NO340959B1 - A method of plugging and abandoning a well - Google Patents
A method of plugging and abandoning a well Download PDFInfo
- Publication number
- NO340959B1 NO340959B1 NO20150744A NO20150744A NO340959B1 NO 340959 B1 NO340959 B1 NO 340959B1 NO 20150744 A NO20150744 A NO 20150744A NO 20150744 A NO20150744 A NO 20150744A NO 340959 B1 NO340959 B1 NO 340959B1
- Authority
- NO
- Norway
- Prior art keywords
- flushing
- tool
- well
- plugging material
- pipe string
- Prior art date
Links
- 238000000034 method Methods 0.000 title claims description 84
- 238000011010 flushing procedure Methods 0.000 claims description 205
- 239000012530 fluid Substances 0.000 claims description 56
- 239000000463 material Substances 0.000 claims description 52
- 239000004568 cement Substances 0.000 claims description 31
- 238000007599 discharging Methods 0.000 claims description 26
- 239000002002 slurry Substances 0.000 claims description 25
- 238000005507 spraying Methods 0.000 claims description 24
- 238000004140 cleaning Methods 0.000 claims description 18
- 238000006073 displacement reaction Methods 0.000 claims description 9
- 238000005086 pumping Methods 0.000 claims description 9
- 239000003082 abrasive agent Substances 0.000 claims description 8
- 230000015572 biosynthetic process Effects 0.000 claims description 8
- 239000002245 particle Substances 0.000 claims description 7
- 238000009826 distribution Methods 0.000 claims description 4
- 238000005553 drilling Methods 0.000 claims description 4
- 239000004576 sand Substances 0.000 claims description 3
- 238000004873 anchoring Methods 0.000 claims description 2
- 238000003801 milling Methods 0.000 description 11
- 238000005516 engineering process Methods 0.000 description 5
- 239000007787 solid Substances 0.000 description 5
- 125000006850 spacer group Chemical group 0.000 description 5
- 230000003750 conditioning effect Effects 0.000 description 4
- 239000002184 metal Substances 0.000 description 4
- 230000004888 barrier function Effects 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 238000002955 isolation Methods 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 239000002253 acid Substances 0.000 description 1
- TZCXTZWJZNENPQ-UHFFFAOYSA-L barium sulfate Chemical compound [Ba+2].[O-]S([O-])(=O)=O TZCXTZWJZNENPQ-UHFFFAOYSA-L 0.000 description 1
- 229910052601 baryte Inorganic materials 0.000 description 1
- 239000010428 baryte Substances 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 239000012459 cleaning agent Substances 0.000 description 1
- 239000000383 hazardous chemical Substances 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 239000003208 petroleum Substances 0.000 description 1
- 239000006187 pill Substances 0.000 description 1
- 239000000344 soap Substances 0.000 description 1
- 239000011343 solid material Substances 0.000 description 1
- 238000009987 spinning Methods 0.000 description 1
- 239000011800 void material Substances 0.000 description 1
- 238000005406 washing Methods 0.000 description 1
- 238000009736 wetting Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B37/00—Methods or apparatus for cleaning boreholes or wells
- E21B37/08—Methods or apparatus for cleaning boreholes or wells cleaning in situ of down-hole filters, screens, e.g. casing perforations, or gravel packs
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/13—Methods or devices for cementing, for plugging holes, crevices or the like
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/13—Methods or devices for cementing, for plugging holes, crevices or the like
- E21B33/134—Bridging plugs
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B41/00—Equipment or details not covered by groups E21B15/00 - E21B40/00
- E21B41/0078—Nozzles used in boreholes
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/11—Perforators; Permeators
- E21B43/116—Gun or shaped-charge perforators
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/12—Packers; Plugs
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/12—Packers; Plugs
- E21B33/1204—Packers; Plugs permanent; drillable
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B37/00—Methods or apparatus for cleaning boreholes or wells
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Piles And Underground Anchors (AREA)
- Cleaning In General (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
- Sink And Installation For Waste Water (AREA)
- Processing Of Stones Or Stones Resemblance Materials (AREA)
- General Preparation And Processing Of Foods (AREA)
- Ultra Sonic Daignosis Equipment (AREA)
- Control And Other Processes For Unpacking Of Materials (AREA)
- Prostheses (AREA)
- Earth Drilling (AREA)
Description
A METHOD OF PLUGGING AND ABANDONING A WELL
The invention concerns a method of plugging and abandoning (P & A) a subterranean well. As such, the present method may be used for temporary or permanent plugging and abandonment of such a well. Further, the present method may be used in any type of subterranean well, including petroleum wells, for example production wells and injection wells.
The present method involves perforation, cleaning and plugging of a longitudinal section of the well located at a desired depth interval in the well. More specifically, the invention concerns a method that provides hydraulic isolation, in the form of a well plug, across a complete cross section of the well along at least the longitudinal section thereof. The plug provides pressure-isolation both horizontally and vertically along said longitudinal section of the well. The well is also provided with a pipe string in at least the longitudinal section of the well where the pressure-isolating well plug is to be form ed.
It is known to establish a pressure-isolating barrier in a well by virtue of mechanically milling and removing a longitudinal section of casing in the well. Cement slurry is then placed into the milled-away section of the well so as to form, upon curing, a pressure-isolating cement barrier across the complete cross section of this milled-away section of the well. This technology is generally referred to as "section milling" and has been used for decades to plug and abandon wells. Such section milling operations are very time-consuming and very costly for operators of the wells. Section milling operations generally require the presence of surface installations to allow metal shavings, so-called swarf, to be separated from the well fluids used during such milling operations. Various types of cleaning fluids are frequently required to allow transportation of such metal shavings (swarf) up to the surface of the well. Further, such metal shavings may become lodged in other equipment in the well, for example in a blowout preventer (BOP), so as to represent obstructions in the well. Such metal shavings are also troublesome to dispose of and generally represent hazardous materials to handle. It is also known to establish such a well plug by means of the method and washing tool disclosed in WO 2012/096580 Al (termed HydraWash technology). This method is suitable for use together with the displacement apparatus and method disclosed in WO 2012/128644 A2 (termed Archimedes technology).
WO 2013/133719 Al, WO 2015/034369 Al and WO 2015/026239 A2 also describe similar methods and tools for establishing such a well plug. Further, US 5.765.756 A describes a downhole flushing tool håving radially moveable flushing nozzles for abrasive flushing of a surface in a well.
The object of the invention is to remedy or reduce at least one disadvantage of the prior art, which includes said section milling technology, or at least to provide a useful alternative to the prior art.
The object is achieved by virtue of features disclosed in the following description and in the subsequent claims.
The invention concerns a method of plugging and abandoning (P & A) a well temporarily or permanently. The method involves perforation, cleaning and plugging of a longitudinal section of the well, said longitudinal section comprising a wellbore, a pipe string placed within the wellbore, and an annulus located between the wellbore and the pipe string.
The present method comprises the following steps:
(A) lowering a perforation tool into the pipe string onto said longitudinal section of the well; (B) by means of the perforation tool, forming perforations (i.e. penetrating holes) in the pipe string along said longitudinal section; (C) by means of a flushing tool attached to a lower end portion of a tubular work string, which is lowered into the pipe string onto said longitudinal section, pumping a
flushing fluid down through the tubular work string, out through at least one flushing outlet in the flushing tool, into the pipe string and further out into said annulus via the perforations in the pipe string, thereby cleaning both the pipe string and the annulus along said longitudinal section,
wherein an outlet axis of at least one of said at least one flushing outlet in the flushing tool is non-perpendicular to a longitudinal axis of the flushing tool, whereby a corresponding flushing jet from the flushing tool also is non-perpendicular to the longitudinal axis of the flushing tool;
(D) pumping a fluidized plugging material down through the tubular work string
and into the pipe string at said longitudinal section;
(E) placing the fluidized plugging material in the pipe string along at least said longitudinal section, thereby also placing the fluidized plugging material in said
annulus via the perforations in the pipe string, whereupon the fluidized plugging material forms a plug covering substantially a complete cross section of the well along at least said longitudinal section of the well;
(F) pulling the tubular work string out of the well; and
(G) abandoning the well. The distinctive characteristic is that the method, in steps (D) and (E), also comprises pumping the fluidized plugging material into the pipe
string via at least one spraying outlet in the flushing tool so as to discharge as a
corresponding spraying jet from the flushing tool.
The non-perpendicular configuration of the at least one flushing outlet in the flushing tool ensures very effective flushing and cleaning of both the pipe string and the annulus outside the pipe string. This in turn ensures good filling and good adhesion of the subsequent plugging material in the pipe string and in the annulus.
By virtue of embodying the fluidized plugging material as a spraying jet emanating from the flushing tool, the plugging material also becomes directional and somewhat concentrated. This is advantageous in that such a spraying jet reaches further out from the flushing tool and may thus more readily and forcefully engage the formation wall defining the wellbore. Such a spraying jet also gains better access to potential voids in said annulus surrounding the pipe string along the longitudinal section of the well.
Said pipe string may be composed of a well pipe of a type known perse, for example a casing or a liner. As such, the pipe string may extend fully or partially, respectively, to the surface of the well.
Typically, the tubular work string is comprised of a drill string or a coiled-tubing string of a type known per se.
Further, flushing with the flushing fluid and spraying with the fluidized plugging material may be performed in one and the same trip into the well. Naturally, these steps will save on the time and cost of plugging and abandoning the well.
In one embodiment, the flushing tool is formed with a plurality of flushing outlets håving respective outlet axes (i.e. longitudinal axes through the flushing outlets) angled within ± 80° of a plane being perpendicular to the longitudinal axis of the flushing tool. By so doing, corresponding flushing jets from the flushing tool are also
angled within ± 80° of said perpendicular plane.
Each of the at least one flushing outlet may also be provided with a releasable nozzle insert. As such, the nozzle insert may be releasably connected to the flushing tool via a threaded connection or similar. Such a nozzle insert is of a suitable size and shape for generating a flushing jet of desired concentration and distribution. The feature of being releasable also ensures that the nozzle insert is readily replaceable, if desired or required.
As such, said nozzle insert may be radially telescopic relative to the flushing tool, and wherein the telescopic motion of the nozzle insert is selectively activated. Such a feature allows the nozzle insert to be selectively extended or retracted relative to the flushing tool. By so doing, the flushing tool may be lowered into the pipe string of the well with the at least one nozzle insert retracted into the flushing tool. Once placed in the well, said nozzle insert may be selectively extended outward from the body of the flushing tool. Such an embodiment of the flushing tool may prove advantageous in cases where the pipe string has one or more restrictions therein requiring a smaller sized flushing tool to be used for allowing access into the pipe string.
Further, the flushing fluid may comprise drilling mud. This is generally a suitable flushing fluid given that drilling mud usually is readily available and also functions as a pressure barrier in a well.
The flushing fluid may also contain a cleaning agent, for example a suitable soap or acid.
Yet further, the fluidized plugging material may comprise cement slurry for formation of a cement plug.
As an alternative or addition, the fluidized plugging material may comprise a fluidized particulate mass for formation of a plug made of particulate mass. Such a particulate mass is generally in an unconsolidated form. A somewhat different use of such a fluidized particulate mass in a well is disclosed in e.g. WO 01/25594 Al and in WO 02/081861 Al.
Between steps (B) and (C), the method may also comprise the following steps:
- pulling the perforation tool out of the well; and
- attaching the flushing tool to the lower portion of the tubular work string for subsequent performance of step (C). By so doing, perforation and flushing are performed in separate trips into the well.
As an alternative, and before step (A), the method may also comprise the following steps:
- connecting the perforation tool and the flushing tool into an assembly thereof; and
- connecting the assembly to said lower portion of the tubular work string. By so doing, perforation and flushing are performed in one and the same trip into the well. Naturally, these steps will save on the time and cost of plugging and abandoning the well.
Further to the latter alternative, the method may also comprise the following steps:
- releasably connecting, before step (A), the perforation tool to a lower end portion of the flushing tool; and - disconnecting, between steps (B) and (C), the perforation tool from the flushing tool. By so doing, the perforation tool is dropped further down into the pipe string and is thus left behind in the well. This may facilitate the subsequent operation of the flushing tool in the well and, as such, may save further on the time and cost of carrying out the operation.
In another embodiment, step (C) of the method comprises rotating the tubular work string whilst flushing. Such rotation ensures larger area coverage of the flushing motion and thus enables better cleaning of the pipe string and the annulus.
Additionally or alternatively, step (C) of the method may also comprise moving the tubular work string in a reciprocating motion whilst flushing. Such reciprocation also ensures larger area coverage of the flushing motion and thus enables better cleaning of the pipe string and the annulus.
Step (E) of the method may also comprise moving the tubular work string within the pipe string whilst placing the fluidized plugging material therein. As such, the tubular work string may be moved in a suitable manner along the perforated longitudinal section of the pipe string for effective placement of the plugging material in the well.
Before step (C), the method may comprise adding an abrasive agent to the flushing fluid. This is particularly appropriate if the annulus is filled with e.g. cement residues (or some other casting material) and/or solid particles settled out within the annulus, e.g. barite particles settled out from drilling mud in the annulus. Such solid materials may become difficult to remove from the annulus if the flushing fluid is void of such an abrasive agent.
In one embodiment, the method comprises adding the abrasive agent to the flushing fluid in an amount of between 0.05 per cent by weight and 1.00 per cent by weight. The abrasive agent may comprise sand particles. As such, and as an example, adding approximately 0.1 per cent by weight of sand to the flushing fluid appears to be a suitable mixture.
Further, the method may comprise discharging the flushing fluid from said at least one flushing outlet in the flushing tool at a discharge velocity of at least 15 metres per second. The present applicant has carried out tests showing that a discharge velocity of 15 metres per second is a minimum value required for allowing the flushing tool to dean sufficiently in the well.
In an advantageous embodiment, the method therefore comprises discharging the flushing fluid from the at least one flushing outlet at a discharge velocity of at least 50 metres per second. The above-mentioned tests have also shown that a discharge velocity of at least 50 metres per second provides a particularly effective cleaning result in the well.
Optimum discharge velocities for the flushing fluid, as well as optimum amounts of abrasive agent added thereto, depend on the type of flushing fluid used, and particularly with respect to the viscosity of the flushing fluid. High-viscosity flushing fluids usually require higher discharge velocities from the flushing tool than those of low-viscosity flushing fluids. This is simply because high-viscosity flushing fluids experience more internal friction, hence are slowed down faster, than that of low-viscosity flushing fluids.
Another embodiment of the method comprises discharging the flushing fluid from the at least one flushing outlet as a substantially rotation-free flushing jet. If such a flushing jet discharges from a nozzle insert disposed in the flushing outlet, this nozzle insert requires less space for support in the flushing tool than that of an alternative nozzle insert håving a design capable of instilling a rotational/spinning effect on the flushing jet.
Before step (D), the method may also comprise disposing and anchoring a plug base in the pipe string, and below the longitudinal section of the well. Such a plug base may comprise a mechanical plug, a packer element and/or at least one cup-shaped element, e.g. swab cup, of a type known perse. The purpose of such a plug base is to support the fluidized plugging material once placed in the well. Typically, such a plug base (e.g. mechanical plug) is deployed into the pipe string carried on a so-called wireline or on a tubular work string, e.g. drill pipe string or coiled tubing, extending up to the surface of the well.
Alternatively, a column of a viscous fluid, i.e. a so-called viscous pill, may be pumped into the pipe string, and below the longitudinal section of the well, to support said fluidized plugging material.
Further, if said longitudinal section is located at a relatively short distance from the bottom of the pipe string, it may not be necessary to set such a plug base in the pipe string. Instead, the fluidized plugging material is filled from the bottom of the pipe string and upward until the plugging material covers the longitudinal section of the well.
In one embodiment of the method, the flushing tool comprises a first section for discharging, in step (C), the flushing fluid via said at least one flushing outlet, and a second section for spraying, in steps (D) and (E), the fluidized plugging material via said at least one spraying outlet in the flushing tool.
As such, the diameter of said spraying jet of fluidized plugging material discharging from said second section of the flushing tool may be larger than the diameter of said flushing jet of flushing fluid discharging from said first section of the flushing tool. By so doing, and as opposed to general placing and displacement of the fluidized plugging material in the well, the plugging material may engage said formation wall more readily and forcefully. The fluidized plugging material will also gain better access to potential voids in the annulus along the longitudinal section of the well. A smaller diameter of said flushing jet of flushing fluid, however, ensures a more concentrated jet for breaking up and flushing away solids and particles along its flow path in the well.
In the latter context, the method may also comprise discharging said spraying jet of fluidized plugging material at a discharge velocity in the order of 15-25 metres per second, and preferably in the order of 18-22 metres per second. This range of discharge velocities is advantageous in achieving the spraying effect of the fluidized plugging material.
In another embodiment of the method, said at least one flushing outlet and said at least one spraying outlet in the flushing tool are one and the same, whereby both the flushing fluid and the fluidized plugging material will discharge through said at least one outlet in the flushing tool; and
- wherein the method comprises discharging said flushing jet of flushing fluid at a higher discharge velocity than that of said subsequent spraying jet of fluidized plugging material. Variations in the discharge velocity of the respective fluids may be
achieved by changing the pump rate of the fluid in question.
As such, the method may comprise discharging the flushing fluid at a discharge velocity of at least 50 metres per second, and then discharging the subsequent fluidized plugging material at a discharge velocity in the order of 15-25 metres per second.
Yet further, the method may also comprise the following steps:
- connecting, before step (D), a displacement body to the tubular work string, and in vicinity of the flushing tool; and - using, in step (E), the displacement body to further displace and distribute the
fluidized plugging material in the pipe string and further out into said annulus via said perforations in the pipe string along the longitudinal section of the well. This facilitates the displacement and distribution of fluidized plugging material within said longitudinal section is facilitated. A displacement body suitable for this purpose is disclosed in WO 2012/128644 A2 (termed Archimedes technology), as mentioned initially.
Hereinafter, an exemplary embodiment of the method is described and depicted in the accompanying drawings, where: Figure 1 shows, in side view, a well within which a casing string is disposed; Figure 2 shows, in side view, the well after håving removed a longer portion of the casing string in accordance with a prior art plugging method (i.e. section milling); Figure 3 shows, in side view, the well of Figure 2 after håving established a plug in the well in accordance with this prior art section milling plugging method; Figure 4 shows, in side view, the well as used in context of the present method, and after håving lowered a perforation tool into the casing string; Figure 5 shows, in side view, the well after håving perforated the casing string with the perforation tool, and after håving pulled the perforation tool out of the well; Figure 6 shows, in side view, the well after håving lowered a flushing tool into the casing string, and whilst using the flushing tool to flush and clean away e.g. solid particles in the well; Figure 7 shows, in side view, the well whilst filling and thus placing a fluidized plugging material into a portion of a longitudinal section of the well, thereby filling substantially the entire cross section of the well with the plugging material along the longitudinal section; Figure 8 shows, in side view, the well after håving plugged the well along the
longitudinal section thereof by means of the present method; and
Figure 9 shows, in side view, a combined perforation and flushing tool for use in
one embodiment of the present method.
The figures are schematic and merely show steps, details and equipment being essential to the understanding of the invention. Further, the figures are distorted with respect to relative dimensions of elements and details shown in the figures. The figures are also somewhat simplified with respect to the shape and richness of detail of such elements and details. Elements not being central to the invention may also have been omitted from the figures. Further, equal, equivalent or corresponding details shown in the figures will be given substantially the same reference numerals. Figure 1 shows a well 1 to be plugged and abandoned after håving removed a longer portion of a pipe string, here in the form of a single casing string 5, in accordance with a prior art plugging method, i.e. so-called section milling (also mentioned initially). The figure shows the casing string 5 disposed within a wellbore 2 of the well 1. A surrounding rock formation 9 defines the wellbore 2. An annulus 8 also exists between the wellbore 2 and the casing string 5. Typical well fluids known to a person skilled in the art are also present in the well 1. Figure 2 shows the well 1 after håving removed a longer portion/section of the casing string 5 in accordance with the noted prior art section milling plugging method. A substantial length of the casing string 5 is thus milled away. Figure 3 then shows the well 1 after håving filled cement slurry, i.e. a fluidized plugging material, into the milled-away section of the well 1 so as to fill the entire cross section Tl thereof. Upon curing, this cement slurry forms a pressure-isolating cement plug 25 along the milled-away section of the well 1, as shown in Figure 3. This section milling method has several disadvantages, as mentioned initially. Figure 4 shows a first step in the present method as applied in a similar well 1. Also here a single casing string 5 is disposed within a wellbore 2 of a well 1 so as to leave an annulus 8 between the wellbore 2 and the casing string 5. A tubular work string,
here in the form of a drill string 3, has been lowered into the casing string 5 onto a longitudinal section LI of the well 1 to be plugged and abandoned by virtue of the present method. A perforation tool, here in the form of a perforation gun 31 of a type known perse, has also been connected to a lower end portion of the drill string 3. Once placed at the longitudinal section LI of the well 1, the perforation gun 31 is activated and forms a number of perforations 51 along the longitudinal section LI and through the wall of the casing string 5, as shown in Figure 5. In one embodiment, the perforation gun 31 may be pulled out of the well 1 and disconnected from the drill string 3 after håving completed the perforation operation.
Figure 6 shows the well 1 after håving lowered a flushing tool 33 into the casing string 5, and onto the longitudinal section LI, whilst the flushing tool 33 is connected to a lower end portion of a drill string 3. This drill string 3 may be the same drill string used in the preceding perforation step, or it may be another type of tubular work string, for example coiled tubing. This figure also shows the flushing tool 33 whilst flushing and cleaning away e.g. solid particles (not shown in the figures) in the well 1 along the longitudinal section LI thereof. A curved arrow at the upper portion of the drill string 3 indicates rotation of the drill string 3, and hence rotation of the flushing tool 33 connected to the drill string 3, whilst flushing and cleaning with the flushing tool 33. Additionally or alternatively, the drill string 3, and thus the flushing tool 33, may be moved in a reciprocating motion whilst flushing and cleaning the longitudinal section LI with the flushing tool 33. Rotation and/or reciprocation of the flushing tool 33 along the longitudinal section LI whilst flushing ensures better and possibly repeated area coverage so as to enable better cleaning of the casing string 5 and the surrounding annulus 8 along the longitudinal section LI of the well 1.
In this particular embodiment, the flushing tool 33 is formed with several flushing outlets 331 distributed in a desired pattern around the flushing tool 33. These flushing outlets 331 have respective outlet axes "b" angled within ± 80° of a plane "c" being perpendicular to the longitudinal axis "a" of the flushing tool 33. By so doing, corresponding flushing jets discharging from the flushing tool 33 are also angled within ± 80° of the perpendicular plane "c". Longitudinal axis "a", outlet axis "b" and perpendicular plane "c" are also shown in Figure 9.
Figure 6 also shows a flushing fluid 35 in the form of flushing jets discharging at high velocity, and as substantially rotation-free jets, from corresponding nozzle inserts 332 provided in the flushing outlets 331 of the flushing tool 33. These nozzle inserts 332 ensure a desired concentration and distribution of the flushing jets upon discharging from the outlets 331 of the flushing tool 33. The flushing jets discharge at various angles relative to said perpendicular plane "c" and go through the corresponding perforations 51 and enter the annulus 8 at different angles. This ensures better access to areas of the annulus 8 located between the perforations 51, thereby ensuring better flushing and cleaning of these intermediate areas of the annulus 8. These angled flushing jets are depicted with straight arrows pointing outward from some of the flushing outlets 331 shown in Figure 6. The flow direction and potential flow paths of the discharging flushing fluid 35 are depicted with curved arrows located around the flushing tool 33 in Figure 6. At a particular instant, the discharging flushing fluid 35 therefore flows out through perforations 51 proximate to the flushing outlets 331, via the annulus 8 outside the casing string 5, and then flows back into the casing string 5 via perforations 51 more distal to the flushing outlets 331. The flushing tool 33 is moved slow ly along the longitudinal section LI whilst simultaneously flushing the casing string 5 and the annulus 8, thereby continuously repeating this instant flushing scenario along the longitudinal section LI of the well 1. This flushing motion goes on until the entire longitudinal section LI has been covered and cleaned sufficiently.
Before plugging the longitudinal section LI of the well 1, a further cleaning and conditioning fluid is typ i ca I ly pumped in the described manner through the flushing tool 33 and into the casing string 5 and annulus 8, thereby further cleaning and conditioning the wellbore 2 and the casing string 5 for the purpose of allowing cement slurry 37, i.e. a fluidized plugging material, to be introduced into at least the longitudinal section LI thereafter (cf. Figs. 7 and 8). This further cleaning and conditioning fluid may be comprised of a so-called spacer fluid, which is typically used to clean away remaining solids in the wellbore 2/annulus 8, but also to ensure water-wetting and conditioning of the casing string 5 and the surrounding rock formation 9 (which defines the wellbore 2) so as to bond well with the subsequent cement slurry 37 to be introduced therein. Such a spacer fluid is generally of less density than the cement slurry 37 used in plugging steps (D) and (E) of the present method. Therefore, the cement slurry 37 easily displaces the spacer fluid during these plugging steps.
Figure 7 shows the well 1 whilst pumping and thus placing cement slurry 37 into a lower portion of the longitudinal section LI of the well 1, thereby filling substantially the entire cross section Tl of the well 1 with cement slurry 37. The figure shows cement slurry 37 flowing out of the lower end of the drill string 3 so as to fill the inside of the casing string 5, after which the cement slurry 37 flows onward into the annulus 8 via the perforations 51 in the wall of the casing string 5. By so doing, the denser cement slurry 37 easily displaces the less dense spacer fluid (or other less dense well fluid), if present, upward within the well 1 and thus removes the spacer fluid from said longitudinal section LI. In context of pumping and displacing the cement slurry 37, the drill string 3 is moved slowly upward whilst filling and placing cement slurry 37 into the casing string 5 along the entire longitudinal section LI of the well 1. This filling and moving step may also continue until cement slurry 37 has been filled into the casing string 5 to some desired level above the longitudinal section LI, whereby at least the longitudinal section LI of the well 1 is filled with cement slurry 37. Before pumping the cement slurry 37 into the casing string 5, a mechanical plug 38 has been disposed and anchored within the casing string 5, and below the longitudinal section LI, to provide a supporting base for the cement slurry 37 once placed in the casing string 5.
Alternatively, and not shown in the figures, the flushing tool 33 may remain connected to the drill string 3 after håving flushed and cleaned the longitudinal section LI. Cement slurry 37 is then pumped down the drill string 3 and discharges from the nozzle inserts 332 provided in the flushing outlets 331 of the flushing tool 33. In this case, the cement slurry 37 may discharge as spraying jets from the flushing tool 33, and at a significantly lower discharge velocity than that of the high discharge velocity of the preceding flushing jets of the flushing fluid 35.
Figure 8 shows the well 1 after håving filled cement slurry 37 into the casing string 5 and the surrounding annulus 8, as described hereinbefore, and after the cement slurry 37 has cured therein so as to form a pressure-isolating cement plug 25 covering substantially the entire cross section Tl of the well 1 along at least the longitudinal section LI thereof.
Upon håving placed the cement slurry 37 into and along at least said longitudinal section LI of the well 1, the drill string 3 (and possibly with an alternative flushing tool 33 connected to the drill string 3) is pulled out of the well 1. The well 1 is then abandoned temporarily or permanently.
Figure 9 shows a selectively releasable perforation tool 31 connected in a releasable manner to a lower end portion of a flushing tool 33 so as to form an assembly 34 thereof. The assembly 34 is connected to a lower portion of the drill string 3 (not shown in Figure 9). Selective release of the perforation tool 31 from the flushing tool 33 may be carried out by technical means and methods known perse. Use of such an assembly 34 allows perforation and flushing to be performed in one and the same trip into the well 1. By so doing, the perforation tool 31 is dropped further down into the casing string 5 and is thus left behind in the well 1. This may facilitate the subsequent operation of the flushing tool 33 in the well 1 and, as such, may save further on the time and cost of carrying out such a plugging operation.
Claims (29)
1. A method of plugging and abandoning a well (1), the method involving perforation, cleaning and plugging of a longitudinal section (LI) of the well (1), said longitudinal section (LI) comprising a wellbore (2), a pipe string (5) placed within the wellbore (2), and an annulus (8) located between the wellbore (2) and the pipe string (5), wherein the method comprises the following steps: (A) lowering a perforation tool (31) into the pipe string (5) onto said longitudinal section (LI) of the well (1); (B) by means of the perforation tool (31), forming perforations (51) in the pipe string (5) along said longitudinal section (LI); (C) by means of a flushing tool (33) attached to a lower end portion of a tubular work string (3), which is lowered into the pipe string (5) onto said longitudinal section (LI), pumping a flushing fluid (35) down through the tubular work string (3), out through at least one flushing outlet (331) in the flushing tool (33), into the pipe string (5) and further out into said annulus (8) via the perforations (51) in the pipe string (5), thereby cleaning both the pipe string (5) and the annulus (8) along said longitudinal section (LI),
wherein an outlet axis (b) of at least one of said at least one flushing outlet (331) in the flushing tool (33) is non-perpendicular to a longitudinal axis (a) of the flushing tool (33), whereby a corresponding flushing jet from the flushing tool (33) also is non-perpendicular to the longitudinal axis (a) of the flushing tool (33); (D) pumping a fluidized plugging material (37) down through the tubular work string (3) and into the pipe string (5) at said longitudinal section (LI); (E) placing the fluidized plugging material (37) in the pipe string (5) along at least said longitudinal section (LI), thereby also placing the fluidized plugging material (37) in said annulus (8) via the perforations (51) in the pipe string (5), whereupon the fluidized plugging material (37) forms a plug (25) covering substantially a complete cross section (Tl) of the well (1) along at least said longitudinal section (LI) of the well (1); (F) pulling the tubular work string (3) out of the well (1); and (G) abandoning the well (1),characterized in thatthe method, in steps (D) and (E), comprises pumping the fluidized plugging material (37) into the pipe string (5) via at least one spraying outlet in the flushing tool (33) so as to discharge as a corresponding spraying jet from the flushing tool (33).
2. The method according to claim 1, wherein flushing with the flushing fluid (35) and spraying with the fluidized plugging material (37) are performed in one and the same trip into the well (1).
3. The method according to claim 1 or 2, wherein the flushing tool (33) is formed with a plurality of flushing outlets (331) håving respective outlet axes (b) angled within ± 80° of a plane (c) being perpendicular to the longitudinal axis (a) of the flushing tool (33), whereby corresponding flushing jets from the flushing tool (33) also are angled within ± 80° of said perpendicular plane (c).
4. The method according to claim 1, 2 or 3, wherein each of the at least one flushing outlet (331) is provided with a releasable nozzle insert (332).
5. The method according to claim 4, wherein said nozzle insert (332) is radially telescopic relative to the flushing tool (33), and wherein the telescopic motion of the nozzle insert (332) is selectively activated.
6. The method according to any one of claims 1-5, wherein the flushing fluid (35) comprises drilling mud.
7. The method according to any one of claims 1-6, wherein the fluidized plugging material (37) comprises cement slurry for formation of a cement plug.
8. The method according to any one of claims 1-7, wherein the fluidized plugging material (37) comprises a fluidized particulate mass for formation of a plug made of particulate mass.
9. The method according to any one of claims 1-8, wherein the method, between steps (B) and (C), also comprises the following steps: - pulling the perforation tool (31) out of the well (1); and - attaching the flushing tool (33) to said lower end portion of the tubular work string (3) for subsequent performance of step (C);
whereby perforation and flushing are performed in separate trips into the well (D-
10. The method according to any one of claims 1-8, wherein the method, before step (A), also comprises the following steps: - connecting the perforation tool (31) and the flushing tool (33) into an assembly (34) thereof; and - connecting the assembly (34) to said lower portion of the tubular work string (3);
whereby perforation and flushing are performed in one and the same trip into the well (1).
11. The method according to claim 10, wherein the method also comprises the following steps: - releasably connecting, before step (A), the perforation tool (31) to a lower end portion of the flushing tool (33); and - disconnecting, between steps (B) and (C), the perforation tool (31) from the flushing tool (33);
whereby the perforation tool (31) is dropped further down into the pipe string (7) and is left behind in the well (1).
12. The method according to any one of claims 1-11, wherein step (C) comprises rotating the tubular work string (3) whilst flushing.
13. The method according to any one of claims 1-12, wherein step (C) comprises moving the tubular work string (3) in a reciprocating motion whilst flushing.
14. The method according to any one of claims 1-13, wherein step (E) comprises moving the tubular work string (3) within the pipe string (5) whilst placing the fluidized plugging material (37) therein.
15. The method according to any one of claims 1-14, wherein the method, before step (C), comprises adding an abrasive agent to the flushing fluid (35).
16. The method according to claim 15, comprising adding the abrasive agent to the flushing fluid (35) in an amount of between 0.05 per cent by weight and 1.00 per cent by weight.
17. The method according to claim 15 or 16, wherein the abrasive agent comprises sand particles.
18. The method according to any one of claims 1-17, comprising discharging the flushing fluid (35) from said at least one flushing outlet (331) in the flushing tool (33) at a discharge velocity of at least 15 metres per second.
19. The method according to claim 18, comprising discharging the flushing fluid (35) from the at least one flushing outlet (331) at a discharge velocity of at least 50 metres per second.
20. The method according to any one of claims 1-19, comprising discharging the flushing fluid (35) from the at least one flushing outlet (331) as a substantially rotation-free flushing jet.
21. The method according to any one of claims 1-20, wherein the method, before step (D), also comprises disposing and anchoring a plug base (38) in the pipe string (5), and below the longitudinal section (LI) of the well (1).
22. The method according to claim 21, wherein the plug base (38) comprises at least one cup-shaped element.
23. The method according to any one of claims 1-22, wherein the flushing tool (33) comprises a first section for discharging, in step (C), the flushing fluid (35) via said at least one flushing outlet (331), and a second section for spraying, in steps (D) and (E), the fluidized plugging material (37) via said at least one spraying outlet in the flushing tool (33).
24. The method according to claim 23, wherein the diameter of said spraying jet of fluidized plugging material (37) discharging from said second section of the flushing tool (33) is larger than the diameter of said flushing jet of flushing fluid (35) discharging from said first section of the flushing tool (33).
25. The method according to claim 24, comprising discharging said spraying jet of fluidized plugging material (37) at a discharge velocity in the order of 15-25 metres per second.
26. The method according to claim 25, comprising discharging said spraying jet of fluidized plugging material (37) at a discharge velocity in the order of 18-22 metres per second.
27. The method according to any one of claims 1-22, wherein said at least one flushing outlet (331) and said at least one spraying outlet in the flushing tool (33) are one and the same, whereby both the flushing fluid (35) and the fluidized plugging material (37) will discharge through said at least one outlet (331) in the flushing tool (33); and - wherein the method comprises discharging said flushing jet of flushing fluid (35) at a higher discharge velocity than that of said subsequent spraying jet of fluidized plugging material (37).
28. The method according to claim 27, comprising discharging the flushing fluid (35) at a discharge velocity of at least 50 metres per second, and then discharging the subsequent fluidized plugging material (37) at a discharge velocity in the order of 15-25 metres per second.
29. The method according to any one of claims 1-28, wherein the method also comprises the following steps: - connecting, before step (D), a displacement body to the tubular work string (3), and in vicinity of the flushing tool (33); and - using, in step (E), the displacement body to further displace and distribute the fluidized plugging material (37) in the pipe string (5) and further out into said annulus (8) via said perforations (51) in the pipe string (5) along the longitudinal section (LI) of the well (1);
thereby facilitating the displacement and distribution of fluidized plugging material (37) within said longitudinal section (LI).
Priority Applications (10)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
NO20150744A NO340959B1 (en) | 2015-06-10 | 2015-06-10 | A method of plugging and abandoning a well |
US15/579,373 US20180187518A1 (en) | 2015-06-10 | 2016-06-01 | A Method of Plugging and Abandoning a Well |
EP16807890.5A EP3307985B1 (en) | 2015-06-10 | 2016-06-01 | A method of plugging and abandoning a well |
PCT/NO2016/050112 WO2016200269A1 (en) | 2015-06-10 | 2016-06-01 | A method of plugging and abandoning a well |
AU2016277179A AU2016277179B2 (en) | 2015-06-10 | 2016-06-01 | A method of plugging and abandoning a well |
CA3026613A CA3026613C (en) | 2015-06-10 | 2016-06-01 | A method of plugging and abandoning a well |
MYPI2017704689A MY192204A (en) | 2015-06-10 | 2016-06-01 | A method of plugging and abandoning a well |
GB1721116.0A GB2555058B (en) | 2015-06-10 | 2016-06-01 | A method of plugging and abandoning a well |
EA201792646A EA036974B1 (en) | 2015-06-10 | 2016-06-01 | Method of plugging and abandoning a well |
DK16807890.5T DK3307985T3 (en) | 2015-06-10 | 2016-06-01 | A method of plugging and abandoning a well |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
NO20150744A NO340959B1 (en) | 2015-06-10 | 2015-06-10 | A method of plugging and abandoning a well |
Publications (2)
Publication Number | Publication Date |
---|---|
NO20150744A1 NO20150744A1 (en) | 2016-12-12 |
NO340959B1 true NO340959B1 (en) | 2017-07-31 |
Family
ID=57503573
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
NO20150744A NO340959B1 (en) | 2015-06-10 | 2015-06-10 | A method of plugging and abandoning a well |
Country Status (10)
Country | Link |
---|---|
US (1) | US20180187518A1 (en) |
EP (1) | EP3307985B1 (en) |
AU (1) | AU2016277179B2 (en) |
CA (1) | CA3026613C (en) |
DK (1) | DK3307985T3 (en) |
EA (1) | EA036974B1 (en) |
GB (1) | GB2555058B (en) |
MY (1) | MY192204A (en) |
NO (1) | NO340959B1 (en) |
WO (1) | WO2016200269A1 (en) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
NO345810B1 (en) | 2017-10-17 | 2021-08-16 | Hydra Systems As | A system and method of cleaning an annular area of a second annulus in a well |
GB2569566B (en) * | 2017-12-20 | 2020-07-22 | Ardyne Holdings Ltd | A method of abandoning a well |
GB2569564B (en) * | 2017-12-20 | 2020-07-22 | Ardyne Holdings Ltd | A method of abandoning a well |
US11773692B2 (en) | 2018-10-18 | 2023-10-03 | Geodynamics, Inc. | Pulse based perf and wash system and method |
WO2020185229A1 (en) * | 2019-03-13 | 2020-09-17 | Halliburton Energy Services, Inc. | Single trip wellbore cleaning and sealing system and method |
NO346617B1 (en) | 2020-03-09 | 2022-10-31 | Hydra Systems As | A fluid diverter tool, system and method of diverting a fluid flow in a well |
US20220307345A1 (en) * | 2021-03-29 | 2022-09-29 | Conocophillips Company | Method and apparatus for use in plug and abandon operations |
CN117189027B (en) * | 2023-11-07 | 2024-02-27 | 中石化西南石油工程有限公司 | Method and device for injecting ash and sealing layer by dragging turbulator by continuous oil pipe |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5765756A (en) * | 1994-09-30 | 1998-06-16 | Tiw Corporation | Abrasive slurry jetting tool and method |
WO2012096580A1 (en) * | 2011-01-12 | 2012-07-19 | Hydra Systems As | Method for combined cleaning and plugging in a well, a washing tool for directional washing in a well, and uses thereof |
WO2013133719A1 (en) * | 2012-03-09 | 2013-09-12 | Hydra Systems As | A method for combined cleaning and plugging in a well and a flushing tool for flushing in a well |
WO2015026239A2 (en) * | 2013-08-21 | 2015-02-26 | Archer Oil Tools As | One trip perforating and washing tool for plugging and abandoning wells |
WO2015034369A1 (en) * | 2013-09-06 | 2015-03-12 | Hydra Systems As | Method for isolation of a permeable zone in a subterranean well |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3052298A (en) * | 1960-03-22 | 1962-09-04 | Shell Oil Co | Method and apparatus for cementing wells |
NO310693B1 (en) | 1999-10-04 | 2001-08-13 | Sandaband Inc | Looseness plug for plugging a well |
NO313923B1 (en) | 2001-04-03 | 2002-12-23 | Silver Eagle As | A method for preventing a fluid in flow in or around a well tube by means of bulk material |
NO339005B1 (en) | 2011-03-24 | 2016-11-07 | Hydra Systems As | Apparatus and method for applying a fluidized plug material to a well |
PL2770161T3 (en) * | 2013-02-20 | 2016-12-30 | Development and rehabilitation of boreholes, wells and springs by a rotary nozzle device with angle adjustable nozzles | |
NO336038B1 (en) * | 2013-08-16 | 2015-04-27 | Hydra Systems As | Procedure for establishing a new well path from an existing well |
-
2015
- 2015-06-10 NO NO20150744A patent/NO340959B1/en unknown
-
2016
- 2016-06-01 CA CA3026613A patent/CA3026613C/en active Active
- 2016-06-01 US US15/579,373 patent/US20180187518A1/en not_active Abandoned
- 2016-06-01 WO PCT/NO2016/050112 patent/WO2016200269A1/en active Application Filing
- 2016-06-01 DK DK16807890.5T patent/DK3307985T3/en active
- 2016-06-01 MY MYPI2017704689A patent/MY192204A/en unknown
- 2016-06-01 AU AU2016277179A patent/AU2016277179B2/en active Active
- 2016-06-01 EA EA201792646A patent/EA036974B1/en not_active IP Right Cessation
- 2016-06-01 EP EP16807890.5A patent/EP3307985B1/en active Active
- 2016-06-01 GB GB1721116.0A patent/GB2555058B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5765756A (en) * | 1994-09-30 | 1998-06-16 | Tiw Corporation | Abrasive slurry jetting tool and method |
WO2012096580A1 (en) * | 2011-01-12 | 2012-07-19 | Hydra Systems As | Method for combined cleaning and plugging in a well, a washing tool for directional washing in a well, and uses thereof |
WO2013133719A1 (en) * | 2012-03-09 | 2013-09-12 | Hydra Systems As | A method for combined cleaning and plugging in a well and a flushing tool for flushing in a well |
WO2015026239A2 (en) * | 2013-08-21 | 2015-02-26 | Archer Oil Tools As | One trip perforating and washing tool for plugging and abandoning wells |
WO2015034369A1 (en) * | 2013-09-06 | 2015-03-12 | Hydra Systems As | Method for isolation of a permeable zone in a subterranean well |
Also Published As
Publication number | Publication date |
---|---|
AU2016277179B2 (en) | 2019-05-30 |
AU2016277179A1 (en) | 2018-01-18 |
MY192204A (en) | 2022-08-08 |
EP3307985A4 (en) | 2019-01-23 |
EP3307985B1 (en) | 2020-07-22 |
DK3307985T3 (en) | 2020-09-14 |
EP3307985A1 (en) | 2018-04-18 |
EA036974B1 (en) | 2021-01-21 |
GB2555058B (en) | 2019-01-02 |
GB201721116D0 (en) | 2018-01-31 |
NO20150744A1 (en) | 2016-12-12 |
CA3026613C (en) | 2022-08-23 |
WO2016200269A1 (en) | 2016-12-15 |
GB2555058A (en) | 2018-04-18 |
EA201792646A1 (en) | 2018-06-29 |
US20180187518A1 (en) | 2018-07-05 |
CA3026613A1 (en) | 2016-12-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA3026613C (en) | A method of plugging and abandoning a well | |
CA2923158C (en) | Method for isolation of a permeable zone in a subterranean well | |
AU2013228113B2 (en) | A method for combined cleaning and plugging in a well and a flushing tool for flushing in a well | |
DK2569506T3 (en) | Method of Combined Cleaning and Blocking in a Well, Washing Tool for Directional Washing in a Well and Applications thereof | |
CA2920967C (en) | Method for establishment of a new well path from an existing well | |
NO20191344A1 (en) | Improvements in or relating to well abandonment | |
AU2018351422B2 (en) | A system and method of cleaning an annular area in a well | |
NO345811B1 (en) | A method of performing abrasive perforation and washing in a well |