Review Workflow SOP and Guidelines

for
Contractors

BIM 360 Docs


G3 Spices, Guntur
BIM 360 – WORK-FLOWS – CONTRACTOR/VENDOR

CONTRACTOR/VENDOR will Final review of all markups and


ITC Package Manager will Consultant will review files comments will be verified by ITC
upload files & inform ITC
have a preliminary check and and add markups on the PDF Package Manager.
Package Manager through
initiate review by selecting only. Final reviewer shall accept or reject or
transmittal
specific workflow Comments shall be added in accept with comment documents
the comments dialogue box. considering criticality of comments

1 2 3 4
UPLOAD INITIATE REVIEW FIRST REVIEWER FINAL REVIEWER
(CONTRACTOR/VENDOR) (ITC PACKAGE MANAGER) (CONSULTANT) (ITC PACKAGE MANAGER)

Final Reviewer (ITC) will create a link of files


with mark-ups and send it to
CONTRACTOR/VENDOR shall correct the documents based on comments Contractor/Vendor with information as
received, and reupload with updated revision number. APPROVED or REJECTED.
CONTRACTOR/VENDOR shall not change the naming conventions.

5
REUPLOAD CORRECTED
FILES
(CONTRACTOR/VENDOR)
Review Workflow Steps (Contractor/Vendor):

Step 1 : Contractor/Vendor will Upload the Files in the respective SHARED folders and inform the ITC Package Managers through transmittals.
Step 2 : ITC Package Managers will have preliminary check of the files, if found OK a Review can be initiated by selecting appropriate Approval
Workflow.
Step 3 : Once the Approval Workflow has been initiated, the Initial Reviewer (i.e. Consultant) will get notified about the approval workflow.
Step 4 : Initial Reviewer will open the Review and click START REVIEW. In case multiple documents he will be doing it one at a time. During
the review he can Add Comments and Markups in the files.
Step 5 : Once Initial Reviewer is done with the reviewing part he can click the SUBMIT REVIEW so that final reviewer will get notified. A box
will appear where Initial Reviewer can Add NOTES about the APPROVAL AND REJECTION of Specific files. He can also Add any other Project
Member’s name if he wish to notify them as well. (Note : At this stage documents has not been formally Accepted or Rejected, it is to
intimate the final reviewer about the document).
Step 6 : ITC Project Manager will get notified about the Final Review (since he is the Final Reviewer). He will open the Review and Click Start
Review.
Step 7 : He will review the comments and markups provided by Initial Reviewer and will provide his Comments and Markups, Save it and
Ultimately APPROVE, REJECT and APPROVE WITH COMMENTS. And Click END REVIEW. (Note : This is the stage where documents are
formally Approved, Rejected, Approved with comments).
Step 8 : Now ITC Manager will click the Reviews tab and go to that specific review, open the files which were reviewed and click the 3 dots on
the top right corner. And from there he will share the link to the Contractor/Vendor and mention which documents has been APPROVED or
REJECTED or APPROVED WITH COMMENTS (In case of Multiple documents).
Step 9 : The Contractor/Vendor will receive a mail with the link. Link will divert him to the reviewed documents with all the Comments and
Markups in it. He has to incorporate all the changes for the Rejected document and Reupload the document in the respective folder.
Guide/Reference for Contractor/Vendor

4
Guide/Reference for Contractor (Uploading Files)
• You have to upload the files in the respective SHARED folder. And Under Shared you to respective Stage of the project
(Here we have shown Construction stage as an example).
• Here we have shown for the FPS Contractor. All the other Contractors has to go to their respective folders and sub folders
to upload the files.

Contractors Folder

Shared Folder

Construction Stage
Guide/Reference for Contractor (Creating Transmittals)
• You Select the files that you uploaded. Go to the 3 dots and select Create Transmittals.

Click the 3 dots

Select the Files you Go to Create Transmittals


uploaded
Guide/Reference for Contractor (To Open Reviewed file)
• This is the mail which will be triggered to you. You click the link and will get diverted to files which were reviewed.

Click the Link


Attached
You can see the file
which was reviewed
Guide/Reference for Contractor (To Open Reviewed file)
• This screen will appear here you will see the numbers of files reviewed, number of Comments and Markups and Approval
Status.
• You click and Open the file.

Numbers of Number of
File Name Approval Status
Markups Comments
Guide/Reference for Contractor (To Open Reviewed file)
• Here you will see all the Markups and Comments.
• Incorporate the Changes (if any) as suggested by the Reviewer. And Reupload in the respective Folders.