A management oriented approach to reduce a project duration and its risk (variability)

Author

Listed:
  • Madadi, M.
  • Iranmanesh, H.
Abstract
The effects of different activities on risk and the expected completion time of a project are not the same; various activities have various effects on the successful completion of a project. Based on this fact, one of the most important issues in project management is to determine important activities and the amount of effort that should be assigned to control them, thereby completing the project successfully. In this paper, one index and one method are proposed to satisfy this necessity. Our main hypothesis is, expending effort on activities and controlling them actively results in activities risk reduction. Based on this hypothesis, the proposed index and method are compared to existing indices in the literature. Comparison results show that the proposed index and method strongly surpass other indices.

Suggested Citation

  • Madadi, M. & Iranmanesh, H., 2012. "A management oriented approach to reduce a project duration and its risk (variability)," European Journal of Operational Research, Elsevier, vol. 219(3), pages 751-761.
  • Handle: RePEc:eee:ejores:v:219:y:2012:i:3:p:751-761
    DOI: 10.1016/j.ejor.2012.01.006
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0377221712000070
    Download Restriction: Full text for ScienceDirect subscribers only

    File URL: https://libkey.io/10.1016/j.ejor.2012.01.006?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Chen, Shih-Pin, 2007. "Analysis of critical paths in a project network with fuzzy activity times," European Journal of Operational Research, Elsevier, vol. 183(1), pages 442-459, November.
    2. Elmaghraby, Salah E., 2000. "On criticality and sensitivity in activity networks," European Journal of Operational Research, Elsevier, vol. 127(2), pages 220-238, December.
    3. Chanas, Stefan & Zielinski, Pawel, 2002. "The computational complexity of the criticality problems in a network with interval activity times," European Journal of Operational Research, Elsevier, vol. 136(3), pages 541-550, February.
    4. Hartmann, Sonke & Kolisch, Rainer, 2000. "Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 127(2), pages 394-407, December.
    5. Hartmann, Sönke & Kolisch, R., 2000. "Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 11180, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
    6. Bajis M. Dodin & Salah E. Elmaghraby, 1985. "Approximating the Criticality Indices of the Activities in PERT Networks," Management Science, INFORMS, vol. 31(2), pages 207-223, February.
    7. Fatemi Ghomi, S. M. T. & Teimouri, E., 2002. "Path critical index and activity critical index in PERT networks," European Journal of Operational Research, Elsevier, vol. 141(1), pages 147-152, August.
    8. Genaro Gutierrez & Anand Paul, 2000. "Analysis of the Effects of Uncertainty, Risk-Pooling, and Subcontracting Mechanisms on Project Performance," Operations Research, INFORMS, vol. 48(6), pages 927-938, December.
    9. Elmaghraby, S. E. & Fathi, Y. & Taner, M. R., 1999. "On the sensitivity of project variability to activity mean duration," International Journal of Production Economics, Elsevier, vol. 62(3), pages 219-232, September.
    10. V. G. Kulkarni & V. G. Adlakha, 1986. "Markov and Markov-Regenerative pert Networks," Operations Research, INFORMS, vol. 34(5), pages 769-781, October.
    11. J. J. Martin, 1965. "Distribution of the Time Through a Directed, Acyclic Network," Operations Research, INFORMS, vol. 13(1), pages 46-66, February.
    12. R. A. Bowman, 1995. "Efficient Estimation of Arc Criticalities in Stochastic Activity Networks," Management Science, INFORMS, vol. 41(1), pages 58-67, January.
    13. Yoram Wind & Thomas L. Saaty, 1980. "Marketing Applications of the Analytic Hierarchy Process," Management Science, INFORMS, vol. 26(7), pages 641-658, July.
    14. R. A. Bowman & J. A. Muckstadt, 1993. "Stochastic Analysis of Cyclic Schedules," Operations Research, INFORMS, vol. 41(5), pages 947-958, October.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2022. "Using Earned Value Management and Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 297(2), pages 451-466.
    2. Cui, Nanfang & Demeulemeester, Erik & Bie, Li, 2016. "Incorporation of activity sensitivity measures into buffer management to manage project schedule riskAuthor-Name: Hu, Xuejun," European Journal of Operational Research, Elsevier, vol. 249(2), pages 717-727.
    3. Fernando Acebes & Javier Pajares & José M. González-Varona & Adolfo López-Paredes, 2021. "Project risk management from the bottom-up: Activity Risk Index," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 29(4), pages 1375-1396, December.
    4. Fernando Acebes & Javier Pajares & Jose M Gonzalez-Varona & Adolfo Lopez-Paredes, 2024. "Project Risk Management from the bottom-up: Activity Risk Index," Papers 2406.00078, arXiv.org.
    5. Vaseghi, Forough & Martens, Annelies & Vanhoucke, Mario, 2024. "Analysis of the impact of corrective actions for stochastic project networks," European Journal of Operational Research, Elsevier, vol. 316(2), pages 503-518.
    6. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2021. "Using Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 288(3), pages 736-752.
    7. Colin, Jeroen & Vanhoucke, Mario, 2014. "Setting tolerance limits for statistical project control using earned value management," Omega, Elsevier, vol. 49(C), pages 107-122.
    8. Servranckx, Tom & Vanhoucke, Mario & Aouam, Tarik, 2021. "Practical application of reference class forecasting for cost and time estimations: Identifying the properties of similarity," European Journal of Operational Research, Elsevier, vol. 295(3), pages 1161-1179.
    9. Tao, Liangyan & Wu, Desheng & Liu, Sifeng & Lambert, James H., 2017. "Schedule risk analysis for new-product development: The GERT method extended by a characteristic function," Reliability Engineering and System Safety, Elsevier, vol. 167(C), pages 464-473.
    10. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2020. "The impact of a limited budget on the corrective action taking process," European Journal of Operational Research, Elsevier, vol. 286(3), pages 1070-1086.
    11. Chen, Yang & Zhang, Xiaoling & Chau, K.W. & Yang, Linchuan, 2022. "How the institutional change in urban redevelopment affects the duration of land redevelopment approval in China?," Land Use Policy, Elsevier, vol. 119(C).
    12. Andrei LINU & Danut DUMITRASCU, 2017. "Risk Management Challenges Of European Social Fund Under Current Programming Period 2014-2020 In Romania," Proceedings of the INTERNATIONAL MANAGEMENT CONFERENCE, Faculty of Management, Academy of Economic Studies, Bucharest, Romania, vol. 11(1), pages 107-119, November.
    13. Martens, Annelies & Vanhoucke, Mario, 2019. "The impact of applying effort to reduce activity variability on the project time and cost performance," European Journal of Operational Research, Elsevier, vol. 277(2), pages 442-453.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Fernando Acebes & Javier Pajares & José M. González-Varona & Adolfo López-Paredes, 2021. "Project risk management from the bottom-up: Activity Risk Index," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 29(4), pages 1375-1396, December.
    2. Fernando Acebes & Javier Pajares & Jose M Gonzalez-Varona & Adolfo Lopez-Paredes, 2024. "Project Risk Management from the bottom-up: Activity Risk Index," Papers 2406.00078, arXiv.org.
    3. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2021. "Using Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 288(3), pages 736-752.
    4. R. Alan Bowman, 2003. "Sensitivity curves for effective project management," Naval Research Logistics (NRL), John Wiley & Sons, vol. 50(5), pages 481-497, August.
    5. Vanhoucke, Mario, 2010. "Using activity sensitivity and network topology information to monitor project time performance," Omega, Elsevier, vol. 38(5), pages 359-370, October.
    6. Elmaghraby, Salah E., 2000. "On criticality and sensitivity in activity networks," European Journal of Operational Research, Elsevier, vol. 127(2), pages 220-238, December.
    7. Junguang Zhang & Dan Wan, 2021. "Determination of early warning time window for bottleneck resource buffer," Annals of Operations Research, Springer, vol. 300(1), pages 289-305, May.
    8. Vaseghi, Forough & Martens, Annelies & Vanhoucke, Mario, 2024. "Analysis of the impact of corrective actions for stochastic project networks," European Journal of Operational Research, Elsevier, vol. 316(2), pages 503-518.
    9. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2022. "Using Earned Value Management and Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 297(2), pages 451-466.
    10. Azaron, Amir & Fatemi Ghomi, S.M.T., 2008. "Lower bound for the mean project completion time in dynamic PERT networks," European Journal of Operational Research, Elsevier, vol. 186(1), pages 120-127, April.
    11. Gary Mitchell, 2010. "On Calculating Activity Slack in Stochastic Project Networks," American Journal of Economics and Business Administration, Science Publications, vol. 2(1), pages 78-85, March.
    12. Salim Rostami & Stefan Creemers & Roel Leus, 2018. "New strategies for stochastic resource-constrained project scheduling," Journal of Scheduling, Springer, vol. 21(3), pages 349-365, June.
    13. J-G Cho & B-J Yum, 2004. "Functional estimation of activity criticality indices and sensitivity analysis of expected project completion time," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 55(8), pages 850-859, August.
    14. Elmaghraby, S. E. & Fathi, Y. & Taner, M. R., 1999. "On the sensitivity of project variability to activity mean duration," International Journal of Production Economics, Elsevier, vol. 62(3), pages 219-232, September.
    15. Martens, Annelies & Vanhoucke, Mario, 2019. "The impact of applying effort to reduce activity variability on the project time and cost performance," European Journal of Operational Research, Elsevier, vol. 277(2), pages 442-453.
    16. Luz Stella Cardona-Meza & Gerard Olivar-Tost, 2017. "Modeling and Simulation of Project Management through the PMBOK® Standard Using Complex Networks," Complexity, Hindawi, vol. 2017, pages 1-12, December.
    17. Carlo Meloni & Marco Pranzo, 2020. "Expected shortfall for the makespan in activity networks under imperfect information," Flexible Services and Manufacturing Journal, Springer, vol. 32(3), pages 668-692, September.
    18. Vanhoucke, Mario, 2011. "On the dynamic use of project performance and schedule risk information during projecttracking," Omega, Elsevier, vol. 39(4), pages 416-426, August.
    19. Bregman, Robert L., 2009. "A heuristic procedure for solving the dynamic probabilistic project expediting problem," European Journal of Operational Research, Elsevier, vol. 192(1), pages 125-137, January.
    20. Davaadorjin Monhor, 2011. "A new probabilistic approach to the path criticality in stochastic PERT," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 19(4), pages 615-633, December.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:ejores:v:219:y:2012:i:3:p:751-761. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/eor .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.