

Publications (2)

Publication Number Publication Date
CN109653213A CN109653213A (en) 2019-04-19
CN109653213B true CN109653213B (en) 2020-12-18

Family

ID=66117470

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811621065.2A Active CN109653213B (en) 2018-12-28 2018-12-28 A kind of construction method of ground connection wall forming groove

Country Status (1)

Country Link
CN (1) CN109653213B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110318388B (en) * 2019-06-24 2021-04-20 中国路桥工程有限责任公司 Underground continuous wall excavation grooving method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2726617B2 (en) * 1993-12-28 1998-03-11 孝豊 藤田 Construction method of underground continuous wall
CN103774690A (en) * 2012-10-19 2014-05-07 上海建工集团股份有限公司 Grabbing, drilling and punching combined underground continuous wall grooving construction method
CN104314071A (en) * 2014-10-24 2015-01-28 广州市第四建筑工程有限公司 Construction method of underground diaphragm wall by employing rotary drilling rig
CN108265734A (en) * 2018-03-31 2018-07-10 中国水利水电第四工程局有限公司 A kind of sand and gravel stratum impervious wall construction method
CN108894210A (en) * 2018-07-12 2018-11-27 中铁隧道局集团有限公司 The comprehensive construction method of continuous wall trench under a kind of COMPLEX MIXED formation condition for sea area

Also Published As

Publication number Publication date
CN109653213A (en) 2019-04-19

Similar Documents

Publication Publication Date Title
EP3839149A1 (en) Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor
CN109440778B (en) Active two-way inclined pile foundation pit support method
CN113445498A (en) Construction process of karst hole pile foundation in complex geology
CN104612179B (en) Through the construction method of the diaphram wall of super thick silty sand ground
CN112392400B (en) Hole forming construction process for slope protection pile in complex geological environment
CN105970916B (en) A kind of construction method of deep basal pit plain concrete diaphram wall
CN102561361A (en) Ultra-deep T-shaped trench-wall pile in soft-toped hard-bottomed soil layer and trench forming method
CN102995659A (en) Method for constructing from central area to periphery of ultra-large type underground engineering
CN111705786A (en) Method for vertical combination construction of composite stratum underground continuous wall and cast-in-situ bored pile
CN214993554U (en) Hydraulic engineering's side slope reinforced structure
CN107191001B (en) Construction Method of Foundation Reinforcement for Demolition and Construction of House Foundation
CN103243740B (en) Construction method of rotary excavating and long spiral combination bored concrete pressure grouting secant pile continuous wall
CN108797578A (en) Crushed stone grouting pile and its construction method with classification enlarged footing
CN107012861A (en) A kind of discrete material core expansive concrete stake and its construction method
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN109653213B (en) A kind of construction method of ground connection wall forming groove
CN108625362A (en) A kind of bayonet type cast-in-situ bored pile building enclosure and construction method
CN102561332B (en) Continuous variable-diameter cement-soil mixed pile forming method
CN204608773U (en) Pile work drilling machine coordinated type breast wall apparatus
CN103334428B (en) Disc type cast-in-place concrete pile and construction process for same
CN211285658U (en) Structure capable of carrying out deep water area hollowing repair in rapid stream state
CN216640561U (en) Novel combined type enclosure structure
CN112252312B (en) Construction method for enhancing integral stress performance of PHC pipe pile
CN110306540A (en) A kind of construction method of full circle swinging casing pile foundation pore-forming
CN105625435B (en) Sea product island multi-section, multi-level special-shaped equipment deep basal pit quick molding method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
OL01 Intention to license declared
OL01 Intention to license declared