Curva S
Curva S
Curva S
"INSTALACIÓN DE LOS SERVICIOS DE EDUCACIÓN INICIAL ESCOLARIZADA QUE LE CORRESPONDE AL CENTRO POBLADO DE TICTE DISTRITO DE MARIAS
OBRA
PROVINCIA DE DOS DE MAYO - REGION HUANUCO"
GRÁFICO COMPARATIVO:
VAL. PROGRAMADOS VS. EJECUTADOS
100% 100.00%
97.96%
90%
80%
73.55%
70%
AVANCE
64.39%
60%
55.96% 55.96% 55.96%
40%
33.49%
30%
24.28%
20%
PROGRAMADO EJECUTADO
10%
5.74%
4.81%
0% 0.00% 0.00%
- Oct. 2019 Nov. 2019 Dic. 2019 Ener.2020 Febr. 2020 Marzo 2020 Abril. 2020 Mayo. 2020
MESES
- - - - - - - - - -
Oct. 2019 100,268.54 100,268.54 5.74% 5.74% Oct. 2019 84,022.85 84,022.85 4.81% 4.81%
Nov. 2019 323,923.92 424,192.46 18.54% 24.28% Nov. 2019 501,042.57 585,065.42 28.68% 33.49%
Dic. 2019 380,536.59 804,729.05 21.78% 46.06% Dic. 2019 392,586.39 977,651.81 22.47% 55.96%
Ener.2020 SUSPENSION DE OBRA N° 01 0.00% 46.06% Ener.2020 SUSPENSION DE OBRA N° 01 0.00% 55.96%
DEL 20-12-2019 AL 02-03- DEL 20-12-2019 AL 02-03-
Febr. 2020 2020 0.00% 46.06% Febr. 2020 2020 0.00% 55.96%
Marzo 2020 480,146.31 1,284,875.36 27.48% 73.55% Marz. 2020 147,235.72 1,124,887.53 8.43% 64.39%
Abril. 2020 426,500.61 1,711,375.96 24.41% 97.96% Abril 2020
Mayo. 2020 35,656.74 1,747,032.70 2.04% 100.00% Mayo 2020
TOTAL 1,747,032.70 100.00% TOTAL 1,124,887.53 64.39%
GRÁFICO DEL CONTROL DE AVANCE
(CURVA "S" - PROGRAMADO VS. EJECUTADO)
"INSTALACIÓN DE LOS SERVICIOS DE EDUCACIÓN INICIAL ESCOLARIZADA QUE LE CORRESPONDE AL CENTRO POBLADO DE TICTE DISTRITO DE MARIAS
OBRA
PROVINCIA DE DOS DE MAYO - REGION HUANUCO"
GRÁFICO COMPARATIVO:
VAL. PROGRAMADOS VS. EJECUTADOS
100% 97.23% 97.23%
95.20%
90%
79.50%
80%
70%
AVANCE
60%
49.37%
50%
45.16%
40%
30%
23.01% PROGRAMADO
Column K
20%
10%
MESES
- - - - - - - - - -
Oct. 2019 77,497.35 77,497.35 49.37% 49.37% Oct. 2019 36,113.74 36,113.74 23.01% 23.01%
Nov. 2019 47,295.87 124,793.22 30.13% 79.50% Nov. 2019 34,780.67 70,894.41 22.16% 45.16%
Dic. 2019 24,658.55 149,451.77 15.71% 95.20% Dic. 2019
Ene. 2020 3,181.74 152,633.51 2.03% 97.23% Ene. 2020
Febr. 2020 - 152,633.51 0.00% 97.23% Febr. 2020
Marz. 2020 4,347.85 156,981.36 2.77% 100.00% Marz. 2020
TOTAL 156,981.36 100.00% TOTAL 70,894.41 45.16%
GRÁFICO DEL CONTROL DE AVANCE
(CURVA "S" - PROGRAMADO VS. EJECUTADO)
"INSTALACIÓN DE LOS SERVICIOS DE EDUCACIÓN INICIAL ESCOLARIZADA QUE LE CORRESPONDE AL CENTRO POBLADO DE TICTE DISTRITO DE MARIAS
OBRA
PROVINCIA DE DOS DE MAYO - REGION HUANUCO"
GRÁFICO COMPARATIVO:
VAL. PROGRAMADOS VS. EJECUTADOS
100.00%
100%
98.23%
90%
80%
70% 68.02%
AVANCE
60%
50%
45.32%
40%
30% 29.60%
Column E Column K
20%
14.20%
10%
2.60%
MESES
- - - - - - - - - -
Oct. 2019 - - 0.00% 0.00% Oct. 2019 32,292.79 32,292.79 2.60% 2.60%
Nov. 2019 176,428.52 176,428.52 14.20% 14.20% Nov. 2019 335,488.33 367,781.12 27.00% 29.60%
Dic. 2019 386,772.03 563,200.55 31.12% 45.32% Dic. 2019
Ene. 2020 282,056.15 845,256.70 22.70% 68.02% Ene. 2020
Febr. 2020 375,466.54 1,220,723.24 30.21% 98.23% Febr. 2020
Marz. 2020 21,945.66 1,242,668.90 1.77% 100.00% Marz. 2020
TOTAL 1,242,668.90 100.00% TOTAL 367,781.12 29.60%
GRÁFICO DEL CONTROL DE AVANCE
(CURVA "S" - PROGRAMADO VS. EJECUTADO)
"INSTALACIÓN DE LOS SERVICIOS DE EDUCACIÓN INICIAL ESCOLARIZADA QUE LE CORRESPONDE AL CENTRO POBLADO DE TICTE DISTRITO DE MARIAS
OBRA
PROVINCIA DE DOS DE MAYO - REGION HUANUCO"
GRÁFICO COMPARATIVO:
VAL. PROGRAMADOS VS. EJECUTADOS 100.00%
100%
90%
82.46%
80%
70%
AVANCE
60%
50%
40% 36.51%
30%
PROGRAMADO
Column K
20%
10%
MESES
- - - - - - - - - -
Oct. 2019 - - 0.00% 0.00% Oct. 2019
Nov. 2019 - - 0.00% 0.00% Nov. 2019
Dic. 2019 - - 0.00% 0.00% Dic. 2019
Ene. 2020 190,170.82 190,170.82 36.51% 36.51% Ene. 2020
Febr. 2020 239,365.67 429,536.49 45.95% 82.46% Febr. 2020
Marz. 2020 91,378.24 520,914.73 17.54% 100.00% Marz. 2020
TOTAL 520,914.73 100.00% TOTAL - 0.00%
GRÁFICO DEL CONTROL DE AVANCE
(CURVA "S" - PROGRAMADO VS. EJECUTADO)
"INSTALACIÓN DE LOS SERVICIOS DE EDUCACIÓN INICIAL ESCOLARIZADA QUE LE CORRESPONDE AL CENTRO POBLADO DE TICTE DISTRITO DE MARIAS
OBRA
PROVINCIA DE DOS DE MAYO - REGION HUANUCO"
GRÁFICO COMPARATIVO:
VAL. PROGRAMADOS VS. EJECUTADOS 100.00%
100%
90%
80%
70%
AVANCE
60%
50%
40%
34.55%
30% 26.80%
PROGRAMADO
Column K
20%
10%
MESES
- - - - - - - - - -
Oct. 2019 - - 0.00% 0.00% Oct. 2019
Nov. 2019 - - 0.00% 0.00% Nov. 2019
Dic. 2019 - - 0.00% 0.00% Dic. 2019
Ene. 2020 21,310.78 21,310.78 26.80% 26.80% Ene. 2020
Febr. 2020 6,164.88 27,475.66 7.75% 34.55% Febr. 2020
Marz. 2020 52,053.20 79,528.86 65.45% 100.00% Marz. 2020
TOTAL 79,528.86 100.00% TOTAL - 0.01%
GRÁFICO DEL CONTROL DE AVANCE
(CURVA "S" - PROGRAMADO VS. EJECUTADO)
"INSTALACIÓN DE LOS SERVICIOS DE EDUCACIÓN INICIAL ESCOLARIZADA QUE LE CORRESPONDE AL CENTRO POBLADO DE TICTE DISTRITO DE MARIAS
OBRA
PROVINCIA DE DOS DE MAYO - REGION HUANUCO"
GRÁFICO COMPARATIVO:
VAL. PROGRAMADOS VS. EJECUTADOS
100%
90%
80%
70% 66.10%
AVANCE
60%
50%
40%
30%
24.61%
PROGRAMADO
Column K
20%
10%
2.59%
0.00% 0.94%
0% 0.00% 0.00% 0.00% 0.00% 0.00%
- Oct. 2019 Nov. 2019 Dic. 2019 Ene. 2020 Febr. 2020 Marz. 2020
MESES
- - - - - - - - - -
Oct. 2019 - - 0.00% 0.00% Oct. 2019
Nov. 2019 925.15 925.15 0.94% 0.94% Nov. 2019
Dic. 2019 1,610.56 2,535.71 1.64% 2.59% Dic. 2019
Ene. 2020 21,570.19 24,105.90 22.02% 24.61% Ene. 2020
Febr. 2020 40,633.70 64,739.60 41.49% 66.10% Febr. 2020
Marz. 2020 33,203.98 97,943.58 33.90% 100.00% Marz. 2020
TOTAL 97,943.58 100.00% TOTAL - 0.00%
GRÁFICO DEL CONTROL DE AVANCE
(CURVA "S" - PROGRAMADO VS. EJECUTADO)
"INSTALACIÓN DE LOS SERVICIOS DE EDUCACIÓN INICIAL ESCOLARIZADA QUE LE CORRESPONDE AL CENTRO POBLADO DE TICTE DISTRITO DE MARIAS
OBRA
PROVINCIA DE DOS DE MAYO - REGION HUANUCO"
GRÁFICO COMPARATIVO:
VAL. PROGRAMADOS VS. EJECUTADOS
99.34%
100% 97.01% 97.01% 97.01%
90%
80%
70%
AVANCE
60%
50%
40%
30%
22.75% PROGRAMADO
Column K
20%
10%
0.00%
0% 0.00% 0.00% 0.00% 0.00% 0.00%
- Oct. 2019 Nov. 2019 Dic. 2019 Ene. 2020 Febr. 2020 Marz. 2020
MESES
- - - - - - - - - -
Oct. 2019 - - 0.00% 0.00% Oct. 2019 3,303.14 3,303.14 22.75% 22.75%
Nov. 2019 14,087.14 14,087.14 97.01% 97.01% Nov. 2019
Dic. 2019 - 14,087.14 0.00% 97.01% Dic. 2019
Ene. 2020 - 14,087.14 0.00% 97.01% Ene. 2020
Febr. 2020 339.25 14,426.39 2.34% 99.34% Febr. 2020
Marz. 2020 95.26 14,521.65 0.66% 100.00% Marz. 2020
TOTAL 14,521.65 100.00% TOTAL 3,303.14 22.75%