CN106544959B - 含有鞍座的主塔吊装节段及桥梁主塔鞍座的施工方法 - Google Patents
含有鞍座的主塔吊装节段及桥梁主塔鞍座的施工方法 Download PDFInfo
- Publication number
- CN106544959B CN106544959B CN201611137030.2A CN201611137030A CN106544959B CN 106544959 B CN106544959 B CN 106544959B CN 201611137030 A CN201611137030 A CN 201611137030A CN 106544959 B CN106544959 B CN 106544959B
- Authority
- CN
- China
- Prior art keywords
- saddle
- tower
- anchor body
- lifting segment
- guide pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明涉及桥梁施工领域,涉及一种含有鞍座的主塔吊装节段,该吊装节段包括劲性骨架及固定于所述劲性骨架内的多组鞍座,所述鞍座中的左右两组相邻鞍座间呈剪刀状交叉设置,上下鞍座间平行且呈间隔设置,每组鞍座包括一锚体和一索导管,且锚体和索导管正对相连。还涉及一种桥梁主塔鞍座的施工方法,包括以下步骤:步骤一:拼装多组鞍座,所述每组鞍座由一锚体和一索导管组成;步骤二:多组鞍座与劲性骨架拼装成一吊装节段,并调整吊装节段中每组鞍座间的相对位置至设计标准,所述拼装的吊装节段至少为一个;步骤三:起吊吊装节段至主塔上安装固定。本发明能够降低鞍座的高空施工难度,加快施工进度,将高空作业转化为地面作业。
Description
技术领域
本发明涉及桥梁施工领域,具体涉及一种含有鞍座的主塔吊装节段和一种桥梁主塔鞍座的施工方法。
背景技术
主塔锚固区的鞍座一般由锚体和索导管组合而成,此种组合形式较传统的索导管形式而言,能够将斜拉索对主塔的拉力转化为锚体对主塔混凝土面的面荷载,从而使主塔的受力更加地合理。这种锚体和索导管组合形式的鞍座的特点为:各组锚体和索导管组成的结构体系上下层交错、内外交错,且锚体、索导管的空间位置复杂。因而在进行此种组合形式的鞍座施工时,空间定位难度大,且需在高空作业进行锚体和索导管的组装,难度和风险较大。
发明内容
针对现有技术中存在的缺陷,本发明的目的在于提供一种含有鞍座的主塔吊装节段和一种桥梁主塔鞍座的施工方法,能够降低鞍座的高空施工难度,同时加快施工进度。
为达到以上目的,本发明采取的技术方案是:包括劲性骨架及固定于所述劲性骨架内的多组鞍座,所述多组鞍座中的左右两组相邻鞍座间交叉设置,上下鞍座间平行且呈间隔设置,每组鞍座包括一锚体和一索导管,且锚体和索导管正对相连,所述鞍座为双层同向回转鞍座。
在上述技术方案的基础上,所述锚体和索导管间通过法兰相连。
在上述技术方案的基础上,所述劲性骨架为框架结构,且包括多根横向和竖向垂直设置的钢梁。
本发明还提供一种桥梁主塔鞍座的施工方法,
在上述技术方案的基础上,所述鞍座为双层同向回转鞍座,包括以下步骤:
步骤一:拼装多组鞍座,所述每组鞍座由一锚体和一索导管组成;
步骤二:多组鞍座与劲性骨架拼装成一吊装节段;
步骤三:起吊吊装节段至主塔上安装固定。
在上述技术方案的基础上,所述步骤一具体为:选取拼装场地,并进行锚体与索导管的拼装形成多组鞍座,所述每组鞍座由一锚体与一索导管正对相连组成。
在上述技术方案的基础上,所述锚体与索导管间通过法兰相连。
在上述技术方案的基础上,所述拼装场地还设置有拼装平台(5),锚体与索导管的拼装以及鞍座与劲性骨架的拼装均在拼装平台上完成。
在上述技术方案的基础上,所述步骤二具体为:
劲性骨架与多组鞍座预拼装成至少一吊装节段,并调整吊装节段中每组鞍座的位置至预设位置,待调整完后,鞍座与劲性骨架间固定,且左右两组相邻鞍座间交叉设置,上下鞍座间平行且呈间隔设置。
在上述技术方案的基础上,采用三向千斤顶调整吊装节段中每组鞍座间的相对位置。
与现有技术相比,本发明的优点在于:鞍座、吊装节段的组装均在地面上完成,将复杂的鞍座的高空定位安装转化成底面作业,极大地减少了施工难度,同时也提高了作业精度。
附图说明
图1为鞍座的结构示意图;
图2为吊装节段拼装时的结构示意图;
图3为吊装节段的结构示意图。
图中:1-锚体,2-索导管,3-劲性骨架,4-三向千斤顶,5-拼装平台。
具体实施方式
以下结合附图对本发明作进一步详细说明。
本发明提供一种含有鞍座的主塔吊装节段,本实施例中,鞍座为双层同向回转鞍座,如图3所示,该吊装节段包括呈框架结构的劲性骨架3及固定于所述劲性骨架3内的多组鞍座,劲性骨架3由多根横向和竖向垂直设置的钢梁焊接而成,鞍座中的左右两组相邻鞍座间呈剪刀状交叉设置,上下鞍座间平行且呈间隔设置,每组鞍座包括一锚体1和一索导管2,如图1所示,且锚体1和索导管2间通过法兰正对相连。
本发明提供一种桥梁主塔鞍座的施工方法,鞍座为双层同向回转鞍座,该施工方法具体包括以下步骤:
步骤一:在桥梁附近设置一拼装场地,拼装场地的设置应当满足拼装时的操作空间、起吊时的吊装空间的需求,并在拼装场地上设置拼装平台5,在拼装平台5上进行锚体1与索导管2的拼装,形成多组鞍座,每组鞍座由一锚体1和一索导管2正对相连组成,且锚体1和索导管2间采用法兰连接。
步骤二:参见图2所示,在拼装平台5上将劲性骨架3与多组鞍座预拼装成一吊装节段,劲性骨架3内鞍座间的位置满足:左右两组相邻鞍座间呈剪刀状交叉设置,上下鞍座间平行且呈间隔设置。采用三向千斤顶4对吊装节段中每组鞍座间的相对位置进行调整,我们还可以在拼装场地设置一坐标系,以便于对每组鞍座间相对位置进行调整,待调整吊装节段中每组鞍座的位置至预设位置后,如图3所示,鞍座与劲性骨架3间通过焊接或其它方式固定。拼装成的吊装节段至少为一个,桥梁的尺寸规格不同,所需的吊装节段的个数也不同,每组鞍座的预设位置也不同。每组鞍座的预设位置在桥梁进行设计工作时设计完成,具体的包括鞍座在劲性骨架3上的具体位置,及左右、上下鞍座间的空间间距。
步骤三:利用起重设备依次将吊装节段吊至主塔上,相邻吊装节段间进行固定。因为斜拉索的角度呈扇形分布,位于主塔锚固区下方的斜拉索与水平面的夹角较大,对应的索导管2的长度也较长,在起吊至主塔上的过程中,该部位的索导管2的变形相对较大,若将索导管2和锚体1同时进行整体吊装,则需要在吊装就位后对索导管2的出口进行一次调整工作,故可以在整体吊装鞍座时,对该区域的索导管2采用后接的方式进行处理,即将鞍座和劲性骨架3进行精确吊装定位后,再采用快速对接的方式对索导管进行安装。
上述施工方法中,鞍座、吊装节段的组装均在地面上完成,将复杂的鞍座的高空定位转化成地面作业,极大地减少了施工难度,同时也提高了作业精度。
本发明不局限于上述实施方式,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也视为本发明的保护范围之内。本说明书中未作详细描述的内容属于本领域专业技术人员公知的现有技术。
Claims (9)
1.一种含有鞍座的主塔吊装节段,其特征在于:包括劲性骨架(3)及固定于所述劲性骨架(3)内的多组鞍座,所述多组鞍座中的左右两组相邻鞍座间交叉设置,上下鞍座间平行且呈间隔设置,每组鞍座包括一锚体(1)和一索导管(2),且锚体(1)和索导管(2)正对相连,所述鞍座为双层同向回转鞍座。
2.如权利要求1所述的一种含有鞍座的主塔吊装节段,其特征在于:所述锚体(1)和索导管(2)间通过法兰相连。
3.如权利要求1所述的一种含有鞍座的主塔吊装节段,其特征在于:所述劲性骨架(3)为框架结构,且包括多根横向和竖向垂直设置的钢梁。
4.一种桥梁主塔鞍座的施工方法,其特征在于:所述鞍座为双层同向回转鞍座,包括以下步骤:
步骤一:拼装多组鞍座,所述每组鞍座由一锚体(1)和一索导管(2)组成;
步骤二:多组鞍座与劲性骨架(3)拼装成一吊装节段;
步骤三:起吊吊装节段至主塔上安装固定。
5.如权利要求4所述的一种桥梁主塔鞍座的施工方法,其特征在于,所述步骤一具体为:选取拼装场地,并进行锚体(1)与索导管(2)的拼装形成多组鞍座,所述每组鞍座由一锚体(1)与一索导管(2)正对相连组成。
6.如权利要求5所述的一种桥梁主塔鞍座的施工方法,其特征在于,所述锚体(1)与索导管(2)间通过法兰相连。
7.如权利要求5所述的一种桥梁主塔鞍座的施工方法,其特征在于:所述拼装场地还设置有拼装平台(5),锚体(1)与索导管(2)的拼装以及鞍座与劲性骨架(3)的拼装均在拼装平台(5)上完成。
8.如权利要求4所述的一种桥梁主塔鞍座的施工方法,其特征在于,所述步骤二具体为:
劲性骨架(3)与多组鞍座预拼装成至少一吊装节段,并调整吊装节段中每组鞍座的位置至预设位置,待调整完后,鞍座与劲性骨架(3)间固定,且左右两组相邻鞍座间交叉设置,上下鞍座间平行且呈间隔设置。
9.如权利要求8所述的一种桥梁主塔鞍座的施工方法,其特征在于:采用三向千斤顶(4)调整吊装节段中每组鞍座间的相对位置。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611137030.2A CN106544959B (zh) | 2016-12-12 | 2016-12-12 | 含有鞍座的主塔吊装节段及桥梁主塔鞍座的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611137030.2A CN106544959B (zh) | 2016-12-12 | 2016-12-12 | 含有鞍座的主塔吊装节段及桥梁主塔鞍座的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106544959A CN106544959A (zh) | 2017-03-29 |
CN106544959B true CN106544959B (zh) | 2018-05-29 |
Family
ID=58397450
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611137030.2A Active CN106544959B (zh) | 2016-12-12 | 2016-12-12 | 含有鞍座的主塔吊装节段及桥梁主塔鞍座的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106544959B (zh) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108487064B (zh) * | 2018-03-09 | 2019-06-25 | 济南城建集团有限公司 | 分离式安装悬索桥主索鞍座施工方法 |
CN111287085A (zh) * | 2020-01-08 | 2020-06-16 | 中铁大桥勘测设计院集团有限公司 | 新型钢混组合形式的斜拉索索塔锚固结构及其施工方法 |
CN112064514A (zh) * | 2020-09-14 | 2020-12-11 | 浙江交工金筑交通建设有限公司 | 一种索鞍刚体化结构及其整体定位安装方法 |
CN113718656B (zh) * | 2021-09-08 | 2023-01-06 | 安徽省公路桥梁工程有限公司 | 桥塔拼装施工方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6429505A (en) * | 1987-07-24 | 1989-01-31 | Ishikawajima Harima Heavy Ind | Method of adjusting catwalk at time of erection of suspension bridge cable through method of air spinning construction |
CN201506952U (zh) * | 2009-04-17 | 2010-06-16 | 四川路桥桥梁工程有限责任公司 | 无支架临时索配合挂篮建筑混凝土斜拉桥 |
CN101967796A (zh) * | 2010-09-19 | 2011-02-09 | 湖南路桥建设集团公司 | 一种平行钢丝斜拉索的安装方法 |
CN103243649A (zh) * | 2013-05-21 | 2013-08-14 | 中交四航局第一工程有限公司 | 一种索鞍快速安装、定位的系统及方法 |
CN105113411A (zh) * | 2015-08-03 | 2015-12-02 | 中铁港航局集团有限公司 | 一种斜拉桥主塔索导管安装和快速精确定位方法 |
CN105648923A (zh) * | 2016-03-31 | 2016-06-08 | 中铁四局集团第工程有限公司 | 一种斜拉索鞍座的定位装置及其定位方法 |
CN205999789U (zh) * | 2016-08-08 | 2017-03-08 | 中交一公局第三工程有限公司 | 斜拉桥混凝土梁索导管支撑定位装置 |
-
2016
- 2016-12-12 CN CN201611137030.2A patent/CN106544959B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6429505A (en) * | 1987-07-24 | 1989-01-31 | Ishikawajima Harima Heavy Ind | Method of adjusting catwalk at time of erection of suspension bridge cable through method of air spinning construction |
CN201506952U (zh) * | 2009-04-17 | 2010-06-16 | 四川路桥桥梁工程有限责任公司 | 无支架临时索配合挂篮建筑混凝土斜拉桥 |
CN101967796A (zh) * | 2010-09-19 | 2011-02-09 | 湖南路桥建设集团公司 | 一种平行钢丝斜拉索的安装方法 |
CN103243649A (zh) * | 2013-05-21 | 2013-08-14 | 中交四航局第一工程有限公司 | 一种索鞍快速安装、定位的系统及方法 |
CN105113411A (zh) * | 2015-08-03 | 2015-12-02 | 中铁港航局集团有限公司 | 一种斜拉桥主塔索导管安装和快速精确定位方法 |
CN105648923A (zh) * | 2016-03-31 | 2016-06-08 | 中铁四局集团第工程有限公司 | 一种斜拉索鞍座的定位装置及其定位方法 |
CN205999789U (zh) * | 2016-08-08 | 2017-03-08 | 中交一公局第三工程有限公司 | 斜拉桥混凝土梁索导管支撑定位装置 |
Non-Patent Citations (1)
Title |
---|
"长山大桥主塔施工技术";苏洪波;《四川水泥》;20150215(第2期);第210、220页 * |
Also Published As
Publication number | Publication date |
---|---|
CN106544959A (zh) | 2017-03-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103243930B (zh) | 超高层钢结构模块化施工系统及其方法 | |
CN106544959B (zh) | 含有鞍座的主塔吊装节段及桥梁主塔鞍座的施工方法 | |
CN106087752B (zh) | 多跨提篮拱桥施工方法 | |
CN106703416A (zh) | 狭小空间中钢结构屋架拔杆吊装方法 | |
CN206692235U (zh) | 一种钢结构穹顶起吊安装装置 | |
CN101440667A (zh) | 大跨度单层雨棚网壳结构安装方法 | |
CN102121273A (zh) | 一种钢筋混凝土烟囱钢内筒液压提升倒装方法 | |
CN206233102U (zh) | 一种可移动式临边作业工作平台 | |
CN109138454A (zh) | 一种超高层建筑外框带状桁架的安装方法 | |
CN105781210B (zh) | 一种锥形塔架及其工具节辅助穿心式整体提升施工方法 | |
CN105804400A (zh) | 一种曲面网架提升施工方法 | |
CN205973618U (zh) | 一种烟囱内筒节提升装置 | |
CN104627849B (zh) | 一种用于内天井管道吊装的吊装设备及吊装方法 | |
CN105018115B (zh) | 干熄焦一次除尘器分片吊装方法 | |
CN106121040A (zh) | 一种焊接格构柱装置及焊接方法 | |
CN106567548B (zh) | 方形原煤斗分段安装工法 | |
CN106567542A (zh) | 一种超高层双塔楼钢结构连廊组装方法 | |
CN101109028A (zh) | 转炉炉壳倒装液压提升方法 | |
CN102226497B (zh) | 大型橡胶卷帘密封干式气柜的制作方法 | |
CN104060836B (zh) | 高曲面网架的提升安装方法 | |
CN107419907B (zh) | 一种炼钢塔楼钢结构平台的交错安装焊接方法 | |
CN101818563B (zh) | 自升式整体提升移动平台及使用方法 | |
CN106120573B (zh) | 跨海多跨提篮拱桥自平衡扣挂施工方法 | |
CN105625732B (zh) | 超高悬挑钢结构桁架无支撑施工方法 | |
CN104775363A (zh) | 上塔柱钢筋节段的组拼方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |