RENCANA ANGGARAN BIAYA
PAKET KEGIATAN : CORYPHA MART
TAHUN : 2023
NO. DEVISI URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN (Rp) JUMLAH
1. PEKERJAAN PERSIAPAN
1.1 Pembersian Lokasi 1.00 Ls 18,400.00 18,400.00
1.2 Pengukuran dan Pemasangan Bowplank 72.00 m1 84,525.00 6,085,800.00
1.3 penyediaan Air 1.00 Ls 1,500,000.00 1,500,000.00
1.4 papan Nama Proyek 1.00 Ls 500,000.00 500,000.00
1.5 mobilisai dan Demobilisai Peralatan 1.00 Ls 5,000,000.00 5,000,000.00
JUMLAH DEVISI 1 13,104,200.00
2. PEKERJAAN GALIAN DAN PONDASI
2.1 Galian Tanah Pondasi 79.60 m3 75,612.50 6,018,755.00
2.2 Urugan Pasir Bawah Pondasi 4.05 m3 287,270.00 1,163,443.50
2.3 Pasangan Anstamping 12.15 m3 684,876.75 8,321,252.51
2.4 Pasangan Pondasi Batu Karang 1 Pc : 5 Psr 68.74 m3 1,013,753.75 69,682,898.39
2.5 Urugan Tanah Kembali 19.90 m3 11,270.00 224,273.00
JUMLAH DEVISI 2 85,410,622.40
3. PEKERJAAN STRUKTUR
3.1 PEKERJAAN SLOOF (15 cm x 30 cm)
3.1.(a) Beton Sloof K- 250 4.16 m3 1,154,490.49 4,805,566.65
3.1.(b) Besi Beton Ulir Ø10 573.50 Kg 19,681.68 11,287,440.61
3.1.(c) Besi Beton Polos Ø8 192.71 Kg 19,681.68 3,792,894.95
3.1.(d) Bekesting Sloof 55.50 m2 238,084.50 13,213,689.75
3.2 KOLOM UTAMA(25 cm x 30 cm) 0.00
3.2.(a) Beton Kolom K-250 4.05 m3 1,154,490.49 4,675,686.47
3.2.(b) Besi Beton Ulir Ø10 267.84 Kg 19,681.68 5,271,539.83
3.2.(c) Besi Beton Polos Ø8 146.25 Kg 19,681.68 2,878,444.97
3.2.(d) Bekesting Kolom 34.2 m2 384,232.25 13,140,742.95
3.3 PEKERJAAN KOLOM PRAKTIS (15 CM X 15 CM ) 0.00
3.3.(a) Beton Kolom K-175 0.49 m3 1,091,721.87 530,576.83
3.3.(b) Besi Beton Ulir Ø10 53.57 Kg 19,681.68 1,054,307.97
3.3.(c) Besi Beton Polos Ø8 73.13 Kg 19,681.68 1,439,222.48
3.3.(d) Bekesting Kolom Praktis 6.05 m2 384,232.25 2,323,836.65
3.4 PEKERJAAN RING BALK 0.00
3.4.(a) Beton Kolom K-175 2.775 m3 1,091,721.87 3,029,528.20
3.4.(b) Besi Beton Ulir Ø10 229.4 Kg 19,681.68 4,514,976.25
3.4.(c) Besi Beton Polos Ø8 120.45 Kg 19,681.68 2,370,559.35
3.4.(d) Bekesting Ring Balk 55.5 m2 398,032.25 22,090,789.88
3.5 PEKERJAAN BALOK LATEI 0.00
3.5.(a) Beton K-175 22.50 m3 1,091,721.87 24,563,742.18
3.5.(b) Besi Beton Polos Ø10 24.80 Kg 19,681.68 488,105.54
3.5.(c) Besi Beton Polos Ø8 13.20 Kg 19,681.68 259,699.70
3.5.(d) Bekesting Balok Latei 3.00 m2 398,032.25 1,194,096.75
3.6 PEKERJAAN RABAT LANTAI 0.00
3.6.(a) Beton K-175 7.00 m3 1,091,721.87 7,642,053.12
3.6.(b) Besi Wermes M4 20.00 Kg 19,681.68 393,633.50
3.7 Pekerjaan Paving Block Persegi Panjang m2 0.00
JUMLAH DEVISI 3 130,961,134.58
4. PEKERJAAN ARSITEKTUR
4.1 PEKERJAAN DINDING
4.1.(a) Pekerjaan Dinding Batako (1 Pc : 4 Psr ) 6.30 m2 150,045.10 945,284.13
4.1.(b) Pekerjaan Plesteran Dinding 5.25 m2 67,029.59 351,905.35
4.1.(c) Pekerjaan Acian Dinding 5.25 m2 39,430.63 207,010.78
4.1.(d) Pekerjaan Pengecetan Dinding Ex. Dullux 5.25 m2 39,430.63 207,010.78
4.2 PEKERJAAN LANTAI m2
4.1.(a) Pekerjaan Lantai Keramik (60cm x 60cm) 0.00 m2 503,125.00 0.00
4.1.(b) Pekerjaan Lantai Keramik KM/WC (30cm x 30cm) 60.00 m2 503,125.00 30,187,500.00
4.3 PEKERJAAN KUSEN ALUMUNIUM PINTU, JENDELA DAN BOVEN
4.3.(a) Tipe JB, Lengkap Dengan Assesoris 1.00 Unit 114,295.63 114,295.63
4.3.(b) Tipe JB-1, Lengkap Dengan Assesoris 1.00 Unit 114,295.63 114,295.63
4.3.(c) Tipe PR-1, Lengkap Dengan Assesoris 1.00 Unit 3,500,000 3,500,000.00
4.3.(d) Tipe PR-2, Lengakap Dengan Assesoris 1.00 Unit 3,500,000 3,500,000.00
4.3.(e) Tipe P, Lengakap Dengan Assesoris 1.00 Unit 3,500,000 3,500,000.00
4.3.(f) Tipe P-1, Lengakap Dengan Assesoris 1.00 Unit 3,500,000 3,500,000.00
4.3.(g) Tipe P - T, Lengakap Dengan Assesoris 1.00 Unit 3,500,000 3,500,000.00
4.3.(h) Tipe BV, Lengakap Dengan Assesoris 1.00 Unit 114,295.63 114,295.63
JUMLAH DEVISI 4 49,741,597.92
5. PEKERJAAN ATAP
5.1 Pekerjaan Rangka Atap baja Ringan 0.12 m2 705,870.00 84,704.40
5.2 Penutup Atap Spandek (0.30mm) 0.00 m2 194,695.00 0.00
5.2 Pekerjaan Plafond
5.3.(a) Pasangan Rangka Plafon Holow 5.40 m2 0.00
5.4.(b) Pasangan Penutup Plafon Calsiboard (6mm) 5.40 m2 0.00
JUMLAH DEVISI 5 84,704.40
6. PEKERJAAN ELEKTRICAL
6.1 Saklar Ganda Broco 10.00 bh 0.00
6.2 Stop Kontak Broco 12.00 bh 0.00
6.3 Sekring Box 2.00 unit 0.00
6.4 Lampu Neon 9 watt 60cm, LED 29.00 bh 0.00
6.5 Lampu Led Baret 17 Watt 10.00 bh 0.00
6.6 kabel Listrik 70.00 m1 0.00
JUMLAH DEVISI 6 0.00
7. PEKERJAAN SANITAIR
7.1 Closed Jongkok Toto 1.00 Unit 0.00
7.2 Kitchen Zing 1.00 Unit 0.00
7.3 Keran Air 2.00 Unit 0.00
7.4 Floor Drain 1.00 Unit 0.00
JUMLAH DEVISI 7 0.00
8. LAIN-LAIN
8.1 Pekerjaan Kanopi Baja Ringan 0.00 M2 0.00
8.2 Penutuup Kanopi Spandek 0,30 mm 0.00 M2 0.00
JUMLAH DEVISI 8 0.00
TOTAL 279,302,259.30
DAFTAR HARGA SATUAN UPAH, BAHAN DAN PERALATAN
IV BAHAN KAYU
I Kayu Klas I Jati m3 Rp14,500,000.00
2 Kayu Klas II Kamper m3 Rp4,000,000.00
3 Kayu Klas III Meranti m3 Rp2,600,000.00
4 KayuKlas IV Terentang m3 Rp1,500,000.00
5 Dolken dia 8 s/d 10 cm p.4m btg Rp6,000.00
6 Kayu 5/7 m3 Rp2,500,000.00
7 Papan 3/20 m3 Rp2,500,000.00
V BAHAN ALMUNIUM
I Kusen Almunium 3", Alexindo m' Rp90,000.00
2 Rangka Jendela Almunium Alexindo m' Rp90,000.00
3 Rangka Fintu Almunium Alexindo m' Rp90,000.00
4 Kusen & Pintu PVC toilet Maspion unt Rp1,400,000.00
5 Engsel 3",ex Bos bh Rp60,000.00
6 Handle pintu type HRE 75.01 ex. Cisa bh Rp225,000.00
7 Selinder type 0851 O ex. Cisa bh Rp75,000.00
8 Door Stoper bh Rp60,000.00
9 Door closer bh Rp200,000.00
10 Slot Tanam bh Rp75,000.00
II Kait Angin bh Rp15,000.00
12 Grendel bh Rp30,000.00
13 Kunci Tanam bh Rp200,000.00
VI BAHAN PELAPIS :
1 Triplek t. 3mm Uk 120x240 cm lbr Rp50,000.00
2 Triplex t. 4 mm Uk 120x240 cm lbr Rp60,000.00
3 Triplex t. 9 mm Uk 120x240 cm lbr Rp120,000.00
IX BAHANKACA:
1 Kaca Polos 3 mm m2 Rp80,000.00
2 Kaca Polos 5 mm m2 Rp125,000.00
3 Kaca Polos 8 mm m2 Rp400,000.00
XI BAHAN FINISHING :
1 Cat kayu/Besi ex. SEIV Kg Rp70,000.00
2 PlamirKayu Kg Rp45,000.00
3 Menikayu ex. Nippon kg Rp45,000.00
4 Wood Filler Impra Kg Rp50,000.00
5 Thinner ND IMPALA Ltr Rp45,000.00
6 Amplas Kayu Lbr Rp6,000.00
7 Kwas cat bh Rp22,500.00
8 Cat Tembok kwl ex. Dulux; Warna standard Kg Rp60,000.00
9 Cat Tembok kw2 ex. Vinilex; Warna standard Kg Rp35,000.00
10 Plamir Tembok Kg Rp15,500.00
11 Lem Kayu kg Rp47,000.00
12 Seal tape bh Rp10,000.00
13 Minyak bekisting Ltr Rp20,000.00
14 Sealant Tube Rp35,000.00
xv PERALATAN ELEKTRIKAL
1 Box panel PVC isi 4 MCB bh Rp50,000.00
2 MCB 6 A bh Rp85,000.00
3 MCB4A bh Rp85,000.00
4 Kabel NYM 2 x 2,5 mm2 m' Rp12,500.00
5 Kabel NYM 3 x 2,5 mm2 m' Rp17,500.00
6 Kabel telephone 4 x 0.5 mm m' Rp7,500.00
7 Isolasi bh Rp15,000.00
8 Saklar tunggal bh Rp20,000.00
9 Saklar ganda bh Rp27,000.00
10 Stop kontak bh Rp25,000.00
11 Outlet TV bh Rp65,000.00
12 Outlet Telephone bh Rp65,000.00
13 Down light / PLC 13 W bh Rp75,000.00
14 Fitting plafond + lampu SL bh Rp135,000.00
15 Lampu TL 2 x 18 watt grille bh Rp375,000.00
16 Lampu TL 2 x 36 watt grille bh Rp675,000.00
17 Downligt Krisbow bh Rp80,000.00
18 Led essential Krissbow bh Rp27,500.00
19 Pipa Listrik5/8" btg Rp15,000.00
20 Tee Dos bh Rp5,000.00
21 L. Bow bh Rp5,000.00
22 Las Dop bh Rp5,000.00
23 Klem Pipa Listrik bh Rp1,500.00
24 Mongkok (listrik) bh Rp5,000.00
25 Fitting Lampu bh Rp20,000.00
26 Fissher bh Rp7,000.00
27 Pipa Conduit m' Rp7,500.00
28 Socket Pipa bh Rp2,000.00
a. Tenaga Kerja
0.100 oh Pekerja 82,500.00 8,250.00
0.010 oh Mandor 155,000.00 1,550.00
Jumlah Tenaga Kerja 9,800.00
b. Bahan
-
Jumlah Harga Bahan
c. Peralatan
Jumlah Herga Peralatan