Electrical & Automation Works For Raw Material Handling System at Tata Steel Limited - Kalinganagar Project
Electrical & Automation Works For Raw Material Handling System at Tata Steel Limited - Kalinganagar Project
Electrical & Automation Works For Raw Material Handling System at Tata Steel Limited - Kalinganagar Project
Contract Details
LOA Ref: KPO/RMHS/Elec & Auto/LOA/129 dated 30th Dec’12
1. ECR Buildings
2. Conv. Galleries & Junction House etc.
3. 6.6kV Switchboards (Power Distribution System).
4. Field Mounted Electrics for Conveying System.
5. Electrics for Yard machines.
6. All Yard Lighting and Road Lighting.
7. ACVS , Fire Fighting & FDA System.
8. CCTV, PA, Communication System.
9. Utility Systems.
L&T Construction
Power Transmission & Distribution
Sl
Major Process Units Target Completion
No.
RMHS Schedule
Coal Handling
&
Coal Preparation System
L&T Construction
Power Transmission & Distribution
Scope of Work
Sl No. Scope UOM Coal Handling & Coal Preparation System
1 Conveyor Nos. 28
2 Length of Conveyor Km 8.03
5 HV MCC Nos. 3
6 Transformer Nos. 10
(2 X 2.5 MVA, 8 X 2 MVA)
7 LT Board Set 16
8 Automation
IO Count Nos. 5316
PLC System Set 2
L&T Construction
Power Transmission & Distribution
Schedule of Completion
Month-1 Month-2 Month-3 Month-4 Month-5 Month-6 Month-7 Month-8 Month-9 Month-10 Month-11
Sl No. Months-----------> Responsibility
Jan'13 Feb'13 Mar'13 Apr'13 May'13 Jun'13 Jul'13 Aug'13 Sep'13 Oct'13 Nov'13
Scope of Work
Base mix Preparation Coke Handling
Sl No. Scope UOM Total
system system
1 Conveyor Nos. 20 26 46
2 Length of Conveyor Km 3.04 5.96 9.00
5 HV MCC Nos. 3 1 4
7 LT Board Set 9 6 15
8 Automation
IO Count Nos. 3636 2716 6352
PLC System Set 1 1 2
L&T Construction
Power Transmission & Distribution
Schedule of Completion
Month-1 Month-2 Month-3 Month-4 Month-5 Month-6 Month-7 Month-8 Month-9 Month-10 Month-11 Month-12 Month-13
Sl No. Months-----------> Responsibility
Jan'13 Feb'13 Mar'13 Apr'13 May'13 Jun'13 Jul'13 Aug'13 Sep'13 Oct'13 Nov'13 Dec'13 Jan'14
Note: Purchase Order for Transformer, HV MCC & LT Boards shall be placed at same time, however active delivery
period shall start after time lag as shown in color.
L&T Construction
Power Transmission & Distribution
Scope of Work
Ore & Flux Lime Handling Sinter Handling
Sl No. Scope UOM Total
Handling System system system
1 Conveyor Nos. 24 7 15 46
2 Length of Conveyor Km 6.10 1.82 2.49 10.42
4 1 1
4 Substation Building Nos. (RM2, RM3, RM4 & (RM8) (RM11) 6
WT MCC-3 Room)
5 HV MCC Nos. 2 2
8 3 2
6 Transformer Nos. (4 X 2.5 MVA, (3 X 2 MVA) (2 X 2 MVA) 13
4 X 2 MVA)
7 LT Board Set 14 6 4 24
8 Automation
IO Count Nos. 3788 2524 2232 8544
PLC System Set 1 1 1 3
L&T Construction
Power Transmission & Distribution
Schedule of Completion
Month-1 Month-2 Month-3 Month-4 Month-5 Month-6 Month-7 Month-8 Month-9 Month-10 Month-11 Month-12 Month-13 Month-14
Sl No. Months-----------> Responsibility
Jan'13 Feb'13 Mar'13 Apr'13 May'13 Jun'13 Jul'13 Aug'13 Sep'13 Oct'13 Nov'13 Dec'13 Jan'14 Feb'14
Note: Purchase Order for Transformer, HV MCC & LT Boards shall be placed at same time, however active delivery
period shall start after time lag as shown in color.
L&T Construction
Power Transmission & Distribution
Organogram
Mr. V.Thulasiram
Segment Head(Process)- Chennai
Mr. D.Chatterjee
Head- Contracts
Engineering Team
At Chennai
Mr. Debashis Roy
Cluster Operation Head- Kolkata
ENGINNER
(CIRCUIT WISE)
L&T Construction
Power Transmission & Distribution
Mobilization Plan
Manpower Deployment Schedule
Total Manday Requirement = 2.26 Lakhs
% Manpower
Month Manday Deployment w.r.t
Peak Strength
1 0 0%
2 1300 6%
3 9204 39%
4 14742 63%
5 21684 93%
6 21970 94%
7 22984 98%
8 23348 100%
9 23348 100%
10 22984 98%
11 23062 99%
12 18148 78%
13 14326 61%
14 9750 42%
Total---> 226850
L&T Construction
Power Transmission & Distribution
Mobilization Plan
Staff Deployment Schedule
35 35
35
30 30 30
30 28
25
25 No of Staff
20
20
15
15
10
10 7
5
5 3
0
0
L&T Construction
Power Transmission & Distribution
3. Obtaining of Order.
L&T Construction
Power Transmission & Distribution