Nothing Special   »   [go: up one dir, main page]

Lecture1 Buildability Ed

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 49

5CN001

Brownfield Regeneration and


Technology
Lecture 1a: Buildability

Dr Emmanuel Daniel
E.daniel2@wlv.ac.uk
Aim and Purpose
Aim:
Understand the application of buildability principles and approach in high
rise construction projects

Learning Outcomes
You will be able to:


Describe and discuss key areas and principles involved in buildability

analysis and evaluation


Identify areas to look at for buildability on construction projects


Discuss the application of buildability principles on construction projects
Why Buildability?

 Lack of integration between design & construction

 Lack of collaboration/communication between designers


and constructors

 Construction is not viewed as production

 Functional view in construction project management

 Late or non involvement of key stakeholders in the design


process
Implication of Traditional Design
and Construction Practice
 Error and rework
 Lost or missed opportunity for innovation
 Cost and time overrun; over 50% of
construction projects in the UK suffer time
and cost overrun.
 Conflicts leading to litigations
Traditional Design and
Construction Practice

Design Construction
What is
Buildability?
Buildability in Design and
Construction Practice

Buildability

Design Construction

Design and construction is viewed as an integrated process


What is Buildability?

Buildability ‘is the extent to which


the design of a building facilitates
ease of construction, subject to the
overall requirements for the
completed building‘ (CIRIA, 1983;
Griffith, 1987)

CII defines constructability as “the


optimal use of construction
knowledge and experience in
planning, design, procurement, and
field operations to achieve overall
project objectives.” (CII, 2019)
What is Buildability?

Buildability is ‘the optimum integration of construction


knowledge and experience in planning, engineering,
procurement, and field operations to achieve overall project
objectives"

Construction Industry Institute (CII)


Research work on Buildability

Most of the initial research work on buildability was


undertaken in the UK and in the USA by:

 The Construction Industry Research Information


Association (CIRIA) based in the UK

 The Construction Industry Institute (CII) based in


the USA

 Please note: buildability is know as


constructability in the USA
Research work on Buildability

The CIRIA identified 16 guideline principles for good


buildability practice:
1. Investigate thoroughly
2. Consider accessibility at the design stage
3. Consider storage at design stage
4. Design for early enclosure
5. Design for minimum time below ground work
6. Suitable materials use
7. Consider the local skill available
8. Design for simple assembly
Research work on Buildability

The CIRIA identified 16 guideline principles for good


buildability practice:
9. Plan for maximize repetition and standardization
10. Maximize the use of plant
11. Allow for sensible tolerances
12. Allow for a practical sequence of operations
13. Plan to avoid change to work
14. Avoid return visits on site; do it right first time
15. Safe construction design
16. Clear communication
Research work on Buildability

The CII also identified 12 guideline principles for good


constructibility practice (CII, 2019):

1. Integration of constructibility into project plan


2. Construction knowledge and experience by the team.
3. Project team must have the required skills
4. Project team must understand client's corporate objectives.
5. Technology use in design solution must be matched with the
skills and resources available.
6. Give attention to external factors that might effect cost and
programme
Research work on Buildability

7. Overall project program must be realistic and have the

commitment of the project team (Involve those who will do the


work in the planning)
8. Construction Methodology should be considered at design
stage
9. Accessibility should be considered in good time
10. Efficiency consideration in specifications development
11. Create room for construction innovation
12. Provide feedback as it is key to learning and improvement
What is the function
of Buildability?
Functions of Buildability

Removal of any uncertainties in the


construction process from the design
stage
Confirming budget for design and
construction

Improved utilization of resources

Optimisation of construction method

Improved safety and better productivity

Enabling improved decision is made at


the design stage

Time and cost benefits

Improved quality in the finished


product
"Good buildability leads to major cost benefits for clients,
designers and builders.
Key Areas of Buildability

• Construction-driven planning and programming


1

• Design simplification
2

• Standardisation and repetition of design element


3

• Specification development for construction efficiency


4
• Mock up or Prototyping of the process or product (First Run
5 Studies)

• Design should allow access for material, labour and plant


6

• Design should allow for construction under harsh weather


7
Buildability Issues

Who is at fault here; the designer or the


constructor?
Buildability Issues

Door below the finish floor level


Buildability Issues

What are the problems with this WC?


Buildability Issues

What went wrong here?


Buildability Issues

What went wrong here?


Buildability Issues

How did we get here?


Buildability Issues

What is wrong with this design?


Buildability Issues

How could we prevent all of these scenarios seen in the


previous slides from happening?

What is wrong with this design?


Towards Improved Buildability

Standardisation
& repetition

Clear Prefabrication
specification

Early
Improved involvement of
Site
investigation &
Buildability contractors
access

Clear
communication
Use of BIM for
buildability
reviews
Key Areas of Buildability

Three principal criteria for good buildability


1- Simplicity 2- Standardisation

3- Clear communication

This process is now enhanced with the emergence of BIM


Buildability Review with BIM

Conflict between architectural and structural drawing


Buildability Review with BIM

Conflict between architectural and structural drawing


Buildability Review with BIM

Water pipe going through an opening instead of wall


Standardized steel formwork Toilet pod produced offsite
What to Evaluate in Buildability
Analysis
1 Dimension and tolerances
What to Evaluate in Buildability
Analysis
2 Practicality of detailing
What to Evaluate in Buildability
Analysis
3 Project program
What to Evaluate in Buildability
Analysis
Project program continued

 Is the programme collaborative?

 Who are those involved in the programme?

 Are key stakeholders such as the subcontractors


involved in developing the program- Last
Planners?

 How was the activity duration arrived at?


What to Evaluate in Buildability
Analysis
4 Selection of procurement system
 How would the supply chain and subcontractors
be selected?

 What procurement option to use (D&B, MC, CM)

 Does the procurement option support early


integration of the supply chains?

 Engagement of specialist contractors and


suppliers; when & how?
What to Evaluate in Buildability
Analysis
5 Arrangement of site facilities

Discuss how the arrangement of facilities on site could lead


to buildability issues?
What to Evaluate in Buildability
Analysis
7 Standardisation

• Allow modular layout of


components

• Allow for high degree of


standardisation and repetition

• Use of typical floors


What to Evaluate in Buildability
Analysis
8 Use of Resources

• Use of plant and equipment


locally.

• Avoid double handling of


materials.

• Economic use of labour and


plant.
What to Evaluate in Buildability
Analysis
9 Prefabrication • Allow prefabrication offsite

• Optimising the mix of offsite


work

Modular bathroom pods


What to Evaluate in Buildability
Analysis
9 Prefabrication

Pre-cast facade Pre-cast concrete element


Source: Hong Kong Housing Association
What to Evaluate in Buildability
Analysis

Others areas to evaluate include:

10 Construction methods

11 Allocation of project cost and time

12 Site constraints

13 Safety and sustainability


Project Buildability evaluation

Project life cycle and buildability evaluation


(Source: Hassan, 1997)
Project Buildability evaluation

The project buildability improvement life cycle


Tutorials

Discuss the areas you would apply buildability


principles on the Boundary Street and Portland
Street project.
Recap

We have:
Described and discussed key areas and principles
involved in buildability analysis and evaluation

Identified areas to look at for buildability in construction


project.

Discussed the application of buildability principles in


construction project
References and Further Reading

• CIRIA, (1983), Construction Industry Research and Information


Association Buildability: An Assessment. CIRIA, London

• CII, (2019), Constructability Implementation (Best Practice). CII


Report [Online]. Available at:
https://www.construction-institute.org/resources/knowledgebase/know
ledge-areas/design-planning-optimization/topics/rt-034
. [Accessed: 27 August 2019]

• Hassan, (1997), Conplan: construction planning and buildability


evaluation in an integrated and intelligent construction environment.
PhD Thesis, University of Salford, United Kingdom.

• Griffith, A (1987), An Investigation into Factors Influencing Buildability


and Levels of Productivity for Application to Selecting Alternative
Design Solution. A Preliminary Report, The Chartered Institute of
Building, London
Any muddy points?

You might also like