Nothing Special   »   [go: up one dir, main page]

Jump to content

APR-1400

From Wikipedia, the free encyclopedia
(Redirected from APR+)

Unit 1 and unit 2 of Barakah nuclear power plant APR-1400 reactors in the United Arab Emirates

The APR-1400 (for Advanced Power Reactor 1400 MW electricity) is an advanced pressurized water nuclear reactor designed by the Korea Electric Power Corporation (KEPCO). Originally known as the Korean Next Generation Reactor (KNGR),[1] this Generation III reactor was developed from the earlier OPR-1000 design and also incorporates features from the US Combustion Engineering (C-E) System 80+ design.[2] Currently in South Korea there are 4 units in operation (Shin Kori unit 3 and 4, Shin Hanul units 1 and 2), and 2 units in construction (Shin Kori unit 5 and 6). Four units are completed and in commercial operation in the United Arab Emirates at Barakah.

History

[edit]

APR-1400 design began in 1992 and was awarded certification by the Korean Institute of Nuclear Safety in May 2002.[3] The design certification application was submitted to the US Nuclear Regulatory Commission (NRC) in December 2014 and in March 2015, it was accepted for technical review to determine if the reactor design meets basic US safety requirements.[4]

In October 2017, European Utility Requirements (EUR) organization approved changes to the APR-1400 design for emergency cooling, allowing the design to be built in countries outside Europe to EUR certification.[5]

As of September 2018, the NRC issued its final safety evaluation report[6] and standard design approval[7] finding the design technically acceptable and valid for 15 years. In April 2019 the NRC approved a rule to certify the APR-1400 standard design.[8][9] In September 2018, the U.S. Nuclear Regulatory Commission gave the APR-1400 Standard Design Approval, and in September 2019 it received a design certificate valid for 15 years.[10]

In 2022, Westinghouse Electric Company, which had acquired Combustion Engineering in 2000, filed a lawsuit in a U.S. federal court against KHNP and Kepco alleging that the APR-1400 was copied from the System 80 reactor. This had the indirect effect that the U.S. government rejected a request for necessary APR-1400 permission to export to a third country while the case is resolved.[11]

Locations

[edit]
Locations of APR-1400 units
  •  Active (number of units)
  •  Under construction [number of units]

South Korea

[edit]

The first commercial APR-1400 reactors at Shin Kori were approved in September 2007,[12] with construction starting in October 2008 (Unit 3) and August 2009 (Unit 4).[3][13][14] Shin Kori-3 was initially scheduled to commence operation by the end of 2013, but the schedules for both Units 3 & 4 were delayed by approximately one year to replace safety-related control cabling, which had failed some tests.[15] Construction of two more APR-1400 units at Shin Kori, Korea (Units 5 and 6) had been expected to begin in 2014,[16] but as of December 2016 plans had not been finalised.[17]

Construction of two new APR-1400s, Shin Hanul Units 1 & 2, began in May 2012 (Unit 1)[18] and June 2013 (Unit 2),[19] with Unit 1 expected to be completed in April 2017.[19] Two more APR-1400s at Shin Hanul were approved in 2014, with construction to start in 2017.[20]

After the election of President Moon Jae-in in May 2017, Korea Hydro & Nuclear Power (KHNP) suspended design work on Shin Hanul-3 and -4,[21] and construction work was suspended on Shin Kori-5 and -6 in July 2017 for a three-month period while a government-appointed committee met to discuss the country's future nuclear power policy.[22] President Moon had signed an agreement in March 2017 calling for the phase-out of nuclear energy while campaigning for president.[21] In October 2017, the committee recommended proceeding with the construction of Shin Kori-5 and -6.[23] President Moon announced he supported the committee's decision, but added that no new construction would be allowed,[24] throwing doubt on the fate of Shin Hanul-3 and -4.

As of April 2020, Shin-Kori 1 and 2 [25] and Shin-Hanul 1 are operational while Shin-Hanul 2 being loaded with fuel.[26]

United Arab Emirates

[edit]

In December 2009, a KEPCO-led consortium was awarded the contract to build four APR-1400 reactors at Barakah, United Arab Emirates.[27] Construction of Barakah Unit 1 started in July 2012,[28] Unit 2 started construction in May 2013,[29] Unit 3 started construction in September 2014[30] and Unit 4 started construction in September 2015.[31][32] Block 1 started to produce energy on 1 August 2020 and went into commercial operation on 6 April 2021.[33][34] several research projects were performed at Khalifa University to ensure the safe operation for the APR1400 nuclear power plant.[35][36][37][38] On 5th of september 2024 the fouth and final reactor started commercial production.

United Kingdom

[edit]

NuGeneration (NuGen) was formed as the joint venture between Engie, Iberdrola, and Scottish and Southern Energy (SSE) to develop the Moorside Nuclear Power Station in Cumbria; the initial plans called for three Westinghouse AP1000 units. SSE was bought out by Engie and Iberdrola in 2011, and Iberdrola's share, in turn, was purchased by Toshiba in 2013. Following the bankruptcy of Toshiba's subsidiary Westinghouse Electric Corporation in March 2017, Engie pulled out of NuGen in July, leaving Toshiba as the sole owner of NuGen. In December 2017, NuGen announced that KEPCO was named the preferred bidder to acquire NuGen from Toshiba; the three AP1000 reactors were to be replaced by two APR-1400 units.[39] In July 2018 Kepco's preferred bidder status was terminated, in response to difficulties financing the development.[40]

Poland

[edit]

In October 2022, Polish utilities PGE and ZE PAK announced an agreement with KHNP to build a number of APR-1400 reactors near ZE PAK's coal-fired plant at Pątnów.[41]

Summary

[edit]
APR-1400 Summary[42] [43] [44] [45]
Site Unit Status Construction
Start
Construction
Complete
Operation
Start
Shin-Kori 3 Operational 16 October 2008 30 October 2015 [a][17] 12 December 2016[17]
4 Operational 19 August 2009 November 2015[b] August 2019[a][25]
5 Under construction September 2016 unknown[46]
6 Under construction September 2017 unknown[46]
Shin-Hanul 1 Operational 10 July 2012 [47][c] May 2022[49]
2 Operational 19 June 2013 April 2020[26] December 2023[50]
3 Construction resumed[51] 2018 unknown
4 Construction resumed[51] 2018 unknown
Barakah 1 Operational 18 July 2012 5 May 2017[d] 6 April 2021[34]
2 Operational 28 May 2013 24 March 2022[54]
3 Operational 24 September 2014 4 November 2021[55] 24 February 2023[56][57]
4 Operational 2 September 2015 [e] 5 september 2024[59][60][54][58]
Notes
  1. ^ a b Delayed by fraudulent cabling issue[15]
  2. ^ Cold hydrostatic testing completed November 2015. Hot functional testing completed April 2016.[46]
  3. ^ Cold hydro testing completed in November 2016; hot functional testing scheduled for May–September 2017.[48]
  4. ^ Cold hydrostatic testing completed 16 February 2016.[52] Initial construction completed 5 May 2017, with remaining testing pending operating license permitting fuel loading.[53]
  5. ^ Major RCS components installed in summer 2017.[58]

Design

[edit]

The APR-1400 is an evolutionary Advanced Light Water Reactor which is based on the previous OPR-1000 design. Under Korean conditions, the reactor produced 1455 MW gross electrical power with a thermal power capacity of 3983 MW (4000 MW nominal).[61]

The design was developed to meet 43 design requirements,[62] with the main developments being evolution in capacity, increased lifetime and enhanced safety. The design improvements also focus on meeting economic objectives and licensing requirements. Compared to the OPR-1000, the key features are:

  • Net Electric power: 1400 MW (40% increase)
  • Design Life: 60 years (50% increase)
  • Seismic Design Basis: 0.3g (50% increase)
  • Core Damage Frequency: less than 10−5/yr (10x decrease)
  • Core fuel assemblies: 241 (36% increase)

Several other changes were incorporated such as moving to complete digital I/C and implementation of new systems in the Safety Injection System (SIT).

Core

[edit]

The reactor core of the APR-1400 consists of 241 fuel assemblies, 93 control element assemblies, and 61 in-core instrumentation assemblies. Each fuel assembly has 236 fuel rods in a 16 x 16 array (some space is taken up by guide tubes for control elements) containing Uranium dioxide (average enrichment of 2.6 w/o),[38][37][36][35] which is capable of producing an average volumetric power density of 100.9 W/cm^3. Up to 30% of the core can also be loaded with Mixed Oxide fuel with minor modifications. The core is designed for an 18-month operating cycle with a discharge burnup up to 60,000 MWD/MTU, with a thermal margin of 10%.[3] For the control element assemblies, 76 Boron carbide pellets rods are used in the full strength control rods, while 17 Inconel-625 is used in the part strength control rods.

Primary

[edit]

Like the OPR-1000 and preceding C-E designs, the APR-1400 has two reactor coolant loops. In each loop, heated primary coolant leaves the reactor pressure vessel (RPV) through one hot leg, passing through one steam generator (SG), returning to the reactor vessel through two cold legs, each equipped with a reactor coolant pump (RCP).[62] In loop 2, there is one pressurizer (PZR) on the hot leg, where a steam bubble is maintained during operation. The loops are arranged symmetrically, so the hot legs are diametrically opposed on the RPV's circumference. Because the steam generators are elevated relative to the RPV, natural convection will circulate reactor coolant in the event of RCP malfunction. The pressurizer is equipped with a pilot-operated relief valve which not only protects against Reactor Coolant System over-pressure, it also allows manual depressurization in the case of a total loss of feedwater.

Secondary

[edit]

Each steam generator has 13,102 Inconel 690 tubes; this material improves resistance to stress corrosion cracking compared to the Inconel 600 used in prior designs.[3] Like the late-evolution System 80+ design, the steam generator design incorporates an integral feedwater economizer, which pre-heats feedwater before it is introduced into the SG. Compared with the OPR-1000 design, the steam generator features a larger secondary feedwater inventory, extending the dry-out time and affording more time for manual operator intervention, should it be needed. The design tube plugging margin is 10%, meaning the unit can operate at full power with up to 10% of the SG tubes plugged. Each of the two main steam lines from the steam generator contain five safety valves, a main steam relief valve and one isolation valve.

APR+

[edit]

The APR-1400 has been further developed into the APR+ design, which received its official type certification on 14 August 2014 after seven years in development.[63] The reactor design features improved safety and among others "a core damage frequency an entire order of magnitude lower than that calculated for the APR1400 design that it supplants".[64] The APR+ core uses 257 fuel assemblies (16 more than APR-1400) to increase output to 1550 MW gross electricity.[61] Certain safety features, such as backup generators, have been increased from two to four independent, redundant systems.[65] The reactor design is also expected to have a shorter construction time of 36 months vs. 52 months for the APR1400.[63] The Cheonji Nuclear Power Plant is the first planned plant with this design.[66]

See also

[edit]

References

[edit]
  1. ^ Goldberg, Stephen M.; Rosner, Robert (2011). Nuclear Reactors: Generation to Generation (PDF). American Academy of Arts and Sciences. p. 7. ISBN 978-0-87724-090-7. Retrieved 26 August 2014. {{cite book}}: |work= ignored (help)
  2. ^ "US design certification sought for APR1400, 2013. WNN".
  3. ^ a b c d Lee, Sang-Seob; Kim, Sung-Hwan; Suh, Kune-Yull (8 October 2009). "The design features of the Advanced Power Reactor 1400" (PDF). Nuclear Engineering and Technology. 41 (8): 995–1004. doi:10.5516/NET.2009.41.8.995. Archived from the original (PDF) on 9 August 2017. Retrieved 4 March 2015.
  4. ^ Ciocco, Jeffrey A. (4 March 2015). "Korea Hydro and Nuclear Power Co., Ltd., and Korea Electric Power Corporation – Acceptance of the Application for Standard Design Certification of the APR1400" (PDF). Letter to Dr. Ha-Hwang Jung and Dr. Hee-Yong Lee. Retrieved 11 March 2015.
  5. ^ "South Korea's AP1400 clear for European export". World Nuclear News. 9 October 2017. Retrieved 5 January 2018.
  6. ^ "NRC: APR1400 Final Safety Evaluations". www.nrc.gov. Retrieved 14 May 2019.
  7. ^ Brown, Frederick D. (28 September 2018). "Standard Design Approval for the Advanced Power Reactor 1400" (PDF) (Letter). Letter to Mr. Yun-Ho Kim. Retrieved 14 May 2019.
  8. ^ "US NRC set to certify APR-1400 reactor design - World Nuclear News". www.world-nuclear-news.org. Retrieved 14 May 2019.
  9. ^ "NRC: Package ML19120A148 - Direct Final Rule: Advanced Power Reactor 1400 Design Certification". www.nrc.gov. Retrieved 14 May 2019.
  10. ^ "Korea's APR-1400 certified by US NRC". Nuclear Engineering International. 2 September 2019. Retrieved 12 September 2019.
  11. ^ "US stalls South Korea's NPP export plans". Nuclear Engineering International. 11 April 2023. Retrieved 11 April 2023.
  12. ^ "Shin-Kori 3 and 4 approved". World Nuclear News. 13 September 2007. Archived from the original on 2 April 2015. Retrieved 11 March 2015.
  13. ^ "Shin-Kori-3, Korea RO (South)". World Nuclear Association. 2015. Retrieved 11 March 2015.
  14. ^ "Shin-Kori-4, Korea RO (South)". World Nuclear Association. 2015. Retrieved 11 March 2015.
  15. ^ a b World Nuclear News (18 October 2013). "Recabling delays Shin Kori start ups". World Nuclear News. Retrieved 16 August 2014.
  16. ^ "Go-ahead for new reactors at Shin Kori". World Nuclear News. World Nuclear Association. 29 January 2014. Retrieved 19 August 2014.
  17. ^ a b c "First Korean APR-1400 enters commercial operation". World Nuclear News. 20 December 2016. Retrieved 23 December 2016.
  18. ^ "Celebrations at South Korean groundbreaking". World Nuclear News. 8 May 2012. Retrieved 11 March 2015.
  19. ^ a b "Second Shin Hanul unit under construction". World Nuclear News. 26 June 2013. Retrieved 11 March 2015.
  20. ^ "Sites agreed for four more South Korean reactors". World Nuclear News. 21 November 2014. Retrieved 11 March 2015.
  21. ^ a b "Design work suspended for new Shin Hanul units". World Nuclear News. 26 May 2017. Retrieved 22 July 2017.
  22. ^ "Construction of two Korean reactors put on hold". World Nuclear News. 14 July 2017.
  23. ^ "Citizens recommend completion of Korean units". World Nuclear News. 20 October 2017. Retrieved 5 January 2018.
  24. ^ "South Korean president accepts public decision". World Nuclear News. 23 October 2017. Retrieved 5 January 2018.
  25. ^ a b "Second APR-1400 unit starts commercial operation". www.world-nuclear-news.org. Retrieved 3 September 2019.
  26. ^ a b "원자력 - 운영 - 건설현황 - 신한울 1,2호기" [Nuclear Power-Operation-Construction Status-Shinhanul 1,2]. www.khnp.co.kr (in Korean). Retrieved 16 April 2020.
  27. ^ "UAE picks Korea as nuclear partner". World Nuclear News. 29 December 2009. Retrieved 11 March 2015.
  28. ^ "Construction under way at Barakah". World Nuclear News. 19 July 2012. Retrieved 11 March 2015.
  29. ^ "Barakah 2 under way". World Nuclear News. 28 May 2013. Retrieved 11 March 2015.
  30. ^ "Construction starts on third Barakah unit". World Nuclear News. 8 May 2012. Retrieved 11 March 2015.
  31. ^ "Nuclear Power in the United Arab Emirates". World Nuclear Association. April 2014. Archived from the original on 18 January 2016. Retrieved 20 August 2014.
  32. ^ "UAE's fourth power reactor under construction". World Nuclear News. 2 September 2015. Retrieved 2 September 2015.
  33. ^ "Arabische Emirate nehmen erstes AKW in Betrieb", Deutsche Welle. 1 August 2020. Retrieved 2 August 2020.
  34. ^ a b Belgium, Central Office, NucNet a s b l, Brussels (24 March 2021). "Barakah-1 / First Commercial Nuclear Plant In Arab World Begins Commercial Operation". The Independent Global Nuclear News Agency. Retrieved 7 April 2021.{{cite web}}: CS1 maint: multiple names: authors list (link)
  35. ^ a b Alrwashdeh, Mohammad, and Saeed A. Alameri. "Preliminary neutronic analysis of alternative cladding materials for APR-1400 fuel assembly." Nuclear Engineering and Design 384 (2021): 111486.
  36. ^ a b Alrwashdeh, Mohammad, and Saeed A. Alameri. 2022. "Chromium-Coated Zirconium Cladding Neutronics Impact for APR-1400 Reactor Core" Energies 15, no. 21: 8008. https://doi.org/10.3390/en15218008
  37. ^ a b Alaleeli, Maithah M., Saeed A. Alameri, and Mohammad Alrwashdeh. 2022. "Neutronic Analysis of SiC/SiC Sandwich Cladding Design in APR-1400 under Normal Operation Conditions" Energies 15, no. 14: 5204. https://doi.org/10.3390/en15145204
  38. ^ a b Alrwashdeh, Mohammad, and Saeed A. Alameri. 2022. "SiC and FeCrAl as Potential Cladding Materials for APR-1400 Neutronic Analysis" Energies 15, no. 10: 3772. https://doi.org/10.3390/en15103772
  39. ^ Vaughan, Adam (6 December 2017). "Korean energy firm rescues UK's Moorside nuclear power project". The Guardian.
  40. ^ "UK's NuGen cuts staff at planned Moorside". Nuclear Engineering International. 12 September 2018. Retrieved 14 September 2018.
  41. ^ Lee, Heesu (31 October 2022). "Poland Signs Deal With Korea to Build Second Nuclear Plant". Bloomberg.
  42. ^ "Samsung-led consortium awarded Korean construction contract". World Nuclear News. World Nuclear Association. 4 June 2015. Retrieved 26 July 2015.
  43. ^ "Fuel loading under way at Shin Kori 3". World Nuclear News. 4 November 2015. Retrieved 16 December 2015.
  44. ^ "Korea, Republic of". IAEA Power Reactor Information System. 2015. Retrieved 11 March 2015.
  45. ^ "United Arab Emirates". IAEA Power Reactor Information System. 2015. Retrieved 11 March 2015.
  46. ^ a b c "Commissioning of second Korean APR1400 postponed". World Nuclear News. 10 August 2017. Retrieved 12 August 2017.
  47. ^ "South Korean APR-1400 starts up : New Nuclear - World Nuclear News".
  48. ^ "Key commissioning test completed at Korean unit". World Nuclear News. 17 November 2016. Retrieved 22 July 2017.
  49. ^ "Korea eyes bigger defense exports to US and joint bid with US for reactor tenders - Pulse by Maeil Business News Korea".
  50. ^ "Second APR-1400 at Shin Hanul starts up : New Nuclear - World Nuclear News".
  51. ^ a b "South Korea to Expand Nuclear Power Utilization". 6 July 2022.
  52. ^ "Testing milestone for Barakah 1". World Nuclear News. 16 February 2016. Retrieved 5 January 2018.
  53. ^ "Completed Barakah 1 awaits permission to load fuel". World Nuclear News. 5 May 2017. Retrieved 22 July 2017.
  54. ^ a b "Second Barakah unit begins commercial operation". World Nuclear News. 28 March 2015.
  55. ^ "Third unit completed at Barakah : New Nuclear - World Nuclear News".
  56. ^ "In the Year of Sustainability UAE Takes Significant Leap towards Net Zero 2050 as Unit 3 of Barakah Nuclear Energy Plant Starts Commercial Operations".
  57. ^ "Barakah 3 begins commercial operation - Nuclear Engineering International". 28 February 2023.
  58. ^ a b "Major components installed at final Barakah unit". World Nuclear News. 14 August 2017. Retrieved 5 January 2018.
  59. ^ Belgium, Central Office, NucNet a s b l, Brussels (1 March 2024). "Barakah / UAE Hails 'Historic Milestone' As Fourth And Final Reactor Begins Commercial Operation". The Independent Global Nuclear News Agency.{{cite web}}: CS1 maint: multiple names: authors list (link)
  60. ^ "Fourth Barakah unit starts up". World Nuclear News.
  61. ^ a b "Advanced Nuclear Power Reactors". World Nuclear Association. August 2014. Archived from the original on 27 August 2014. Retrieved 29 August 2014.
  62. ^ a b Kim, Han-Gon (28 October 2009). The Design Characteristics of Advanced Power Reactor 1400 (PDF). Korea Hydro & Nuclear Power Co (Report). IAEA. IAEA-CN-164-3S09. Retrieved 13 August 2017.
  63. ^ a b Peachey, Caroline (26 August 2014). "Design approval for Korean APR+ reactor". Nuclear Engineering International. Retrieved 11 March 2015.
  64. ^ Davis, Will (2 September 2014). "APR+ Design Certification Announced". atomic power review. Archived from the original on 2 April 2015. Retrieved 11 March 2015.
  65. ^ "APR+ Reactor". Korea Electric Power Company (KEPCO). 2011. Archived from the original on 29 September 2015. Retrieved 11 March 2015.
  66. ^ "KEPCO E&C - KEPCO Engineering & Construction Company, Inc". www.kepco-enc.com. Retrieved 2 January 2024.
[edit]