Operational Experience in Managing Contingencies: Western Regional Load Despatch Center (WRLDC), India
Operational Experience in Managing Contingencies: Western Regional Load Despatch Center (WRLDC), India
Operational Experience in Managing Contingencies: Western Regional Load Despatch Center (WRLDC), India
Managing Contingencies
2
Indian Power Control Centers
NLDC - 1
Total installed capacity 147 GW RLDC - 5
(Source: CEA report
http://www.cea.nic.in/power_sec_reports/Executiv SLDC - 31
e_Summary/index_Executive_Summary.html)
ALDC - 100+
3
Hierarchy of Control Centers
The Unified Load Despatch and Communication
(ULDC) scheme sets up the hierarchy of control
centers in India
1
5
31
>
100
4
Inter-regional Transfer
Capacity present - 22800MW
37,000 MW by 2012
NORTHERN
REGION
4,900 MW 11,700 MW
NORTH-
EASTERN
REGION
5,850 MW
WESTERN 2,650 MW
REGION EASTERN
REGION
1,200 MW
3,700 MW
SOUTHERN
REGION
OVERALL POWER SCENARIO OF WESTERN REGION
Madhya
Pradesh
Energy Shortage 14 %
GOA
WESTERN REGION-31.3.09
Look-up Tables
Remedial Action module is not available
Alternative is to use Look up tables
Look up tables provide following information
What are the expected contingencies?
What is the system behavior for each contingency?
Corrective actions to be taken
What actions ?
Which order ? (Ranking Criteria ?)
Which agency ?
Look up tables are prepared after extensive offline
studies on the system using PSS/E
8
Co-ordination for Contingency
Management: Via Look-up Tables
Multiple agencies are involved in system operation
Common real-time system model is needed for all
Studies carried out by WR for all major contingencies
Internal threats (Trippings inside WR)
External threats (Trippings outside WR)
The study cases and results are made available for all
agencies for verification
Workshops conducted to disseminate look up tables
Corrective actions are agreed upon by all agencies
Permissible load angles for extremes of corridors
determined through stability studies
9
Objective:
To make Look-up Tables (Example below)
Corrective Agency
Contin- System
Rank Action required to take
gency Behaviour
to be taken action
400kV Itarsi- Voltage decay Export to NR via HVDC
1
•
WRLDC
Indore ckt. I (collapse at Vindhyachal to be done
& II Indore)
MP to reduce drawl at
2 Indore/Nagda
MPSEB
• Critical L/L on
Itarsi-Khandwa 3 GEB to reduce drawal GEB
corridor
SSP/ISP generation if MPSEB,
4 possible could be GEB, and
brought immediately WRLDC
10
Presentation Outline
11
Interfaces Between EMS Weather Rainfall
Subsystems
Generator, Tieline,
Frequency Measurements
Actual Load
SCADA GDC SDF/ WIF
Generator Controls
Historical
IS PNA
Subsystem Interchange
Schedules
Interchange
Transactions
Generator Schedules,
Load Schedule
3
12
EMS (the journey so far…..)
13
EMS (the journey so far…..)
14
Salient Features of EMS in WR
15
Model Verification and SE tuning
16
SE working status
SE working satisfactorily
Tele-metered and estimated data with in permissible
limits
Real-time network analysis (RTNA) study run at least
twice a day
Day-off peak @ 1200 hrs
Evening peak @ 1900 hrs
Converged RTNA made available for studies
RTNA also run in case of
Contingency
Outage clearance
Corrective measures taken for security enhancement
17
Advantages of EMS in grid operation
Outages can be planned better
The Contingency Analysis (CA) module of EMS helps in
better emergency handling online. It would facilitate quicker
restoration.
The State Estimator (SE) output, properly tuned, gives
proper estimate of the grid measurands which can be used
during non-availability of communication channels and grid
operation is not affected.
The SCADA system also improves due to continuous
availability, comparison and improvement in EMS output
thereby improving the decision making process in real-time.
18
Presentation Outline
19
Contingency Analysis (CA)
20
Contingency Analysis (CA)
• The CA can be run based on the following modes
21
Contingency Analysis Execution Modes
22
Execution Status of Contingency Case
23
Composite Severity Index (SI) indicator
Ranking of contingencies based on SI
SI = Weighted Sum of percentage limit excursions
Voltage CA Branch CA
Voltage Violations Branch Violations
Contingencies Contingencies
compared based compared based on
on voltage branch loading
degradation profile violations
Corresponding Corresponding
ranks displayed ranks displayed
24
Presentation Outline
25
Contingency Evaluation
26
Presentation Outline
27 WRLDC, Mumbai
Case Study:
Contingency Management in WR Grid
• Due to Concentration of generation in the Eastern
part of the grid and major load centers in the
Western part of the grid, there is bulk active
power transmission from Eastern to Western part
over long distances primarily through three critical
flow gates viz;
28 WRLDC, Mumbai
Base Case Scenario
• On 25.05.2008, Western Regional grid was running in an
integrated manner and catering a demand of about 25000
MW at 1130 hours.
• The import was around 1200 MW from ER, 1400 MW from
NR, 750 MW was exported to SR
• Due to rains in NR and ER, the frequency profile was on the
higher side in the NEW grid
• Therefore economy exchanges were transacted with SR
(Power wheeled through WR) and consumed by WR due to
low UI rates
29
Flow Gates Loaded Close to Limits
31
Following contingencies were chosen for
security assessment
400kV C’pur-Parli S/C outage
400kV C’pur-Parli D/C outage
400kV C’pur-Parli T/C outage
400kV Koradi-Bhusawal S/C outage
400kV Koradi-Bhusawal D/C outage
400kV Itarsi-Khandwa S/C outage
400kV Itarsi-Khandwa D/C outage
32
33
34
Contingency Analysis Results
• The contingencies of Chandrapur-Parli D/C,
Chandrapur-Parli T/C and Koradi-Bhusawal D/C
outage are extreme and the programme did not
converge because the grid may not be able to
sustain these contingencies under the same
power system conditions.
• As these contingencies are fatal, the composite
severity index by voltage / branch / composite
does not show any value. However, they are
ranked at first in the order of severity of
contingencies.
35
Contingency Analysis Results
• The contingency of Itarsi-Khandwa D/C outage
has been found to be harmful by CA which entails
system operators to take emergency measures for
restoring back the normalcy.
• The composite severity index order by voltage
comes to be 4150.8 whereas the composite
severity index order by branch comes to
447526.5 which is ranked as the most severe
contingency after the first three most severe
contingencies as explained in the above
paragraph.
36
Contingency Analysis Results
Similarly, other contingencies like Koradi-Bhusawal
S/C outage, Chandrapur-Parli S/C outage and Itarsi-
Khandwa S/C outage have been found harmful by CA
which prompts operators to take emergency action.
They are also ranked subsequently based on
composite severity index order by voltage and by
branch violations
37
Look-up Table for Koradi-Bhusawal SC Outage
Agency
Contin- System Corrective Action to
Rank
gency Behaviour required to be taken take
action
400kV • Critical line 1 Open Bhusawal-Aurangabad MSEB
Koradi- loading on
Bhusawal- ckt.II Increase Koyna generation
2 atleast by 500 MW
MSEB
SC • Large
angular Maximise power flow on
separation C’pur-Padghe HVDC bipole
between 3 may be upto 1900 MW MSEB
Koradi & (maximum overloading
Bhusawal capacity)
• Low voltage
4 Increase export to SR WRLDC
at Bhusawal
Koradi/Chandrapur
5 generation to be reduced
MSEB
Agency
Contin- System Corrective Action to
Rank
gency Behaviour required to be taken take
action
400kV • Critical Maximise power flow on C’pur-
Chandrapur Loading on 1 Padghe HVDC bipole
MSEB
– Parli SC surviving ckts
2 Export to SR to the max. extent WRLDC
• Critical
Loading on Koyna gen. to be picked up
Koradi- 3 immediately and increased to MSEB
Bhusawal the max.level above 1000 MW
corridor
4 MSEB drawal to be reduced MSEB
• Large angular
MSEB to take up load shedding
separation 5 at Parli, Lonikhand, karad etc.
MSEB
between
Chandrapur C’pur generation to be reduced
and Parli lines 6 if frequency is more than 49 Hz
MSEB
39
Conclusion
• It is evident from the above case study that
CA module of PNA extends valuable inputs to the
system operators in evaluating the credible
contingencies so that preventive action can be
planned well in advance to ensure the security of
the grid.
40
41