Abstract
Major factors of project success include using tools of performance measurements and feedbacks. Earned value management (EVM) is a unique issue within megaprojects due to their inevitable external risks and variations. In order to improve the effectiveness and accuracy of future status estimation of megaprojects, in this paper a novel evaluation model is proposed which takes account of interval type-2 fuzzy sets (IT2FSs) to cope with uncertainty. In the proposed approach, in addition to cost and time criteria, a great deal of attention is paid for other important factors affecting project success, including quality, stakeholder satisfaction, safety and risk, which is computed from different perspectives. Moreover, to make informed decisions and to reduce uncertainty in assessment of megaprojects, key performance indicators (KPIs) are provided. Also, a new extension of multi-criteria decision-making method is introduced to weigh KPIs in future performance equations. Finally, the proposed IT2F-EVM approach is applied to control and estimate the future status of a real case study in a petro-refinery company. The results show that the approach can successfully address highly uncertain environments.
Similar content being viewed by others
Explore related subjects
Discover the latest articles, news and stories from top researchers in related subjects.References
Abdi A, Taghipour S, Khamooshi H (2018) A model to control environmental performance of project execution process based on greenhouse gas emissions using earned value management. Int J Proj Manag 36(3):397–413
Acebes F, Pajares J, Galán JM, López-Paredes A (2014) A new approach for project control under uncertainty. Going back to the basics. Int J Proj Manag 32(3):423–434
Anbari FT (2003) Earned value project management method and extensions. Proj Manag J 34(4):12–23
Babar S, Thaheem MJ, Ayub B (2016) Estimated cost at completion: integrating risk into earned value management. J Constr Eng Manag 143(3):04016104
Bagherpour M, Zareei A, Noori S, Heydari M (2010) Designing a control mechanism using earned value analysis: an application to production environment. Int J Adv Manuf Technol 49(5–8):419–429
Batselier J, Vanhoucke M (2017) Improving project forecast accuracy by integrating earned value management with exponential smoothing and reference class forecasting. Int J Proj Manag 35(1):28–43
Bryde D, Unterhitzenberger C, Joby R (2018) Conditions of success for earned value analysis in projects. Int J Proj Manag 36(3):474–484
Castillo O, Amador-Angulo L, Castro JR, Garcia-Valdez M (2016) A comparative study of type-1 fuzzy logic systems, interval type-2 fuzzy logic systems and generalized type-2 fuzzy logic systems in control problems. Inf Sci 354:257–274
Castillo O, Cervantes L, Soria J, Sanchez M, Castro JR (2016) A generalized type-2 fuzzy granular approach with applications to aerospace. Inf Sci 354:165–177
Celik E, Gumus AT (2015) An assessment approach for non-governmental organizations in humanitarian relief logistics and an application in Turkey. Technol Econ Dev Econ. https://doi.org/10.3846/20294913.2015.1056277
Chang CJ, Yu SW (2018) Three-variance approach for updating earned value management. J Constr Eng Manag 144(6):04018045
Chen SM, Lee LW (2010) Fuzzy multiple attributes group decision-making based on the ranking values and the arithmetic operations of interval type-2 fuzzy sets. Expert Syst Appl 37(1):824–833
Chen SM, Lee LW (2010) Fuzzy multiple attributes group decision-making based on the ranking values and the arithmetic operations of interval type-2 fuzzy sets. Expert Syst Appl 37(1):824–833
Choi YI, Ahn J (2018) Earned value management considering technical readiness level and its application to new space launcher program. Int J Aeronaut Space Sci 19(1):227–237
Coban R (2010) Computational intelligence-based trajectory scheduling for control of nuclear research reactors. Prog Nucl Energy 52(4):415–424
Coban R (2011) A fuzzy controller design for nuclear research reactors using the particle swarm optimization algorithm. Nucl Eng Des 241(5):1899–1908
Coban R, Aksu IO (2018) Neuro-controller design by using the multifeedback layer neural network and the particle swarm optimization. Tehnički vjesnik 25(2):437–444
Coban R, Can B (2009) An expert trajectory design for control of nuclear research reactors. Expert Syst Appl 36(9):11502–11508
Collin J (2002) Measuring the success of building projects–improved project delivery initiatives. Int J 11(2):203–221
Dorfeshan Y, Mousavi SM (2019) A new interval type-2 fuzzy decision method with an extended relative preference relation and entropy to project critical path selection. Int J Fuzzy Syst Appl 8(1):19–47
Dorfeshan Y, Mousavi SM, Vahdani B (2018) A multi-criteria analysis model under an interval type-2 fuzzy environment with an application to production project decision problems. J Qual Eng Prod Optim 3(1):43–66
Dorfeshan Y, Mousavi SM, Mohagheghi V, Vahdani B (2018) Selecting project-critical path by a new interval type-2 fuzzy decision methodology based on MULTIMOORA, MOOSRA and TPOP methods. Comput Ind Eng 120:160–178
Ghorabaee MK, Amiri M, Sadaghiani JS, Zavadskas EK (2015) Multi-criteria project selection using an extended VIKOR method with interval type-2 fuzzy sets. Int J Inf Technol Decis Mak 14(5):993–1016
Gomes LFAM, Lima MMPP (1992) From modeling individual preferences to multicriteria ranking of discrete alternatives: a look at prospect theory and the additive difference model. Found Comput Decis Sci 17(3):171–184
Hashemi ST, Kaur H (2017) A hybrid conceptual cost estimating model using ANN and GA for power plant projects. Neural Comput Appl 28(11):1–12
Henderson K (2004) Further developments in earned schedule. Meas News 1(1):15–22
Hu J, Zhang Y, Chen X, Liu Y (2013) Multi-criteria decision making method based on possibility degree of interval type-2 fuzzy number. Knowl Based Syst 43:21–29
Jacob DS, Kane M (2004) Forecasting schedule completion using earned value metrics revisited. Meas News 1(11):7
Kerzner H (2011) Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. Wiley, New York
Kerzner H (2017) Project management: a systems approach to planning, scheduling, and controlling. Wiley, New York
Kim E, Wells WG Jr, Duffey MR (2003) A model for effective implementation of earned value management methodology. Int J Proj Manag 21(5):375–382
Lester A (2017) Project management, planning and control: managing engineering, construction and manufacturing projects to PMI, APM and BSI standards. Elsevier, Amsterdam
Lipke W (2003) Schedule is different. Meas News 31(4):31–34
Liu HT, Cheng HS (2016) An improved grey quality function deployment approach using the grey TRIZ technique. Comput Ind Eng 92:57–71
Liu S, Lin Y (2006) Grey information: theory and practical applications. Springer, Berlin
Mavrotas G, Caloghirou Y, Koune J (2005) A model on cash flow forecasting and early warning for multi-project programmes: application to the Operational Programme for the Information Society in Greece. Int J Proj Manag 23(2):121–133
Mendel JM (2003) “Type-2 fuzzy sets: some questions and answers”, IEEE connections, newsletter of the IEEE. Neural Netw Soc 1:10–13
Mendel JM, John RI, Liu F (2006) Interval type-2 fuzzy logic systems made simple. IEEE Trans Fuzzy Syst 14(6):808–821
Mohagheghi V, Mousavi SM, Vahdani B (2017) Analyzing project cash flow by a new interval type-2 fuzzy model with an application to construction industry. Neural Comput Appl 28(11):3393–3411
Mohagheghi V, Mousavi SM, Vahdani B, Shahriari MR (2017) R&D project evaluation and project portfolio selection by a new interval type-2 fuzzy optimization approach. Neural Comput Appl 28(12):3869–3888
Mohagheghi V, Mousavi SM, Vahdani B, Siadat A (2017) A mathematical modeling approach for high and new technology-project portfolio selection under uncertain environments. J Intell Fuzzy Syst 32(6):4069–4079
Moradi N, Mousavi SM, Vahdani B (2017) An earned value model with risk analysis for project management under uncertain conditions. J Intell Fuzzy Syst 32(1):97–113
Mortaji STH, Bagherpour M, Noori S (2013) Fuzzy earned value management using LR fuzzy numbers. J Intell Fuzzy Syst 24(2):323–332
Muhwezi L, Acai J, Otim G (2014) An assessment of the factors causing delays on building construction projects in Uganda. Int J Constr Eng Manag 3(1):13–23
Naeni LM, Salehipour A (2011) Evaluating fuzzy earned value indices and estimates by applying alpha cuts. Expert Syst Appl 38(7):8193–8198
Naeni LM, Shadrokh S, Salehipour A (2014) A fuzzy approach for the earned value management. Int J Proj Manag 32(4):709–716
Najafi A, Azimi F (2016) An extension of the earned value management to improve the accuracy of schedule analysis results. Iran J Manag Stud 9(1):63–85
Ong HY, Wang C, Zainon N (2016) Integrated earned value Gantt chart (EV-Gantt) tool for project portfolio planning and monitoring optimization. Eng Manag J 28(1):39–53
Ontiveros-Robles E, Melin P, Castillo O (2018) Comparative analysis of noise robustness of type 2 fuzzy logic controllers. Kybernetika 54(1):175–201
Oztaysi B (2015) A group decision making approach using interval type-2 fuzzy AHP for enterprise information systems project selection. J Mult Valued Logic Soft Comput 24(5):1–15
Picornell M, Pellicer E, Torres-Machí C, Sutrisna M (2016) Implementation of earned value management in unit-price payment contracts. J Manag Eng 33(3):06016001
Ponz-Tienda JL, Pellicer E, Yepes V (2012) Complete fuzzy scheduling and fuzzy earned value management in construction projects. J Zhejiang Univ Sci A 13(1):56–68
Project Management Institute (2013) A guide to the project management body of knowledge (PMBOK Guide), 5h edn. Project Management Institute, Newtown Square
Project Management Institute (2011) Practice standard for earned value management. Project Management Institute, Incorporated
Qin J, Liu X, Pedrycz W (2015) An extended VIKOR method based on prospect theory for multiple attribute decision making under interval type-2 fuzzy environment. Knowl Based Syst 86:116–130
Qin J, Liu X, Pedrycz W (2017) An extended TODIM multi-criteria group decision making method for green supplier selection in interval type-2 fuzzy environment. Eur J Oper Res 258(2):626–638
Radujković M, Sjekavica M (2017) Project management success factors. Proc Eng 196:607–615
Sari IU, Kahraman C (2015) Interval type-2 fuzzy capital budgeting. Int J Fuzzy Syst 17(4):635–646
Sogandi F, Mousavi SM, Amiri A (2018) Self-starting control chart and post signal diagnostics for monitoring project earned value management indices. J Ind Syst Eng 11(2):85–100
Sutrisna M, Pellicer E, Torres-Machi C, Picornell M (2018) Exploring earned value management in the Spanish construction industry as a pathway to competitive advantage. Int J Constr Manag 18(6):1–12
Turner R (2016) Gower handbook of project management. Routledge, New York
Vandevoorde S, Vanhoucke M (2006) A comparison of different project duration forecasting methods using earned value metrics. Int J Proj Manag 24(4):289–302
Vanhoucke M (2009) Measuring time: improving project performance using earned value management, vol 136. Springer, Berlin
Vanhoucke M (2010) Using activity sensitivity and network topology information to monitor project time performance. Omega 38(5):359–370
Vanhoucke M (2016) Integrated project management sourcebook. Springer, Berlin
Zadeh LA (1974) Fuzzy logic and its application to approximate reasoning. In IFIP congress, vol 591
Zareei S (2018) Project scheduling for constructing biogas plant using critical path method. Renew Sustain Energy Rev 81(1):756–759
Zolfaghari S, Mousavi SM (2018) Construction-project risk assessment by a new decision model based on De-Novo multi-approaches analysis and hesitant fuzzy sets under uncertainty. J Intell Fuzzy Syst 35:639–649
Author information
Authors and Affiliations
Corresponding author
Ethics declarations
Conflict of interest
The authors declare that they have no conflict of interest.
Additional information
Publisher's Note
Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.
Rights and permissions
About this article
Cite this article
Eshghi, A., Mousavi, S.M. & Mohagheghi, V. A new interval type-2 fuzzy approach for analyzing and monitoring the performance of megaprojects based on earned value analysis (with a case study). Neural Comput & Applic 31, 5109–5133 (2019). https://doi.org/10.1007/s00521-018-04002-x
Received:
Accepted:
Published:
Issue Date:
DOI: https://doi.org/10.1007/s00521-018-04002-x