Steve Sawch Assistant Director For Construction Management NSLS-II Conventional Facilities Advisory Committee Review November 9 & 10, 2009
Steve Sawch Assistant Director For Construction Management NSLS-II Conventional Facilities Advisory Committee Review November 9 & 10, 2009
Steve Sawch Assistant Director For Construction Management NSLS-II Conventional Facilities Advisory Committee Review November 9 & 10, 2009
Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities Advisory Committee Review November 9 & 10, 2009 BROOKHAVEN SCIENCE ASSOCIATES 1
CM Status Outline
Construction Safety Status Of CM Activities Project Staffing Commissioning External CM Services Issues and Challenges Path Forward Conclusions
2
BROOKHAVEN SCIENCE ASSOCIATES
Construction Safety
Maintain Best in Class Safety Program Objective Early Incidents a Concern Torcon Needs to Reinforce Safety Effort CF-CM Working Closely with ESH Regular Meetings to Continue Improvements
Daily Morning Safety Meetings w/ Torcon
Will implement corrective actions as needed pending accident investigation report findings Our success measured by our Safety Performance
3
BROOKHAVEN SCIENCE ASSOCIATES
Construction Management
CM Team Inspecting and Managing Construction Activities Managing Geo-Tech Engineers and Testing Agencies Ongoing Involvement with ESH Managing Environmental Compliance Partnering with Torcon Managing prompt return on Submittals and RFIs Verifying Compliance
Status Of CM Activities
CF CM Up and Running CM Team Permanent Staff Hired CM Plan Completed and Approved periodic updates CM Procedures Manual Completed periodic updates Site Office Designed, Built, Occupied and Operational CM Support and Staff Augmentation Contract in place Ring Building Contract Awarded in February
Torcons ESH Plan Approved, NTP on March 25, 2009 Site Logistics and Mobilization Complete Phasing/Schedule Developed
Procedures Manual
Submittal Log
Project Staffing
Current Staffing
Permanent Staffing Hires Complete (6 positions filled) Staff Augmentation Started (2 positions filled to date)
10
CF Staffing Plan
11
12
Commissioning
Construction Phase
Submittal Review Witness Start Up Functional Testing
13
Commissioning (continued)
Warranty Period
Commissioning Status
Reviewed Ring Building T-II Design Prepared Ring Building Commissioning Plan Review of Ring Building Submittals
14
BROOKHAVEN SCIENCE ASSOCIATES
Commissioning (continued)
16
Commissioning Plan
17
Outside CM Services
CM Review Report
19
20
21
CM Audit Recommendations
CM Team to Read and Sign Contract (Complete) T&M Tickets to Include Disclaimer (Stamp Made)
Signature verifies time and material only but does not change contractual obligations of either party
Safety
Best in Class Program Going Forward
Change Management Submitting and Processing Proposals Different LOB Contractor Ongoing Logistics Meetings with Torcon
23
BROOKHAVEN SCIENCE ASSOCIATES
Path Forward
Refocus Best in Class Project Safety Program Work with Torcon to Facilitate Project Continue Inspection and Testing Effort Continuous Improvement of CF Procedures Manual Ramp Up Commissioning Prepare for Upcoming Activities Checklist
Structural Steel, Roofing (SSR), Wall Panel
Conclusion
Project on Track
Within Budget On Schedule Torcon a Proven GC
Continued Partnering
BNL, Contractors and Designers Identify Shared Goals
25
BROOKHAVEN SCIENCE ASSOCIATES