Morais et al., 2006 - Google Patents
Reliability centered maintenance for capacitor voltage transformersMorais et al., 2006
- Document ID
- 805107055921434449
- Author
- Morais D
- Rolim J
- Coser J
- Zurn H
- Publication year
- Publication venue
- 2006 International Conference on Probabilistic Methods Applied to Power Systems
External Links
Snippet
Reliability centered maintenance (RCM) allows power companies to improve service quality and prevent equipment functional failure. This paper presents an RCM model for capacitor voltage transformers, which has been developed based on experience of maintenance …
- 239000003990 capacitor 0 title abstract description 28
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
- G01R31/12—Testing dielectric strength or breakdown voltage; Testing or monitoring effectiveness or level of insulation, e.g. of a cable or of an apparatus, for example using partial discharge measurements; Electrostatic testing
- G01R31/1227—Testing dielectric strength or breakdown voltage; Testing or monitoring effectiveness or level of insulation, e.g. of a cable or of an apparatus, for example using partial discharge measurements; Electrostatic testing of components, parts or materials
- G01R31/1236—Testing dielectric strength or breakdown voltage; Testing or monitoring effectiveness or level of insulation, e.g. of a cable or of an apparatus, for example using partial discharge measurements; Electrostatic testing of components, parts or materials of surge arresters
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
- G01R31/02—Testing of electric apparatus, lines or components, for short-circuits, discontinuities, leakage of current, or incorrect line connection
- G01R31/027—Testing of transformers
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
- G01R31/40—Testing power supplies
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Murugan et al. | Failure analysis of power transformer for effective maintenance planning in electric utilities | |
Scatiggio et al. | Health index: The TERNA's practical approach for transformers fleet management | |
Akbari et al. | Failure modes and effects analysis (FMEA) for power transformers | |
Brandtzæg | Health indexing of Norwegian power transformers | |
Schweitzer et al. | Line protection: Redundancy, reliability, and affordability | |
Morais et al. | Reliability centered maintenance for capacitor voltage transformers | |
Haghgoo et al. | Reliability modelling of capacitor voltage transformer using proposed Markov model | |
Suwanasri et al. | Risk‐based maintenance for asset management of power transformer: practical experience in Thailand | |
Suwanasri et al. | Risk assessment based on condition and importance criteria for power transformer in Thailand transmission network | |
Vasquez et al. | Risk‐based approach for power transformer replacement considering temperature, apparent age, and expected capacity | |
Leffler et al. | Failures of Electrical Machines-Review | |
Martinez-Monseco | An approach to a practical optimization of reliability centered maintenance. Case study: power transformer in hydro power plant | |
Yang et al. | A novel method of decision‐making for power transformer maintenance based on failure‐probability‐analysis | |
Carneiro | Substation power transformer risk management: Predictive methodology based on reliability centered maintenance data | |
Krieg et al. | Techniques and experience in on-line transformer condition monitoring and fault diagnosis in ElectraNet SA | |
Lapworth et al. | Transformer failure modes and planned replacement | |
CN115792461A (en) | Transformer state maintenance method and device with reliability as center | |
Papic et al. | Reliability assessment of multiple substations in Idaho system using a node-breaker model | |
Mendler et al. | Electrical equipment maintenance 101 | |
Lapworth et al. | The asset health review for managing reliability risks associated with ongoing use of ageing system power transformers | |
Recksiedler et al. | Life Extension and Upgrading of HVDC Systems | |
Drewiske et al. | Assessing the health of an electrical system: An approach from the forest products industry | |
Siregar et al. | Investigation experience due to high number of CVTs failure (Part: 1) | |
Srinuntawong et al. | Data Warehouse and Asset Management Intelligence Architecture for Condition Assessment of Major Equipment in Power Plant | |
Onuh et al. | Critical assessment of power transformers reliability in the Nigerian electricity supply industry (A Case Study) |