How to update

Baseline in
Primavera P6
Khuong DoSeptember 6, 2016Primavera P6,Schedule

Post navigation
Previous
Next
Baseline is something we usually do not change. However in some case we need to change it.

I will show you how to do it.

We have a simple project which is assigned a baseline


After a few update period, the project is delayed quite far from the baseline
After discussion with the Owner, they allow us to update our baseline to be identical to current
schedule.

There are some ways to update baseline.

Option 1:

We will create a new baseline based on our current schedule and assign the new baseline to our
project.

First you have to make an important configuration.

Go to menu Admin -> Admin Preferences.

In Earned Value tab, select “At completion values with current dates”
Go to menu Project -> Maintain Baselines. Click Add to create a new baseline

Go to menu Project -> Assign Baselines. Select baseline B2


Now you can see the baseline have been updated
Option 2 : Restore baseline

Go to menu Project -> Assign Baselines. Select Current project

Go to menu Project -> Maintain Baselines. Select the baseline and click on Restore button
Now go to the Project window and we can see the baseline become a normal project which we can
open and update easily.
After finish updating the baseline project, you will convert it to become a baseline again.

Open your “main” project. Go to menu Project -> Maintain Baselines. Click on Add button. Now we
will select option “Convert another project…”

And select the updated baseline project


Now your project will have a new baseline.