INTRODUCTION
What is concrete?
Concrete is a most widely used construction material, Commonly
made by mixing of Cement with Fine Aggregate, Coarse Aggregate, Water
and Admixture.
Air content
Air content measures the total air content in a sample
of fresh concrete but does not indicate what the final
in-place air content is, because a certain amount of air
is lost in transportation Consolidating, placement, and
finishing.
Measurement of Air Content in Concrete by Press
ure Air Method
Setting Time
The action of changing mixed cement from a fluid
state to a solid state is called “Setting of
Cement”. Initial Setting Time is defined as the period
elapsing between the time when water is added to the
cement and the time at which the needle of 1 mm
square section fails to pierce the test block to a depth
of about 5 mm from the bottom of the mold. Final
Setting Time is defined as the period elapsing
between the time when water is added to cement and
the time at which the needle of 1 mm square section
with 5 mm diameter attachment makes an impression
on the test block.
Compressive strength