CN109624287A - End seal host - Google Patents

End seal host Download PDF

Info

Publication number
CN109624287A
CN109624287A CN201811596437.0A CN201811596437A CN109624287A CN 109624287 A CN109624287 A CN 109624287A CN 201811596437 A CN201811596437 A CN 201811596437A CN 109624287 A CN109624287 A CN 109624287A
Authority
CN
China
Prior art keywords
guide rail
collet
pedestal
flush end
flush
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811596437.0A
Other languages
Chinese (zh)
Other versions
CN109624287B (en
Inventor
李学文
钟鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Li Xuewen
Original Assignee
Dongguan Guiliu Environmental Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dongguan Guiliu Environmental Technology Co Ltd filed Critical Dongguan Guiliu Environmental Technology Co Ltd
Priority to CN201811596437.0A priority Critical patent/CN109624287B/en
Publication of CN109624287A publication Critical patent/CN109624287A/en
Application granted granted Critical
Publication of CN109624287B publication Critical patent/CN109624287B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B29WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
    • B29CSHAPING OR JOINING OF PLASTICS; SHAPING OF MATERIAL IN A PLASTIC STATE, NOT OTHERWISE PROVIDED FOR; AFTER-TREATMENT OF THE SHAPED PRODUCTS, e.g. REPAIRING
    • B29C57/00Shaping of tube ends, e.g. flanging, belling or closing; Apparatus therefor, e.g. collapsible mandrels
    • B29C57/10Closing

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Lining Or Joining Of Plastics Or The Like (AREA)

Abstract

The present invention discloses a kind of end seal host, including rack, flush end device, flush end feed arrangement, end seal heat seal device, translation mechanism, translation pedestal and two centering synchronous fixtures.Translation pedestal one along the length and width direction of rack is slidedly arranged on the top of rack, and translation mechanism is installed on rack and drives translation pedestal sliding;Two centering synchronous fixtures another one along the length and width direction of rack are in be installed on translation pedestal at interval, flush end device and end seal heat seal device are respectively installed on translation pedestal, and the glide direction of flush end device and end seal heat seal device respectively along translation pedestal aligns with a centering synchronous fixture, flush end feed arrangement is installed on translation pedestal and flush end device is driven to do on translation pedestal toward polyslip along the glide direction of translation pedestal.End seal host of the invention is able to achieve the purpose being sealed to the end of steel-plastics composite pipe, to improve production efficiency.

Description

End seal host
Technical field
The present invention relates to a kind of equipment that the end for steel-plastics composite pipe is sealed, more particularly to a kind of steel that is used for mould The end seal host that the end of multiple tube is sealed.
Background technique
With the continuous development of the economy and the continuous progress of society, miscellaneous object is provided for people's production and life life The matter consumer goods, and pipe fitting is exactly a kind of in all multi-products.
It is well known that occurring a kind of emerging multiple tube tubing in the market to meet the special requirement of every profession and trade, referred to as For steel-plastics composite pipe.Wherein, in steel-plastics composite pipe, steel is a kind of ferrous material, and plastics are usually high density polyethylene (HDPE) (HDPE)。
Currently, steel-plastics composite pipe has many classification, it can be steel strip reinforced steel-plastics composite pipe, nothing according to the textural classification of tubing Stitch steel pipe enhancing steel-plastics composite pipe, hole pattern steel band steel-plastics composite pipe and steel wire mesh frame steel-plastics composite pipe.Currently, on the market most For it is popular be steel strip reinforced steel-plastics composite pipe, that is, our steel-plastic composite pressure pipes for often saying, this tubing middle layer are High-carbon steel band logical crosses steel belt layer made of cans and butt welding, and ectonexine is high density polyethylene (HDPE) (HDPE).It is this Tubing middle layer is steel band, so tubing load performance is very good.Just since the middle layer of steel-plastics composite pipe is steel belt layer, if in Between steel belt layer can be corroded when being chronically at exposed state and get rusty, therefore, it is necessary to carry out closed (letter to the end of steel-plastics composite pipe Claim end seal), to prevent extraneous corrosive deposit from causing entire steel to mould by the region erosion of the intermediate steel belt layer of steel-plastics composite pipe The intermediate steel belt layer of multiple tube gets rusty.
And being sealed at present to the end of steel-plastics composite pipe is all to lean on the craft of operator complete, therefore increase operation The burden of personnel, and it is well known that the maximum gauge of steel-plastics composite pipe can accomplish 290 millimeters, it is therefore, pure by operator's Removing the end part seal for completing so bulky steel-plastics composite pipe by hand is very laboriously, to further increase the negative of operator Load, correspondingly reduces production efficiency.
Therefore, it is badly in need of that a kind of reduction operator is wanted to bear and improves the end seal host of production efficiency to overcome above-mentioned lack It falls into.
Summary of the invention
It is born the purpose of the present invention is to provide a kind of reduction operator and improves the end seal host of production efficiency.
To achieve the goals above, the present invention provides a kind of end seal host, and the end progress being applicable in steel-plastics composite pipe is close Envelope, including rack, flush end device, flush end feed arrangement, end seal heat seal device, translation mechanism, translation pedestal and two centering synchronize Fixture.Translation pedestal one along the length and width direction of the rack is slidedly arranged on the top of the rack, described flat Telephone-moving structure is installed on the rack and the translation pedestal is driven to slide;Length of the two centering synchronous fixtures along the rack With another one in width direction in being installed on the translation pedestal at interval, the flush end device and end seal heat seal device are each It is installed on the translation pedestal, and the flush end device and end seal heat seal device are respectively along the glide direction and one of the translation pedestal A centering synchronous fixture aligns, and the flush end feed arrangement is installed on the translation pedestal and drives the flush end device Glide direction along the translation pedestal is done on the translation pedestal toward polyslip.
Preferably, the two centering synchronous fixtures are mutually aligned along direction is spaced apart, the flush end device, flush end feeding dress It sets and end seal heat seal device three is located at outside the same side of the centering synchronous fixture.
Preferably, the flush end device includes flush end motor and the flush end cutterhead connecting with the flush end motor, it is described flat It holds the rotation centerline of cutterhead along the glide direction arrangement of the translation pedestal, and has on the end face of the flush end cutterhead multiple The blade block of a circle is lined up in the circumferential direction of the flush end cutterhead.
Preferably, the flush end device also includes flush end reduction gearbox, the flush end motor is vertical and is installed on institute facing downward Flush end reduction gearbox, and the input axis connection of the output end of the flush end motor and the flush end reduction gearbox are stated, the flush end slows down The output shaft of case arranges that the flush end cutterhead is installed on the output of the flush end reduction gearbox along the glide direction of the translation pedestal On axis.
Preferably, the flush end feed arrangement includes feeding motor, feed screw, feeding screw and feeds pedestal, it is described Feeding pedestal is slidedly arranged on the top of the translation pedestal along the glide direction of the translation pedestal, and the feed screw is along described flat The glide direction for moving pedestal is installed at the top of the translation pedestal, and the feeding nut sleeve is loaded on the feeding pedestal, The feeding screw also sliding sleeve is installed on the translation pedestal and drives the feeding in the feed screw, the feeding motor Lead screw rotation, the flush end reduction gearbox are installed on the feeding pedestal.
Preferably, being equipped with belt drive structure, chain drive structure or gear between the feeding motor and the feed screw Drive mechanism.
Preferably, the belt drive structure includes the main pulley being installed on the output shaft of the feeding motor, is installed on Slave belt wheel on the feed screw and it is sheathed on the main pulley and from the transmission belt on belt wheel.
Preferably, the centering synchronous fixture includes fixed frame, first straight line driver, second straight line driver, One collet, the second collet, the first sliding block, first connecting rod, second connecting rod, the first guide rail and the second guide rail, the fixed frame peace Loaded on the translation pedestal, first guide rail is installed on the fixed frame, and second guide rail vertically divides described first equally Guide rail, second guide rail are also fixed on first guide rail and/or fixed frame, first collet and each cunning of the second collet It is aligned set on first guide rail and along the guide direction of first guide rail, the first straight line driver and second straight line are driven Dynamic device is respectively installed on the fixed frame, and the output end of the first straight line driver is connect with first collet, and described The output end of two linear actuators is connect with second collet, and the first end of the first connecting rod and first collet are cut with scissors It connects, the second end of the first connecting rod and first sliding block are hinged, the first end of the second connecting rod and second collet Hingedly, the second end of the second connecting rod and first sliding block are hinged, and first sliding block is also slidedly arranged on second guide rail, The first connecting rod is arranged symmetrically centered on second guide rail with the second connecting rod.
Preferably, end seal host of the invention further includes third guide rail, the 4th guide rail, third connecting rod, fourth link and Two sliding blocks, the third guide rail are also led along described second along the direction arrangement for being parallel to first guide rail, the third guide rail The guide direction of rail is alternate with first guide rail to be opened, and the 4th guide rail is arranged simultaneously along the direction for being parallel to second guide rail It aligns with second guide rail, the 4th guide rail vertically divides the third guide rail, first collet and the second collet equally It is also slidedly arranged on the third guide rail, the first end of the third connecting rod and first collet are hinged, and the of the third connecting rod Two ends and second sliding block are hinged, and the first end of the fourth link and second collet are hinged, the fourth link Second end and second sliding block are hinged, and second sliding block is also slidedly arranged on the 4th guide rail, the third connecting rod with it is described Fourth link is arranged symmetrically centered on the 4th guide rail.
Preferably, first guide rail to the 4th guide rail is respectively guide rod, the first end of first guide rail is slidably worn The first side frame wall that first collet is fixed on the fixed frame again is crossed, the second end of first guide rail slidably passes through Second collet is fixed on the second side frame wall opposite with the first side frame wall of the fixed frame again, and the third is led The first end of rail slidably passes through first collet and is fixed on the first side frame wall again, and the second end of the third guide rail is sliding Second collet is passed through dynamicly and is fixed on the second side frame wall again, and the first sliding block sliding sleeve is in second guide rail, institute The second sliding block sliding sleeve is stated in the 4th guide rail.
Compared with prior art, by translation mechanism and translation pedestal, so that a centering synchronous fixture clamping is extraneous defeated While the steel-plastics composite pipe sent, also make another centering synchronous fixture clamping by flush end device treated steel plastic compount Pipe;Then, flush end device is under the action of flush end feed arrangement, comes to external world's conveying and the steel clamped by positioning synchronous fixture Intermediate steel belt layer in the end of plastic composite cuts predetermined depth, so that it is cricoid recessed to form out the end of steel-plastics composite pipe Fall into space;And end seal heat seal device is hot-forming to being carried out by the end of the processed steel-plastics composite pipe of flush end device, moulds steel Inside and outside plastic layer in the end of multiple tube is heated and is filled in dented space, to realize to the end of steel-plastics composite pipe Therefore automatic-sealed improves production efficiency and reduces the burden of operator.
Detailed description of the invention
Fig. 1 is the planar structure schematic diagram of end seal host of the invention in main view direction.
Fig. 2 is the top view of end seal host shown in FIG. 1.
Fig. 3 is the side view that end seal host shown in FIG. 1 projects from left to right.
Fig. 4 is planar structure schematic diagram of the centering synchronous fixture in end seal host of the invention in main view direction.
Fig. 5 is the side view that centering synchronous fixture shown in Fig. 4 projects from left to right.
Fig. 6 is the top view of centering synchronous fixture shown in Fig. 4.
Fig. 7 a to Fig. 7 b is the state diagram that centering synchronous fixture shown in Fig. 4 clamps steel-plastics composite pipe.
Fig. 8 a to Fig. 8 b is the procedure chart that the end of steel-plastics composite pipe is sealed.
Specific embodiment
For the technology contents that the present invention will be described in detail, construction feature, below in conjunction with embodiment and cooperate attached drawing make into One step explanation.
It please referring to Fig.1 to Fig.3, end seal host 100 of the invention, which is applicable in, is sealed the end of steel-plastics composite pipe 200, Cutting off predetermined depth with the intermediate steel belt layer 220 in the end to steel-plastics composite pipe 200, (depth is flexibly set according to practical feelings Set), so that the end of steel-plastics composite pipe 200 be made to form cricoid dented space 230 (state is as shown in Fig. 8 a) and make inside and outside modeling Glue-line 210 is heated to fill sunk structure 230 (state is as shown in Fig. 8 b), to realize the close of the end of steel-plastics composite pipe 200 Envelope.Wherein, end seal host 100 of the invention includes rack 10, flush end device 30, flush end feed arrangement 40, end seal heat seal device 50, translation mechanism 60, translation pedestal 70 and two centering synchronous fixtures 80.It translates pedestal 70 and is slidedly arranged on machine along 10 width direction of rack The top of frame 10, certainly, according to actual needs, translation pedestal 70 can also be slidedly arranged on along the length direction of rack 10 rack 10 it Top, thus it is without being limited thereto;Translation mechanism 60 is installed on rack 10 and translation pedestal 60 is driven to slide, and is preferably translation mechanism 60 include a cylinder or hydraulic cylinder, and the output end of cylinder or hydraulic cylinder is connect with translation pedestal 60, so that it is higher to translate pedestal 60 Effect is done toward polyslip, but not limited to this.Two centering synchronous fixtures 80 are in be installed at interval along the length direction of rack 10 It translates on pedestal 70, certainly, according to actual needs, two positioning synchronous fixtures 80 can be also separated at intervals along the width direction of rack 10 Arrangement, thus it is without being limited thereto.Flush end device 30 and end seal heat seal device 50 are respectively installed on translation pedestal 70, by translation pedestal 70 Support, and slid together by the drive of translation pedestal 70;Flush end device 30 and end seal heat seal device 50 are respectively along the sliding of translation pedestal 70 Direction aligns with a centering synchronous fixture 80, is preferably, two centering synchronous fixtures 80 are mutually aligned along direction spaced apart, Flush end device 30, flush end feed arrangement 40 and 50 three of end seal heat seal device are located at outside the same side of centering synchronous fixture 80, with Prevent flush end device 30, flush end feed arrangement 40 and 50 three of end seal heat seal device not outside the same side of centering synchronous fixture 80 And steel-plastics composite pipe 200 clamped by positioning synchronous fixture 80 is caused to hinder, so that it is guaranteed that flush end device 30, flush end feeding dress Functional reliability between 40, end seal heat seal device 50 and centering synchronous fixture 80 is set, but not limited to this.Flush end feed arrangement 40 is pacified Loaded on translation pedestal 70 and flush end device 30 is driven to do on translation pedestal 70 toward polyslip along the glide direction of translation pedestal 70, The demand of predetermined depth is cut off to meet flush end device 30 to the intermediate steel belt layer 220 in the end of steel-plastics composite pipe 200.More Body, it is as follows:
As shown in Figure 1 to Figure 3, flush end device 30 includes flush end motor 31 and the flush end cutterhead connecting with flush end motor 31 32, the rotation centerline of flush end cutterhead 32 is arranged along the glide direction of translation pedestal 70, and is had on the end face of flush end cutterhead 32 Multiple blade blocks 321 that a circle is lined up in the circumferential direction of flush end cutterhead 32, to improve flush end cutterhead 32 to steel-plastics composite pipe 200 Processing efficiency;Specifically, flush end device 30 also includes flush end reduction gearbox 33, and flush end motor 31 is vertical and is installed on flush end facing downward Reduction gearbox 33, rationally to utilize the space of flush end reduction gearbox 33, and the output end of flush end motor 31 and flush end reduction gearbox 33 is defeated Enter axis connection, along the glide direction arrangement of translation pedestal 70, flush end cutterhead 32 is installed on flat the output shaft 331 of flush end reduction gearbox 33 On the output shaft 331 for holding reduction gearbox 33, to carry out reduction of speed to flush end motor 31 by flush end reduction gearbox 33, so that flush end knife Disk 32 obtains bigger torque, but not limited to this.
As shown in Figure 1 to Figure 3, flush end feed arrangement 40 includes feeding motor 41, feed screw 42, feeding screw and feeding Pedestal 44, feeding pedestal 44 is slidedly arranged on the top of translation pedestal 70 along the glide direction of translation pedestal 70, right by translation pedestal 70 It feeds pedestal 44 and support is provided;Feed screw 42 is installed at the top of translation pedestal 70 along the glide direction of translation pedestal 70, Support is provided to feed screw 42 by translation pedestal 70 to fix;Nut sleeve is fed loaded on feeding pedestal 44, feeding screw is also sliding Be placed on feed screw 42, feeding motor 41 is installed on translation pedestal 70 and feed screw 42 driven to rotate, thus by rotate into Feeding pedestal 44 is driven to slide on translation pedestal 70 by feeding screw to lead screw 42;Flush end reduction gearbox 33 is installed on feeding seat On body 44, to realize that the drive flush end device 30 of flush end feed arrangement 40 does the purpose of feed motion.Specifically, feeding motor 41 with It is equipped with belt drive structure 45 between feed screw 42 and is set as chain drive structure or gear drive according to actual needs certainly Structure, therefore be not limited.For example, belt drive structure 45 includes the main pulley being installed on the output shaft of feeding motor 41 451, the slave belt wheel 452 that is installed on feed screw 42 and it is sheathed on main pulley 451 and from the transmission belt 453 on belt wheel 452, with Realize feeding motor 41 to the purpose of the separate smooth drive of feed screw 42, but not limited to this.
As shown in Figures 4 to 6, centering synchronous fixture 80 is straight including fixed frame 81, first straight line driver 821, second Line drive 822, the first collet 831, the second collet 832, the first sliding block 841, first connecting rod 851, second connecting rod 852, first Guide rail 861 and the second guide rail 862, fixed frame 81 be installed on translation pedestal 70 on, be preferably, the length of fixed frame 81 with The length direction for translating pedestal 70 is identical, so that fixed frame 81 rationally utilizes in the space for translating pedestal 70.First guide rail 861 It is installed on fixed frame 81, is fixed by fixed frame 81;Second guide rail 862 vertically divides the first guide rail 61 equally, and the second guide rail 862 is solid Due on the first guide rail 861, support is provided to the second guide rail 862 by the first guide rail 861;Certainly, according to actual needs, second lead Rail 862 can also be fixed on fixed frame 81, alternatively, being fixed on the first guide rail 861 and fixed frame 81 simultaneously, therefore be not limited to This.First collet 831 and the second collet 832 are respectively slidedly arranged on the first guide rail 861 and along guide direction (such as Fig. 4 of the first guide rail 861 In left and right directions) alignment, be preferably that the guide direction of the first guide rail 861 is not arranged along the length direction of rack 10, but not It is limited to this.First straight line driver 821 and second straight line driver 822 are respectively installed on fixed frame 81, are by fixed frame 81 First straight line driver 821 and second straight line driver 822 provide support;The output end of first straight line driver 821 and first Collet 831 connects, and drives the first collet 831 to slide by first straight line driver 821;The output end of second straight line driver 822 It is connect with the second collet 832, drives the second collet 832 to slide by second straight line driver 822.The first end of first connecting rod 851 Hinged with the first collet 831, the second end of first connecting rod 851 and the first sliding block 841 are hinged;The first end of second connecting rod 852 with Second collet 832 is hinged, and the second end of second connecting rod 852 and the first sliding block 841 are hinged, and the first sliding block 841 is also slidedly arranged on second Guide rail 862, first connecting rod 851 are arranged symmetrically centered on the second guide rail 862 with second connecting rod 852, are realized by the first collet 831 and the second fast person in collet 832 by the first connecting rod 851 or second connecting rod 852 hinged with fast person together with the first sliding block 841 go that second connecting rods 852 or first connecting rod 851 hinged with slow person is driven to move synchronously, thus realize the first collet 831 and The synchronism for closing movement is opened between second collet 832, so that the first collet 831 and the second collet 832 embrace the steel of folder jointly every time The center of plastic composite 200 is all located at same position.Specifically, centering synchronous fixture 80 further includes third guide rail the 863, the 4th Guide rail 864, third connecting rod 853, fourth link 854 and the second sliding block 842.Third guide rail 863 is along being parallel to the first guide rail 861 Direction arrangement, third guide rail 863 is also along the guide direction (up and down direction in such as Fig. 4) of the second guide rail 862 and the first guide rail 861 Alternate to open, the 4th guide rail 864 vertically divides third guide rail 863 equally, and the 4th guide rail 864 is along the direction cloth for being parallel to the second guide rail 862 It sets and aligns with the second guide rail 862;First collet 831 and the second collet 832 are also slidedly arranged on third guide rail 863;Third connecting rod 853 first end and the first collet 831 are hinged, and the second end of third connecting rod 853 and the second sliding block 842 are hinged, fourth link 854 First end and the second collet 832 it is hinged, the second end of fourth link 854 and the second sliding block 842 are hinged, and the second sliding block 842 is also It is slidedly arranged on the 4th guide rail 864;Third connecting rod 853 is arranged symmetrically centered on the 4th guide rail 864 with fourth link 854, therefore, By third guide rail 863, the 4th guide rail 864, third connecting rod 853, fourth link 854 and the second sliding block 842, for sliding to first Block 841, first connecting rod 851, second connecting rod 852, the first guide rail 861 and the second guide rail 862 are balanced, so that the first folder First 831 with the second collet 832 close it is more stable smooth in motion process, and steel-plastics composite pipe 200 is clamped it is more firm, but not It is limited to this.For example, 861 to the 4th guide rail 864 of the first guide rail is respectively guide rod, and the first end of the first guide rail 861 is slidably It is fixed on the first side frame wall 811 of fixed frame 81 again across the first collet 831, the second end of the first guide rail 861 is slidably worn Cross the second side frame wall 812 opposite with the first side frame wall 811 that the second collet 832 is fixed on fixed frame 81 again, third guide rail 863 first end slidably passes through the first collet 831 and is fixed on the first side frame wall 811, the second end sliding of third guide rail 863 again Ground passes through the second collet 832 and is fixed on the second side frame wall 812 again, and 841 sliding sleeve of the first sliding block is in the second guide rail 862, the second sliding block 842 sliding sleeves are in the 4th guide rail 864, so that the first guide rail 861 and the space occupied by fixed frame 81 of third guide rail 863 are small, and Sufficient space is provided for the clamping work of steel-plastics composite pipe 200, also makes the sliding of the first sliding block 841 and the second sliding block 842 It is more reliable, but not limited to this;It is preferably that the first end of the second guide rail 862 is in fixedly to be set in the middle part of the first guide rail 861 Place, to ensure the reliability of the second guide rail 862 and the installation of the first guide rail 861;The first end of 4th guide rail 864 is in fixedly to be set with In the center of third guide rail 863, to ensure the reliability of the 4th guide rail 864 with the installation of third guide rail 863.
As shown in Figures 4 to 6, first straight line driver 821 is fixed on the first side frame wall 811, first straight line driver 821 Output end pass through the first side frame wall 811 connect again with the first collet 831, second straight line driver 822 is fixed on the second side frame Outside wall 812, and the output end of second straight line driver 822 passes through the second side frame wall 812 and connect again with the second collet 832, in this way Design can make the more compact structure of centering synchronous fixture 80;Specifically, the third side frame wall 813 of fixed frame 81 and the 4th side Frame wall 814 respectively offers evacuation through-hole 815, is preferably the first side frame wall 811, third side frame wall 813, the second side frame wall 812 And the 4th side frame 814 it is successively end to end, to constitute rectangular fixed frame 81, but not limited to this;And first connecting rod 851, second connecting rod 852 and third guide rail 863 are placed through in the evacuation through-hole 815 of third side frame wall 813, avoid third side frame 813 pairs of the wall first connecting rods 851 moved and second connecting rod 852 interfere, it is ensured that the reliability of movement;Third connecting rod 853, Double leval jib 854 and the 4th guide rail 864 are placed through in the evacuation through-hole 815 of the 4th side frame wall 814, avoid the 4th side frame wall 814 The third connecting rod 853 and fourth link 854 of movement are interfered, it is ensured that the reliability of movement.It wherein, is raising smooth slippage Property, the first collet 831 are set with the first guide sleeve 833 being slidably matched respectively with the first guide rail 861 and third guide rail 863, and second Collet 832 is set with the second guide sleeve 834 being slidably matched respectively with the first guide rail 861 and third guide rail 863, therefore leads by first Set 833, more smoothly slides so that the first collet 831 is done on the first guide rail 861 and third guide rail 863, similarly, by second Guide sleeve 834 more smoothly slides so that the second collet 832 is done on the first guide rail 861 and third guide rail 863;Specifically, first Both collet 831 and the second collet 832 respectively have the circular arc clamping face 8311,8321 faced each other, more matching steel-plastics composite pipe 200 shape, but not limited to this.To simplify linear drives structure, first straight line driver 821 and second straight line driver 822 Respectively be cylinder, with simplify provide linear drives structure, and have the advantages that it is high-efficient, certainly, according to actual needs, first directly Line drive 821 and second straight line driver 822 can also be hydraulic cylinder or linear motor, therefore without being limited thereto.
In conjunction with Fig. 4 to Fig. 7 b, synchronous fixture 80 of feeling relieved is illustrated the clamping principle of steel-plastics composite pipe 200: such as Fig. 7 a It is shown, steel-plastics composite pipe 200 is placed in the space between the first collet 831 and the second collet 832;Then, first straight line Driver 821 drives the first collet 831 to slide towards close to 832 direction of the second collet, meanwhile, second straight line driver 822 drives Second collet 832 slides towards close to 831 direction of the first collet, so that the first collet 831 and the second collet 832 embrace folder jointly Steel-plastics composite pipe 200, state is as shown in Fig. 7 b;Wherein, folder steel plastic compount is embraced jointly in the first collet 831 and the second collet 832 During pipe 200, mobile the first fast collet 831 drives the first sliding block 841 along the second guide rail 862 by first connecting rod 851 Sliding synchronization also drives the second sliding block 842 to slide along the 4th guide rail 864, by the first sliding block slid by third connecting rod 853 841 drive the movement of second connecting rod 852 and the second sliding block 842 that fourth link 854 is driven to move, thus by the second connecting rod moved 852 and fourth link 854 drive the second mobile slow collet 832 jointly, that is, realize that fast person drags slow person, final both realize is moved Dynamic synchronism achievees the purpose that every time the center of clamped steel-plastics composite pipe 200 is all located on same position, in order to flush end dress Set 31 pairs one centering synchronous fixture 80 on steel-plastics composite pipe 200 and end seal heat seal device 50 to another feel relieved synchronous fixture Steel-plastics composite pipe 200 on 800 is processed accordingly.
In conjunction with attached drawing, the working principle of end seal host of the invention is illustrated: as shown in Fig. 2, firstly, by a steel Plastic composite 200 is delivered to the position to align with the centering synchronous fixture 80 in left side, at this point, translation mechanism 60 drives translating base Body 70 translates the sliding of the arrow direction in pedestal 70 along Fig. 2, by the translation pedestal 70 that slides together with the translation pedestal 70 On flush end device 30, flush end feed arrangement 40, end seal heat seal device 50 and the centering synchronous fixture 80 of the left and right sides move together It is dynamic, until steel-plastics composite pipe 200 enters in the centering synchronous fixture 80 with left side;Then, by the centering synchronous fixture 80 in left side Steel-plastics composite pipe 200 is clamped;And then, flush end device 30 realizes the steel to clamping under the cooperation of flush end feed arrangement 40 The end of plastic composite 200 is processed, and process is as shown in Fig. 8 a to Fig. 8 b;When after processing is completed, at this point, translation mechanism 60 drives Make to translate pedestal 70 and translate arrow meaning opposite direction in pedestal 70 along Fig. 2 and slide, by the translation pedestal 70 that slides together with Flush end device 30, flush end feed arrangement 40, end seal heat seal device 50 and two centering synchronous fixtures 80 1 on the translation pedestal 70 Movement is played, until the centering synchronous fixture 80 in left side is moved away from by the finished steel-plastics composite pipe 200 of flush end device 30;Then, will The finished steel-plastics composite pipe 200 of flush end device 30 conveys the position to align with the centering synchronous fixture 80 on right side down, together When, continue to carry out a new steel-plastics composite pipe 200 toward the centering conveying of synchronous fixture 80 in left side;At this point, translation mechanism 60 drives Translation pedestal 70 translate the arrow direction in pedestal 70 along Fig. 2 and slides, by the translation pedestal 70 that slides together with the translation The centering synchronous fixture 80 of flush end device 30, flush end feed arrangement 40, end seal heat seal device 50 and the left and right sides on pedestal 70 It moves together, adds until in the centering synchronous fixture 80 that a new steel-plastics composite pipe 200 enters left side and by flush end device 30 The steel-plastics composite pipe 200 that work is crossed enters in the centering synchronous fixture 80 on right side;It then, will be new by the centering synchronous fixture 80 in left side The clamping of a steel-plastics composite pipe 200 and by 80 pairs of centering synchronous fixture of right side by the finished steel plastic compount of flush end device 30 Pipe 200 is clamped;Finally, flush end device 30 under the cooperation of flush end feed arrangement 40, realizes the steel-plastics composite pipe to clamping 200 end is processed, and process is as shown in Fig. 8 a to Fig. 8 b;Equally, steel clamped by the centering synchronous fixture 80 by right side Plastic composite 200 by under the work of end seal heat seal device 50 realize to by flush end device 30 process after steel-plastics composite pipe 200 it End is sealed, and state is as shown in Fig. 8 b;Therefore, constantly repeat above-mentioned process, it can realize steel-plastics composite pipe 200 it The batch production of end part seal.
Compared with prior art, by translation mechanism 60 and translation pedestal 70, so that centering synchronous fixture 80 clamping While steel-plastics composite pipe 200 that external world's conveying comes, also make another centering clamping of synchronous fixture 80 by flush end device 30 Steel-plastics composite pipe 200 after reason;Then, flush end device 30 is under the action of flush end feed arrangement 40, external world's conveying is come and by Intermediate steel belt layer 220 in the end of steel-plastics composite pipe 200 clamped by positioning synchronous fixture 80 cuts predetermined depth, to make The end of steel-plastics composite pipe 200 forms out a dented space 230;And 50 pairs of end seal heat seal device processed by flush end device 30 The end of steel-plastics composite pipe 200 carry out it is hot-forming, make the inside and outside plastic layer 210 of the end of steel-plastics composite pipe 200 by hot melt and Be filled in dented space 230, to realize the automatic-sealed to the end of steel-plastics composite pipe 200, therefore, improve production efficiency and Reduce the burden of operator.
The person of being worth noting, end seal heat seal device 50 is structure known in the art, therefore is no longer carried out herein specifically It is bright.
The above disclosure is only a preferred example of the present invention, and the scope of the invention cannot be limited thereby, Therefore equivalent changes made in accordance with the claims of the present invention belong to the range that the present invention is covered.

Claims (10)

1. a kind of end seal host, is applicable in and is sealed to the end of steel-plastics composite pipe, which is characterized in that the end seal host includes Rack, flush end device, flush end feed arrangement, end seal heat seal device, translation mechanism, translation pedestal and two centering synchronous fixtures, institute State the top that translation pedestal one along the length and width direction of the rack is slidedly arranged on the rack, the translation mechanism peace Loaded on the rack and the translation pedestal is driven to slide, the two centering synchronous fixtures are along the length and width side of the rack To middle another one in being installed on the translation pedestal at interval, the flush end device and end seal heat seal device are respectively installed on institute Translation pedestal is stated, and the flush end device and end seal heat seal device are respectively described fixed along the glide direction of the translation pedestal and one Heart synchronous fixture aligns, and the flush end feed arrangement is installed on the translation pedestal and drives the flush end device along described flat The glide direction for moving pedestal is done on the translation pedestal toward polyslip.
2. end seal host according to claim 1, which is characterized in that the two centering synchronous fixtures are along direction phase spaced apart Mutually alignment, the flush end device, flush end feed arrangement and end seal heat seal device three are located at the same of the centering synchronous fixture Outside side.
3. end seal host according to claim 1, which is characterized in that the flush end device include flush end motor and with it is described The flush end cutterhead of flush end motor connection, the rotation centerline of the flush end cutterhead along the translation pedestal glide direction arrangement, And there are multiple blade blocks that a circle is lined up in the circumferential direction of the flush end cutterhead on the end face of the flush end cutterhead.
4. end seal host according to claim 3, which is characterized in that the flush end device also includes flush end reduction gearbox, institute It states flush end motor vertically and is installed on the flush end reduction gearbox facing downward, and the output end of the flush end motor subtracts with the flush end The input axis connection of fast case, glide direction arrangement of the output shaft of the flush end reduction gearbox along the translation pedestal, the flush end Cutterhead is installed on the output shaft of the flush end reduction gearbox.
5. end seal host according to claim 4, which is characterized in that the flush end feed arrangement include feeding motor, into To lead screw, feeding screw and feeding pedestal, the feeding pedestal is slidedly arranged on the translation along the glide direction of the translation pedestal The top of pedestal, the feed screw is along the top that the glide direction of the translation pedestal is installed on the translation pedestal, institute Feeding nut sleeve is stated loaded on the feeding pedestal, the feeding screw also sliding sleeve is in the feed screw, the feeding motor It is installed on the translation pedestal and the feed screw is driven to rotate, the flush end reduction gearbox is installed on the feeding pedestal.
6. end seal host according to claim 5, which is characterized in that set between the feeding motor and the feed screw There are belt drive structure, chain drive structure or gear transmission structure.
7. end seal host according to claim 5, which is characterized in that the belt drive structure includes to be installed on the feeding Main pulley on the output shaft of motor, the slave belt wheel being installed on the feed screw and it is sheathed on the main pulley and from belt wheel On transmission belt.
8. end seal host according to claim 1, which is characterized in that the centering synchronous fixture includes fixed frame, One linear actuator, second straight line driver, the first collet, the second collet, the first sliding block, first connecting rod, second connecting rod, first Guide rail and the second guide rail, the fixed frame are installed on the translation pedestal, and first guide rail is installed on the fixed frame, Second guide rail vertically divides first guide rail equally, and second guide rail is also fixed on first guide rail and/or fixed frame Frame, first collet and the second collet are respectively slidedly arranged on first guide rail and are aligned along the guide direction of first guide rail, The first straight line driver and second straight line driver are respectively installed on the fixed frame, the first straight line driver it is defeated Outlet is connect with first collet, and the output end of the second straight line driver is connect with second collet, and described first The first end of connecting rod and first collet are hinged, and the second end of the first connecting rod and first sliding block are hinged, and described The first end of two connecting rods and second collet are hinged, and the second end of the second connecting rod and first sliding block are hinged, described First sliding block is also slidedly arranged on second guide rail, and the first connecting rod is in centered on second guide rail with the second connecting rod It is arranged symmetrically.
9. end seal host according to claim 8, which is characterized in that further include third guide rail, the 4th guide rail, third company Bar, fourth link and the second sliding block, the third guide rail is along the direction arrangement for being parallel to first guide rail, the third guide rail It also opens along the guide direction of second guide rail is alternate with first guide rail, the 4th guide rail is led along being parallel to described second The direction of rail, which is arranged, simultaneously to align with second guide rail, and the 4th guide rail vertically divides the third guide rail equally, and described first Collet and the second collet are also slidedly arranged on the third guide rail, and the first end of the third connecting rod and first collet are hinged, institute Second end and second sliding block for stating third connecting rod are hinged, and the first end of the fourth link and second collet are hinged, The second end of the fourth link and second sliding block are hinged, and second sliding block is also slidedly arranged on the 4th guide rail, described Third connecting rod is arranged symmetrically centered on the 4th guide rail with the fourth link.
10. end seal host according to claim 9, which is characterized in that first guide rail to the 4th guide rail is respectively guiding Bar, the first end of first guide rail slidably pass through the first side frame that first collet is fixed on the fixed frame again Wall, the second end of first guide rail slidably pass through second collet be fixed on again the fixed frame with described first The second opposite side frame wall of side frame wall, the first end of the third guide rail slidably pass through first collet be fixed on again it is described First side frame wall, the second end of the third guide rail slidably pass through second collet and are fixed on the second side frame wall again, The first sliding block sliding sleeve is in second guide rail, and the second sliding block sliding sleeve is in the 4th guide rail.
CN201811596437.0A 2018-12-24 2018-12-24 End seal host Expired - Fee Related CN109624287B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811596437.0A CN109624287B (en) 2018-12-24 2018-12-24 End seal host

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811596437.0A CN109624287B (en) 2018-12-24 2018-12-24 End seal host

Publications (2)

Publication Number Publication Date
CN109624287A true CN109624287A (en) 2019-04-16
CN109624287B CN109624287B (en) 2021-09-24

Family

ID=66077608

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811596437.0A Expired - Fee Related CN109624287B (en) 2018-12-24 2018-12-24 End seal host

Country Status (1)

Country Link
CN (1) CN109624287B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114536731A (en) * 2022-02-25 2022-05-27 湖北兴欣科技股份有限公司 Steel mesh reinforced steel-plastic composite pipe two-end simultaneous plastic packaging device

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060119004A1 (en) * 2004-12-02 2006-06-08 Graham Packaging Company, L.P. Method and apparatus for reforming the neck finish end surface of blow molded plastic container
KR20090115401A (en) * 2008-05-02 2009-11-05 주식회사성호철관 Apparatus for setting flange of synthetic resin pipe
CN101683765A (en) * 2008-09-26 2010-03-31 上海汤臣塑胶实业有限公司 Device used for sealing bi-layer axial hollow tube end face
CN102172723A (en) * 2010-12-09 2011-09-07 中山市奥美森工业有限公司 Sealing machine
CN105946213A (en) * 2016-06-15 2016-09-21 隋为民 Manufacturing method and equipment for tube fuse seal of plastic composite tube of steel framework
CN107471531A (en) * 2017-08-30 2017-12-15 浙江伟星新型建材股份有限公司 Multiple tube injection sealing method and apparatus
CN206899777U (en) * 2017-04-25 2018-01-19 湖北兴欣科技股份有限公司 Multiple tube closing device and multiple tube closure system
CN207345076U (en) * 2017-11-03 2018-05-11 广东东方管业有限公司 Tubing sealing machine
CN207509733U (en) * 2017-11-27 2018-06-19 临安磊落塑料厂 Plastic pipe sealing machine

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060119004A1 (en) * 2004-12-02 2006-06-08 Graham Packaging Company, L.P. Method and apparatus for reforming the neck finish end surface of blow molded plastic container
KR20090115401A (en) * 2008-05-02 2009-11-05 주식회사성호철관 Apparatus for setting flange of synthetic resin pipe
CN101683765A (en) * 2008-09-26 2010-03-31 上海汤臣塑胶实业有限公司 Device used for sealing bi-layer axial hollow tube end face
CN102172723A (en) * 2010-12-09 2011-09-07 中山市奥美森工业有限公司 Sealing machine
CN105946213A (en) * 2016-06-15 2016-09-21 隋为民 Manufacturing method and equipment for tube fuse seal of plastic composite tube of steel framework
CN206899777U (en) * 2017-04-25 2018-01-19 湖北兴欣科技股份有限公司 Multiple tube closing device and multiple tube closure system
CN107471531A (en) * 2017-08-30 2017-12-15 浙江伟星新型建材股份有限公司 Multiple tube injection sealing method and apparatus
CN207345076U (en) * 2017-11-03 2018-05-11 广东东方管业有限公司 Tubing sealing machine
CN207509733U (en) * 2017-11-27 2018-06-19 临安磊落塑料厂 Plastic pipe sealing machine

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114536731A (en) * 2022-02-25 2022-05-27 湖北兴欣科技股份有限公司 Steel mesh reinforced steel-plastic composite pipe two-end simultaneous plastic packaging device
CN114536731B (en) * 2022-02-25 2023-06-16 湖北兴欣科技股份有限公司 Device for simultaneously molding and sealing two ends of steel-mesh reinforced steel-plastic composite pipe

Also Published As

Publication number Publication date
CN109624287B (en) 2021-09-24

Similar Documents

Publication Publication Date Title
CN101722218B (en) Forming device in pipe bender
KR101747995B1 (en) Tube system bending machine
CN204770935U (en) Pipe cutting machine
CN201572831U (en) Forming device in pipe bender
CN107626785A (en) A kind of CNC tube bending machine and bending method
CN109551402A (en) Centering synchronous fixture
CN109624287A (en) End seal host
CN115365670A (en) Chuck device for laser pipe cutting machine
CN102126143A (en) Improved clamp structure of band sawing machine
KR101747996B1 (en) 2-Head 2-Radius system bending machine
CN215393723U (en) I-shaped steel arch welding integrated equipment for tunnel
CN207357850U (en) A kind of common curved CNC tube bending machine in left and right
CN207139403U (en) Special material grasping feed system in a kind of machining center
CN109624288A (en) Online automatic end seal machine
CN205764465U (en) A kind of self-centering clamp for laser pipe cutter
CN209716265U (en) A kind of CNC tube bending machine
CN209319241U (en) A kind of tubing bending cutting all-in-one machine
CN106348001A (en) Firefighting mainframe casing moving device used between working tables
CN107138780B (en) A kind of solid tubes face milling, step are machined in integrated processing unit (plant)
CN201693250U (en) Improved clamp structure of band saw machine
CN206185233U (en) Full -automatic bow saw blanking machine
CN209452589U (en) Automatic spinning machine
CN206010016U (en) A kind of clamping and feeding mechanism of planet cut-off
CN216914794U (en) Automatic blow pipe inner hole machining device for automobile inter-cooling pipeline
CN208178800U (en) Rear cross-tube sub-unit welding fixture

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20210621

Address after: 523000 Room 101, No.39, Dali Xinxing 1st Road, Qingxi Town, Dongguan City, Guangdong Province

Applicant after: Li Xuewen

Address before: 523000 2nd floor, building a, 39 Xinxing 1st Road, Dali Village, Qingxi Town, Dongguan City, Guangdong Province

Applicant before: DONGGUAN GUILIU ENVIRONMENTAL TECHNOLOGY Co.,Ltd.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210924

CF01 Termination of patent right due to non-payment of annual fee