Business Plan Quick Lime
Business Plan Quick Lime
Business Plan Quick Lime
HARGA ( Rp
NO INVESTASI JUML SATUAN
SATUAN
A. MESIN & PERALATAN PRODUKSI
1 Rotary Kiln Capacity 300 Ton/day 1 Unit 95,000,000,000
2 Limestone Crusher Capacity 400 Ton/day 1 Unit 4,250,000,000
3 Excavator 2 Unit 1,860,000,000
4 Instalasi Jembatan Timbang Capacity 150 Tons 1 Unit 650,000,000
5 Instalasi Listrik & Genset 2.500 kVA 1 Paket 4,550,000,000
6 Wheel loader 4 Unit 750,000,000
HARGA ( Rp )
TOTAL
95,000,000,000
4,250,000,000
3,720,000,000
650,000,000
4,550,000,000
3,000,000,000
111,170,000,000
NTARIS KANTOR
250,000,000
6,000,000,000
32,000,000,000
195,000,000
285,000,000
1,060,000,000
52,500,000
62,500,000
27,000,000
17,500,000
450,000,000
175,000,000
40,574,500,000
ERTAMA
4,954,879,091
2,986,875,000
88,860,000
66,000,000
8,096,614,091
159,841,114,091
DISCRIPTIONS Pra Produksi Month 1st Month 2nd Month 3rd Month 4th Month 5th Month 6th Month 7th Month 8th Month 9th
PENDAPATAN
1. Penjualan :
- 4.500 Ton X Rp 900.000,- 4,050,000,000 4,050,000,000 4,050,000,000 4,050,000,000 4,050,000,000 4,050,000,000 4,050,000,000 4,050,000,000
TOTAL PENDAPATAN ( CASH IN ) - 4,050,000,000 4,050,000,000 4,050,000,000 4,050,000,000 4,050,000,000 4,050,000,000 4,050,000,000 4,050,000,000
A. BIAYA LANGSUNG - - - - - - - - -
1. Biaya Tambang & Produksi:
a. Peledakan
b. Sopir Excavator (2 orang) 4,800,000 4,800,000 4,800,000 4,800,000 4,800,000 4,800,000 4,800,000 4,800,000 4,800,000
c. Uang Makan Sopir Excavator 6,000,000 6,000,000 6,000,000 6,000,000 6,000,000 6,000,000 6,000,000 6,000,000 6,000,000
d. Solar (20 lt/jam X 2 X 8 Jam) 73,440,000 73,440,000 73,440,000 73,440,000 73,440,000 73,440,000 73,440,000 73,440,000 73,440,000
e. Bahan Bakar Gas 1,513,636,364 1,513,636,364 1,513,636,364 1,513,636,364 1,513,636,364 1,513,636,364 1,513,636,364 1,513,636,364 1,513,636,364
f. Listrik Crusher + Solar Ganset 20,000,000 20,000,000 20,000,000 20,000,000 20,000,000 20,000,000 20,000,000 20,000,000 20,000,000
g. Pengawas (3 Orang) 7,500,000 7,500,000 7,500,000 7,500,000 7,500,000 7,500,000 7,500,000 7,500,000 7,500,000
h. Tenaga Kerja Produksi (15 Orang) 26,250,000 26,250,000 26,250,000 26,250,000 26,250,000 26,250,000 26,250,000 26,250,000 26,250,000
Total Biaya Tambang & Produksi 1,651,626,364 1,651,626,364 1,651,626,364 1,651,626,364 1,651,626,364 1,651,626,364 1,651,626,364 1,651,626,364 1,651,626,364
2. Distribusi :
a. Dari Tambang - Produksi 140,625,000 140,625,000 140,625,000 140,625,000 140,625,000 140,625,000 140,625,000 140,625,000 140,625,000
b. Ke Krakatau Steel 855,000,000 855,000,000 855,000,000 855,000,000 855,000,000 855,000,000 855,000,000 855,000,000 855,000,000
Total Biaya Distribusi 995,625,000 995,625,000 995,625,000 995,625,000 995,625,000 995,625,000 995,625,000 995,625,000 995,625,000
TOTAL BIAYA LANGSUNG 2,647,251,364 2,647,251,364 2,647,251,364 2,647,251,364 2,647,251,364 2,647,251,364 2,647,251,364 2,647,251,364 2,647,251,364
B. BIAYA OPERASIONAL KANTOR
1. Biaya Administrasi & Kantor
1. Direktur 7,500,000 7,500,000 7,500,000 7,500,000 7,500,000 7,500,000 7,500,000 7,500,000 7,500,000
2. Manajer 3,500,000 3,500,000 3,500,000 3,500,000 3,500,000 3,500,000 3,500,000 3,500,000 3,500,000
3. Staff Kantor (3 Orang) 6,000,000 6,000,000 6,000,000 6,000,000 6,000,000 6,000,000 6,000,000 6,000,000 6,000,000
3. ATK 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000
4. Telepon + Internet 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000
5. Listrik 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000
6. Konsumsi (15 + 7 Orang) 4,620,000 4,620,000 4,620,000 4,620,000 4,620,000 4,620,000 4,620,000 4,620,000 4,620,000
Total Biaya Adm. & Kantor 29,620,000 29,620,000 29,620,000 29,620,000 29,620,000 29,620,000 29,620,000 29,620,000 29,620,000
2. Biaya Kantor Tidak Langsung
1. Transportasi/perjalanan dinas 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000
2. Perawatan mesin 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000
3. Perawatan kantor 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000
4. CSR 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000
Total Biaya Kantor Tidak Langsung 22,000,000 22,000,000 22,000,000 22,000,000 22,000,000 22,000,000 22,000,000 22,000,000 22,000,000
Total Biaya Operasional Kantor 51,620,000 51,620,000 51,620,000 51,620,000 51,620,000 51,620,000 51,620,000 51,620,000 51,620,000
PENDAPATAN BRUTTO (2,698,871,364) 1,351,128,636 1,351,128,636 1,351,128,636 1,351,128,636 1,351,128,636 1,351,128,636 1,351,128,636 1,351,128,636
C. INVESTASI MODAL
1. Total Investasi Mesin & Peralatan ###
2. Total Investasi Tanah, Bangunan dll 40,574,500,000
###
3. Total Modal Kerja Bulan Pertama 8,096,614,091
Total Investasi Awal ###
D. SALDO LABA ( RUGI )
1. Pendapatan :
a. Pendapatan Brutto Bulan/Tahun Ke - 1,351,128,636 1,351,128,636 1,351,128,636 1,351,128,636 1,351,128,636 1,351,128,636 1,351,128,636 1,351,128,636
b. Pendapatan Sebelumnya
2. Hutang Modal (159,841,114,091) (158,489,985,455) (157,138,856,818) ### ### ### ### ###
TOTAL SALDO LABA ( RUGI ) - (158,489,985,455) ### ### ### ### ### ### ###
Month 10th Month 11th Month 12th
- - -
Loan Rp 159,841.1
I.R.R Err:523
R.O.I 1.79%
avg. cash in flows - Rp 54,396
avg. amount of invested - R 30,349
3,963,000,000
BIA EXA/JAM
SOLAR/JAM 15 LITER
SOPIR/JAM 7500/JAM
Kal 600
Kal Gas 9,500
1 kg gas 16
kg
TOTAL TOTAL
DISCRIPTIONS
YEAR I YEAR II
PENDAPATAN
1. Penjualan :
- 4.500 Ton X Rp 900.000,- 44,550,000,000 49,005,000,000
A. BIAYA LANGSUNG
1. Biaya Tambang & Produksi:
a. Peledakan - -
b. Sopir Excavator (2 orang) 57,600,000 63,360,000
c. Uang Makan Sopir Excavator 72,000,000 79,200,000
d. Solar (20 lt/jam X 2 X 8 Jam) 881,280,000 969,408,000
e. Bahan Bakar Gas 18,163,636,364 19,980,000,000
f. Listrik Crusher + Solar Ganset 240,000,000 264,000,000
g. Pengawas (3 Orang) 90,000,000 99,000,000
h. Tenaga Kerja Produksi (15 Orang) 315,000,000 346,500,000
Total Biaya Tambang & Produksi 19,819,516,364 21,801,468,000
2. Distribusi :
a. Dari Tambang - Produksi 1,687,500,000 1,856,250,000
b. Ke Krakatau Steel 10,260,000,000 11,286,000,000
Total Biaya Distribusi 11,947,500,000 13,142,250,000
TOTAL BIAYA LANGSUNG 31,767,016,364 34,943,718,000
- - -
69,696,000 76,665,600 84,332,160
87,120,000 95,832,000 105,415,200
1,066,348,800 1,172,983,680 1,290,282,048
21,978,000,000 24,175,800,000 26,593,380,000
290,400,000 319,440,000 351,384,000
108,900,000 119,790,000 131,769,000
381,150,000 419,265,000 461,191,500
23,981,614,800 26,379,776,280 29,017,753,908