CN107241805A - A kind of uplink resource allocating method and device - Google Patents
A kind of uplink resource allocating method and device Download PDFInfo
- Publication number
- CN107241805A CN107241805A CN201710573697.5A CN201710573697A CN107241805A CN 107241805 A CN107241805 A CN 107241805A CN 201710573697 A CN201710573697 A CN 201710573697A CN 107241805 A CN107241805 A CN 107241805A
- Authority
- CN
- China
- Prior art keywords
- resource
- spusch
- dci
- frequency domain
- pusch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04W—WIRELESS COMMUNICATION NETWORKS
- H04W72/00—Local resource management
- H04W72/20—Control channels or signalling for resource management
- H04W72/23—Control channels or signalling for resource management in the downlink direction of a wireless link, i.e. towards a terminal
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04W—WIRELESS COMMUNICATION NETWORKS
- H04W72/00—Local resource management
- H04W72/04—Wireless resource allocation
- H04W72/044—Wireless resource allocation based on the type of the allocated resource
- H04W72/0453—Resources in frequency domain, e.g. a carrier in FDMA
Landscapes
- Engineering & Computer Science (AREA)
- Computer Networks & Wireless Communication (AREA)
- Signal Processing (AREA)
- Mobile Radio Communication Systems (AREA)
Abstract
The embodiments of the invention provide a kind of uplink resource allocating method and device, method includes:As the up shared data channel sPUSCH of communication base station scheduling low time delay, communication base station judges the frequency domain resource where sPUSCH, if scheduled up shared data channel PUSCH takes before the sPUSCH that has been scheduled;If so, then communication base station generates conflicted resource indicating downlink control information DCI, conflicted resource indicates that DCI includes resource informations of the sPUSCH in the upper occupancy of frequency domain, is directed to PUSCH for indicating user terminal, is punched in the PUSCH positions overlapping with sPUSCH;Communication base station sends conflicted resource to user terminal and indicates DCI;User terminal by punching cause transmitted PUSCH no longer take with the equitant band segments of sPUSCH, so as to avoid user terminal the problem of uplink time-frequency domain resources conflict.
Description
Technical field
The present invention relates to wireless communication field, more particularly to a kind of uplink resource allocating method and device.
Background technology
With the high speed development of the communication technology, the various terminals of user, such as:The smart machines such as mobile phone, tablet personal computer all may be used
To carry out the transmission of data message by communication network.And with the construction of 5G communication networks, it is desirable to communication base station and user
There can be higher data transmission bauds between terminal, to support the demand of following substantial amounts of data transfer.
Communication base station to user terminal send control information or transmission data be referred to as data downstream transmission, user terminal to
Communication base station sends control information or transmission data are referred to as data upstream transmission.Uplink and downlink transfer can when
Between on be divided into TTI (Transmission Time Interval, Transmission Time Interval) one by one, a TTI is 1ms,
The scheduler of communication base station can call the frequency domain resource on the communication frequency domain in the 1ms in a TTI, for sending control
Information or transmission data.The resource for being completely used for data transfer that can be dispatched in a TTI is properly termed as a subframe, one
The length of individual subframe is also that data and control information can be included in 1ms, the frame structure of subframe, for example, communication base station can be
Contain PDCCH (Physical Downlink Control Channel, physical down control in n-th of subframe in downlink transfer
Channel processed), PDCCH is used to carry scheduling and other control information, can be individual in the n-th+k of uplink with scheduling user terminal
Subframe sends PUSCH (Physical Uplink Shared Channel, physical uplink Data Shared Channel), and k typically takes 4.
PUSCH is used to send control information or transmission data to communication base station.
In order to improve the data transmission bauds between communication base station and user terminal, original TTI in a communication network
A kind of basis of frame, it is proposed that sTTI (short-Transmission Time Interval, the Transmission Time Interval of shortening)
Frame.The resource that sTTI takes in time domain is less than TTI, for example, can be 0.5ms, can have two sTTI in a TTI.Accordingly
, in uplink or downlink transfer, sPDCCH (short-Physical Downlink can be contained in sTTI
Control Channel, low time delay Physical Downlink Control Channel) or sPUSCH (short-Physical Uplink Shared
Channel, low time delay physical uplink Data Shared Channel), all kinds of control information and data for transmitting low time delay.In reality
In, TTI and sTTI can be used simultaneously, in a sub- frame in, by the scheduling of communication base station, make TTI and sTTI
The resource of used frequency domain is different, i.e., one sub- frame in, and the data that TTI is transmitted use the part in whole frequency ranges,
And the data transmitted in sTTI use the frequency range of another part.
Referring to Fig. 1, ordinate is frequency domain in Fig. 1, and abscissa is time domain, and a TTI length subframes 101 are divided into two
Contained sPUSCH occupies the frequency domain resource of half in sTTI, and two sTTI;Subframe 102, then be not divided into
STTI, its frequency domain resource can be completely shared by PUSCH contained in TTI.
Based on These characteristics, now in the art, when communication network can use TTI and sTTI simultaneously, user terminal exists
During uplink, the problem of frequency domain resource conflicts is likely to result in.For example,
In subframe n, communication base station sends a scheduling control information to the first user terminal, makes the first user terminal in subframe
N+4 sends PUSCH, and now whole available frequency bands on subframe n+4 frequency domains are distributed to the first user terminal by base station;
In next subframe n+1, communication base station receives the control information of second user terminal transmission, the control information
Communication base station is notified, second user terminal needs the sPUSCH to communication base station uplink low time delay, so communication base station meeting
In subframe n+2, the schedule information of low time delay is sent to second user terminal, due to being the schedule information of low time delay, is used
STTI is as Transmission Time Interval, when communication base station scheduling second user terminal is also sent in subframe n+4 to communication base station
During sPUSCH.Now corresponding subframe n+4 all upstream band resources are already allocated to the first user terminal.Due to TTI's
Scheduling decision of the scheduling decision prior to sTTI, TTI frequency domain resource distribution may block sTTI frequency domain resource distribution, so that
Cause uplink frequency domain resources distribution conflict.
The content of the invention
The purpose of the embodiment of the present invention is to provide a kind of uplink resource allocating method and device, to avoid user terminal from existing
The problem of uplink time-frequency domain resources conflict.Concrete technical scheme is as follows:
The embodiment of the invention discloses a kind of uplink resource allocating method, applied to communication base station, including:
As the up shared data channel sPUSCH of communication base station scheduling low time delay, the communication base station judges described
Frequency domain resource where sPUSCH, if scheduled up shared data channel before the sPUSCH that has been scheduled
PUSCH takes;
If so, then the communication base station generates conflicted resource indicating downlink control information DCI, the conflicted resource is indicated
DCI includes resource informations of the sPUSCH in the upper occupancy of frequency domain, the PUSCH is directed to for indicating user terminal, in institute
The PUSCH and sPUSCH equitant positions on frequency domain are stated to be punched;
The communication base station sends the conflicted resource to user terminal and indicates DCI.
Optionally, the conflicted resource indicates that DCI includes default public wireless network temporary mark RNTI, described default
Public RNTI is used to indicate that the cyclic check code CRC in DCI is scrambled to the conflicted resource.
Optionally, the conflicted resource indicates that DCI includes filling data, the conflict money containing the filling data
Source indicates that DCI length is consistent with the DCI length of reference format.
Optionally, it is described if so, then communication base station generation conflicted resource indicating downlink control information DCI, including:
As the multiple sPUSCH on frequency domain consecutive hours, the communication base station is by the multiple sPUSCH in the upper of frequency domain
The resource information of occupancy, merges into a merging resource information;
The communication base station generates the conflicted resource and indicates DCI, and the conflicted resource indicates that DCI includes the merging money
Source information.
The embodiment of the invention discloses a kind of uplink resource allocating method, applied to user terminal, including:
The user terminal receives the conflicted resource indicating downlink control information DCI that communication base station is sent, the conflict money
Source indicates that DCI includes upper occupancy of the low time delay up shared data channel sPUSCH scheduled in the communication base station in frequency domain
Resource information;
The user terminal judges whether PUSCH to be sent;
When the user terminal has PUSCH to be sent, the user terminal judges that the conflicted resource is indicated in DCI
The sPUSCH the upper occupancy in frequency domain resource information, if with the PUSCH to be sent on frequency domain have weight
Folded part;
When the conflicted resource indicates that the resource information of the upper occupancy in frequency domain of the sPUSCH in DCI is treated with described
The PUSCH of transmission on frequency domain have overlapping part when, the user terminal the PUSCH to be sent with it is described
Punched at the position of frequency domain overlapping sPUSCH.
Optionally, after the conflicted resource indicating downlink control information DCI that the user terminal reception communication base station is sent,
Methods described also includes:
When the conflicted resource is indicated in DCI comprising default public wireless network temporary mark RNTI, the user is whole
End indicates that DCI descrambles according to the default public RNTI to the conflicted resource;
The user terminal obtains the upper occupancy in frequency domain of the sPUSCH from the conflicted resource instruction DCI after descrambling
Resource information.
The embodiment of the invention discloses a kind of ascending resource distributor, applied to communication base station, including:
Judge module, for as the communication base station scheduling up shared data channel sPUSCH of low time delay, judging institute
State sPUSCH place frequency domain resource, if scheduled up shared data channel before the sPUSCH that has been scheduled
PUSCH takes;
Generation module, for being adjusted before the sPUSCH that when the frequency domain resource where the sPUSCH, has been scheduled
When the up shared data channel PUSCH of degree takes, conflicted resource indicating downlink control information DCI, the conflicted resource are generated
Indicate that DCI includes resource informations of the sPUSCH in the upper occupancy of frequency domain, the PUSCH be directed to for indicating user terminal,
In the PUSCH and sPUSCH, equitant position is punched on frequency domain;
Sending module, DCI is indicated for sending the conflicted resource to user terminal.
The embodiment of the invention discloses a kind of ascending resource distributor, applied to user terminal, including:
Receiving module, the conflicted resource indicating downlink control information DCI for receiving communication base station transmission, the conflict money
Source indicates that DCI includes upper occupancy of the low time delay up shared data channel sPUSCH scheduled in the communication base station in frequency domain
Resource information;
First judge module, for judging whether PUSCH to be sent;
Second judge module, for when the user terminal has PUSCH to be sent, judging that the conflicted resource refers to
Show the resource information of the upper occupancy in frequency domain of the sPUSCH in DCI, if with the PUSCH to be sent on frequency domain
With overlapping part;
Perforating module, the money of the upper occupancy in frequency domain for indicating the sPUSCH in DCI when the conflicted resource
When source information and the PUSCH to be sent have overlapping part on frequency domain, the PUSCH to be sent with it is described
Punched at the position of frequency domain overlapping sPUSCH.
The embodiment of the invention discloses a kind of communication base station, including processor, communication interface, memory and communication bus,
Wherein, processor, communication interface, memory completes mutual communication by communication bus;
Memory, for depositing computer program;
Processor, for performing during the program deposited on memory, is applied to lead to for realizing in the embodiment of the present invention
Believe the uplink resource allocating method of base station.
The embodiment of the invention discloses a kind of user terminal, including processor, communication interface, memory and communication bus,
Wherein, processor, communication interface, memory completes mutual communication by communication bus;
Memory, for depositing computer program;
Processor, for performing during the program deposited on memory, is applied to use for realizing in the embodiment of the present invention
The uplink resource allocating method of family terminal.
A kind of uplink resource allocating method and device provided in an embodiment of the present invention, in embodiments of the present invention, work as communication
During base station scheduling sPUSCH, the frequency domain resource where scheduled sPUSCH is judged, if institute before the sPUSCH that has been scheduled
The PUSCH of scheduling takes;If the frequency domain resource where sPUSCH is taken by PUSCH scheduled before, communicate base
Stand generation conflicted resource indicating downlink control information DCI, and sends conflicted resource instruction DCI to user terminal.User terminal
The resource information of the sPUSCH that contains in DCI in the upper occupancy of frequency domain is indicated according to the conflicted resource, for PUSCH, in PUSCH
Equitant position carries out punching by punching so that transmitted PUSCH no longer takes and sPUSCH phases on frequency domain with sPUSCH
Overlapping band segment, so as to avoid user terminal the problem of uplink time-frequency domain resources conflict.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing
There is the accompanying drawing used required in technology description to be briefly described.
Fig. 1 provides PUSCH and sPUSCH structural representation for the embodiment of the present invention;
Fig. 2 is the flow chart of the uplink resource allocating method provided in an embodiment of the present invention applied to communication base station;
The schematic diagram that Fig. 3 conflicts for generation ascending resource distribution provided in an embodiment of the present invention;
Fig. 4 is the schematic diagram that sPUSCH provided in an embodiment of the present invention and multiple PUSCH overlap in frequency domain;
Fig. 5 is continuous sPUSCH schematic diagrames on multiple frequency domains provided in an embodiment of the present invention;
Fig. 6 is the flow chart of the uplink resource allocating method provided in an embodiment of the present invention applied to user terminal;
Fig. 7 is the schematic diagram that communication base station provided in an embodiment of the present invention is interacted with user terminal;
Fig. 8 is the structure chart of the ascending resource distributor provided in an embodiment of the present invention applied to communication base station;
Fig. 9 is the structure chart of the ascending resource distributor provided in an embodiment of the present invention applied to user terminal;
Figure 10 is the structural representation of communication base station provided in an embodiment of the present invention;
Figure 11 is the structural representation of user terminal provided in an embodiment of the present invention.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on
Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made
Embodiment, belongs to the scope of protection of the invention.
Referring to Fig. 2, Fig. 2 is the uplink resource allocating method flow provided in an embodiment of the present invention applied to communication base station
Figure, including:
Step 201, as the up shared data channel sPUSCH of communication base station scheduling low time delay, communication base station judges
Frequency domain resource where sPUSCH, if scheduled up shared data channel PUSCH is accounted for before the sPUSCH that has been scheduled
With.
When carrying out the transmission communication of data, communication base station can send to contain to each user terminal to be used to dispatch user
Terminal sends the control information of various information, for example, PDCCH or sPDCCH etc..When user terminal receives the control information
When, it is possible to according to the instruction of the control information, corresponding data and control information are uploaded to communication base station.User terminal is to logical
The data and control information that letter base station is uploaded can be carried by sPUSCH or PUSCH.Communication base station by above-mentioned mode,
The scheduling to sPUSCH or PUSCH can be realized.
When communication base station scheduling user terminal is in a sTTI, and sPUSCH is sent to communication base station, communication base station can
First to judge the frequency domain resource on the sTTI where scheduled sPUSCH, if shared by PUSCH scheduled before
With.
For example, with reference to Fig. 3, in subframe 301 in Fig. 3, communication base station uses downlink transfer, sends and controls to each user terminal
Information processed, e.g., the PDCCH containing scheduling control information use uplink, in subframe 301 for dispatching the first user terminal
During the 4th subframe 305 afterwards, PUSCH is sent to communication base station, and the whole frequency domain resource of subframe 305 is distributed on the
One user terminal sends PUSCH;
In subframe 303, communication base uses downlink transfer, and control information is sent to each user terminal, and scheduling second is used
Family terminal uses uplink, also in subframe 305, and sPUSCH is sent to communication base station.
Now, communication base station is when dispatching sPUSCH, it can be determined that go out, in the subframe 305 where scheduled sPUSCH
Frequency domain resource, scheduled PUSCH, the i.e. frequency domain resource of the subframe 305 be before being allocated for sending before
Through being distributed on the first user terminal, for sending PUSCH.
Specifically, communication base station can judge scheduled sPUSCH institutes using the modes such as record, or daily record are inquired about
Frequency domain resource, if by institute before scheduling PUSCH shared by.
Step 202, if so, then communication base station generates conflicted resource indicating downlink control information DCI, conflicted resource is indicated
DCI include sPUSCH the upper occupancy of frequency domain resource information, for indicating user terminal be directed to the PUSCH, PUSCH with
SPUSCH is punched the equitant position on frequency domain.
When communication base station is judged, the frequency domain resource where scheduled sPUSCH, institute before the sPUSCH that has been scheduled
When the PUSCH of scheduling takes, communication base station can generate a conflicted resource and indicate DCI.
DCI can be carried by PDCCH, when communication base station to user terminal transmitted by Downlink Control Information, can include
Up-downgoing resource allocation, HARQ (Hybrid Automatic Repeat reQuest, hybrid automatic repeat-request) information, work(
Rate control etc..
When conflicted resource indicates that DCI is used exclusively for solving user terminal to communication base station transmission sPUSCH or PUSCH, on
Row resource allocation produces Downlink Control Information during conflict.
In conflicted resource indicates DCI, resource informations of one or more sPUSCH in the upper occupancy of frequency domain can be included,
Send specific frequency band range used in the sPUSCH., can be with after user terminal, which receives the conflicted resource, indicates DCI
The resource information of sPUSCH in DCI in the upper occupancy of frequency domain is indicated according to conflicted resource, to transmitted, and with this
The PUSCH that in uplink frequency domain resource conflict occurs for sPUSCH is punched so that the PUSCH transmitted by user terminal is not
Take again with the equitant frequency domain resources of sPUSCH, so as to avoid during uplink, sPUSCH is provided with PUSCH frequency domains
Source is to the problem of conflict.
Transmitted data or control information are punched, are to remove part to transmitted data or control information to use
In the data or information of scrambling, the integrality of the data to be sent or control information can't be destroyed, belongs to prior art,
This is repeated no more.In embodiments of the present invention, user terminal is punched to transmitted PUSCH, can sending
During PUSCH, the frequency domain resource being perforated is not used.And then avoid PUSCH and sPUSCH frequency domain resource overlap and
Conflict.
Step 303, communication base station sends the conflicted resource to user terminal and indicates DCI.
Communication base station is generated after conflicted resource instruction DCI, it is possible to is sent the conflicted resource to user terminal and is indicated
DCI.Communication base station can be sent using the form of the broadcast user terminal all into the communication base station institute coverage to be contained
The conflicted resource indicates DCI information.User terminal can obtain communication base station transmitted information, and therefrom obtain the conflict
Resource indicate DCI and other be used for dispatch control information of the user terminal etc..
User terminal is obtained after conflicted resource instruction DCI, it can be determined that whether have PUSCH to be sent, if
DCI is indicated without the conflicted resource that can then abandon receiving, without subsequent treatment;
If there is PUSCH to be sent, then judge conflicted resource indicate one or more of DCI sPUSCH in frequency
The resource information of the upper occupancy in domain, if there is overlapping part on frequency domain with PUSCH to be sent, if without overlapping
Part, then can abandon the conflicted resource and indicate DCI, without subsequent treatment;
When conflicted resource indicates the resource information and PUSCH to be sent of the upper occupancy in frequency domain of the sPUSCH in DCI
When having overlapping part on frequency domain, user terminal can be directed to the PUSCH to be sent, to the PUSCH and sPUSCH weights
Punched at the position of folded frequency domain, user terminal is no longer to take and the equitant parts of sPUSCH sending the PUSCH
Frequency range, it is to avoid during uplink PUSCH with sPUSCH conflicting in frequency domain resource.
In embodiments of the present invention, when communication base station dispatches sPUSCH, the frequency domain where scheduled sPUSCH is judged
Resource, if scheduled PUSCH takes before the sPUSCH that has been scheduled;If the frequency domain resource is by scheduled before
PUSCH take, then communication base station generation conflicted resource indicating downlink control information DCI, and sends the conflict to user terminal
Resource indicates DCI.User terminal indicates that the sPUSCH contained in DCI believes in the resource of the upper occupancy of frequency domain according to the conflicted resource
Breath, for PUSCH, in PUSCH and sPUSCH, equitant position is punched on frequency domain, is caused by punching transmitted
PUSCH no longer take with the equitant band segments of sPUSCH, so as to avoid user terminal uplink time-frequency domain provide
The problem of source conflicts.
Optionally, in uplink resource allocating method provided in an embodiment of the present invention, conflicted resource indicates that DCI includes in advance
If public RNTI (Radio Network Tempory Identity, Radio Network Temporary Identifier), presetting public RNTI is used for
Cyclic check code CRC in DCI, which is scrambled, to be indicated to conflicted resource.
In actual applications, with multiple PUSCH frequency domain resource may occur for the sPUSCH scheduled in communication base station simultaneously
Conflict, and multiple PUSCH are transmitted by different user terminals.For example, with reference to Fig. 4, Fig. 4 represents a TTI subframe, should
TTI subframes can be divided into two sTTI, and wherein ordinate represents frequency domain, and abscissa represents time domain, and region 401 is the first use
Family terminal the first PUSCH to be sent, region 402 is second user terminal the 2nd PUSCH to be sent, and region 403 is the 3rd
User terminal sPUSCH to be sent, it is seen that region 403, while occupying the portion in region 401 and region 402, i.e.,
SPUSCH there occurs overlapping with the first PUSCH and the 2nd PUSCH frequency domain.
In this case, if for each transmission PUSCH user terminal, individually producing a conflicted resource and referring to
Show DCI, then can greatly increase the portfolio of communication base station.
DCI is indicated in order to generate unified conflicted resource for multiple different user terminals, can be in conflicted resource
Indicate in DCI using default public RNTI.It is public user's mark to preset public RNTI, by the public identifier, can be with
The conflicted resource that communication base station is generated indicates that DCI is recognized by whole user terminals of this cell.And make
Obtain each user terminal and may determine that the DCI indicates DCI for conflicted resource.
Preset public RNTI can be used for conflicted resource indicate DCI middle CRC (Cyclic Redundancy Check,
Cyclic check code) scrambled.CRC is a kind of a kind of hash function that brief fixed digit check code is produced according to data, main
To be used for the mistake detected or verification data is transmitted or is likely to occur after preserving.
Scramble, the data transmitted can be encrypted to presetting the CRC in public RNTI.Can only have
The user terminal of corresponding descrambling capabilities can be obtained and identified indicates DCI containing the conflicted resource for presetting public RNTI.Tool
Body, the method for scrambling belongs to prior art, will not be repeated here.
Conflicted resource indicates DCI as a kind of DCI of new definition, the DCI that its structure length etc. may be with reference format, example
Such as " DCI 0 ", " DCI 1A " DCI formats difference, so that user terminal blind check DCI number of times can be increased.
In order to avoid user terminal increases the blind check number of times for DCI, in ascending resource provided in an embodiment of the present invention point
In method of completing the square, the conflicted resource indicates that DCI includes filling data, and the conflicted resource containing filling data indicates DCI length
Degree is consistent with the DCI length of reference format.
Because filling data do not have specific meaning, so filling data can be arbitrary data mode, and
In indicating DCI in conflicted resource, resource informations of one or more sPUSCH in the upper occupancy of frequency domain may be contained, so
Conflicted resource indicates that the length of the filling data in DCI is not also fixed.As long as ensureing that generated conflicted resource indicates DCI's
Length is consistent with the DCI length of reference format.
For example, with reference to table 1, table 1 is a kind of structure type that conflicted resource indicates DCI.
Table 1
In table 1 containing three sPUSCH the upper occupancy of frequency domain resource information, and containing preset public RNTI, preset
Public RNTI is used to indicate that the CRC in DCI is scrambled to the conflicted resource.
Conflicted resource indicates that each information can represent that first three field is used to refer in table 1 with a field in DCI
Show resource informations of each sPUSCH of user terminal in the upper occupancy of frequency domain, DCI is indicated due to conflicted resource and adjusted for up
The DCI format 0 of degree is compared, the field except indicating resource information, and conflicted resource indicates no longer to include DCI lattice in DCI form
Other fields in formula 0.Therefore, multiple sPUSCH resource information can be included in the form that conflicted resource indicates DCI
Field.For example, when upstream bandwidth is 20MHz, the resource of resource allocation is that other field lengths in 13 bits, DCI format 0 are tired out
Meter can accommodate the field of second resource information;When upstream bandwidth is less than 20MHz, as resource allocation field subtracts in proportion
It is few, and the length of other fields is fixed, other field lengths are accumulative can to accommodate more than two sPUSCH resources instruction
Field.
Filling data cause the conflicted resource to indicate that DCI length is identical with the DCI length of reference format.It is readily appreciated that
It is that the conflicted resource described in table 1 indicates that DCI structure type is only a kind of schematical structure type, in actual applications
It can also as needed be adjusted, as long as disclosure satisfy that the function of conflicted resource instruction DCI in the embodiment of the present invention, then all may be used
To be used as available structure type.
Optionally, in uplink resource allocating method provided in an embodiment of the present invention, it is characterised in that described if so, then
The communication base station generates conflicted resource indicating downlink control information DCI, including:
As multiple sPUSCH on frequency domain consecutive hours, communication base station by multiple sPUSCH the upper occupancy of frequency domain resource believe
Breath, merges into a merging resource information.
Communication base station generates the conflicted resource and indicates DCI, and the conflicted resource indicates that DCI includes the merging resource letter
Breath.
As shown in figure 5, Fig. 5 represents a TTI subframe, the TTI subframes can be divided into two sTTI, wherein ordinate
Frequency domain is represented, abscissa represents time domain, and region 501 is the first user terminal the first PUSCH to be sent, and region 502 is second
User terminal the 2nd PUSCH to be sent, region 503 is the 3rd user terminal the first sPUSCH to be sent, and region 504 is the
Four user terminals the 2nd sPUSCH to be sent, it is seen that region 503 and region 504, on the vertical scale continuously, that is to say, that first
SPUSCH and the 2nd sPUSCH are continuous on frequency domain.
In this case, communication base station merges into one by multiple sPUSCH in the resource information of the upper occupancy of frequency domain
Merge resource information, so can be when the conflicted resource of generation indicates DCI, it is not necessary to a plurality of sPUSCH occur in frequency domain
The resource information of upper occupancy, can only include a merging resource information.
For example, for the subframe shown in Fig. 5, if wherein the first sPUSCH and the 2nd sPUSCH resource information not by
A merging resource information is merged into, then the conflicted resource produced indicates that DCI can be as shown in table 2,
Table 2
When the first sPUSCH and the 2nd sPUSCH resource information is merged into one article of merging resource information, then what is produced rushes
Prominent resource indicates that DCI can be as shown in table 3,
Table 3
When conflicted resource indicates that one is comprised only in DCI merges resource information, each user terminal can be according to the conjunction
And resource information is punched.It is overlapping with the PUSCH phases transmitted by this user terminal without being found out in a plurality of resource information
Folded sPUSCH resource information, is then punched in the resource information according to the sPUSCH.It is whole so as to improve each user
The efficiency at end, and then improve the efficiency of whole data transmission network.
Referring to Fig. 6, Fig. 6 is the flow of the uplink resource allocating method provided in an embodiment of the present invention applied to user terminal
Figure, including:
Step 601, user terminal receives the conflicted resource indicating downlink control information DCI that communication base station is sent, conflict money
Source indicates that DCI includes resources of the up shared data channel sPUSCH of low time delay scheduled in communication base station in the upper occupancy of frequency domain
Information.
Each user terminal hair of the communication base station typically using the form of broadcast into cell or in base station range
Various types of data and information are sent, user terminal can receive communication base station in real time and send Various types of data and information.And pass therethrough
It is various to be used to distinguish mark of user etc., obtain data and information for different user terminals.
In embodiments of the present invention, user terminal receives the data and information transmitted by communication base station, and therefrom extracts
Conflicted resource indicates DCI.The conflicted resource is indicated in DCI containing one or more sPUSCH scheduled in communication base station in frequency domain
Upper occupancy resource information.
Step 602, user terminal judges whether PUSCH to be sent.
User terminal is received after conflicted resource instruction DCI, it can be determined that whether need what is sent to communication terminal
PUSCH, the PUSCH can send conflicted resource instruction DCI forward direction scheduling of user terminals, and user for communication base station
Terminal is receiving the PUSCH that conflicted resource indicates not send also after DCI.
Step 603, when user terminal has PUSCH to be sent, user terminal judges that conflicted resource is indicated in DCI
The resource information of the sPUSCH upper occupancy in frequency domain, if there is overlapping part on frequency domain with PUSCH to be sent.
When user terminal has PUSCH to be sent, user terminal is obtained wherein in can indicating DCI from conflicted resource
The resource information of the contained one or more sPUSCH upper occupancy in frequency domain.Frequency domain shared by PUSCH to be sent
Resource is known for user terminal, so user terminal can indicate each in DCI according to conflicted resource
The resource information of the sPUSCH upper occupancy in frequency domain, judges PUSCH to be sent on frequency domain, be by with it is one or more
SPUSCH has overlapping afoul part.
Step 604, when conflicted resource indicate DCI in sPUSCH the upper occupancy in frequency domain resource information with it is to be sent
PUSCH on frequency domain have overlapping part when, user terminal is in the position of frequency domain overlapping with sPUSCH PUSCH to be sent
Put place's punching.
User terminal pin is to sent PUSCH, at the position of frequency domain overlapping with sPUSCH the PUSCH to be sent
After punching, when sending the PUSCH to be sent, the part frequency domain resource by punching is not used, using only not being perforated
Frequency domain resource be transmitted.While ensure PUSCH to be sent integrality, it is to avoid PUSCH and sPUSCH frequency domain
Resource overlaps and conflicted.
In actual applications, the conflicted resource that user terminal is received is indicated can be comprising default public wireless net in DCI
Network temporary mark RNTI, this presets the user terminal that public RNTI can be used for distinguishing the cell that communication base station is covered, i.e., originally
The user terminal of cell can preset public RNTI by this, and punching is determined in the Various types of data and information broadcasted from communication base station
Prominent resource indicates DCI.
And the CRC in DCI, which is scrambled, to be indicated to conflicted resource due to this can be used to preset public RNTI, so with
Family terminal can use the descrambling mode corresponding with presetting public RNTI to liquidate after conflicted resource instruction DCI is received
Prominent resource indicates that DCI is descrambled.And from after descrambling conflicted resource indicate DCI in obtain one or more sPUSCH
The resource information of the upper occupancy of frequency domain.Wherein, when the resource information of the multiple sPUSCH upper occupancy in frequency domain connects on frequency domain
When continuous, it can be merged in conflicted resource indicates DCI with the resource information of a upper occupancy in frequency domain by multiple sPUSCH
Merging resource information together describes the resource information of the multiple sPUSCH upper occupancy in frequency domain.
Referring to Fig. 7, Fig. 7 is the schematic diagram that communication base station provided in an embodiment of the present invention is interacted with user terminal, including:
Step one, communication base station scheduling sPUSCH.
Communication base station sends the first PUSCH what subframe n dispatched the first user terminal and second user terminal in subframe n+4
With the 2nd PUSCH data.
In subframe n+1, communication base station learns that the 3rd user terminal and fourth user terminal send the first sPUSCH and second
SPUSCH demand, so that in subframe n+2, communication base station is dispatched the 3rd user terminal and fourth user terminal and sent out in subframe n+4
Send the first sPUSCH and the 2nd sPUSCH data.
Step 2, communication base station judges scheduled sPUSCH, if exist with PUSCH scheduled before scheduling sPUSCH
Mutually conflict in frequency domain resource.
Communication base station is by judging it is known that the first sPUSCH and the 2nd sPUSCH and scheduled before first
PUSCH and the 2nd PUSCH mutually conflict in frequency domain resource.Its specific frequency domain occupancy situation is as shown in Figure 5.
Step 3, communication base station generates and sends conflicted resource and indicates DCI.
Scheduled PUSCH phases in frequency domain resource before the sPUSCH scheduled in communication base station, with scheduling sPUSCH
Conflict.Communication base station generates a conflicted resource and indicates DCI, and the conflicted resource indicates that DCI CRC enters by presetting public RNTI
Row scrambling, and due to the first sPUSCH and the 2nd sPUSCH on frequency domain it is continuous, so the conflicted resource indicates that DCI contains the
Merging resource informations of one sPUSCH and the 2nd sPUSCH after the resource information of the upper occupancy of frequency domain merges.In order that the conflict
Resource indicates that DCI is consistent with the DCI length of reference format, and the conflicted resource indicates that DCI also includes a number of filling data.
After conflicted resource instruction DCI is generated, communication base station sends the conflicted resource to each user terminal and indicated
DCI, so that user terminal indicates that merging resource information contained in DCI is entered to transmitted PUSCH according to the conflicted resource
Row punching.
Step 4, user terminal receives conflicted resource and indicates DCI.
First user terminal and second user terminal receive the conflicted resource and indicate DCI, because communication base station is in subframe n
+ 2 conflicted resources sent indicate DCI, so the first user terminal and second user terminal can be in subframe n+2 or subframe n+3
Receive the conflicted resource and indicate DCI.
Step 5, user terminal descrambling conflicted resource indicates DCI.
First user terminal and second user terminal receive the conflicted resource and indicated after DCI, it is possible to use and the punching
Prominent resource indicates that the default public RNTI in DCI thinks corresponding descrambling mode, indicates that DCI descrambles to the conflicted resource, and
Obtained from the conflicted resource instruction DCI after descrambling and merge resource information.
Step 6, user terminal is punched to PUSCH.
First user terminal and second user terminal judge communication according to the merging resource information obtained in previous step
The first sPUSCH and the 2nd sPUSCH scheduled in base station, respectively first PUSCH to be sent with the first user terminal and
Two user terminals the 2nd PUSCH to be sent, overlaps and conflicts on frequency domain.
So the first user terminal and second user terminal are according to the merging resource information, respectively in the first sPUSCH,
Two sPUSCH merge with this to be punched at position of equitant frequency domain resource of resource information so that transmitted by subframe n+4
During the first sPUSCH and two sPUSCH, the first sPUSCH and the 2nd sPUSCH are not used and the first sPUSCH and second
SPUSCH equitant frequency domain resources, it is to avoid PUSCH overlaps and conflicted with sPUSCH frequency domain resource.
Referring to Fig. 8, Fig. 8 is the structure of the ascending resource distributor provided in an embodiment of the present invention applied to communication base station
Figure, including:
Judge module 801, for as the communication base station scheduling up shared data channel sPUSCH of low time delay, judging
Frequency domain resource where the sPUSCH, if scheduled up shared data channel before the sPUSCH that has been scheduled
PUSCH takes;
Generation module 802, for institute before the sPUSCH that when the frequency domain resource where the sPUSCH, has been scheduled
When the up shared data channel PUSCH of scheduling takes, conflicted resource indicating downlink control information DCI, the conflict money are generated
Source indicates that DCI includes resource informations of the sPUSCH in the upper occupancy of frequency domain, for indicating user terminal for described
PUSCH, in the PUSCH and sPUSCH, equitant position is punched on frequency domain;
Sending module 803, DCI is indicated for sending the conflicted resource to user terminal.
In embodiments of the present invention, when communication base station dispatches sPUSCH, the frequency domain where scheduled sPUSCH is judged
Resource, if scheduled PUSCH takes before the sPUSCH that has been scheduled;If frequency domain resource where sPUSCH by
Before scheduled PUSCH takes, then communication base station generation conflicted resource indicating downlink control information DCI, and to user terminal
Send the conflicted resource and indicate DCI.User terminal indicates that the sPUSCH contained in DCI is accounted on frequency domain according to the conflicted resource
Resource information, for PUSCH, in PUSCH and sPUSCH, equitant position is punched and made by punching on frequency domain
Transmitted PUSCH no longer take with the equitant band segments of sPUSCH, so as to avoid user terminal in uplink
The problem of time-frequency domain resources conflict.
Optionally, in ascending resource distributor provided in an embodiment of the present invention, the institute in the generation module 802
State conflicted resource and indicate that DCI includes default public wireless network temporary mark RNTI, it is described to preset public RNTI for institute
State conflicted resource and indicate that the cyclic check code CRC in DCI is scrambled.
Optionally, in ascending resource distributor provided in an embodiment of the present invention, the institute in the generation module 802
State conflicted resource indicate DCI include fill data, containing it is described filling data the conflicted resource indicate DCI length and
The DCI length of reference format is consistent.
Optionally, in ascending resource distributor provided in an embodiment of the present invention, the generation module 802 is specifically used
In:As the multiple sPUSCH on frequency domain consecutive hours, by the multiple sPUSCH the upper occupancy of frequency domain resource information, close
And be a merging resource information;And the conflicted resource instruction DCI is generated, the conflicted resource indicates that DCI includes described close
And resource information.
Referring to Fig. 9, Fig. 9 is the structure of the ascending resource distributor provided in an embodiment of the present invention applied to user terminal
Figure, including:
Receiving module 901, the conflicted resource indicating downlink control information DCI for receiving communication base station transmission, the punching
The up shared data channel sPUSCH of low time delay that prominent resource indicates DCI and included scheduled in the communication base station is accounted on frequency domain
Resource information;
First judge module 902, for judging whether PUSCH to be sent;
Second judge module 903, for when the user terminal has PUSCH to be sent, judging the conflict money
Source indicates the resource information of the upper occupancy in frequency domain of the sPUSCH in DCI, if with the PUSCH to be sent in frequency
There is overlapping part on domain;
Perforating module 904, for the upper occupancy in frequency domain as the sPUSCH in conflicted resource instruction DCI
When resource information and the PUSCH to be sent have overlapping part on frequency domain, the PUSCH to be sent with it is described
Punched at the position of frequency domain overlapping sPUSCH.
In embodiments of the present invention, user terminal pin is to sent PUSCH, in the PUSCH and sPUSCH to be sent
After being punched at the position of overlapping frequency domain, when sending the PUSCH to be sent, the part frequency domain money by punching is not used
Source, is transmitted using only the frequency domain resource not being perforated.While ensureing PUSCH to be sent integrality, it is to avoid
PUSCH overlaps and conflicted with sPUSCH frequency domain resource.
Optionally, in ascending resource distributor provided in an embodiment of the present invention, described device also includes:
Descrambling module, for being indicated when the conflicted resource in DCI comprising default public wireless network temporary mark RNTI
When, DCI, which descrambles, to be indicated to the conflicted resource according to the default public RNTI;And indicated from the conflicted resource after descrambling
The resource information of the upper occupancy in frequency domain of the sPUSCH is obtained in DCI.
For device embodiment, because it is substantially similar to embodiment of the method, so description is fairly simple, it is related
Part illustrates referring to the part of embodiment of the method.
As shown in Figure 10, the embodiment of the present invention additionally provides a kind of communication base station 1000, including processor 1001, communication
Interface 1002, memory 1003 and communication bus 1004, wherein, processor 1001, communication interface 1002, memory 1003 passes through
Communication bus 1004 completes mutual communication,
Memory 1003, for depositing computer program;
Processor 1001, for performing during the program deposited on memory 1003, realizes following steps:
As the up shared data channel sPUSCH of communication base station scheduling low time delay, the communication base station judges described
Frequency domain resource where sPUSCH, if scheduled up shared data channel before the sPUSCH that has been scheduled
PUSCH takes;
If so, then the communication base station generates conflicted resource indicating downlink control information DCI, the conflicted resource is indicated
DCI includes resource informations of the sPUSCH in the upper occupancy of frequency domain, the PUSCH is directed to for indicating user terminal, in institute
The PUSCH and sPUSCH equitant positions on frequency domain are stated to be punched;
The communication base station sends the conflicted resource to user terminal and indicates DCI.
As shown in figure 11, the embodiment of the present invention additionally provides a kind of user terminal 1100, including processor 1101, communication connect
Mouth 1102, memory 1103 and communication bus 1104, wherein, processor 1101, communication interface 1102, memory 1103 passes through logical
Letter bus 1104 completes mutual communication,
Memory 1103, for depositing computer program;
Processor 1101, for performing during the program deposited on memory 1103, realizes following steps:
The user terminal receives the conflicted resource indicating downlink control information DCI that communication base station is sent, the conflict money
Source indicates that DCI includes upper occupancy of the low time delay up shared data channel sPUSCH scheduled in the communication base station in frequency domain
Resource information;
The user terminal judges whether PUSCH to be sent;
When the user terminal has PUSCH to be sent, the user terminal judges that the conflicted resource is indicated in DCI
The sPUSCH the upper occupancy in frequency domain resource information, if with the PUSCH to be sent on frequency domain have weight
Folded part;
When the conflicted resource indicates that the resource information of the upper occupancy in frequency domain of the sPUSCH in DCI is treated with described
The PUSCH of transmission on frequency domain have overlapping part when, the user terminal the PUSCH to be sent with it is described
Punched at the position of frequency domain overlapping sPUSCH.
The communication bus mentioned in above-mentioned communication base station 1000 and user terminal 1100 can be Peripheral Component Interconnect standard
(Peripheral Pomponent Interconnect, abbreviation PCI) bus or EISA (Extended
Industry Standard Architecture, abbreviation EISA) bus etc..The communication bus can be divided into address bus, number
According to bus, controlling bus etc..For ease of representing, only represented in figure with a thick line, it is not intended that only one bus or one
The bus of type.
The communication that communication interface is used between above-mentioned electronic equipment and other equipment.
Memory can include random access memory (Random Access Memory, abbreviation RAM), can also include
Nonvolatile memory (non-volatile memory), for example, at least one magnetic disk storage.Optionally, memory may be used also
To be storage device that at least one is located remotely from aforementioned processor.
Above-mentioned processor can be general processor, including central processing unit (Central Processing Unit,
Abbreviation CPU), network processing unit (Ne twork Processor, abbreviation NP) etc.;It can also be digital signal processor
(Digital Signal Processing, abbreviation DSP), application specific integrated circuit (Applica tion Specific
Integrated Circuit, abbreviation ASIC), field programmable gate array (Field-Programmable Gate Array,
Abbreviation FPGA) or other PLDs, discrete gate or transistor logic, discrete hardware components.
In the another embodiment that the present invention is provided, a kind of computer-readable recording medium is additionally provided, the computer can
The instruction that is stored with storage medium is read, when run on a computer so that computer performs any institute in above-described embodiment
The uplink resource allocating method stated.
In the above-described embodiments, it can come real wholly or partly by software, hardware, firmware or its any combination
It is existing.When implemented in software, it can realize in the form of a computer program product whole or in part.The computer program
Product includes one or more computer instructions.When loading on computers and performing the computer program instructions, all or
Partly produce according to the flow or function described in the embodiment of the present invention.The computer can be all-purpose computer, special meter
Calculation machine, computer network or other programmable devices.The computer instruction can be stored in computer-readable recording medium
In, or the transmission from a computer-readable recording medium to another computer-readable recording medium, for example, the computer
Instruction can pass through wired (such as coaxial cable, optical fiber, numeral from web-site, computer, server or data center
User's line (DSL)) or wireless (such as infrared, wireless, microwave) mode to another web-site, computer, server or
Data center is transmitted.The computer-readable recording medium can be any usable medium that computer can be accessed or
It is comprising data storage devices such as one or more usable mediums integrated server, data centers.The usable medium can be with
It is magnetic medium, (for example, floppy disk, hard disk, tape), optical medium (for example, DVD) or semiconductor medium (such as solid state hard disc
Solid State Disk (SSD)) etc..
It should be noted that herein, such as first and second or the like relational terms are used merely to a reality
Body or operation make a distinction with another entity or operation, and not necessarily require or imply these entities or deposited between operating
In any this actual relation or order.Moreover, term " comprising ", "comprising" or its any other variant are intended to
Nonexcludability is included, so that process, method, article or equipment including a series of key elements not only will including those
Element, but also other key elements including being not expressly set out, or also include being this process, method, article or equipment
Intrinsic key element.In the absence of more restrictions, the key element limited by sentence "including a ...", it is not excluded that
Also there is other identical element in process, method, article or equipment including the key element.
Each embodiment in this specification is described by the way of related, identical similar portion between each embodiment
Divide mutually referring to what each embodiment was stressed is the difference with other embodiment.It is real especially for system
Apply for example, because it is substantially similar to embodiment of the method, so description is fairly simple, related part is referring to embodiment of the method
Part explanation.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the scope of the present invention.It is all
Any modification, equivalent substitution and improvements made within the spirit and principles in the present invention etc., are all contained in protection scope of the present invention
It is interior.
Claims (10)
1. a kind of uplink resource allocating method, it is characterised in that applied to communication base station, including:
As the up shared data channel sPUSCH of communication base station scheduling low time delay, the communication base station judges described
Frequency domain resource where sPUSCH, if scheduled up shared data channel before the sPUSCH that has been scheduled
PUSCH takes;
If so, then the communication base station generates conflicted resource indicating downlink control information DCI, the conflicted resource indicates DCI bags
Resource informations of the sPUSCH in the upper occupancy of frequency domain is included, the PUSCH is directed to for indicating user terminal, described
The PUSCH and sPUSCH is punched the equitant position on frequency domain;
The communication base station sends the conflicted resource to user terminal and indicates DCI.
2. according to the method described in claim 1, it is characterised in that the conflicted resource indicates that DCI includes presetting public nothing
Line Network Temporary Identifier RNTI, the default public RNTI is for indicating the conflicted resource cyclic check code CRC in DCI
Scrambled.
3. according to the method described in claim 1, it is characterised in that the conflicted resource indicates that DCI includes filling data, contains
The conflicted resource for having the filler evidence indicates that DCI length is consistent with the DCI length of reference format.
4. any method according to claims 1 to 3, it is characterised in that described if so, the then communication base station generation
Conflicted resource indicating downlink control information DCI, including:
As the multiple sPUSCH on frequency domain consecutive hours, the communication base station by the multiple sPUSCH frequency domain upper occupancy
Resource information, merge into one merging resource information;
The communication base station generates the conflicted resource and indicates DCI, and the conflicted resource indicates that DCI includes the merging resource letter
Breath.
5. a kind of uplink resource allocating method, it is characterised in that applied to user terminal, including:
The user terminal receives the conflicted resource indicating downlink control information DCI that communication base station is sent, and the conflicted resource refers to
Show that DCI includes resources of the up shared data channel sPUSCH of low time delay scheduled in the communication base station in the upper occupancy of frequency domain
Information;
The user terminal judges whether PUSCH to be sent;
When the user terminal has PUSCH to be sent, the user terminal judges that the conflicted resource indicates the institute in DCI
State the resource information of the sPUSCH upper occupancy in frequency domain, if with the PUSCH to be sent on frequency domain have it is overlapping
Part;
When the conflicted resource indicate DCI in the sPUSCH the upper occupancy in frequency domain resource information with it is described to be sent
PUSCH on frequency domain have overlapping part when, the user terminal the PUSCH to be sent and the sPUSCH weight
Punched at the position of folded frequency domain.
6. method according to claim 5, it is characterised in that the user terminal receives the conflict money that communication base station is sent
After the indicating downlink control information DCI of source, methods described also includes:
When the conflicted resource is indicated in DCI comprising default public wireless network temporary mark RNTI, the user terminal root
DCI, which descrambles, to be indicated to the conflicted resource according to the default public RNTI;
The user terminal obtains the money of the upper occupancy in frequency domain of the sPUSCH from the conflicted resource instruction DCI after descrambling
Source information.
7. a kind of ascending resource distributor, it is characterised in that applied to communication base station, including:
Judge module, for as the communication base station scheduling up shared data channel sPUSCH of low time delay, judging described
Frequency domain resource where sPUSCH, if scheduled up shared data channel before the sPUSCH that has been scheduled
PUSCH takes;
Generation module, for scheduled before the frequency domain resource where the sPUSCH, the sPUSCH that has been scheduled
When up shared data channel PUSCH takes, conflicted resource indicating downlink control information DCI is generated, the conflicted resource is indicated
DCI includes resource informations of the sPUSCH in the upper occupancy of frequency domain, the PUSCH is directed to for indicating user terminal, in institute
The PUSCH and sPUSCH equitant positions on frequency domain are stated to be punched;
Sending module, DCI is indicated for sending the conflicted resource to user terminal.
8. a kind of ascending resource distributor, it is characterised in that applied to user terminal, including:
Receiving module, the conflicted resource indicating downlink control information DCI for receiving communication base station transmission, the conflicted resource refers to
Show that DCI includes resources of the up shared data channel sPUSCH of low time delay scheduled in the communication base station in the upper occupancy of frequency domain
Information;
First judge module, for judging whether PUSCH to be sent;
Second judge module, for when the user terminal has PUSCH to be sent, judging that the conflicted resource is indicated
The resource information of the upper occupancy in frequency domain of the sPUSCH in DCI, if having with the PUSCH to be sent on frequency domain
There is overlapping part;
Perforating module, the resource letter of the upper occupancy in frequency domain for indicating the sPUSCH in DCI when the conflicted resource
When breath has overlapping part with the PUSCH to be sent on frequency domain, in the PUSCH to be sent and the sPUSCH
Punched at the position of overlapping frequency domain.
9. a kind of communication base station, it is characterised in that including processor, communication interface, memory and communication bus, wherein, processing
Device, communication interface, memory completes mutual communication by communication bus;
Memory, for depositing computer program;
Processor, for performing during the program deposited on memory, realizes any described method and steps of claim 1-4.
10. a kind of user terminal, it is characterised in that including processor, communication interface, memory and communication bus, wherein, processing
Device, communication interface, memory completes mutual communication by communication bus;
Memory, for depositing computer program;
Processor, for performing during the program deposited on memory, realizes any described method and steps of claim 5-6.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710573697.5A CN107241805B (en) | 2017-07-14 | 2017-07-14 | A kind of uplink resource allocating method and device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710573697.5A CN107241805B (en) | 2017-07-14 | 2017-07-14 | A kind of uplink resource allocating method and device |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107241805A true CN107241805A (en) | 2017-10-10 |
CN107241805B CN107241805B (en) | 2019-11-12 |
Family
ID=59990545
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710573697.5A Active CN107241805B (en) | 2017-07-14 | 2017-07-14 | A kind of uplink resource allocating method and device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107241805B (en) |
Cited By (25)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109618362A (en) * | 2019-02-15 | 2019-04-12 | 中国联合网络通信集团有限公司 | A kind of communication means and equipment |
CN110034893A (en) * | 2018-01-12 | 2019-07-19 | 维沃移动通信有限公司 | A kind of UCI sending method and mobile terminal |
WO2019183942A1 (en) * | 2018-03-30 | 2019-10-03 | Oppo广东移动通信有限公司 | Uplink control information transmission method and device |
WO2019192294A1 (en) * | 2018-04-04 | 2019-10-10 | 电信科学技术研究院有限公司 | Method for indicating to interrupt transmission, network side device and terminal |
CN110324108A (en) * | 2018-03-28 | 2019-10-11 | 普天信息技术有限公司 | The MCS selection method and device of reverse link traffic channel |
CN110324123A (en) * | 2018-03-29 | 2019-10-11 | 北京展讯高科通信技术有限公司 | Time-domain resource distribution method and device, storage medium, the terminal of PUSCH |
CN110661830A (en) * | 2018-06-29 | 2020-01-07 | 中国电信股份有限公司 | Resource scheduling method and device, vehicle-mounted terminal, base station and vehicle networking system |
WO2020024249A1 (en) * | 2018-08-03 | 2020-02-06 | Oppo广东移动通信有限公司 | Data transmission method, terminal device, network device and storage medium |
CN110958707A (en) * | 2018-09-27 | 2020-04-03 | 北京三星通信技术研究有限公司 | Resource control method, electronic device, and computer-readable storage medium |
WO2020082939A1 (en) * | 2018-10-26 | 2020-04-30 | 电信科学技术研究院有限公司 | Information transmission method, terminal device, and network device |
WO2020082933A1 (en) * | 2018-10-26 | 2020-04-30 | 电信科学技术研究院有限公司 | Data transmission method and apparatus |
CN111294976A (en) * | 2019-04-26 | 2020-06-16 | 北京展讯高科通信技术有限公司 | Uplink transmission method, user terminal and computer readable storage medium |
WO2020192748A1 (en) * | 2019-03-27 | 2020-10-01 | FG Innovation Company Limited | Method and apparatus for handling overlapping pusch durations |
WO2020191777A1 (en) * | 2019-03-28 | 2020-10-01 | Zte Corporation | Methods and devices for scheduling transmission of control information |
CN111836398A (en) * | 2019-08-20 | 2020-10-27 | 维沃移动通信有限公司 | Transmission method, terminal equipment and network side equipment |
CN111836378A (en) * | 2019-08-15 | 2020-10-27 | 维沃移动通信有限公司 | Frequency domain resource allocation method, network side equipment and terminal |
CN112312545A (en) * | 2019-07-26 | 2021-02-02 | 大唐移动通信设备有限公司 | Method and equipment for canceling uplink channel transmission |
CN113170431A (en) * | 2018-09-28 | 2021-07-23 | 株式会社Ntt都科摩 | User terminal and wireless communication method |
WO2021147104A1 (en) * | 2020-01-23 | 2021-07-29 | 华为技术有限公司 | Data transmission method and apparatus |
CN113196849A (en) * | 2018-12-27 | 2021-07-30 | 夏普株式会社 | Terminal device, base station device, and communication method |
CN113596817A (en) * | 2021-07-29 | 2021-11-02 | 重庆御芯微信息技术有限公司 | Multi-terminal physical resource allocation method for wireless access point |
CN114915391A (en) * | 2021-02-10 | 2022-08-16 | 维沃移动通信有限公司 | Conflict indication method and device and electronic equipment |
CN115622676A (en) * | 2018-09-28 | 2023-01-17 | 大唐移动通信设备有限公司 | Resource allocation method, base station and terminal |
CN116132008A (en) * | 2018-02-09 | 2023-05-16 | 高通股份有限公司 | Method and apparatus for wireless communication |
WO2024104057A1 (en) * | 2022-11-14 | 2024-05-23 | 华为技术有限公司 | Resource allocation method and apparatus |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106465318A (en) * | 2014-05-19 | 2017-02-22 | 高通股份有限公司 | Apparatus and method for synchronous multiplexing and multiple access for different latency targets utilizing thin control |
WO2017078786A1 (en) * | 2015-11-03 | 2017-05-11 | Intel IP Corporation | Short transmission time interval (tti) |
CN106797282A (en) * | 2014-09-26 | 2017-05-31 | 高通股份有限公司 | Ultralow delay LTE uplink frame structures |
CN106797642A (en) * | 2014-10-03 | 2017-05-31 | 高通股份有限公司 | The downlink and uplink channel of low latency |
-
2017
- 2017-07-14 CN CN201710573697.5A patent/CN107241805B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106465318A (en) * | 2014-05-19 | 2017-02-22 | 高通股份有限公司 | Apparatus and method for synchronous multiplexing and multiple access for different latency targets utilizing thin control |
CN106465319A (en) * | 2014-05-19 | 2017-02-22 | 高通股份有限公司 | Apparatus and method for synchronous multiplexing and multiple access for different latency targets utilizing thin control |
CN106797282A (en) * | 2014-09-26 | 2017-05-31 | 高通股份有限公司 | Ultralow delay LTE uplink frame structures |
CN106797642A (en) * | 2014-10-03 | 2017-05-31 | 高通股份有限公司 | The downlink and uplink channel of low latency |
WO2017078786A1 (en) * | 2015-11-03 | 2017-05-11 | Intel IP Corporation | Short transmission time interval (tti) |
Cited By (44)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110034893A (en) * | 2018-01-12 | 2019-07-19 | 维沃移动通信有限公司 | A kind of UCI sending method and mobile terminal |
US11601923B2 (en) | 2018-01-12 | 2023-03-07 | Vivo Mobile Communication Co., Ltd. | UCI transmission method and mobile terminal |
CN116132008A (en) * | 2018-02-09 | 2023-05-16 | 高通股份有限公司 | Method and apparatus for wireless communication |
CN110324108A (en) * | 2018-03-28 | 2019-10-11 | 普天信息技术有限公司 | The MCS selection method and device of reverse link traffic channel |
CN110324123B (en) * | 2018-03-29 | 2021-09-07 | 北京紫光展锐通信技术有限公司 | Time domain resource allocation method and device of PUSCH, storage medium and terminal |
CN110324123A (en) * | 2018-03-29 | 2019-10-11 | 北京展讯高科通信技术有限公司 | Time-domain resource distribution method and device, storage medium, the terminal of PUSCH |
US11582731B2 (en) | 2018-03-30 | 2023-02-14 | Guangdong Oppo Mobile Telecommunications Corp., Ltd. | Uplink control information transmission method and device |
US12063654B2 (en) | 2018-03-30 | 2024-08-13 | Guangdong Oppo Mobile Telecommunications Corp., Ltd. | Uplink control information transmission method and device |
WO2019183942A1 (en) * | 2018-03-30 | 2019-10-03 | Oppo广东移动通信有限公司 | Uplink control information transmission method and device |
WO2019192294A1 (en) * | 2018-04-04 | 2019-10-10 | 电信科学技术研究院有限公司 | Method for indicating to interrupt transmission, network side device and terminal |
CN110661830A (en) * | 2018-06-29 | 2020-01-07 | 中国电信股份有限公司 | Resource scheduling method and device, vehicle-mounted terminal, base station and vehicle networking system |
CN110661830B (en) * | 2018-06-29 | 2022-11-11 | 中国电信股份有限公司 | Resource scheduling method and device, vehicle-mounted terminal, base station and vehicle networking system |
WO2020024249A1 (en) * | 2018-08-03 | 2020-02-06 | Oppo广东移动通信有限公司 | Data transmission method, terminal device, network device and storage medium |
US11552766B2 (en) | 2018-08-03 | 2023-01-10 | Guangdong Oppo Mobile Telecommunications Corp., Ltd. | Method for data transmission, terminal device and network device |
CN110958707A (en) * | 2018-09-27 | 2020-04-03 | 北京三星通信技术研究有限公司 | Resource control method, electronic device, and computer-readable storage medium |
CN113170431A (en) * | 2018-09-28 | 2021-07-23 | 株式会社Ntt都科摩 | User terminal and wireless communication method |
CN115622676A (en) * | 2018-09-28 | 2023-01-17 | 大唐移动通信设备有限公司 | Resource allocation method, base station and terminal |
CN111107658A (en) * | 2018-10-26 | 2020-05-05 | 电信科学技术研究院有限公司 | Information transmission method, terminal equipment and network equipment |
CN111107658B (en) * | 2018-10-26 | 2022-03-11 | 大唐移动通信设备有限公司 | Information transmission method, terminal equipment and network equipment |
WO2020082939A1 (en) * | 2018-10-26 | 2020-04-30 | 电信科学技术研究院有限公司 | Information transmission method, terminal device, and network device |
WO2020082933A1 (en) * | 2018-10-26 | 2020-04-30 | 电信科学技术研究院有限公司 | Data transmission method and apparatus |
CN111107632A (en) * | 2018-10-26 | 2020-05-05 | 电信科学技术研究院有限公司 | Data transmission method and device |
CN113196849B (en) * | 2018-12-27 | 2024-03-12 | 夏普株式会社 | Terminal device, base station device, and communication method |
CN113196849A (en) * | 2018-12-27 | 2021-07-30 | 夏普株式会社 | Terminal device, base station device, and communication method |
CN109618362A (en) * | 2019-02-15 | 2019-04-12 | 中国联合网络通信集团有限公司 | A kind of communication means and equipment |
WO2020192748A1 (en) * | 2019-03-27 | 2020-10-01 | FG Innovation Company Limited | Method and apparatus for handling overlapping pusch durations |
US11184909B2 (en) | 2019-03-27 | 2021-11-23 | FG Innovation Company Limited | Method and apparatus for handling overlapping PUSCH durations |
WO2020191777A1 (en) * | 2019-03-28 | 2020-10-01 | Zte Corporation | Methods and devices for scheduling transmission of control information |
CN113678552A (en) * | 2019-03-28 | 2021-11-19 | 中兴通讯股份有限公司 | Method and apparatus for transmission of scheduling control information |
CN113678552B (en) * | 2019-03-28 | 2024-02-23 | 中兴通讯股份有限公司 | Method and apparatus for scheduling transmission of control information |
CN111294976A (en) * | 2019-04-26 | 2020-06-16 | 北京展讯高科通信技术有限公司 | Uplink transmission method, user terminal and computer readable storage medium |
CN112312545A (en) * | 2019-07-26 | 2021-02-02 | 大唐移动通信设备有限公司 | Method and equipment for canceling uplink channel transmission |
CN112312545B (en) * | 2019-07-26 | 2024-06-07 | 大唐移动通信设备有限公司 | Method and equipment for canceling uplink channel transmission |
CN111836378B (en) * | 2019-08-15 | 2023-07-25 | 维沃移动通信有限公司 | Frequency domain resource allocation method, network side equipment and terminal |
CN111836378A (en) * | 2019-08-15 | 2020-10-27 | 维沃移动通信有限公司 | Frequency domain resource allocation method, network side equipment and terminal |
CN111836398A (en) * | 2019-08-20 | 2020-10-27 | 维沃移动通信有限公司 | Transmission method, terminal equipment and network side equipment |
CN111836398B (en) * | 2019-08-20 | 2022-05-03 | 维沃移动通信有限公司 | Transmission method, terminal equipment and network side equipment |
CN113439468A (en) * | 2020-01-23 | 2021-09-24 | 华为技术有限公司 | Data transmission method and device |
WO2021147104A1 (en) * | 2020-01-23 | 2021-07-29 | 华为技术有限公司 | Data transmission method and apparatus |
CN113439468B (en) * | 2020-01-23 | 2023-02-03 | 华为技术有限公司 | Data transmission method and device |
CN114915391A (en) * | 2021-02-10 | 2022-08-16 | 维沃移动通信有限公司 | Conflict indication method and device and electronic equipment |
CN113596817B (en) * | 2021-07-29 | 2023-08-01 | 重庆御芯微信息技术有限公司 | Multi-terminal physical resource allocation method of wireless access point |
CN113596817A (en) * | 2021-07-29 | 2021-11-02 | 重庆御芯微信息技术有限公司 | Multi-terminal physical resource allocation method for wireless access point |
WO2024104057A1 (en) * | 2022-11-14 | 2024-05-23 | 华为技术有限公司 | Resource allocation method and apparatus |
Also Published As
Publication number | Publication date |
---|---|
CN107241805B (en) | 2019-11-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107241805B (en) | A kind of uplink resource allocating method and device | |
CN109194456B (en) | Method and device in wireless communication | |
CN110278062A (en) | Resource instruction determines method and device | |
AU2019316855B2 (en) | Transmission method and device for uplink control information and computer storage medium | |
CN110476385A (en) | Method and apparatus for receiving downlink transmission | |
CN109587809B (en) | Method and device for aperiodic SRS | |
US20210099987A1 (en) | Allocating transmission resources in communication networks that provide low latency services | |
WO2021052254A1 (en) | Data transmission method, apparatus and system | |
CN107332646A (en) | HARQ-ACK sending method and device | |
CN107071905A (en) | Communication between devices method, user equipment and base station | |
CN108702279A (en) | For distributing the method and apparatus for confirming resource | |
CN106851744A (en) | The method and apparatus of radio communication | |
CN107801243A (en) | A kind of downlink transmission method and device | |
CN105578608A (en) | Downlink control information transmitting and receiving method and device | |
CN106605441A (en) | Low-latency, low-bandwidth and low duty cycle operation in a wireless communication system | |
CN109952733A (en) | Flexible radio resources allocation | |
CN104125045A (en) | Method for transmitting ACK/NACK messages | |
JP7377863B2 (en) | Channel access instruction method and device | |
CN111247830A (en) | Data transmission method, apparatus, computer program and carrier therefor | |
CN110535610B (en) | Scheduling indication method, device and storage medium | |
CN110099449B (en) | Uplink information transmission method and device | |
CN109699075A (en) | A kind of ascending HARQ code book feedback and method of reseptance, device and medium | |
WO2016138841A1 (en) | Data transmission method, feedback information transmission method, and related device | |
CN111406431A (en) | Indicating continuous resource allocation | |
CN109474990A (en) | Resource allocation method, terminal and the network equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |