Nothing Special   »   [go: up one dir, main page]

CN106624285A - 350 MW unit main steam pipeline-P91 welding process - Google Patents

350 MW unit main steam pipeline-P91 welding process Download PDF

Info

Publication number
CN106624285A
CN106624285A CN201611272669.1A CN201611272669A CN106624285A CN 106624285 A CN106624285 A CN 106624285A CN 201611272669 A CN201611272669 A CN 201611272669A CN 106624285 A CN106624285 A CN 106624285A
Authority
CN
China
Prior art keywords
welding
temperature
speed
carried out
heated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611272669.1A
Other languages
Chinese (zh)
Inventor
李世霞
吕杰
史学军
陆小斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Iron And Steel Vocational Technical College
Original Assignee
Gansu Iron And Steel Vocational Technical College
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu Iron And Steel Vocational Technical College filed Critical Gansu Iron And Steel Vocational Technical College
Priority to CN201611272669.1A priority Critical patent/CN106624285A/en
Publication of CN106624285A publication Critical patent/CN106624285A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K9/00Arc welding or cutting
    • B23K9/16Arc welding or cutting making use of shielding gas
    • B23K9/167Arc welding or cutting making use of shielding gas and of a non-consumable electrode
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K9/00Arc welding or cutting
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K9/00Arc welding or cutting
    • B23K9/0026Arc welding or cutting specially adapted for particular articles or work
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K9/00Arc welding or cutting
    • B23K9/235Preliminary treatment
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P15/00Making specific metal objects by operations not covered by a single other subclass or a group in this subclass
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K2101/00Articles made by soldering, welding or cutting
    • B23K2101/04Tubular or hollow articles
    • B23K2101/14Heat exchangers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K2103/00Materials to be soldered, welded or cut
    • B23K2103/02Iron or ferrous alloys
    • B23K2103/04Steel or steel alloys

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Plasma & Fusion (AREA)
  • Arc Welding In General (AREA)

Abstract

The invention discloses a 350 MW unit main steam pipeline-P91 welding process. The welding process mainly comprises the five steps of pre-welding preparation, pre-welding preheating, control of interlayer temperature, welding and post-welding heat treatment. According to the 350 MW unit main steam pipeline-P91 welding process, the welding beam is uniform and attractive, the molding is good, the performance of impact toughness, welding brittleness, post-welding heat treatment, welding heat affected zone of the welding joint can be improved, and the service life of a boiler and a pipeline can be prolonged.

Description

A kind of 350MW Main Steam Pipeline of Unit-P91 welding procedures
Technical field
The present invention relates to pipeline welding technical field, specially a kind of 350MW Main Steam Pipeline of Unit-P91 welding procedures.
Background technology
ASME SA335P91 steel pipes, with excellent elevated temperature strength and high temperature oxidation resistance, but the relatively low conjunction of its welding performance Golden heat resisting steel is poor, if welding procedure is not good enough, weld metal ballistic work often occurs lowly, in addition welding point different characteristic region Mechanical property difference and easily cause stress concentration, therefore be also easy to produce initial failure.Such as certain power plant 125MW unit main steam pipes Road, due to welding point hardness deficiency, booster after running 9 months.Therefore, optimization welding is concentrated mainly on to the research of T/P91 Technique, seeks technology controlling and process joint performance mechanism, and innovative technology core technology improves impact toughness of welded joint, weldering The performance of fragility, post weld heat treatment and welding heat affected zone is connect, it is that industry energy conservation wound effect is carried to improve boiler and pipeline service life For technical support.Boiler tubing operation does not reach the time of standard requirement, and the security incidents such as booster occur in advance, can follow at present Welding procedure scope it is larger.Welding condition matches improper with thermal parameter, by technological experiment, selects preferred process, Training for skilled worker provides technical parameter.
The content of the invention
It is an object of the invention to provide a kind of 350MW Main Steam Pipeline of Unit-P91 welding procedures, to solve the above-mentioned back of the body The problem proposed in scape technology.
For achieving the above object, the present invention provides following technical scheme:A kind of 350MW Main Steam Pipeline of Unit-P91 welding Technique, it is characterised in that:Comprise the following steps:
A, welding preparation:
A, back cover layer:Back cover welding is carried out using the two-sided protection weldering of tungsten inert gas, welding material is MTS3 welding wires, is welded Silk specification is φ 2.4mm;
B, packed layer:Layer welding is filled using manual electric arc welding, welding material is Chromo T91 welding rods, and welding rod is advised Lattice are φ 2.5mm;
C, capping layer:Capping layer welding is carried out using manual electric arc welding, welding material is Chromo T91 welding rods, and welding rod is advised Lattice are φ 3.2mm;
D, bevel:Double V-groove is opened steel pipe with lathe and boring and milling machine, and bevel angle is 55 ° -65 °, and root face is 1.2mm- 1.5mm;
B, weld preheating:Mother metal is preheated using Electric heating, preheating speed is 100 DEG C/h-150 DEG C/h, in advance Hot temperature is 150-200 DEG C, reaches constant temperature 120min-150min after preheating temperature;
C, control interlayer temperature:Using being heated up using Electric heating, thermometric is carried out using infrared thermometer, controlled Welding temperature processed is welded afterwards at 200 DEG C -300 DEG C;
D, welding:Comprise the following steps:
A, envelope backing weld:Gas tungsten arc welding is adopted with the speed of welding and 9- of 42mm/min-57mm/min The intake velocity of 11L/min is welded, welding current 90-110A, weldingvoltage 10-16V, heat input 1.3-1.7KJ/ mm;
B, packed layer welding:Adopt manual electric arc welding and welded with the speed of welding of 50mm/min-60mm/min, weld Electric current 70-90A, weldingvoltage 18-20V, heat input 1.5-1.8KJ/mm;
C, the welding of capping layer:Adopt manual electric arc welding and welded with the speed of welding of 70-80mm/min, welding current 115-125A, weldingvoltage 18-20V, heat input 1.3-2.0KJ/mm;
E, post weld heat treatment:Weldment is first lowered the temperature, is heated up afterwards, then constant temperature, then the mode lowered the temperature is heat-treated.
Preferably, heat treatment method is comprised the following steps in step E:
A, weldment is carried out into Slow cooling with the speed of 100 DEG C/h-150 DEG C/h, until temperature is down to 100 DEG C -120 DEG C Constant temperature 1h afterwards;
B, weldment heated by electrically heated mode again, heated up with the speed of 100 DEG C/h-150 DEG C/h, Constant temperature 4h after rising to 750 DEG C -770 DEG C;
C, weldment carried out with the speed of 100 DEG C/h-150 DEG C/h slowly cooling to 300 DEG C again, naturally cooled to afterwards Normal temperature.
Compared with prior art, the invention has the beneficial effects as follows:Main steam line-P91 welding procedure the weld seams of the present invention Uniform attractive in appearance, shaping is good, can improve impact toughness of welded joint, welding fragility, post weld heat treatment and sweating heat The performance of the zone of influence, improves boiler and pipeline service life.
Specific embodiment
The technical scheme in the embodiment of the present invention is clearly and completely described below, it is clear that described embodiment Only a part of embodiment of the invention, rather than the embodiment of whole.Based on the embodiment in the present invention, the common skill in this area The every other embodiment that art personnel are obtained under the premise of creative work is not made, belongs to the model of present invention protection Enclose.
Embodiment one:
A kind of 350MW Main Steam Pipeline of Unit-P91 welding procedures, comprise the following steps:
A, welding preparation:
A, back cover layer:Back cover welding is carried out using gas tungsten arc welding, welding material is MTS3 welding wires, and welding wire is advised Lattice are φ 2.4mm;
B, packed layer:Layer welding is filled using manual electric arc welding, welding material is Chromo T91 welding rods, and welding rod is advised Lattice are φ 2.5mm;
C, capping layer:Capping layer welding is carried out using manual electric arc welding, welding material is Chromo T91 welding rods, and welding rod is advised Lattice are φ 3.2mm;
D, bevel:Double V-groove is opened steel pipe with lathe and boring and milling machine, and bevel angle is 55 °, and root face is 1.2mm;
B, weld preheating:Mother metal is preheated using Electric heating, preheating speed is 80 DEG C/h, preheating temperature is 150, reach constant temperature 120min after preheating temperature;
C, control interlayer temperature:Using being heated up using Electric heating, thermometric is carried out using infrared thermometer, controlled Welding temperature processed is welded afterwards at 200 DEG C;
D, welding:Comprise the following steps:
A, envelope backing weld:Gas tungsten arc welding is adopted with the speed of welding of 42mm/min and
The intake velocity of 9L/min is welded, welding current 90A, weldingvoltage 10V, heat input 1.3KJ/mm;
B, packed layer welding:Adopt manual electric arc welding and welded with the speed of welding of 50mm/min, welding current 70A, Weldingvoltage 18V, heat input 1.5KJ/mm;
C, the welding of capping layer:Adopt manual electric arc welding and welded with the speed of welding of 70mm/min, welding current 115A, Weldingvoltage 18V, heat input 1.3KJ/mm;
E, post weld heat treatment:Weldment is first lowered the temperature, is heated up afterwards, then constant temperature, then the mode lowered the temperature is heat-treated.
In the present embodiment, heat treatment method is comprised the following steps in step E:
A, weldment is carried out into Slow cooling with the speed of 90 DEG C/h, until constant temperature 1h after temperature is down to 100 DEG C;
B, weldment heated by electrically heated mode again, heated up with the speed of 90 DEG C/h, risen to 750 DEG C Constant temperature 4h afterwards;
C, weldment carried out with the speed of 90 DEG C/h slowly cooling to 300 DEG C again, normal temperature is naturally cooled to afterwards.
Embodiment two:
A kind of 350MW Main Steam Pipeline of Unit-P91 welding procedures, comprise the following steps:
A, welding preparation:
A, back cover layer:Back cover welding is carried out using gas tungsten arc welding, welding material is MTS3 welding wires, and welding wire is advised Lattice are φ 2.4mm;
B, packed layer:Layer welding is filled using manual electric arc welding, welding material is Chromo T91 welding rods, and welding rod is advised Lattice are φ 2.5mm;
C, capping layer:Capping layer welding is carried out using manual electric arc welding, welding material is Chromo T91 welding rods, and welding rod is advised Lattice are φ 3.2mm;
D, bevel:Double V-groove is opened steel pipe with lathe and boring and milling machine, and bevel angle is 65 °, blunt
While being 1.5mm;
B, weld preheating:Mother metal is preheated using Electric heating, preheating speed is 100 DEG C/h, preheating temperature is 200 DEG C, reach constant temperature 150min after preheating temperature;
C, control interlayer temperature:Using being heated up using Electric heating, thermometric is carried out using infrared thermometer, controlled Welding temperature processed is welded afterwards at 300 DEG C;
D, welding:Comprise the following steps:
A, envelope backing weld:The entering with the speed of welding of 57mm/min and 11L/min that adopt gas tungsten arc welding Gas speed is welded, welding current 110A, weldingvoltage 16V, heat input 1.7KJ/mm;
B, packed layer welding:Adopt manual electric arc welding and welded with the speed of welding of 60mm/min, welding current 90A, Weldingvoltage 20V, heat input 1.8KJ/mm;
C, the welding of capping layer:Adopt manual electric arc welding and welded with the speed of welding of 80mm/min, welding current 125A, Weldingvoltage 20V, heat input 2.0KJ/mm;
E, post weld heat treatment:Weldment is first lowered the temperature, is heated up afterwards, then constant temperature, then the mode lowered the temperature is heat-treated.
In the present embodiment, heat treatment method is comprised the following steps in step E:
A, weldment is carried out into Slow cooling with the speed of 100 DEG C/h, until constant temperature 1h after temperature is down to 120 DEG C;
B, weldment heated by electrically heated mode again, heated up with the speed of 100 DEG C/h, risen to 770 Constant temperature 4h after DEG C;
C, weldment carried out with the speed of 100 DEG C/h slowly cooling to 300 DEG C again, normal temperature is naturally cooled to afterwards.
Embodiment three:
A kind of 350MW Main Steam Pipeline of Unit-P91 welding procedures, comprise the following steps:
A, welding preparation:
A, back cover layer:Back cover welding is carried out using gas tungsten arc welding, welding material is MTS3 welding wires, and welding wire is advised Lattice are φ 2.4mm;
B, packed layer:Layer welding is filled using manual electric arc welding, welding material is Chromo T91 welding rods, and welding rod is advised Lattice are φ 2.5mm;
C, capping layer:Capping layer welding is carried out using manual electric arc welding, welding material is Chromo T91 welding rods, and welding rod is advised Lattice are φ 3.2mm;
D, bevel:Double V-groove is opened steel pipe with lathe and boring and milling machine, and bevel angle is 58 °, and root face is 1.3mm;
B, weld preheating:Mother metal is preheated using Electric heating, preheating speed is 85 DEG C/h, preheating temperature is 180 DEG C, reach constant temperature 130min after preheating temperature;
C, control interlayer temperature:Using being heated up using Electric heating, thermometric is carried out using infrared thermometer, controlled Welding temperature processed is welded afterwards at 240 DEG C;
D, welding:Comprise the following steps:
A, envelope backing weld:Gas tungsten arc welding is adopted with the air inlet of the speed of welding of 50mm/min and 9L/min Speed is welded, welding current 95A, weldingvoltage 12V, heat input 1.4KJ/mm;
B, packed layer welding:Adopt manual electric arc welding and welded with the speed of welding of 54mm/min, welding current 75A, Weldingvoltage 18V, heat input 1.6KJ/mm;
C, the welding of capping layer:Adopt manual electric arc welding and welded with the speed of welding of 74mm/min, welding current 122A, Weldingvoltage 18V, heat input 1.5KJ/mm;
E, post weld heat treatment:Weldment is first lowered the temperature, is heated up afterwards, then constant temperature, then the mode lowered the temperature is heat-treated.
In the present embodiment, heat treatment method is comprised the following steps in step E:
A, weldment is carried out into Slow cooling with the speed of 95 DEG C/h, until constant temperature 1h after temperature is down to 105 DEG C;
B, weldment heated by electrically heated mode again, heated up with the speed of 95 DEG C/h, risen to 750 Constant temperature 4h after DEG C -770 DEG C;
C, weldment carried out with the speed of 95 DEG C/h slowly cooling to 300 DEG C again, normal temperature is naturally cooled to afterwards.
Example IV:
A kind of 350MW Main Steam Pipeline of Unit-P91 welding procedures, comprise the following steps:
A, welding preparation:
A, back cover layer:Back cover welding is carried out using gas tungsten arc welding, welding material is MTS3 welding wires, and welding wire is advised Lattice are φ 2.4mm;
B, packed layer:Layer welding is filled using manual electric arc welding, welding material is Chromo T91 welding rods, and welding rod is advised Lattice are φ 2.5mm;
C, capping layer:Capping layer welding is carried out using manual electric arc welding, welding material is Chromo T91 welding rods, and welding rod is advised Lattice are φ 3.2mm;
D, bevel:Double V-groove is opened steel pipe with lathe and boring and milling machine, and bevel angle is 60 °, and root face is 1.2mm- 1.5mm;
B, weld preheating:Mother metal is preheated using Electric heating, preheating speed is 90 DEG C/h, preheating temperature is 180 DEG C, reach constant temperature 135min after preheating temperature;
C, control interlayer temperature:Using being heated up using Electric heating, thermometric is carried out using infrared thermometer, controlled Welding temperature processed is welded afterwards at 250 DEG C;
D, welding:Comprise the following steps:
A, envelope backing weld:The entering with the speed of welding of 50mm/min and 10L/min that adopt gas tungsten arc welding Gas speed is welded, welding current 100A, weldingvoltage 13V, heat input 1.5KJ/mm;
B, packed layer welding:Adopt manual electric arc welding and welded with the speed of welding of 55mm/min, welding current 80A, Weldingvoltage 19V, heat input 1.7KJ/mm;
C, the welding of capping layer:Adopt manual electric arc welding and welded with the speed of welding of 75mm/min, welding current 120A, Weldingvoltage 19V, heat input 1.5KJ/mm;
E, post weld heat treatment:Weldment is first lowered the temperature, is heated up afterwards, then constant temperature, then the mode lowered the temperature is heat-treated.
In the present embodiment, heat treatment method is comprised the following steps in step E:
A, weldment is carried out into Slow cooling with the speed of 100 DEG C/h, until constant temperature 1h after temperature is down to 110 DEG C;
B, weldment heated by electrically heated mode again, heated up with the speed of 95 DEG C/h, risen to 760 DEG C Constant temperature 4h afterwards;
C, weldment carried out with the speed of 95 DEG C/h slowly cooling to 300 DEG C again, normal temperature is naturally cooled to afterwards.
Experimental example:
By three groups of test test specimen point to be welded, per group of 6 test specimens, each test specimen is taken different in various embodiments of the present invention Welding method, preheating temperature, welding parameter, Technology for Heating Processing and welding operation personnel, determine weld hardness, heat affecting after welding Area's hardness and mother metal hardness, data measured such as following table:
The main steam line welding procedure even weld of the present invention is attractive in appearance, and shaping is good, can improve welding and connect The performance of head impact flexibility, welding fragility, post weld heat treatment and welding heat affected zone, improves
Boiler and pipeline service life.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with Understanding can carry out various changes, modification, replacement to these embodiments without departing from the principles and spirit of the present invention And modification, the scope of the present invention be defined by the appended.

Claims (2)

1. a kind of 350MW Main Steam Pipeline of Unit-P91 welding procedures, it is characterised in that:Comprise the following steps:
A, welding preparation:
A, back cover layer:Back cover welding is carried out using gas tungsten arc welding, welding material is MTS3 welding wires, and welding wire specification is φ2.4mm;
B, packed layer:Layer welding is filled using manual electric arc welding, welding material is Chromo T91 welding rods, and welding rod specification is φ2.5mm;
C, capping layer:Capping layer welding is carried out using manual electric arc welding, welding material is Chromo T91 welding rods, and welding rod specification is φ3.2mm;
D, bevel:Double V-groove is opened steel pipe with lathe and boring and milling machine, and bevel angle is 55 ° -65 °, and root face is 1.2mm- 1.5mm;
E, back filled argon protection, prevent the oxidation of sealing run;
B, weld preheating:Mother metal is preheated using Electric heating, preheating speed is 100 DEG C/h-150 DEG C/h, preheating is warm Spend for 150-200 DEG C, reach constant temperature 120min-150min after preheating temperature;
C, control interlayer temperature:Using being heated up using Electric heating, thermometric, control weldering are carried out using infrared thermometer Jointing temp is welded afterwards at 200 DEG C -300 DEG C;
D, welding:Comprise the following steps:
A, envelope backing weld:Gas tungsten arc welding is adopted with the speed of welding and 9-11L/ of 42mm/min-57mm/min The gas flow of min is welded, welding current 90-110A, weldingvoltage 10-16V, heat input 1.3-1.7KJ/mm;
B, packed layer welding:Adopt manual electric arc welding and welded with the speed of welding of 50mm/min-60mm/min, welding current 70-90A, weldingvoltage 18-20V, heat input 1.5-1.8KJ/mm;
C, the welding of capping layer:Adopt manual electric arc welding and welded with the speed of welding of 70-80mm/min, welding current 115- 125A, weldingvoltage 18-20V, heat input 1.3-2.0KJ/mm;
E, post weld heat treatment:Weldment is first lowered the temperature, is heated up afterwards, then constant temperature, then the mode lowered the temperature is heat-treated.
2. a kind of 350MW Main Steam Pipeline of Unit-P91 welding procedures according to claim 1, it is characterised in that:It is described Heat treatment method is comprised the following steps in step E:
A, weldment is carried out into Slow cooling with the speed of 100 DEG C/h-150 DEG C/h, until permanent after temperature is down to 100 DEG C -120 DEG C Warm 1h;
B, weldment heated by electrically heated mode again, heated up with the speed of 100 DEG C/h-150 DEG C/h, risen to Constant temperature 4h after 750 DEG C -770 DEG C;
C, weldment carried out with the speed of 100 DEG C/h-150 DEG C/h slowly cooling to 300 DEG C again, naturally cooled to afterwards often Temperature.
CN201611272669.1A 2016-12-29 2016-12-29 350 MW unit main steam pipeline-P91 welding process Pending CN106624285A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611272669.1A CN106624285A (en) 2016-12-29 2016-12-29 350 MW unit main steam pipeline-P91 welding process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611272669.1A CN106624285A (en) 2016-12-29 2016-12-29 350 MW unit main steam pipeline-P91 welding process

Publications (1)

Publication Number Publication Date
CN106624285A true CN106624285A (en) 2017-05-10

Family

ID=58838531

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611272669.1A Pending CN106624285A (en) 2016-12-29 2016-12-29 350 MW unit main steam pipeline-P91 welding process

Country Status (1)

Country Link
CN (1) CN106624285A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108176911A (en) * 2017-12-18 2018-06-19 南京德邦金属装备工程股份有限公司 A kind of P91 materials welding and heat treatment method
CN108825299A (en) * 2018-05-30 2018-11-16 贵州锦丰矿业有限公司 A kind of movable type filling pipeline device and construction method
CN110331273A (en) * 2019-05-23 2019-10-15 山东电力建设第三工程有限公司 A kind of weld bond heat treatment method of soft alloy pipeline

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1398694A (en) * 2002-04-25 2003-02-26 石家庄电力工业学校焊接培训中心 T91 steel welding process
CN1721118A (en) * 2005-06-02 2006-01-18 石家庄电力工业学校焊接培训中心 P91 steel welding method
CN1935438A (en) * 2006-06-09 2007-03-28 浙江省火电建设公司 P92 steel welding process
JP2009248175A (en) * 2008-04-10 2009-10-29 Nippon Steel Corp Tig welding method of high-strength steel using flux-containing wire
CN102618713A (en) * 2012-03-10 2012-08-01 广东省韶关粤江发电有限责任公司 Heat treatment method for welding SA335-P91/P92 steel by ultra-supercritical coal-fired power plant
CN102615380A (en) * 2012-03-10 2012-08-01 广东省韶关粤江发电有限责任公司 Welding process of ultra-supercritical fossil power unit for welding SA335-P91/P92 steel
CN103643025A (en) * 2013-12-11 2014-03-19 安徽三兴检测有限公司 Method of improving toughness of novel martensite heat-resistant steel A355P91 welding seam
CN105033414A (en) * 2015-07-09 2015-11-11 安徽金阳金属结构工程有限公司 Pipeline welding process

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1398694A (en) * 2002-04-25 2003-02-26 石家庄电力工业学校焊接培训中心 T91 steel welding process
CN1721118A (en) * 2005-06-02 2006-01-18 石家庄电力工业学校焊接培训中心 P91 steel welding method
CN1935438A (en) * 2006-06-09 2007-03-28 浙江省火电建设公司 P92 steel welding process
JP2009248175A (en) * 2008-04-10 2009-10-29 Nippon Steel Corp Tig welding method of high-strength steel using flux-containing wire
CN102618713A (en) * 2012-03-10 2012-08-01 广东省韶关粤江发电有限责任公司 Heat treatment method for welding SA335-P91/P92 steel by ultra-supercritical coal-fired power plant
CN102615380A (en) * 2012-03-10 2012-08-01 广东省韶关粤江发电有限责任公司 Welding process of ultra-supercritical fossil power unit for welding SA335-P91/P92 steel
CN103643025A (en) * 2013-12-11 2014-03-19 安徽三兴检测有限公司 Method of improving toughness of novel martensite heat-resistant steel A355P91 welding seam
CN105033414A (en) * 2015-07-09 2015-11-11 安徽金阳金属结构工程有限公司 Pipeline welding process

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
严祯荣等: "超(超)临界锅炉用厚壁SA335-P91钢管的高效率焊接方法", 《中国特种设备安全》 *
孙咸: "工艺方法欲改进,焊接材料需出新(下)――T91/P91钢焊接材料应用述评", 《金属加工(热加工)》 *
张国栋等: "基于正交试验设计的高温管道焊接工艺优化", 《焊接学报》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108176911A (en) * 2017-12-18 2018-06-19 南京德邦金属装备工程股份有限公司 A kind of P91 materials welding and heat treatment method
CN108825299A (en) * 2018-05-30 2018-11-16 贵州锦丰矿业有限公司 A kind of movable type filling pipeline device and construction method
CN110331273A (en) * 2019-05-23 2019-10-15 山东电力建设第三工程有限公司 A kind of weld bond heat treatment method of soft alloy pipeline

Similar Documents

Publication Publication Date Title
CN106624285A (en) 350 MW unit main steam pipeline-P91 welding process
CN101700599B (en) Submerged automatic arc welding method of SA335P91 steel
CN109865955B (en) Welding method combining manual tungsten electrode argon arc welding and shielded metal arc welding for G115 large-diameter pipe
CN103643025B (en) Method of improving toughness of novel martensite heat-resistant steel A355P91 welding seam
CN101596640A (en) The welding procedure of super martensitic stainless steel
CN109317789B (en) Welding method for surfacing pipe plate of heat exchanger and T91 heat exchange pipe
CN106312268B (en) A kind of welding procedure of low activation martensitic steel and 316L stainless steel dissimilar steel connectors
CN107598340A (en) Big thick plate T-joint welding method
CN102463406A (en) Welding process of heat-resistant steel cylinder type casing
CN105880834A (en) Welding method of Q890 high-strength steel
CN103350272B (en) A kind of welding procedure of T91 and 12Cr1MoV dissimilar steel
CN102398105A (en) Process method for integral quenching and tempering of X80 steel-grade submerged-arc automatic welding pipe fitting
CN105033418A (en) Q690D high-strength steel welding process
CN102581450A (en) Multi-wire submerged-arc multi-layer multi-pass welding process
CN103521887A (en) Welding technology of 45 steel and 35 CrMo cast steel
CN107813071A (en) A kind of big wall thickness cryogenic pipelines pipe fitting welding wire for submerged-arc welding of high intensity
CN104874937B (en) Bainite heat resisting steel 12Cr2MoWVTiB welding procedure
CN100389924C (en) P91 steel welding method
CN102601502A (en) Re-nanocrystallization welding device for nanometer bainite steel and method
CN106077908B (en) A kind of welding method of Centrifugal Casting Iron Pipe part
CN111992855A (en) Welding and combined heat treatment method for martensite heat-resistant steel G115 large-diameter thick-wall pipeline
CN109530849B (en) Welding construction method for carbon steel pipeline in acidic environment
CN107825085A (en) Aircraft engine tubular bracket integral welding method and aircraft engine tubular bracket
CN108296638B (en) Method for improving strip steel welding quality of continuous galvanizing production line
CN105643061A (en) Welding method for CO2 gas shielded welding for super-strength thick steel plate

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170510

RJ01 Rejection of invention patent application after publication