CN104179341A - Method for mounting combining and positioning devices of cantilever bearing frames - Google Patents
Method for mounting combining and positioning devices of cantilever bearing frames Download PDFInfo
- Publication number
- CN104179341A CN104179341A CN201410417799.4A CN201410417799A CN104179341A CN 104179341 A CN104179341 A CN 104179341A CN 201410417799 A CN201410417799 A CN 201410417799A CN 104179341 A CN104179341 A CN 104179341A
- Authority
- CN
- China
- Prior art keywords
- encorbelmenting
- bolt
- heavy frame
- wall
- leading edge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 23
- 238000009434 installation Methods 0.000 claims abstract description 32
- 229910000831 Steel Inorganic materials 0.000 claims description 34
- 239000004567 concrete Substances 0.000 claims description 34
- 239000010959 steel Substances 0.000 claims description 34
- 238000003466 welding Methods 0.000 claims description 12
- 239000000725 suspension Substances 0.000 claims description 9
- 238000005452 bending Methods 0.000 claims description 6
- 239000011178 precast concrete Substances 0.000 claims description 6
- 230000003014 reinforcing effect Effects 0.000 claims description 5
- 238000004519 manufacturing process Methods 0.000 claims description 4
- 238000002513 implantation Methods 0.000 claims description 3
- 230000035515 penetration Effects 0.000 claims description 3
- 229920003023 plastic Polymers 0.000 claims description 3
- 239000004033 plastic Substances 0.000 claims description 3
- 230000002787 reinforcement Effects 0.000 claims description 2
- 210000001320 hippocampus Anatomy 0.000 claims 4
- 210000003205 muscle Anatomy 0.000 claims 4
- 230000015572 biosynthetic process Effects 0.000 claims 1
- 230000015271 coagulation Effects 0.000 claims 1
- 238000005345 coagulation Methods 0.000 claims 1
- 230000006835 compression Effects 0.000 claims 1
- 238000007906 compression Methods 0.000 claims 1
- 239000000284 extract Substances 0.000 claims 1
- 238000009415 formwork Methods 0.000 claims 1
- 230000008014 freezing Effects 0.000 claims 1
- 238000007710 freezing Methods 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 14
- 238000010586 diagram Methods 0.000 description 7
- 238000003825 pressing Methods 0.000 description 7
- 230000000149 penetrating effect Effects 0.000 description 3
- 238000007711 solidification Methods 0.000 description 3
- 230000008023 solidification Effects 0.000 description 3
- 238000009435 building construction Methods 0.000 description 2
- 210000005069 ears Anatomy 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000007787 solid Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000000605 extraction Methods 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 125000006850 spacer group Chemical group 0.000 description 1
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
本发明公开了一种悬挑承力架组合定位装置安装方法,包括如下步骤:一)悬挑承力架的前缘定位装置安装;二)悬挑承力架的尾部固定装置安装;三)悬挑承力架拉索的前缘吊耳安装;四)悬挑承力架的穿墙吊耳安装;五)悬挑承力架拉索的可调拉索安装;六)悬挑承力架拉索的连墙件安装。本发明的优点是:可提高悬挑脚手架安装精准性、使用可靠性、提高施工效率;装置可重复使用,降低施工成本,保证质量。
The invention discloses a method for installing a combined positioning device of a cantilevered load-bearing frame, comprising the following steps: 1) installing the front edge positioning device of the cantilevered load-bearing frame; 2) installing the tail fixing device of the cantilevered load-bearing frame; 3) Installation of the front edge lugs of the cables of the cantilever load-bearing frame; 4) Installation of the through-wall lugs of the cantilever load-bearing frame; 5) Installation of adjustable cables for the cables of the cantilever load-bearing frame; The installation of the connecting wall parts of the cable. The invention has the advantages of improving the installation accuracy and reliability of the cantilevered scaffold, and improving the construction efficiency; the device can be used repeatedly, reducing the construction cost and ensuring the quality.
Description
技术领域 technical field
本发明涉及一种建筑施工方法,更具体的说,是涉及一种悬挑承力架组合定位装置安装方法。 The invention relates to a building construction method, more specifically, to a method for installing a combined positioning device of a cantilever bearing frame.
背景技术 Background technique
现有的建筑施工扣件式钢管脚手架施工技术,在悬挑脚手架的安装及其辅助装置方面的规定较为简易,而实际施工安装中存在安全、质量、成本等许多问题,如承力架拉索与型钢接触部位的保护问题,立杆在承力架上定位问题,承力架固定装置的重复使用问题,承力架吊耳装置及设置问题,悬挑脚手架连墙件的设置方式与再应用问题等,这些问题会影响悬挑脚手架的使用安全,影响安装操作质量和建筑物保护周期,影响脚手架租赁单位的经济效益。目前的施工技术存在现场焊接条件差、焊接质量低、易引发火灾等问题。 The existing construction technology of fastener-type steel pipe scaffolding for building construction has relatively simple regulations on the installation of cantilevered scaffolding and its auxiliary devices, but there are many problems in the actual construction and installation, such as safety, quality, and cost. The protection of the parts in contact with the section steel, the positioning of the vertical pole on the load-bearing frame, the reuse of the load-bearing frame fixing device, the lifting lug device and setting of the load-bearing frame, the setting method and re-application of the cantilevered scaffolding wall parts Problems, etc. These problems will affect the safety of the use of cantilevered scaffolding, affect the quality of installation operations and building protection cycle, and affect the economic benefits of scaffolding rental units. The current construction technology has problems such as poor on-site welding conditions, low welding quality, and easy fire hazards.
发明内容 Contents of the invention
本发明针对现有技术的不足,而提供一种施工安装简易便捷、可反复使用、安全可靠、能节约租赁和使用成本、提高承力架安全稳定性的悬挑承力架组合定位装置安装方法。 Aiming at the deficiencies of the prior art, the present invention provides an installation method of a cantilever load-bearing frame combination positioning device that is simple and convenient in construction and installation, can be used repeatedly, is safe and reliable, can save rental and use costs, and improves the safety and stability of the load-bearing frame .
本发明的一种悬挑承力架组合定位装置安装方法,包括以下步骤: A method for installing a combined positioning device of a cantilever bearing frame according to the present invention comprises the following steps:
A、预埋安装前缘吊耳: A. Pre-embedded installation of front edge lugs:
在混凝土墙体施工时预埋安装前缘吊耳,将前缘吊耳安装在悬挑承力架的伸出端的前缘部位,安装时将挂环朝上,下托筋与悬挑承力架下轴截面接触,限位筋与悬挑承力架上轴截面接触,平行向内滑移,使用三角形木塞将前缘吊耳与悬挑承力架稳定在90°状态; Pre-buried and installed the front edge lugs during the construction of the concrete wall, and installed the front edge lugs on the front edge of the protruding end of the cantilever bearing frame. The cross-section of the lower shaft of the frame is in contact, the limit rib is in contact with the upper shaft cross-section of the cantilever bearing frame, and slides inward in parallel, and the front edge lug and the cantilever bearing frame are stabilized at 90° by using a triangular wooden stopper;
B、预埋安装穿墙吊耳: B. Pre-buried installation through the wall lugs:
首先将护套管按预定位置预埋在混凝土墙体中,预埋时保持护套管尾端外高内低,护套管长度与混凝土墙体厚度一致,护套管作为穿墙杆前端从中穿入和拔出的间隔之用;然后将穿墙杆螺纹端从护套管外口穿入吊环在外,挡板穿入穿墙杆中螺纹中,将固定螺母拧入;待混凝土墙体达到凝固期后,将固定螺母拧紧,采取双螺母加固; Firstly, the sheath pipe is pre-embedded in the concrete wall according to the predetermined position. When pre-embedding, keep the tail end of the sheath pipe high on the outside and low on the inside. The length of the sheath pipe is consistent with the thickness of the concrete wall. It is used for the interval between penetration and extraction; then the threaded end of the wall-through rod is inserted from the outer port of the sheath pipe into the suspension ring, the baffle is penetrated into the thread of the wall-through rod, and the fixing nut is screwed in; when the concrete wall reaches the After the solidification period, tighten the fixing nut and adopt double nuts for reinforcement;
C、预埋安装尾部固定装置: C. Pre-embedded installation of tail fixing device:
在混凝土楼板施工时预埋安装尾部固定装置,首先安装护套管,护套管的长度和混凝土楼板厚度相同,在混凝土楼板支模绑扎钢筋时,将护套管、下托板和固定螺栓同时与钢筋绑扎固定; Pre-buried and installed the tail fixing device during the construction of the concrete floor. First, install the sheath tube. The length of the sheath tube is the same as the thickness of the concrete floor. Binding and fixing with steel bars;
然后将悬挑承力架的双轴对称截面端置于楼层面上四周内侧,一端伸出楼层外侧承载悬挑立杆架,另一端置于楼层面上预埋护套管和伸出的固定螺栓对应的中间位置,作为固定段安装尾部固定装置; Then place the biaxially symmetrical cross-section end of the cantilever bearing frame on the inner side of the floor, one end extends out of the floor to carry the cantilevered pole frame, and the other end is placed on the floor to pre-embed the sheath tube and the extended fixing bolt The corresponding middle position is used as a fixed section to install the tail fixing device;
最后安装尾部固定装置,每根悬挑承力架中设置二组尾部固定装置,将上压板从固定螺栓中穿入,采用固定螺母拧入固定螺栓之中,对称拧紧固定螺母,压紧悬挑承力架,再拧紧第二个固定螺母防止松懈,尾部固定装置安装后下托板与楼板底部贴紧,悬挑承力架下截面与楼板上部贴紧,上压板与悬挑承力架的上截面贴紧,形成尾部固定装置混凝土楼板和悬挑承力架牢固的整体; Finally install the tail fixing device, set two sets of tail fixing devices in each cantilever bearing frame, penetrate the upper pressure plate through the fixing bolts, screw the fixing nuts into the fixing bolts, tighten the fixing nuts symmetrically, and press the cantilever Bearing frame, then tighten the second fixing nut to prevent loosening. After the tail fixing device is installed, the lower supporting plate is closely attached to the bottom of the floor, the lower section of the cantilever bearing frame is closely attached to the upper part of the floor, and the upper pressure plate is closely attached to the cantilever bearing frame. The upper section is tightly attached to form a solid whole of the concrete floor of the tail fixing device and the cantilever bearing frame;
D、安装前缘定位装置; D. Install the leading edge positioning device;
将前缘定位装置的两根U型螺栓分别从悬挑承力架伸出端的前缘部位穿入,将两块承压板分别通过两个U形螺栓穿入,置于悬挑承力架上部截面,将垫块置于U形螺栓中,使用固定螺母拧入U形螺栓两端,将承压板、U形螺栓、垫块和悬挑承力架形成四位一体,前缘定位装置调整后,对称拧紧固定螺母; Insert the two U-shaped bolts of the front edge positioning device from the front edge of the cantilever bearing frame extension, respectively penetrate the two pressure bearing plates through the two U-shaped bolts, and place them on the cantilever bearing frame For the upper section, place the pads in the U-shaped bolts, use the fixing nuts to screw into the two ends of the U-shaped bolts, and form a four-in-one structure of the pressure bearing plate, U-shaped bolts, pads and cantilever bearing frame, and the front edge positioning device After adjustment, tighten the fixing nuts symmetrically;
E、安装悬挑立杆和横杆: E. Install cantilevered poles and crossbars:
在前缘定位装置的定位轴上固定安装两根悬挑立杆,在两根悬挑立杆之间通过钢管扣件固定安装横杆; Two cantilevered vertical rods are fixedly installed on the positioning shaft of the front edge positioning device, and a cross bar is fixedly installed between the two cantilevered vertical rods through steel pipe fasteners;
F、安装可调拉索: F. Install the adjustable cable:
可调拉索分为上拉索和下拉索,首先安装上拉索,将上拉索的一端从穿墙吊耳中连同鸡心环一并穿出,穿出的上拉索超过三只绳扣固定距离时开始折返,穿入并折返后的上拉索包裹鸡心环形成可活动的绳耳挂环状时,按规定将三只绳扣与上拉索固定,上拉索伸长的另一端与花篮螺栓连接; The adjustable cable is divided into the upper cable and the lower cable. First, install the upper cable, and pass one end of the upper cable through the wall lug together with the heart ring. The upper cable that passes through is more than three rope buckles. When the distance is fixed, it starts to turn back. When the top cable that has been penetrated and turned back wraps the heart ring to form a movable rope ear hanging ring, fix the three rope buckles with the top cable according to the regulations, and the other end of the top cable is extended. Connect with turnbuckle bolts;
然后安装下拉索,将下拉索的一端从穿墙吊耳中连同鸡心环一并穿出,穿出的下拉索超过三只绳扣固定距离时开始折返,穿入并折返后的下拉索包裹鸡心环形成可活动的绳耳挂环状时,按规定将三只绳扣与下拉索固定,下拉索伸长的另一端与花篮螺栓连接; Then install the pull-down cable, and pass one end of the pull-down cable through the wall lug together with the heart ring. When the pull-down cable passes through the fixed distance of the three rope buckles, it starts to turn back, and the pull-down cable that passes through and turns back wraps the heart When the ring forms a movable rope ear hanging ring, fix the three rope buckles with the pull-down cable according to the regulations, and the other end of the pull-down cable is connected to the turnbuckle bolt;
最后安装调节花篮螺栓,上拉索的上端与穿墙吊耳连接,下端挂入花篮螺栓的挂钩上,下拉索挂入花篮螺栓的挂钩上,下端挂入前缘吊耳的挂环中,上拉索、下拉索、花篮螺栓连为一体形成直线后,调节花篮螺栓至拉索绷紧即可; Finally, install and adjust the turnbuckle bolts. The upper end of the upper cable is connected to the hanging lug through the wall, and the lower end is hung on the hook of the turnbuckle bolt. After the cable, pull cable and turnbuckle are connected together to form a straight line, adjust the turnbuckle until the cable is tight;
G、安装连墙件: G. Install the wall parts:
将护套管在预制混凝土墙体时植入预制混凝土墙体的钢筋中,护套管植入位置符合专项方案要求,将连墙件的固定螺栓的一端从混凝土墙体外侧穿入护套管,至连接板端面与混凝土墙体接触止,在穿出混凝土墙体的固定螺栓的部位,将垫板套入固定螺栓中,将两个固定螺母拧入固定螺栓之中;待预制混凝土墙体凝固成型后,将两个固定螺母拧紧,至连墙件固定在墙体上呈水平状,把连接杆与连墙杆通过钢管扣件固定连接,形成悬挑立杆、横杆和连墙件成一整体。 Insert the sheath tube into the steel bar of the precast concrete wall when the concrete wall is prefabricated. The implantation position of the sheath tube meets the requirements of the special plan. Insert one end of the fixing bolt of the wall fitting into the sheath tube from the outside of the concrete wall. , until the end face of the connecting plate is in contact with the concrete wall, insert the backing plate into the fixing bolt at the part of the fixing bolt passing through the concrete wall, and screw the two fixing nuts into the fixing bolt; the prefabricated concrete wall After solidification and molding, tighten the two fixing nuts until the wall parts are fixed on the wall in a horizontal state, and the connecting rods and the wall rods are fixedly connected by steel pipe fasteners to form cantilevered vertical bars, horizontal bars and wall parts into a whole.
所述悬挑承力架由双轴对称截面的H型钢制成。 The cantilever bearing frame is made of H-shaped steel with biaxially symmetrical cross section.
所述悬挑承力架的固定段长度不小于悬挑段长度的1.25倍。 The length of the fixed section of the cantilevered bearing frame is not less than 1.25 times the length of the cantilevered section.
所述前缘吊耳由挂环、立筋、限位筋和下托筋组成;所述前缘吊耳制作过程为:把直径20mm钢筋从下托筋开始沿悬挑承力架一侧90°弯折,至悬挑承力架的上轴截面时开始向内收合折弯8-10°形成带折弯的立筋,再向下折返成带吊耳状的弧度形成挂环,再继续向下折返成形成对称的花篮形立筋,再与下托筋交会处进行固定,在立筋二侧的垂直部位悬挑承力架上轴截面焊接一根限位筋,防止前缘吊耳在悬挑承力架上滑动或脱落。 The front edge lifting lug is composed of a hanging ring, vertical ribs, limit ribs and lower supporting ribs; the manufacturing process of the leading edge lifting lugs is as follows: a steel bar with a diameter of 20 mm is placed along one side of the cantilever bearing frame for 90 degrees from the lower supporting ribs. ° bending, when reaching the upper shaft section of the cantilevered load-bearing frame, it starts to bend inwardly for 8-10° to form a vertical rib with bending, and then folds back downwards to form a hanging ring with a radian in the shape of a lifting ear, and then Continue to fold back down to form a symmetrical flower basket-shaped vertical bar, and then fix it at the intersection with the lower support bar. A limit rib is welded to the upper shaft section of the cantilevered force-bearing frame at the vertical part on both sides of the vertical bar to prevent the front edge from hanging. Ears slide or fall off on overhanging bearing frame.
所述穿墙吊耳由护套管、穿墙杆、吊环、挡板和固定螺母组成;所述穿墙杆和吊环为一整体,穿墙杆前端为80-100mm螺纹段,尾端制成直径80-100mm的吊环,作为上拉索使用;所述挡板由矩形钢板制成,在挡板的中心位置设置有固定穿墙杆的孔。 The wall-piercing lug is composed of a sheath pipe, a wall-piercing rod, a lifting ring, a baffle and a fixing nut; the wall-piercing rod and the hanging ring are integrated, and the front end of the wall-piercing rod is an 80-100mm threaded section, and the tail end is made of A suspension ring with a diameter of 80-100mm is used as an upper cable; the baffle is made of a rectangular steel plate, and a hole for fixing a wall-through rod is arranged at the center of the baffle.
所述尾部固定装置由上压板、下托板、固定螺栓、固定螺母和护套管组成;所述上压板由厚度15-20mm的矩形钢板制成,在上压板中心部位两侧设置有固定螺栓用的孔;所述下托板由厚度15-20mm的矩形钢板制成,在下托板两侧与上压板对应的位置开设有两个焊接孔,所述固定螺栓穿过焊接孔,固定螺栓端部设置有长度25-35mm螺纹;所述护套管由外径22-25mm塑料穿线管制成。 The tail fixing device is composed of an upper pressing plate, a lower supporting plate, fixing bolts, fixing nuts and a sheath tube; the upper pressing plate is made of a rectangular steel plate with a thickness of 15-20 mm, and fixing bolts are arranged on both sides of the center of the upper pressing plate The hole used; the lower supporting plate is made of a rectangular steel plate with a thickness of 15-20mm, and two welding holes are opened at the positions corresponding to the upper pressing plate on both sides of the lower supporting plate, and the fixing bolts pass through the welding holes, and the fixed bolt ends The upper part is provided with a thread with a length of 25-35mm; the sheath tube is made of a plastic threading tube with an outer diameter of 22-25mm.
所述前缘定位装置由U型螺栓、承压板、定位轴、垫块和固定螺母组成;所述U形螺栓采用钢筋制成“U”形,U形螺栓上端设置有长度25-35mm螺纹;所述承压板由厚度10-15mm矩形钢板制成,在承压板两侧开设两个螺栓孔,U形螺栓从孔中穿出固定承压板;所述定位轴固定连接在承压板的中心位置;所述垫块由厚度8-10mm矩形钢板制成,在垫块中心位置开设略大于U形螺栓直径的孔。 The front edge positioning device is composed of U-shaped bolts, pressure bearing plates, positioning shafts, pads and fixing nuts; the U-shaped bolts are made of steel bars into a "U" shape, and the upper ends of the U-shaped bolts are provided with threads with a length of 25-35mm. The pressure bearing plate is made of a rectangular steel plate with a thickness of 10-15mm, and two bolt holes are opened on both sides of the pressure bearing plate, and U-shaped bolts pass through the holes to fix the pressure bearing plate; the positioning shaft is fixedly connected to the pressure bearing plate. The center position of the plate; the pad is made of a rectangular steel plate with a thickness of 8-10mm, and a hole slightly larger than the diameter of the U-shaped bolt is opened at the center of the pad.
所述连墙件由连接杆、连墙杆、连接板、垫板、固定螺栓、固定螺母和护套管组成;所述连墙杆与连接板焊接固定,所述连接板中心位置设置有与固定螺栓直接对应的孔,将固定螺栓无丝扣的一端插入孔中略低于连接板,所述固定螺栓与连接板垂直固定焊接,所述连墙杆端面与连接板平面点焊接,所述垫板中间开设有螺栓孔。 The wall connecting piece is composed of a connecting rod, a wall connecting rod, a connecting plate, a backing plate, a fixing bolt, a fixing nut and a sheath tube; The hole directly corresponding to the fixing bolt, insert the end of the fixing bolt without thread into the hole slightly lower than the connecting plate, the fixing bolt and the connecting plate are fixed and welded vertically, the end face of the connecting wall rod is spot-welded with the connecting plate plane, the Bolt holes are provided in the middle of the backing plate.
所述U形螺栓上端螺纹段为左右旋螺纹,螺纹上设置有两个固定螺母,一个为左旋和另一个为右旋。 The threaded section at the upper end of the U-shaped bolt is a left-handed thread, and two fixing nuts are arranged on the thread, one is left-handed and the other is right-handed.
所述U形螺栓拧紧扭力矩不小于40N.m,不大于65N.m。 The tightening torque of the U-shaped bolts is not less than 40N.m and not greater than 65N.m.
本发明的有益效果是:(1)实用本发明方法安装后悬挑承力架立杆定位稳定,承力架尾部稳固,上下双吊耳及拉索固定,非预埋连墙件可任意位置使用,增加了连墙件使用范围。(2)本发明安装方法可提高悬挑脚手架安装精准性和使用可靠性,保证施工质量。(3)本发明的装置作为悬挑脚手架附属产品,可定制生产制作,弥补了目前没有承力架附属固定装置的空白。(4)本发明的装置可重复使用,能降低施工成本,提高施工效率。 The beneficial effects of the present invention are: (1) After the method of the present invention is applied, the vertical rod of the cantilever load-bearing frame is positioned stably, the tail of the load-bearing frame is stable, the upper and lower double lugs and cables are fixed, and the non-embedded wall parts can be placed at any position Use, increase the scope of use of wall parts. (2) The installation method of the present invention can improve the installation accuracy and reliability of the cantilevered scaffold, and ensure the construction quality. (3) The device of the present invention, as an accessory product of a cantilevered scaffold, can be customized and produced, which makes up for the gap that there is no accessory fixing device for a load-bearing frame at present. (4) The device of the present invention can be used repeatedly, which can reduce construction cost and improve construction efficiency.
附图说明 Description of drawings
图1是本发明的总安装示意图; Fig. 1 is the general installation schematic diagram of the present invention;
图2是本发明图1中的前缘定位装置示意图; Fig. 2 is a schematic diagram of the leading edge positioning device in Fig. 1 of the present invention;
图3是本发明图1中的尾部固定装置示意图; Fig. 3 is a schematic diagram of the tail fixing device in Fig. 1 of the present invention;
图4是本发明图1中的前缘吊耳示意图; Fig. 4 is a schematic diagram of the leading edge lifting lug in Fig. 1 of the present invention;
图5是本发明图1中的穿墙吊耳示意图; Fig. 5 is a schematic diagram of the wall-piercing lug in Fig. 1 of the present invention;
图6是本发明图1中的可调拉索示意图; Fig. 6 is a schematic diagram of the adjustable dragline in Fig. 1 of the present invention;
图7是本发明图1中的连墙件示意图。 Fig. 7 is a schematic diagram of the wall connecting piece in Fig. 1 of the present invention.
具体实施方式 Detailed ways
下面结合附图对本发明作进一步的描述。 The present invention will be further described below in conjunction with the accompanying drawings.
如图1所示,本发明的一种悬挑承力架组合定位装置安装方法,包括以下步骤: As shown in Figure 1, a method for installing a cantilever bearing frame combined positioning device of the present invention includes the following steps:
A、预埋安装前缘吊耳6: A. Pre-embedded installation of front edge lifting lug 6:
在混凝土墙体5-2施工时预埋安装前缘吊耳6,将前缘吊耳6安装在悬挑承力架2的伸出端的前缘部位,安装时将挂环6-1朝上,下托筋6-4与悬挑承力架2下轴截面接触,限位筋6-3与悬挑承力架2上轴截面接触,平行向内滑移,使用三角形木塞将前缘吊耳6与悬挑承力架2稳定在90°状态; During the construction of the concrete wall 5-2, the front edge lug 6 is pre-buried and installed, and the front edge lug 6 is installed on the front edge of the protruding end of the cantilever bearing frame 2, and the hanging ring 6-1 is facing upward during installation. , the lower supporting rib 6-4 is in contact with the lower shaft section of the cantilever bearing frame 2, the limit rib 6-3 is in contact with the upper shaft section of the cantilever bearing frame 2, and slides inward in parallel, using a triangular wooden stopper to seal the front edge The lifting lug 6 and the cantilever bearing frame 2 are stable at 90°;
B、预埋安装穿墙吊耳7: B. Pre-embedded installation through the wall lug 7:
首先将护套管7-1按预定位置预埋在混凝土墙体5-2中,预埋时保持护套管7-1尾端外高内低,护套管7-1长度与混凝土墙体5-2厚度一致,护套管7-1作为穿墙杆7-2前端从中穿入和拔出的间隔之用;然后将穿墙杆7-2螺纹端从护套管7-1外口穿入吊环7-3在外,挡板穿入穿墙杆7-2中螺纹中,将固定螺母7-5拧入;待混凝土墙体5-2达到凝固期后,将固定螺母7-5拧紧,采取双螺母加固; First, the sheath pipe 7-1 is pre-embedded in the concrete wall 5-2 according to the predetermined position. When pre-embedding, the tail end of the sheath pipe 7-1 is kept high on the outside and low on the inside, and the length of the sheath pipe 7-1 is the same as that of the concrete wall. 5-2 The thickness is the same, and the sheath pipe 7-1 is used as a space for the front end of the wall-piercing rod 7-2 to penetrate and pull out; Penetrate the suspension ring 7-3 outside, and the baffle penetrates into the thread in the wall rod 7-2, and screw the fixing nut 7-5 in; after the concrete wall 5-2 reaches the solidification period, tighten the fixing nut 7-5 , reinforced with double nuts;
C、预埋安装尾部固定装置4: C. Pre-embedded installation of tail fixing device 4:
在混凝土楼板5-1施工时预埋安装尾部固定装置4,首先安装护套管4-5,护套管4-5的长度和混凝土楼板厚度相同,在混凝土楼板支模绑扎钢筋时,将护套管4-5、下托板4-2和固定螺栓4-3同时与钢筋绑扎固定; When the concrete floor 5-1 is constructed, the tail fixing device 4 is pre-embedded, and the sheath pipe 4-5 is installed at first. The length of the sheath pipe 4-5 is the same as the thickness of the concrete floor. The sleeve pipe 4-5, the lower supporting plate 4-2 and the fixing bolt 4-3 are bound and fixed with the reinforcing bar at the same time;
然后将悬挑承力架2的双轴对称截面端置于楼层面上四周内侧,一端伸出楼层外侧承载悬挑立杆架1,另一端置于楼层面上预埋护套管4-5和伸出的固定螺栓4-3对应的中间位置,作为固定段安装尾部固定装置4; Then place the biaxially symmetrical cross-section end of the cantilever bearing frame 2 on the inner side of the floor, one end stretches out from the outside of the floor to carry the cantilever pole frame 1, and the other end is placed on the floor to pre-embed the sheath pipe 4-5 The intermediate position corresponding to the protruding fixing bolt 4-3 is used as a fixing section to install the tail fixing device 4;
最后安装尾部固定装置4,每根悬挑承力架2中设置二组尾部固定装置4,将上压板4-1从固定螺栓4-3中穿入,采用固定螺母4-4拧入固定螺栓4-3之中,对称拧紧固定螺母4-4,压紧悬挑承力架2,再拧紧第二个固定螺母4-4防止松懈,尾部固定装置4安装后下托板4-2与楼板5-1底部贴紧,悬挑承力架2下截面与楼板5-1上部贴紧,上压板4-1与悬挑承力架2的上截面贴紧,形成尾部固定装置4混凝土楼板5-1和悬挑承力架2牢固的整体; Finally install the tail fixing device 4, set two sets of tail fixing devices 4 in each cantilever bearing frame 2, penetrate the upper pressure plate 4-1 from the fixing bolt 4-3, and screw the fixing nut 4-4 into the fixing bolt Among 4-3, tighten the fixing nuts 4-4 symmetrically, press the cantilever bearing frame 2, and then tighten the second fixing nut 4-4 to prevent loosening. After the tail fixing device 4 is installed, the lower supporting plate 4-2 and the floor 5-1 The bottom is close, the lower section of the cantilever bearing frame 2 is closely attached to the upper part of the floor 5-1, and the upper pressure plate 4-1 is closely attached to the upper section of the cantilever bearing frame 2, forming a tail fixing device 4 Concrete floor 5 -1 and the cantilever bearing frame 2 are a solid whole;
D、安装前缘定位装置3; D. Install the leading edge positioning device 3;
将前缘定位装置3的两根U型螺栓3-1分别从悬挑承力架2伸出端的前缘部位穿入,将两块承压板3-2分别通过两个U形螺栓3-1穿入,置于悬挑承力架2上部截面,将垫块3-4置于U形螺栓3-1中,使用固定螺母3-5拧入U形螺栓3-1两端,将承压板3-2、U形螺栓3-1、垫块3-4和悬挑承力架2形成四位一体,前缘定位装置3调整后,对称拧紧固定螺母3-5; Insert the two U-shaped bolts 3-1 of the front edge positioning device 3 from the front edge of the extended end of the cantilever bearing frame 2, and pass the two pressure-bearing plates 3-2 through the two U-shaped bolts 3-1 respectively. 1 penetrate, place on the upper section of the cantilever bearing frame 2, place the cushion block 3-4 in the U-shaped bolt 3-1, use the fixing nut 3-5 to screw into the two ends of the U-shaped bolt 3-1, and place the bearing Pressing plate 3-2, U-shaped bolt 3-1, cushion block 3-4 and cantilever bearing frame 2 form a four-in-one body. After the front edge positioning device 3 is adjusted, tighten the fixing nut 3-5 symmetrically;
E、安装悬挑立杆1和横杆1-1: E. Install the cantilevered pole 1 and the crossbar 1-1:
在前缘定位装置3的定位轴3-3上固定安装两根悬挑立杆1,在两根悬挑立杆1之间通过钢管扣件1-2固定安装横杆1-1; Two cantilevered vertical rods 1 are fixedly installed on the positioning shaft 3-3 of the leading edge positioning device 3, and a cross bar 1-1 is fixedly installed between the two cantilevered vertical rods 1 through a steel pipe fastener 1-2;
F、安装可调拉索: F. Install the adjustable cable:
可调拉索分为上拉索8-1和下拉索8-2,首先安装上拉索8-1,将上拉索8-1的一端从穿墙吊耳7中连同鸡心环8-3一并穿出,穿出的上拉索8-1超过三只绳扣8-4固定距离时开始折返,穿入并折返后的上拉索8-1包裹鸡心环8-3形成可活动的绳耳8-5挂环状时,按规定将三只绳扣8-4与上拉索8-1固定,上拉索8-1伸长的另一端与花篮螺栓9连接; The adjustable cable is divided into an upper cable 8-1 and a lower cable 8-2. First, install the upper cable 8-1, and put one end of the upper cable 8-1 from the wall hanging ear 7 together with the heart ring 8-3 Go out together, when the upper stay cable 8-1 that passes out exceeds the fixed distance of three rope buckles 8-4, it starts to turn back, and the upper stay cable 8-1 after passing through and turned back wraps the heart ring 8-3 to form a movable When the rope lug 8-5 hangs in the form of a ring, fix the three rope buckles 8-4 with the upper stay cable 8-1 according to the regulations, and the other end of the upper stay cable 8-1 elongated is connected with the turnbuckle bolt 9;
然后安装下拉索8-2,将下拉索8-2的一端从穿墙吊耳7中连同鸡心环8-3一并穿出,穿出的下拉索8-2超过三只绳扣8-4固定距离时开始折返,穿入并折返后的下拉索8-2包裹鸡心环8-3形成可活动的绳耳8-5挂环状时,按规定将三只绳扣8-4与下拉索8-2固定,下拉索8-2伸长的另一端与花篮螺栓9连接; Then install the drop cable 8-2, and pass one end of the drop cable 8-2 together with the heart ring 8-3 from the wall hanging ear 7, and the drop cable 8-2 that passes through exceeds three rope buckles 8-4 When the fixed distance starts to turn back, when the pull-down cable 8-2 wrapping the heart ring 8-3 after penetrating and turning back forms a movable rope ear 8-5 hanging ring shape, connect the three rope buckles 8-4 with the pull-down cable according to regulations. 8-2 is fixed, and the other end of the extension of the pull-down cable 8-2 is connected with the basket bolt 9;
最后安装调节花篮螺栓9,上拉索8-1的上端与穿墙吊耳7连接,下端挂入花篮螺栓9的挂钩上,下拉索8-2挂入花篮螺栓9的挂钩上,下端挂入前缘吊耳6的挂环6-1中,上拉索8-1、下拉索8-2、花篮螺栓9连为一体形成直线后,调节花篮螺栓9至拉索绷紧即可; Finally install and adjust the turnbuckle bolt 9, the upper end of the upper pull cable 8-1 is connected with the wall-through lug 7, the lower end is hung on the hook of the turnbuckle bolt 9, the lower cable 8-2 is hung on the hook of the turnbuckle bolt 9, and the lower end is hung into the hook of the turnbuckle bolt 9. In the hanging ring 6-1 of the lifting lug 6 at the front edge, after the upper cable 8-1, the lower cable 8-2, and the turnbuckle bolt 9 are connected to form a straight line, adjust the turnbuckle bolt 9 until the cable is tight;
G、安装连墙件10: G. Install the wall piece 10:
将护套管10-7在预制混凝土墙体5-2时植入预制混凝土墙体5-2的钢筋中,护套管10-7植入位置符合专项方案要求,将连墙件10的固定螺栓10-5的一端从混凝土墙体5-2外侧穿入护套管10-7,至连接板10-3端面与混凝土墙体5-2接触止,在穿出混凝土墙体5-2的固定螺栓10-5的部位,将垫板10-4套入固定螺栓10-5中,将两个固定螺母10-6拧入固定螺栓10-5之中;待预制混凝土墙体5-2凝固成型后,将两个固定螺母10-6拧紧,至连墙件10固定在墙体上呈水平状,把连接杆10-1与连墙杆10-2通过钢管扣件1-2固定连接,形成悬挑立杆1、横杆1-1和连墙件10成一整体。 The sheath pipe 10-7 is implanted into the steel bar of the precast concrete wall 5-2 when the prefabricated concrete wall 5-2 is in place, and the implantation position of the sheath pipe 10-7 meets the requirements of the special plan, and the fixing of the connecting wall piece 10 One end of the bolt 10-5 penetrates the sheath pipe 10-7 from the outside of the concrete wall 5-2 until the end surface of the connecting plate 10-3 contacts the concrete wall 5-2, and passes through the concrete wall 5-2 Fix the position of the bolt 10-5, insert the backing plate 10-4 into the fixing bolt 10-5, screw the two fixing nuts 10-6 into the fixing bolt 10-5; wait for the precast concrete wall 5-2 to solidify After forming, tighten the two fixing nuts 10-6 until the wall fitting 10 is fixed on the wall in a horizontal state, and the connecting rod 10-1 and the connecting rod 10-2 are fixedly connected through the steel pipe fastener 1-2, The cantilevered vertical bar 1, the cross bar 1-1 and the wall connecting piece 10 are formed as a whole.
所述悬挑承力架2由双轴对称截面的H型钢制成,悬挑承力架2的固定段长度不小于悬挑段长度的1.25倍。 The cantilevered load-bearing frame 2 is made of biaxially symmetrical H-shaped steel, and the length of the fixed section of the cantilevered load-bearing frame 2 is not less than 1.25 times the length of the cantilevered section.
如图4所示,所述前缘吊耳6由挂环6-1、立筋6-2、限位筋6-3和下托筋6-4组成;所述前缘吊耳6制作过程为:把直径20mm钢筋从下托筋6-4开始沿悬挑承力架2一侧90°弯折,至悬挑承力架2的上轴截面时开始向内收合折弯8-10°形成带折弯的立筋6-2,再向下折返成带吊耳状的弧度形成挂环6-1,再继续向下折返成形成对称的花篮形立筋6-2,再与下托筋6-4交会处进行固定,在立筋6-2二侧的垂直部位悬挑承力架2上轴截面焊接一根限位筋6-3,防止前缘吊耳6在悬挑承力架2上滑动或脱落。 As shown in Figure 4, the front edge lug 6 is composed of a hanging ring 6-1, a vertical rib 6-2, a limit rib 6-3 and a lower support rib 6-4; the manufacturing process of the front edge lug 6 It is: bend the steel bar with a diameter of 20mm from the lower supporting bar 6-4 along one side of the cantilever bearing frame 2 at 90°, and start to fold inwardly when reaching the upper shaft section of the cantilever bearing frame 2 for 8-10° ° Form the vertical rib 6-2 with bending, then fold back downwards to form a hanging ring 6-1 in a radian with hanging ears, and then continue to fold back downwards to form a symmetrical flower basket-shaped vertical rib 6-2, and then connect with the lower Fix at the intersection of support ribs 6-4, and weld a limit rib 6-3 on the upper shaft section of the cantilever bearing frame 2 at the vertical position on both sides of the vertical rib 6-2 to prevent the front edge lifting lug 6 from being placed on the cantilever bearing. Sliding or falling off on the power frame 2.
如图5所示,所述穿墙吊耳7由护套管7-1、穿墙杆7-2、吊环7-3、挡板7-4和固定螺母7-5组成;所述穿墙杆7-2和吊环7-3为一整体,穿墙杆7-2前端为80-100mm螺纹段,尾端制成直径80-100mm的吊环7-3,作为上拉索8-1使用;所述挡板7-4由矩形钢板制成,在挡板7-4的中心位置设置有固定穿墙杆7-2的孔。 As shown in Figure 5, the wall penetrating lug 7 is composed of a sheath pipe 7-1, a wall penetrating rod 7-2, a lifting ring 7-3, a baffle plate 7-4 and a fixing nut 7-5; Rod 7-2 and suspension ring 7-3 are a whole, and the front end of wall penetration rod 7-2 is an 80-100mm threaded segment, and the tail end is made into suspension ring 7-3 with a diameter of 80-100mm, which is used as upper stay cable 8-1; The baffle 7-4 is made of a rectangular steel plate, and a hole for fixing the wall-through rod 7-2 is arranged at the center of the baffle 7-4.
如图3所示,所述尾部固定装置4由上压板4-1、下托板4-2、固定螺栓4-3、固定螺母4-4和护套管4-5组成;所述上压板4-1由厚度15-20mm的矩形钢板制成,在上压板4-1中心部位两侧设置有固定螺栓4-3用的孔;所述下托板4-2由厚度15-20mm的矩形钢板制成,在下托板4-2两侧与上压板4-1对应的位置开设有两个焊接孔,所述固定螺栓4-3穿过焊接孔,固定螺栓4-3端部设置有长度25-35mm螺纹;所述护套管4-5由外径22-25mm塑料穿线管制成。 As shown in Figure 3, the tail fixing device 4 is composed of an upper pressing plate 4-1, a lower supporting plate 4-2, a fixing bolt 4-3, a fixing nut 4-4 and a sheath pipe 4-5; the upper pressing plate 4-1 is made of a rectangular steel plate with a thickness of 15-20mm, and holes for fixing bolts 4-3 are arranged on both sides of the center of the upper platen 4-1; the lower supporting plate 4-2 is made of a rectangular plate with a thickness of 15-20mm. Made of steel plate, there are two welding holes on both sides of the lower supporting plate 4-2 corresponding to the upper platen 4-1, the fixing bolt 4-3 passes through the welding hole, and the end of the fixing bolt 4-3 is provided with a length 25-35mm thread; the sheath pipe 4-5 is made of a plastic threading pipe with an outer diameter of 22-25mm.
如图2所示,所述前缘定位装置3由U型螺栓3-1、承压板3-2、定位轴3-3、垫块3-4和固定螺母3-5组成;所述U形螺栓3-1采用钢筋制成“U”形,U形螺栓3-1上端设置有长度25-35mm螺纹;所述承压板3-2由厚度10-15mm矩形钢板制成,在承压板3-2两侧开设两个螺栓孔,U形螺栓3-1从孔中穿出固定承压板3-2;所述定位轴3-3固定连接在承压板3-2的中心位置;所述垫块3-4由厚度8-10mm矩形钢板制成,在垫块3-4中心位置开设略大于U形螺栓3-1直径的孔。 As shown in Figure 2, the front edge positioning device 3 is composed of a U-bolt 3-1, a pressure plate 3-2, a positioning shaft 3-3, a spacer 3-4 and a fixing nut 3-5; the U The U-shaped bolt 3-1 is made of steel bar into a "U" shape, and the upper end of the U-shaped bolt 3-1 is provided with a thread with a length of 25-35 mm; the pressure-bearing plate 3-2 is made of a rectangular steel plate with a thickness of 10-15 mm. Two bolt holes are opened on both sides of the plate 3-2, and U-shaped bolts 3-1 pass through the holes to fix the pressure bearing plate 3-2; the positioning shaft 3-3 is fixedly connected to the center of the pressure bearing plate 3-2 ; The pad 3-4 is made of a rectangular steel plate with a thickness of 8-10mm, and a hole slightly larger than the diameter of the U-shaped bolt 3-1 is opened at the center of the pad 3-4.
如图7所示,所述连墙件10由连接杆10-1、连墙杆10-2、连接板10-3、垫板10-4、固定螺栓10-5、固定螺母10-6和护套管10-7组成;所述连墙杆10-2与连接板10-3焊接固定,所述连接板10-3中心位置设置有与固定螺栓10-5直接对应的孔,将固定螺栓10-5无丝扣的一端插入孔中略低于连接板10-3,所述固定螺栓10-5与连接板10-3垂直固定焊接,所述连墙杆10-2端面与连接板10-3平面点焊接,所述垫板10-4中间开设有螺栓孔。 As shown in Figure 7, the wall connecting piece 10 is composed of connecting rod 10-1, connecting wall rod 10-2, connecting plate 10-3, backing plate 10-4, fixing bolt 10-5, fixing nut 10-6 and The sheath pipe 10-7 is composed of; the connecting wall bar 10-2 is welded and fixed with the connecting plate 10-3, and the center position of the connecting plate 10-3 is provided with a hole directly corresponding to the fixing bolt 10-5, and the fixing bolt 10-5 One end without threaded buckle is inserted into the hole slightly lower than the connection plate 10-3, the fixing bolt 10-5 is fixed and welded vertically with the connection plate 10-3, and the end surface of the connecting wall rod 10-2 is connected with the connection plate 10 -3 Plane spot welding, and a bolt hole is opened in the middle of the backing plate 10-4.
所述U形螺栓3-1上端螺纹段为左右旋螺纹,螺纹上设置有两个固定螺母,一个为左旋和另一个为右旋,U形螺栓3-1拧紧扭力矩不小于40N.m,不大于65N.m。 The thread section at the upper end of the U-shaped bolt 3-1 is a left-handed thread, and two fixing nuts are arranged on the thread, one is left-handed and the other is right-handed, and the tightening torque of the U-shaped bolt 3-1 is not less than 40N.m. Not more than 65N.m.
本发明的装置安装使用后拆卸方法为: The method for disassembling the device after installation and use of the present invention is as follows:
(1)调节花篮螺栓9使上拉索8-1和下拉索8-2松解,拆卸花篮螺栓9、上拉索8-1以及下拉索8-2; (1) Adjust the turnbuckle bolt 9 to loosen the upper cable 8-1 and the lower cable 8-2, and remove the turnbuckle bolt 9, the upper cable 8-1 and the lower cable 8-2;
(2)拆卸悬挑立杆1和横杆1-1; (2) Disassemble the cantilevered vertical bar 1 and the cross bar 1-1;
(3)拆卸连接杆10-1和连墙件10; (3) Disassemble the connecting rod 10-1 and the wall piece 10;
(4)拆卸穿墙吊耳7; (4) Remove the wall-through lug 7;
(5)拆卸前缘定位装置3; (5) Disassemble the leading edge positioning device 3;
(6)拆卸尾部固定装置4; (6) Remove the tail fixing device 4;
(7)拆卸悬挑承力架2; (7) Disassemble the cantilever bearing frame 2;
(8)将各个部件进行组合预紧,防止散落丢失以备再次使用。 (8) Combine and pretighten the various parts to prevent them from being scattered and lost for reuse.
实施例 Example
在某市大型商场高层建设中,60多米高的商贸大厦工程项目采用了悬挑承力架组合定位装置安装方法,成功的解决了悬挑脚手架附属装置缺失的问题,悬挑承力架组合定位装置安装时架设精准、安装方便简单、现场无火源、节约钢材、租赁综合成本低、做到安全可靠的文明施工。悬挑承力架组合定位装置制作虽然需要一次性成本投入,但是经过在该工程成本测算,一次性成本投入仅是既往成本投入的1/2,而且该装置可以重复使用至少10次以上,能大大节约成本。 In the high-rise construction of a large shopping mall in a city, the 60-meter-high commercial building project adopted the installation method of the combined positioning device of the cantilevered bearing frame, which successfully solved the problem of the lack of attachments of the cantilevered scaffolding, and the combined positioning of the cantilevered bearing frame The installation of the device is accurate, convenient and simple to install, there is no fire source on site, steel is saved, the comprehensive cost of leasing is low, and safe and reliable civilized construction is achieved. Although the production of the combined positioning device of the cantilever bearing frame requires a one-time cost investment, the one-time cost investment is only 1/2 of the previous cost investment after the cost calculation of the project, and the device can be reused at least 10 times. Great cost savings.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410417799.4A CN104179341B (en) | 2014-08-25 | 2014-08-25 | An installation method of a combined positioning device for a cantilever bearing frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410417799.4A CN104179341B (en) | 2014-08-25 | 2014-08-25 | An installation method of a combined positioning device for a cantilever bearing frame |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104179341A true CN104179341A (en) | 2014-12-03 |
CN104179341B CN104179341B (en) | 2016-03-23 |
Family
ID=51960658
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410417799.4A Active CN104179341B (en) | 2014-08-25 | 2014-08-25 | An installation method of a combined positioning device for a cantilever bearing frame |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104179341B (en) |
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105298107A (en) * | 2015-10-16 | 2016-02-03 | 河北中建工程有限公司 | High supporting frame of high-altitude large cantilever structure |
CN105332516A (en) * | 2015-11-25 | 2016-02-17 | 中建七局(上海)有限公司 | Installation method of combined positioning devices of overhung heavy frame |
CN105442840A (en) * | 2015-11-11 | 2016-03-30 | 西安建筑科技大学 | Construction method of cantilever formwork supporting frame |
CN106592948A (en) * | 2016-12-19 | 2017-04-26 | 山东万鑫建设有限公司 | Design and construction technology of self-stabilized section steel suspended scaffold |
CN107060312A (en) * | 2017-04-28 | 2017-08-18 | 天长市华利机械实业有限公司 | One kind is used for the overall fixing device of scaffold |
CN107780643A (en) * | 2016-08-24 | 2018-03-09 | 中国二十冶集团有限公司 | Equipment conveying extendable platform for eminence restricted clearance |
CN108843008A (en) * | 2018-06-05 | 2018-11-20 | 广东省建筑科学研究院集团股份有限公司 | A kind of postposition H profile steel builder's jack and its construction method |
CN109296194A (en) * | 2018-09-21 | 2019-02-01 | 邓伟 | Suspension pieces and overhanging scaffold for scaffold |
CN109853933A (en) * | 2018-12-19 | 2019-06-07 | 中国建筑第四工程局有限公司 | A kind of basket type builder's jack and its construction method |
CN110043018A (en) * | 2019-05-20 | 2019-07-23 | 谢兰英 | A kind of floor edge scaffold fixed mechanism and its application method |
CN110344574A (en) * | 2019-07-12 | 2019-10-18 | 无锡市亨利富建设发展有限公司 | A kind of assembling the shaped steel suspension scaffolding |
CN110439249A (en) * | 2019-07-25 | 2019-11-12 | 江苏溧阳建设集团有限公司 | A kind of overhanging heavy frame and its installation method |
CN111206765A (en) * | 2020-03-12 | 2020-05-29 | 中国建筑第四工程局有限公司 | Can have enough to meet need formula scaffold wire rope pull ring of encorbelmenting |
CN112282340A (en) * | 2020-09-27 | 2021-01-29 | 中铁一局集团有限公司 | Special-shaped sliding suspension cage for mounting steel structure cornice outer plate and mounting method |
CN112324120A (en) * | 2020-11-16 | 2021-02-05 | 江苏方洋能源科技有限公司 | Overhanging scaffold |
CN112609979A (en) * | 2020-12-18 | 2021-04-06 | 中国建筑第四工程局有限公司 | Wall connecting piece erecting method for connecting ultrahigh external frame of external wall |
CN113550550A (en) * | 2021-06-30 | 2021-10-26 | 重庆建工第三建设有限责任公司 | Overhanging unit type scaffold convenient to assemble and disassemble |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010189970A (en) * | 2009-02-19 | 2010-09-02 | Asahi Gakuen Group:Kk | Assembling structure of scaffold for construction work |
CN101906870A (en) * | 2010-07-29 | 2010-12-08 | 正太集团有限公司 | Suspended scaffolding |
CN202031313U (en) * | 2011-04-25 | 2011-11-09 | 中建七局第三建筑有限公司 | Supporting connection structure for overhanging scaffold |
CN202227676U (en) * | 2011-09-07 | 2012-05-23 | 南通市达欣工程股份有限公司 | Movable fixture for anchoring cantilever steel beam of scaffold |
CN203320934U (en) * | 2013-05-31 | 2013-12-04 | 马鞍山十七冶工程科技有限责任公司 | Horizontal pre-buried-type wall-connecting device of overhanging scaffold |
-
2014
- 2014-08-25 CN CN201410417799.4A patent/CN104179341B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010189970A (en) * | 2009-02-19 | 2010-09-02 | Asahi Gakuen Group:Kk | Assembling structure of scaffold for construction work |
CN101906870A (en) * | 2010-07-29 | 2010-12-08 | 正太集团有限公司 | Suspended scaffolding |
CN202031313U (en) * | 2011-04-25 | 2011-11-09 | 中建七局第三建筑有限公司 | Supporting connection structure for overhanging scaffold |
CN202227676U (en) * | 2011-09-07 | 2012-05-23 | 南通市达欣工程股份有限公司 | Movable fixture for anchoring cantilever steel beam of scaffold |
CN203320934U (en) * | 2013-05-31 | 2013-12-04 | 马鞍山十七冶工程科技有限责任公司 | Horizontal pre-buried-type wall-connecting device of overhanging scaffold |
Non-Patent Citations (2)
Title |
---|
冯淼: ""斜拉式悬挑外脚手架施工方案设计"", 《广西城镇建设》, no. 8, 31 August 2009 (2009-08-31) * |
刘文峰等: ""型钢悬挑脚手架组件标准化研究"", 《建筑安全》, vol. 29, no. 1, 31 January 2014 (2014-01-31) * |
Cited By (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105298107B (en) * | 2015-10-16 | 2018-06-29 | 河北中建工程有限公司 | A kind of high carriage of High Large Cantilever structure |
CN105298107A (en) * | 2015-10-16 | 2016-02-03 | 河北中建工程有限公司 | High supporting frame of high-altitude large cantilever structure |
CN105442840A (en) * | 2015-11-11 | 2016-03-30 | 西安建筑科技大学 | Construction method of cantilever formwork supporting frame |
CN105332516A (en) * | 2015-11-25 | 2016-02-17 | 中建七局(上海)有限公司 | Installation method of combined positioning devices of overhung heavy frame |
CN107780643A (en) * | 2016-08-24 | 2018-03-09 | 中国二十冶集团有限公司 | Equipment conveying extendable platform for eminence restricted clearance |
CN106592948A (en) * | 2016-12-19 | 2017-04-26 | 山东万鑫建设有限公司 | Design and construction technology of self-stabilized section steel suspended scaffold |
CN107060312A (en) * | 2017-04-28 | 2017-08-18 | 天长市华利机械实业有限公司 | One kind is used for the overall fixing device of scaffold |
CN108843008A (en) * | 2018-06-05 | 2018-11-20 | 广东省建筑科学研究院集团股份有限公司 | A kind of postposition H profile steel builder's jack and its construction method |
CN109296194B (en) * | 2018-09-21 | 2020-12-08 | 邓伟 | A unsettled piece and overhanging type scaffold for scaffold |
CN109296194A (en) * | 2018-09-21 | 2019-02-01 | 邓伟 | Suspension pieces and overhanging scaffold for scaffold |
CN109853933A (en) * | 2018-12-19 | 2019-06-07 | 中国建筑第四工程局有限公司 | A kind of basket type builder's jack and its construction method |
CN110043018A (en) * | 2019-05-20 | 2019-07-23 | 谢兰英 | A kind of floor edge scaffold fixed mechanism and its application method |
CN110043018B (en) * | 2019-05-20 | 2023-11-03 | 广东碧越建筑工程有限公司 | Floor edge scaffold fixing mechanism and application method thereof |
CN110344574A (en) * | 2019-07-12 | 2019-10-18 | 无锡市亨利富建设发展有限公司 | A kind of assembling the shaped steel suspension scaffolding |
CN110344574B (en) * | 2019-07-12 | 2022-01-04 | 无锡市亨利富建设发展有限公司 | Assembled shaped steel scaffold frame of encorbelmenting |
CN110439249A (en) * | 2019-07-25 | 2019-11-12 | 江苏溧阳建设集团有限公司 | A kind of overhanging heavy frame and its installation method |
CN111206765A (en) * | 2020-03-12 | 2020-05-29 | 中国建筑第四工程局有限公司 | Can have enough to meet need formula scaffold wire rope pull ring of encorbelmenting |
CN112282340A (en) * | 2020-09-27 | 2021-01-29 | 中铁一局集团有限公司 | Special-shaped sliding suspension cage for mounting steel structure cornice outer plate and mounting method |
CN112324120A (en) * | 2020-11-16 | 2021-02-05 | 江苏方洋能源科技有限公司 | Overhanging scaffold |
CN112609979A (en) * | 2020-12-18 | 2021-04-06 | 中国建筑第四工程局有限公司 | Wall connecting piece erecting method for connecting ultrahigh external frame of external wall |
CN113550550A (en) * | 2021-06-30 | 2021-10-26 | 重庆建工第三建设有限责任公司 | Overhanging unit type scaffold convenient to assemble and disassemble |
Also Published As
Publication number | Publication date |
---|---|
CN104179341B (en) | 2016-03-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104179341B (en) | An installation method of a combined positioning device for a cantilever bearing frame | |
CN201605810U (en) | A type steel beam self-supporting lifting formwork supporting device | |
CN204040446U (en) | The shaped steel suspension scaffolding structure | |
CN201614738U (en) | A combined support device for steel reinforced concrete transfer beam formwork | |
CN102561669B (en) | Cantilever scaffold and construction method thereof | |
CN101624871A (en) | Instrumental operation platform for shear wall formwork of elevator shaft | |
CN202937005U (en) | Cast-in-situ concrete beam lateral template reinforcement device | |
CN204960368U (en) | String formula bearing structure is opened in space | |
CN203891462U (en) | Form erecting device for fair-faced concrete independent columns | |
CN103510466A (en) | Wet joint construction method for T-shaped beam bridge deck system | |
CN211421839U (en) | Hoop type concrete pouring template system for plugging through floor slab pipeline hole gap | |
CN205805002U (en) | A kind of safety rope fixing device for job site | |
CN108222503A (en) | A kind of combined large pier stud steel form | |
CN206158192U (en) | Concrete pump pipe's simple easily fixable device on concrete face | |
CN203034796U (en) | Reinforced device of shear wall end formwork | |
CN202706554U (en) | Adjustable bolt fastener for unilateral mould plate | |
CN202990407U (en) | Quick-release scaffold | |
CN201447862U (en) | Instrumental operating platform used for elevator shaft shear wall shuttering erection | |
CN207376661U (en) | A kind of plugging structure of poured band of outer wall of basement | |
CN103195235A (en) | Design and calculation for detachable steel plate type steel fixture | |
CN208088145U (en) | A kind of T beam flange plates cantilever bracket fixing device | |
CN205314525U (en) | Detachable scaffold is wall spare even | |
CN205859353U (en) | A kind of cable bearer | |
CN211621992U (en) | Steel construction pipe truss roof support built-in fitting | |
CN203270938U (en) | Steel skeleton and steel pipe concrete combination column |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20141203 Assignee: Anhui Zhengwu Construction and Installation Engineering Co.,Ltd. Assignor: CHINA MCC17 GROUP Co.,Ltd. Contract record no.: X2025980000279 Denomination of invention: Installation method of a cantilever load-bearing frame combination positioning device Granted publication date: 20160323 License type: Common License Record date: 20250114 |