Precios Unitario Pendientes
Precios Unitario Pendientes
Precios Unitario Pendientes
Inicio Obra:
Fin Obra:
DOCUMENTO
ART. 45 A.1 RLOPySRM
Lugar: TEPIC, NAYARIT
Inicio Obra:
Fin Obra:
DOCUMENTO
ART. 45 A.1 RLOPySRM
Lugar: TEPIC, NAYARIT
MATERIALES
PLACA DE 1 1/4 KG $17.25 * 80.016090 $1380.28
7018 SOLDADURA ELECTRODO 7018 KG $35.00 * 2.400483 $84.02
THINNER THINNER ESTANDAR LT $25.00 * 0.800161 $20.00
PRIMCOMEX PRIMARIO ANTICORROSIVO MCA COMEX LT $81.67 * 0.800161 $65.35
EQTORRE ANDAMIOS % $1,004.94 * 0.030000 $30.15
%MO5 EQUIPO DE SEGURIDAD % $1,004.94 * 0.030000 $30.15
Inicio Obra:
Fin Obra:
DOCUMENTO
ART. 45 A.1 RLOPySRM
Lugar: TEPIC, NAYARIT
MATERIALES
PLACA DE 1 1/4 KG $17.25 * 50.919330 $878.36
7018 SOLDADURA ELECTRODO 7018 KG $35.00 * 1.527580 $53.47
THINNER THINNER ESTANDAR LT $25.00 * 0.509193 $12.73
PRIMCOMEX PRIMARIO ANTICORROSIVO MCA COMEX LT $81.67 * 0.509193 $41.59
EQTORRE ANDAMIOS % $628.09 * 0.030000 $18.84
%MO5 EQUIPO DE SEGURIDAD % $628.09 * 0.030000 $18.84
Inicio Obra:
Fin Obra:
DOCUMENTO
ART. 45 A.1 RLOPySRM
Lugar: TEPIC, NAYARIT
MATERIALES
PLACA DE 1 1/4 KG $17.25 * 34.069661 $587.70
7018 SOLDADURA ELECTRODO 7018 KG $35.00 * 1.022090 $35.77
THINNER THINNER ESTANDAR LT $25.00 * 0.340697 $8.52
PRIMCOMEX PRIMARIO ANTICORROSIVO MCA COMEX LT $81.67 * 0.340697 $27.82
EQTORRE ANDAMIOS % $418.72 * 0.030000 $12.56
%MO5 EQUIPO DE SEGURIDAD % $418.72 * 0.030000 $12.56
Inicio Obra:
Fin Obra:
DOCUMENTO
ART. 45 A.1 RLOPySRM
Lugar: TEPIC, NAYARIT
MATERIALES
PLACA DE 1 1/4 KG $17.25 * 25.922568 $447.16
7018 SOLDADURA ELECTRODO 7018 KG $35.00 * 0.777677 $27.22
THINNER THINNER ESTANDAR LT $25.00 * 0.259226 $6.48
PRIMCOMEX PRIMARIO ANTICORROSIVO MCA COMEX LT $81.67 * 0.259226 $21.17
EQTORRE ANDAMIOS % $314.04 * 0.030000 $9.42
%MO5 EQUIPO DE SEGURIDAD % $314.04 * 0.030000 $9.42
Inicio Obra:
Fin Obra:
DOCUMENTO
ART. 45 A.1 RLOPySRM
Lugar: TEPIC, NAYARIT
MATERIALES
ESMALTE ALQUIDALICO LT $73.68 * 0.010500 $0.77
EQTORRE ANDAMIOS % $0.53 * 0.030000 $0.02
%MO5 EQUIPO DE SEGURIDAD % $0.53 * 0.030000 $0.02