Advanced Technology of Tunneling in Hard Rock Mining
Advanced Technology of Tunneling in Hard Rock Mining
Advanced Technology of Tunneling in Hard Rock Mining
TECHNOLOGY OF TUNNELING IN
HARD ROCK MINING AND A CASE STUDY.
INTRODUCTION
Atunnelis an underground or underwater passageway, dug through the surrounding
soil/earth/rock and enclosed except for entrance and exit, commonly at each end.
A tunnel may be for foot or vehicular roadtraffic, forrail traffic, or for acanal.
The Delaware Aqueduct in New York, USA is the longest tunnel of any type in the
world at 137 km (85 mi).
Factors for all types of tunnel progressing:
Excavate
Dispose of the muck
Line the excavated ground.
Mine tunnels:
TYPES OF TUNNELS
engineering projects
PIPE JACKING
Pipe jacking is a technique of installing pipes underground using small diameter
TBMs.
Usually termed as micro tunnelling, this method is best deployed in cohesive soils.
This method can now be employed either in cohesive or non cohesive soils, in dry
or watery conditions, to jacking through very hard rock and ground conditions
comprised of mixed composites, such as cobbles and big boulders.
ROAD HEADERS
:
A longitudinal roadheader by Mitsui Miike Machinery Co., Ltd.
HTTPS://MININGANDBLASTING.FILES.WORDPRESS.COM/2009/09/ROCK-EXCAVATION-HANDBOOK-TUNNELING.PDF
Cut and cover tunneling is well proven technique for shallow tunnels.
Top-down Method
In the cut-and-cover top-downor diaphragm wall method, the opposite process takes place in
constructing the tunnel.
Atrencheror trench cutter is typically used to dig a trench out of the the ground first before concrete
walls are built.
This processes consists of using a slurry mixture to build aslurry wall.
The slurry wall provides temporary support to the sides of the trench before concrete is poured for a
permanent wall structure.
Once the concrete walls of the tunnel are completed, the roof of the tunnel is constructed and the
surface roadway restored.
Excavationof the tunnel is then carried out through openings in the tunnel roof top-down to the
tunnel floor.
The tunnel floor slab is the last part of construction to be completed.
Rock Properties
Comments
Primarily for laying pipelines;
small cross-section and limited
capability in hard rocks show
little scope of its use in
underground mining
Pipe Jacking
5 20
Hammer Tunneling
2 10
Up to 30 m
Roadheaders
5 15
Up to 45 m
TBMs
15 - 50
Up to 160 m
3.5 m - 5 m & 7 - 15 m
(without rock support
installation)
HTTPS://MININGANDBLASTING.FILES.WORDPRESS.COM
RANGE OF METHODS COMPARED TO UNIAXAL COMPRESSIVE STRENGTH AND TUNNELING
METHODS IN DIFFERENT ROCK/SOIL CONDITIONS
TBM
From the above considerations and facts, TBMs are the most suitable technical
considerations for the constructions of tunnels in mining projects.
The greatest use of TBMs for mining has been for mine access at the Stillwater
Mine in USA, where a third campaign of TBM excavation is currently underway.
In the early 1990, a TBM was used for the development of more than 12 km of
tunnels at the San Manuel Mine in Arizona. A 4.6 diameter open main beam type of
TBM was used.
Project
Location
Yeara
Length, km
Size, m
Canada
1957
0.30
2.74
Nchanga
Zambia
1970
3.2
3.65
USA
1977
0.20
7.4
South Africa
1977
0.30
1.84
Oak Grove
Blyvoor
Fosdalen
Norway
1977
670
3.15
Blumenthal
Germany
1979
10.6
6.5
Westfalen
Germany
1979
12.7
6.1
Canada
1984
3.6
7.6
Autlan
Mexico
1985
1.8
3.6
Kiena
Canada
1986
1.4
2.3
Stillwater EB
USA
1988-91
6.4
Fraser (CUB)
Canada
1989
1.5
2.1
Rio Blanco
Chile
1992
11.0
5.7
San Manuel
USA
1993
10.5
4.6
Cigar Lake
Canada
1997
> 20
4.5
Port Hedland
Australia
1998
1.3
5.0
Stillwater EB
USA
1998-01
11.2
4.6
Mineral Creek
USA
2001
4.0
6.0
South Africa
2001
0.35
2.4
Italy
2003
8.5
4.9
Donkin Morien
Amplats
Monte Giglio
Tashan Coal
China
2007
4.9
Ok Tedi
PNG
2008
4.8
5.6
Los Bronces
Chile
2009
8.0
4.2
Stillwater Blitz
USA
2012-13
6.8
5.5
Grosvenor Coal
Australia
2013
1.0
8.0
Oz Minerals
Australia
2013
11.0
Northparkes
Australia
2013
2.0
5.0
Chile
2014
6.0
10.0
El Teniente
a
HTTPS://MININGANDBLASTING.FILES.WORDPRESS.COM
5.8
Geological conditions:
TBMs are most appropriate applied in homogeneous rock conditions that are conductive for
excavation, including very strong rock varying from 150 MPa to 250 MPa.
Extremely strong, massive(widely jointed) and abrasive rock will impact TBM progress; however,
larger(19 in. Or 483mm) cutters in conjunction with high power capacity can result in attractive
TBM progress rates.
Depth of cover/potential overstressing:
Evaluation of the potential for overstressing requires knowledge of the uniaxial compressive
strength (UCS) and in situ stresses.
TBMs are not much appropriate for long, deep tunnels, where the lengths may be subjected to
low rock strengths. Here drill and blast tunnels works with high capacity tunnel support.
Site access and terrain:
Appropriate site access and terrain with low gradient rocks must be considered for mobilization of
TBM equipment.
The weight of large size TBMs(>8-10 m) can exceed 130 te, so special lowboy vehicles are
typically required to bring TBMs.
While many mine sites are well established with haul roads, declines, shafts TBMs can be
accessed to the mine through this paths.
http://inside.mines.edu/
Contractor experience:
it includes key skilled labour positions, such as TBM
operators, mechanics and electrician, who are
professionally trained in handling and operating TBMs.
Concrete linings for TBM tunnel:
In some cases it may be cost effective to design tunnel
lining with concrete in order to minimize maintenance
requirements over the life of a mine.
Precast concrete segmental linings are commonly used
for the major urban metro and water/waste wear
projects /, as well as for hydropower tunnels in mixed
bedrock conditions.
HTTPS://MININGANDBLASTING.FILES.WORDPRESS.COM
LATEST MODEL OF
TBM
Herrenknecht tunneling boring machines Canigou and Alberas are compact
powerhouse:equipped with an installed power of 1250kW, they have a torque of
2000 kNm with a cutterhead diameter of 4.3 meters. The tunnel boring machines
have a lenghth of 301 and 253 meters respectively and weighs 620 tonnes. The
double shield TBMs started at their launch portals in March and October 2012 to
excavate and line 8.2 km long tunnel through the hard rock of the Catalan Pyreness.
"Canigou" (M-1619M) - one of the two Herrenknecht Double Shield TBMs ( 4,256mm) for the excavation of the INELFE Tunnel project.
The back-up systems of the two Double Shield TBMs are designed for high tunnelling performances, allowing the storage of the segments and other material for two
ring building
sequences.
CASE
STUDY
San Manuel Mine Tunnel
Robbins TBM extends the life of a large underground mine
Machine Type
Diameter
Tunnel Type
Mining
Tunnel Length
Owner
Contractor
Location
The project owner, Magma Copper Company, awarded the construction contract to a joint
venture of Frontier-Kemper Constructors Inc. and Deilmann-Haniel GmbH. The joint venture
chose a 4.6 m (15.1 ft) Main Beam Robbins TBM to bore the mining tunnel.
Geology
The Lower Kalamazoo geology is quite complex, consisting of orebodies, porphyry, and
granodiorite. The tunnel route includes numerous faults and dikes it passed through the
San Manuel fault six times and the Virgin Fault five times. Much of the rock had been
weakened by hydrothermal metamorphosis.
TBM
Robbins designed the new hard rock Main Beam TBM specifically for the geological
conditions. The 4.6 m (15.1 ft) diameter cutterhead could reverse rotational direction to
prevent jamming when it encountered fractured rock. The machine also featured thirty-three
17 inch (432 mm) backloading disc cutters for greater safety.
Boring began on November 11, 1993 in a specially prepared concrete chamber. There were
no major problems crossing the San Manuel Fault, but wet clay at the Virgin Fault resulted in
slow boring. The TBM continued to encounter soft clay and crumbling ground.
Robbins and the contractors added several features to the machine to optimize performance.
They increased muck flow through the cutterhead, increased cutterhead torque, and added
additional rock support to the tunnel. After the initial modifications, TBM performance greatly
improved. Daily advances tripled to 22.94 m (75.3 ft) per day for the first 15 months of
boring and the machine averaged more than 30 m (98.5 ft) per day for the rest of the project.
The TBM stayed on schedule and holed through on December 4, 1995.
CONCLUSION
Tunneling is one of the most hazardous projects in engineering and construction. It is
also one of the most expensive. For this reason, extensive planning and surveying
goes into the pre-excavation stage of the project.
The applicability of TBMs for mining projects offer benefits where timing of essence
in order to advance mining development and achieve early startup operations. TBMs
are not much suitable in some cases of weak rock strata and long tunnel projects as
compared to drill and blast system. So TBMs should be modified for some of the
issues such as the multiple speed cutterheads to provide more torque at lower speed
for operating highly fractured ground.
1.
REFERENCE
S
https://en.wikipedia.org/wiki/Tunnel
2. https://en.wikipedia.org/wiki/Drilling_and_blasting
3. http://science.howstuffworks.com/engineering/structural/tunnel1.htm
4. http://www.magmineserv.com/cave.html
5. http://jme.shahroodut.ac.ir/pdf_4_72b0cc9fcdcecffc8e4b8fff3c75aa59.html
6. http://www.umich.edu/~gs265/tunnel.html
7. www.slideshare.net
8. www.nodig-construction.com
THANK YOU