Standard Form of Bidding Documents (Civil Works-Large Contracts)
Standard Form of Bidding Documents (Civil Works-Large Contracts)
Standard Form of Bidding Documents (Civil Works-Large Contracts)
DOCUMENTS
ACKNOWLEDGEMENT
Pakistan Engineering Council extends deep appreciations and acknowledges the contribution in
developing and finalizing this document by the following experts of the Pakistan Engineering
Council (PEC):
Appreciation is also placed to the following Experts who reviewed the Draft of this
document and rendered useful advice:
TABLE OF CONTENTS
PREFACE iii
INSTRUCTIONS TO BIDDERS 3
BIDDING DATA 19
DRAWINGS................................................................................................................... 163
PREFACE
1. Pakistan Engineering Council (PEC) being the statutory regulatory body has been entrusted
to regulate the engineering profession in Pakistan. It has carried out standardization of
“country specific” documents to regulate and streamline hiring of engineering consultancy
services and procurement of works in line with advice by Planning Commission, Govt of
Pakistan in 1996. Standard Form of Bidding Documents (Civil Works) is one such document
prepared by a team of experts comprising employers, constructors and consultants. A part of
this document titled - “Pakistan Standard Conditions of Contract” after approval by the
Executive Committee of Pakistan Engineering Council was printed in Dec 1992. It was
reprinted in July 1993 incorporating editorial amendments and was then issued to various
organizations in the country. With the passage of time, this document was developed into a
complete bidding document which was notified for implementation by Government of
Pakistan. On the basis of feedback received from the users of this document and comments
from PPRA in September 2005, it was revised upto June 11, 2007. Current version of this
document has been updated and very useful information and experience has been
incorporated in this document. It is expected that use of this revised Bidding Document will
provide an equitable and just basis of contract agreements for procurement of works in line
with the international practice and relevant PEC Bye-laws thus minimizing ambiguities and
likely contractual disputes.
3. This document is to be used for all works with estimated value of more than Rs 100 Million.
While preparing this document, the following publications/documents have been referred to:
i. Pakistan Standard Conditions of Contract (Civil) 1 st Edition reprinted in July
1993.
ii. Standard Form of bidding documents (Civil Works) printed in 2002, initially
harmonized with Public Procurement Rules, 2004 in 2005 and lastly revised in
June 2007.
iii. World Bank Standard Bidding Documents - Procurement of Works March 2012
based on FIDIC-MDB HARMONISED EDITION 2010.
iv. Public Procurement Rules, 2004
4. This document has been approved by ECNEC in its meeting on _____________. The
document has been notified by Planning Commission, Government of Pakistan vide
Notification No. ________________________. It is, therefore, mandatory for all
engineering organizations and departments at Federal and Provincial level and district
governments to use this document for procurement of works funded locally,PSDP and/or
through donor agencies.
5. Any suggestions for improvement shall be appreciated. These may be addressed to Registrar,
PEC, Ataturk Avenue, G-5/2, Islamabad (e-mail: registrar@pec.org.pk).
INSTRUCTIONS TO
USERS OF THIS DOCUMENT
The Instructions to Bidders can be used as given. User may have to make changes in the text
under some special circumstances. Any change should be made with care and only in the Section
“Bidding Data”.
The General Conditions (GC) and Particular Conditions (PC) prepared by the PEC on the basis of
FIDIC-MDB should be retained as such. Any further amendment in the Particular Conditions can
be made by the users only as indicated by the PEC in Para-E hereinafter or within the Particular
Conditions.
Completion of the Forms and preparation of Bill of Quantities should be made as suggested
hereinafter.
The user is required to prepare the following for completion of the Bidding Documents:
(i) Particular Conditions (PC) (as specified herein)
(ii) Specifications - Special Provisions
(iii) Specifications - Technical Provisions
(iv) Bill of Quantities
(v) Drawings
The user’s attention is drawn to the Preface and it is once again emphasised that while preparing
the part in PC, no Clause of GC should be deleted and that the amendments made in PC should be
such as not to change the spirit of the document.
1. Letterof Bid:
Only Bid Reference No. shall be filled in by the Employer (refer Para B.7 above). All
other blanks are to be left open for filling in by the Bidder.
2. Appendix-A to Bid (Schedule of Adjustment Data)
i. Table I (Local Currency)
In this Table, the Bidder shall (a) indicate amount of local currency payment, and
the Employer shall (b) enter the source and base values of indices for the different
elements of cost, and (c) derive weightings for local currency payment.
ii. Table II (Foreign Currency)
In this Table, the Bidder shall (a) indicate amount of foreign currency payment, (b)
indicate the source and base values of indices for the different foreign currency
elements of cost, (c) derive its proposed weightings foreign currency payment,
except the non-adjustable portion which will be filled in by the Employer, and (d) in
the case of very large and/or complex works contracts, it may be necessary to
specify several families of price adjustment formulae corresponding to the different
works involved.
iii. Table III (Foreign Currency Requirements)
In this Table, the Bidder shall provide information regarding Factors (inputs)
Requirements (refer, in accordance with the proportion of various currencies with
reference to GC Clause-14, Contract Price and Payments).
iv. Table IV (Summary of Payment Currencies)
In this Table, the Bidder shall list the exchange rates used in the currency
conversion.
v. Only contracts having duration of more than six months should be liable to price
adjustment.
vi. User of this price adjustment provisions may add or delete any element as deemed
appropriate.
vii. In case the price adjustable elements are not covered in the schedule of Pakistan
Institute of Cost and Contract (PICC), the Base price and the source thereof shall be
mentioned by the Employer and the corresponding column of the Table I should be
amended accordingly.
viii. Price adjustment will be applicable to all contracts including Item Rate Contracts,
Lump sum Contracts and %-age over Contracts based on Bill of Quantities,
provided such provision is a part of the Contract.
ix. Where no foreign currency payments are foreseen, the Employer should stamp
Table II, III and IV as “Not Used” and, referring to Sub-Clauses 14.15 of GC that
all payments shall be in local currency only. Clause IB-13 should also be modified
accordingly through the changes in Bidding Data.
3. Appendix-B to Bid (Bill of Quantities and Day Work)
Bills for various items are given by way of example only. The Employer should
prepare the Bill of Quantities appropriate to the Works. In preparation of the Bill of
Quantities, Columns under (1), (2), (3) and (4) should be completed by the Employer
whereas spaces under Columns (5) and (6) as well as the Totals at the bottom shall be
left blank for filling in by the Bidder. However, columns (5) & (6) will be filled in by
the Employer if the unit of Item is Provisional Sum.
Referring to Schedule of Daywork Rates for Labour, Materials and Constructional
Plant, the types of labour, materials and constructional plant under Column (2) as well
as quantities under Column (4) are given by way of example only. The Employer
should determine the types of labour, materials and constructional plant as well as the
quantities thereof, estimated to be utilized, on Daywork basis depending upon the
nature of the Works.
4. Appendix-C to Bid (Construction Schedule)
If the Employer requires partial completion of the Works by Sections (for example
Parts-A, B, C etc.), these should be identified and time for completion thereof are to be
specified and the blank spaces may be filled in by the Employer.
5. Appendix-D to Bid (Method of Performing the Work)
The Employer may expand the requirements as stated in this Appendix-D keeping in
view the requirements of the Works.
6. Appendix-E to Bid (List of Major Equipment)
Appendix-F to Bid (Contractor’s Organisation Chart)
Appendix-G to Bid (List of Sub-Contractor)
Appendix-H to Bid (Estimated Progress Payments)
Appendix-I to Bid (Construction Camp & Housing Facilities)
All blank spaces in the above appendices are to be filled in by the Bidder.
7. Appendix –J to Bid (Integrity Pact)
The Employer is to provide the form of the Integrity Pact which the bidder shall sign
and stamp along with his Bid.
D. Forms
Bid Security:
The Employer, before issuing the Bidding Documents, should enter the following in the
blank spaces:
(i) Penal Sum of Security, in words as well as figures, which should be the same as
established at Sub-Para B.6 above.
(ii) Bid Reference Number should be the same as per Sub-Para B.7 above.
(iii) Standard Forms of Securities provided in this document are to be issued by a bank. In
case the bidder chooses guaranties from insurance companies for accompanying his
bid or performance of Contract or against receipt of advance, the relevant format shall
be tailored accordingly without changing the spirit of the forms of securities.
E. Conditions of Contract
The conditions of contract comprise General Conditions (GC) and Particular Conditions
(PC). The PC complement the GC to specify date and contractual requirements linked to
the special circumstances of the Employer, the Engineer, the overall project, and the Works.
The PC consists of two parts, Part A, Contract Data and Part B, Specific Provisions.
General Conditions of Contract (GC)
The General Conditions used are the FIDIC-MDB Harmonized Edition-2010 for the
Conditions of Contract for Construction prepared and copyrighted by the International
Federation of Consulting Engineers (Fédération Internationale des Ingénieurs-Conseils, or
FIDIC). These conditions shall be used unchanged.
Particular Conditions of Contracts (PC)
Part A, Contract Data of the PC, includes data to complement the GC in a manner similar
to the way in which the Bid Data Sheet complements the Instructions to Bidders. The
Employer shall insert relevant data prior to the issue of the bidding document. The number
of days, where required to be inserted, shall be a multiple of seven for consistency with the
Conditions of Contract. Whenever there is a conflict, the provisions herein shall prevail
over those in the GC.
Part B, Specific Provisions of the PC are provisions for use by the Employer to meet the
special circumstances not covered by the GC. Whoever drafts the Specific Provisions
should be thoroughly familiar with the provisions of the GC and with any specific
requirements of the contract. Legal advice is recommended when amending provisions or
drafting new ones.
The PC provisions take precedence over those in the GC. Clause Numbers in the PC
correspond to those in the GC.
i. Referring to Sub-Clause 1.5, the Employer may add, in the order of priority, such
other documents which form part of the Contract.
ii. Referring to first paragraph of Sub-Clause 3.1 information as applicable is provided
thereunder.
iii. Referring to Sub-Clause 5 of GC if the Employer desires the Bidder to use the
services of nominated subcontractor(s), the Employer should make necessary
provisions of Provisional Sums and provide blank spaces for filling in the percentage
rate(s) and estimated amounts resulting therefrom in BOQ to Bid. The blank spaces
for the rate(s) and the estimated amount(s) shall be filled in by the Bidder.
Suitable text referring to such provisions should be added under the Sub-Clause.
iv. Referring to Sub-Clause 8.3 of GC, the Employer should specify the form in which
the Programme is to be submitted by the Bidder, e.g., critical path network, simple bar
chart or PERT.
v. In case the Employer considers that if completion by the Contractor of the whole
Works, or of any section thereof, earlier than the specified completion will be of
substantial benefit to him, he may add a GC Sub-Clause 8.13 “Bonus for Early
Completion”. The amount of daily bonus should normally be half of the rates
specified for the amount of daily liquidated damages. A ceiling of total bonus (say, 5
percent of Contract Price) may be inserted to discourage unrealistically rapid Contract
implementation by the Contractor, which could adversely affect overall performance.
In addition, the rate(s) and the limit for bonus as determined will be entered in
Contract Data.
vi. Referring to Sub-Clause 20 of GC, the Employer shall decide the venue of
Arbitration, which should be within the country/project location.
F. Specifications-Special Provisions
To be prepared and incorporated by the Employer. Inclusion of the Conditions of Contract
in Special Provisions should be avoided.
G. Specifications-Technical Provisions
To be prepared and incorporated by the Employer.
(Precise and clear Specifications are prerequisite for bidders to respond realistically and
competitively to the requirements of the Employer without qualifying or conditioning their
bids. In the context of both national and international competitive bidding, the
Specifications must be drafted to permit the widest possible competition and, at the same
time, present a clear statement of the required standards of materials, Plant, other supplies,
and workmanship to be provided. Only if this is done will the objectives of economy,
efficiency, and equality in procurement be realized, responsiveness of bids be ensured, and
the subsequent task of bid evaluation facilitated. The Specifications should require that all
materials, Plant, and other supplies to be incorporated in the Works are new, unused, of the
most recent or current models, and incorporate all recent improvements in design and
materials unless provided otherwise in the Contract. A clause setting out the scope of the
Works is often included at the beginning of the Specifications, and it is customary to give a
list of the Drawings. Where the Contractor is responsible for the design of any part of the
permanent Works, the extent of his obligations must be stated.
Specification shall be generic and shall not include references to brand names, model
numbers, catalogue numbers or similar classifications. However, if the Employer is
convinced that the use of or a reference to a brand name or catalogue number is essential to
complete an otherwise incomplete specification, such use or reference shall be qualified
with the words “or equivalent”.
Care must be taken in drafting Specifications to ensure that they are not restrictive. In the
specification of standards for materials, Plant, other supplies, and workmanship, recognized
international standards should be used as much as possible. The specifications shall
consider all site conditions but not limited to seismic conditions, weather conditions and
environmental impact. Where other particular standards are used, whether national
standards or other standards, the Specifications should state that materials, Plant, other
supplies, and workmanship meeting other authoritative standards, and which ensure equal
performance, as the standards mentioned, will also be acceptable.)
H. Drawings
To be prepared and incorporated by the Employer.
1. The __________________________________________________________________
(Name of Employer)
(“the Employer”) has applied for/received a loan/credit from the
__________________________________________________towards the cost of
(Name of Funding Agency/GOP/Provincial Govt/Any Other)
___________________________________________ and it is intended that part of the
(Name of Project)
proceeds of the loan/credit will be applied to eligible payments under the Contract for the
_____________________________________________________________________.
(Brief description of the Works)
2. The Employer invites sealed bids from eligible persons or firms or joint venture of firms
licensed by the Pakistan Engineering Council in the appropriate category for the Works. A
foreign bidder is entitled to bid only in a joint venture with a Pakistani constructor in
accordance with the relevant provisions of PEC bye-laws.
3. Bidders may obtain further information from, inspect at and acquire the Bidding
Documents from the Office of the Employer, at ______________________________
_____________________________________________________________________
(Mailing Address)
4. A complete set of Bidding Documents may be purchased by an interested bidder on
submission of a written application to the above office and upon payment of a non-
refundable fee of Rs. _________________________.
(Insert Amount)
at or before _____ hours, on ___________ (Date). Bids will be opened at _____ hours on
the same day, in the presence of bidder’s representatives who choose to attend at the same
address. (Indicate Address and Exact Location if it differs).
6. Bidders wishing to offer discounts in case they are awarded the contract will be allowed to
do so, provided those discounts are included in the Letter of Bid.
[Note: the bids shall be opened at least thirty minutes after the deadline for submission
of bids]
INSTRUCTIONS TO BIDDERS
INSTRUCTIONS TO BIDDERS
Table of Clauses
A. General 5
IB 1. Scope of Bid 5
IB 2. Source of Funds 5
IB 3. Eligible Bidders 5
IB 4. One Bid per Bidder 5
IB 5. Cost of Bidding.......................................................................................................5
IB 6. Site Visit ………….…………………………………………………..……………5
B. Bidding Documents 6
IB 7. Contents of Bidding Documents 6
IB 8. Clarification of Bidding Documents 6
IB 9. Amendment of Bidding Documents 6
C. Preparation of Bids 7
IB 10. Language of Bid 7
IB 11. Documents Accompanying the Bid 9
IB 12. Bid Prices 9
IB 13. Currencies of Bid and Payment..………………………………….…………….....9
IB 14. Bid Validity 10
IB 15. Bid Security 10
IB 16. Alternate Proposals by Bidder ……………….………………..…………...….....11
IB 17. Pre-Bid Meeting …11
IB 18. Format and Signing of Bid ………………………………….……………….…. 11
D. Submission of Bids 12
IB 19. Sealing and Marking of Bids 12
IB 20. Deadline for Submission of Bids 13
IB 21. Late Bids 13
IB 22. Modification, Substitution and Withdrawal of Bids 13
F. Award of Contract 16
IB 29. Award Criteria 16
IB 30 Employer’s Right to Accept any Bid and to Reject any or all Bids ….…….……16
IB 31. Notification of Award 17
IB 32 Performance Security ………………………………………………..……….… 17
IB 33. Signing of Contract Agreement 17
IB 34. General Performance of the Bidders 17
IB 35 Integrity Pact…………………………………………………...………………....18
IB 36. Instructions not Part of Contract ……………………………………..………..….18
INSTRUCTIONS TO BIDDERS
A. GENERAL
IB.1 Scope of Bid 1.1 The Employer as defined in the Bidding Data hereinafter
called “the Employer” wishes to receive bids for the
construction and completion of works as described in these
Bidding Documents, and summarised in the Bidding Data
hereinafter referred to as the “Works”.
1.2 The successful bidder will be expected to complete the Works
within the time specified in the Contract Data.
IB.2 Source of 2.1 The Employer has applied for/received a loan/credit from the
Funds source(s) in various currencies towards the cost of the project
specified in the Bidding Data and it is intended that part of the
proceeds of this loan/credit will be applied to eligible
payments under the Contract for which these Bidding
Documents are issued.
IB.3 Eligible Bidders 3.1 This Invitation for Bids is open to all bidders meeting the
following requirements:
a) Duly licensed by the Pakistan Engineering Council
(PEC) in the category relevant to the value of the
Works.
b) Duly prequalified / enlisted by the Employer, where
required.
IB.4 One Bid per 4.1 Each bidder shall submit only one bid either by himself, or as
Bidder a partner in a joint venture. A bidder who submits or
participates in more than one bid (other than alternatives
pursuant to Clause IB.16) will be disqualified.
IB.5 Cost of Bidding 5.1 The bidders shall bear all costs associated with the
preparation and submission of their respective bids and the
Employer will in no case be responsible or liable for those
costs, regardless of the conduct or outcome of the bidding
process.
IB.6 Site Visit 6.1 The bidders are advised to visit and examine the Site of
Works and its surroundings and obtain for themselves on their
own responsibility all information that may be necessary for
preparing the bid and entering into a contract for construction
of the Works. All cost in this respect shall be at the bidder’s
own expense.
6.2 The bidders and any of their personnel or agents will be
granted permission by the Employer to enter upon his
premises and lands for the purpose of such inspection, but
only upon the express condition that the bidders, their
personnel and agents, will release and indemnify the
Employer, his personnel and agents from and against all
liability in respect thereof and will be responsible for death or
personal injury, loss of or damage to property and any other
loss, damage, costs and expenses incurred as a result of such
inspection
PAKISTAN ENGINEERING COUNCIL
6 Instructions to Bidders
B. BIDDING DOCUMENTS
IB.7 Contents of 7.1 The Bidding Documents, in addition to invitation for bids, are
Bidding those stated below and should be read in conjunction with any
Documents Addenda issued in accordance with Clause IB.9:
1. Instructions to Bidders
2. Bidding Data
3. General Conditions (GC)
4. Particular Conditions (PC)
Part-A: Contract Data
Part-B: Specific Provisions
5. Specification - Special Provisions
6. Specificaiton - Technical Specifications
7. Letter of Bid
8. Appendices to Bid including bill of quantities
9. Standard Form
i) Form of Bid Security
ii) Form of Contract Agreement
iii) Form of Performance Security
iv) Form of Mobilization Advance Guarantee
10. Drawings
7.2 The bidders are expected to examine carefully the contents
of all the above documents. Failure to comply with the
requirements of bid submission will be at the Bidder’s own
risk. Pursuant to Clause IB 26, bids which are not
substantially responsive to the requirements of the Bidding
Documents will be rejected.
IB.8 Clarification 8.1 Any prospective bidder requiring any clarification (s)
of Bidding in respect of the Bidding Documents may notify the
Documents Employer in writing at the Employer’s address indicated in
the Invitation for Bids. The Employer will respond to any
request for clarification which he receives earlier than the
period specified in the Bidding Data, prior to the deadline for
submission of bids.
Copies of the Employer’s response will be forwarded to all
purchasers of the Bidding Documents, including a description
of the enquiry but without identifying its source.
IB.9 Amendment 9.1 At any time prior to the deadline for submission of bids, the
of Bidding Employer may, for any reason, whether at his own initiative
Documents or in response to a clarification requested by a prospective
bidder, modify the Bidding Documents by issuing addendum.
9.2 Any addendum thus issued shall be part of the Bidding
Documents pursuant to Sub Clause IB 7.1 hereof and shall be
communicated in writing to all purchasers of the Bidding
Documents. Prospective bidders shall acknowledge receipt of
each addendum in writing to the Employer.
C. PREPARATION OF BIDS
IB.10 Language 10.1 The bid and all correspondence and documents related to the
of Bid bid exchanged by a bidder and the Employer shall be in the
bid language stipulated in the Bidding Data and Particular
Conditions of Contract. Supporting documents and printed
literature furnished by the bidders may be in any other
language provided the same are accompanied by an accurate
translation of the relevant parts in the bid language, in which
case, for purposes of evaluation of the bid, the translation in
bid language shall prevail.
IB.12 Bid Prices 12.1 The price and discount if any quoted by the Bidders in the
Letter of Bid and in the Bill of Quantity shall conform to the
requirement specified below:
Unless stated otherwise in the Bidding Documents, the
Contract shall be for the whole of the Works as described in
Sub Clause IB 1.1 hereof, based on the unit rates and / or
prices.
12.2 The bidders shall fill in rates and prices for all items of the
Works described in the Bill of Quantities. Items against which
no rate or price is entered by a bidder will not be paid for by
the Employer when executed and shall be deemed covered by
rates and prices for other items in the Bill of Quantities.
12.3 All duties, taxes and other levies payable by the Contractor
under the Contract, or for any other cause, as on the date 28
days prior to the deadline for submission of bids shall be
included in the rates and prices and the total Bid Price
submitted by a bidder.
Additional / reduced duties, taxes and levies due to
subsequent additions or changes in legislation shall be
reimbursed / deducted as per Sub Clause 13.7 of the General
Conditions of Contract.
12.4 The rates and prices quoted by the bidders are subject to
adjustment during the performance of the Contract in
accordance with the provisions of Sub Clause 13.8 of the
General Conditions of Contract. The bidders shall furnish the
prescribed information for the price adjustment formulae in
Appendix-A to Bid, and shall submit with their bids such
other supporting information as required under the said
Clause.
IB.13 Currencies 13.1 The unit rates and the prices shall be quoted by the bidder
of Bid and entirely in Pak rupees. A bidder expecting to incur
Payment expenditures in other currencies for inputs to the Works
supplied from outside the Employer’s country (referred to as
the “Foreign Currency Requirements”) shall indicate the same
in Appendix-A to Bid. The proportion of the Bid Price
(excluding Provisional Sums) needed by him for the payment
of such Foreign Currency Requirements either (i) entirely in
the currency of the Bidder’s home country or, (ii) at the
bidder’s option, entirely in Pak rupees provided always that a
bidder expecting to incur expenditures in a currency or
currencies other than those stated in (i) and (ii) above for a
portion of the foreign currency requirements, and wishing to
be paid accordingly, shall indicate the respective portions in
his bid.
IB.14 Bid Validity 14.1 Bids shall remain valid for the period stipulated in the
Bidding Data after the Date of Bid Opening specified in
Clause IB 23.
14.2 In exceptional circumstances, prior to expiry of the original
bid validity period, the Employer may request that the bidders
extend the period of validity for a specified additional period
which shall in no case be more than the original bid validity
period. The request and the responses thereto shall be made in
writing. A bidder may refuse the request without forfeiting his
Bid Security. A bidder agreeing to the request will not be
required or permitted to modify his bid, but will be required
to extend the validity of his Bid Security for the period of the
extension, and in compliance with Clause IB 15 in all
respects.
IB.15 Bid Security 15.1 Each bidder shall furnish, as part of his bid, a Bid Security in
original form in the amount stipulated in the Bidding Data in
Pak Rupees or an equivalent amount in a freely convertible
currency.
15.2 The Bid Security shall be, at the option of the bidder, in the
form of Deposit at Call or a Guarantee issued by a Scheduled
Bank in Pakistan or from a foreign bank duly counter
guaranteed by a Scheduled Bank in Pakistan or from an
insurance company having at least AA rating from
PACRA/JCR in favour of the Employer valid for a period 28
days beyond the Bid Validity date. The Bid Security of Joint
Venture shall be in the name of Joint Venture submitting the
bid.
15.3 Any bid not accompanied by an acceptable Bid Security shall
be rejected by the Employer as non-responsive.
15.4 The bid securities of unsuccessful bidders will be returned as
promptly as possible, but not later than 28 days after the
expiration of the period of Bid Validity.
15.5 The Bid Security of the successful bidder will be returned
when the bidder has furnished the required Performance
Security and signed the Contract Agreement.
IB.16 Alternate 16.1 Should any bidder consider that he can offer any advantages
Proposals to the Employer by a modification to the designs,
by Bidder specifications or other conditions, he may, in addition to his
bid to be submitted in strict compliance with the Bidding
Documents, submit any Alternate Proposal(s) containing (a)
relevant design calculations; (b) technical specifications; (c)
proposed construction methodology; and (d) any other
relevant details / conditions, provided always that the total
sum entered on the Letter of Bid shall be that which
represents complete compliance with the Bidding Documents.
16.2 Alternate Proposal(s), if any, of the lowest evaluated
responsive bidder only may be considered by the Employer as
the basis for the award of Contract to such bidder.
IB.17 Pre-Bid 17.1 The Employer may, on his own or at the request of any
Meeting prospective bidder(s), hold a pre-bid meeting to clarify issues
and to answer any questions on matters related to the Bidding
Documents. The date, time and venue of pre-bid meeting, if
convened, is as stipulated in the Bidding Data. All prospective
bidders or their authorized representatives shall be invited to
attend such a pre-bid meeting.
17.2 The bidders are requested to submit questions, if any, in
writing so as to reach the Employer not later than seven (7)
days before the proposed pre-bid meeting.
17.3 Minutes of the pre-bid meeting, including the text of the
questions raised and the replies given, will be transmitted
without delay to all purchasers of the Bidding Documents.
Any modification of the Bidding Documents listed in Sub-
Clause 7.1 hereof which may become necessary as a result of
the pre-bid meeting shall be made by the Employer
exclusively through the issue of an Addendum pursuant to
Clause IB.9 and not through the minutes of the pre-bid
meeting.
17.4 Absence at the pre-bid meeting will not be a cause for
disqualification of a bidder.
IB.18 Format and 18.1 Bidders are particularly directed that the amount entered on
Signing of Bid the Letter of Bid shall be for performing the Contract strictly
in accordance with the Bidding Documents.
18.2 All appendices to Bid are to be properly completed and
signed.
18.3 No alteration is to be made in the Letter of Bid nor in the
Appendices thereto except in filling up the blanks as directed.
If any such alterations be made or if these instructions be not
D. SUBMISSION OF BIDS
IB.19 Sealing and 19.1 Each bidder shall submit his bid as under:
Marking of (a) ORIGINAL and each copy of the Bid shall be
Bids separately sealed and put in separate envelopes and
marked as such.
(b) The envelopes containing the ORIGINAL and copies
will be put in one sealed envelope and addressed /
identified as given in Sub Clause IB 19.2 hereof.
19.2 The inner and outer envelopes shall:
(a) be addressed to the Employer at the address provided in
the Bidding Data.
(b) bear the name and identification number of the contract
as defined in the Bidding Data; and
(c) provide a warning not to open before the time and date
for bid opening, as specified in the Bidding Data.
19.3 In addition to the identification required in Sub Clause IB
19.2 hereof, the inner envelope shall indicate the name and
address of the bidder to enable the bid to be returned
unopened in case it is declared “late” pursuant to Clause
IB.21.
19.4 If the outer envelope is not sealed and marked as above, the
Employer will assume no responsibility for the misplacement
or premature opening of the Bid.
IB.20 Deadline for20.1 Bids must be received by the Employer at the address
Submission of specified no later than the time and date stipulated in
Bids the Bidding Data.
20.2 The Employer may, at his discretion, extend the deadline for
submission of bids by issuing an amendment in accordance
with Clause IB.9, in which case all rights and obligations of
the Employer and the bidders previously subject to the
original deadline will thereafter be subject to the deadline as
extended
IB.21 Late Bids 21.1 Any bid received by the Employer after the deadline
for submission of bids prescribed in Clause IB.20
will be returned unopened to such bidder.
IB.22 Modification, 22.1 Any bidder may modify, substitute or withdraw his bid after
Substitution and bid submission provided that the modification, substitution or
Withdrawal of written notice of withdrawal is received by the Employer
Bids prior to the deadline for submission of bids.
22.2 The modification, substitution, or notice for withdrawal of
any bid shall be prepared, sealed, marked and delivered in
accordance with the provisions of Clause IB.19 with the outer
and inner envelopes additionally marked “MODIFICATION”,
“SUBSTITUTION” or “WITHDRAWAL” as appropriate.
IB.23 Bid Opening 23.1 The Employer will open the bids, including withdrawals,
substitution and modifications made pursuant to Clause
IB.22, in the presence of bidders’ representatives who choose
to attend, at the time, date and location stipulated in the
Bidding Data. The bidders’ representatives who are present
shall sign a register evidencing their attendance.
23.2 Envelopes marked “MODIFICATION”, “SUBSTITUTION”
or “WITHDRAWAL” shall be opened and read out first. Bids
for which an acceptable notice of withdrawal has been
submitted pursuant to Clause IB.22 shall not be opened.
23.3 The bidder’s name, total Bid Price and price of any Alternate
Proposal(s), any discounts, bid modifications, substitution and
withdrawals, the presence or absence of Bid Security, and
such other details as the Employer may consider appropriate,
will be announced by the Employer at the opening of bids.
23.4 Employer shall prepare minutes of the bid opening, including
the information disclosed to those present in accordance with
the Sub Clause IB 23.3.
IB.24 Process to be 24.1 Information relating to the examination, clarification,
Confidential evaluation and comparison of bid and recommendations for
the award of a contract shall not be disclosed to bidders or
any other person not officially concerned with such process
before the announcement of bid evaluation report which shall
be done at least ten (10) days prior to issue of Letter of
Acceptance. The announcement to all Bidders will include
table(s) comprising read out prices, discounted prices, price
adjustments made, final evaluated prices and
recommendations against all the bids evaluated. Any effort by
a bidder to influence the Employer’s processing of bids or
award decisions may result in the rejection of such bidder’s
bid. Whereas any bidder feeling aggrieved may lodge a
written complaint not later than fifteen (15) days after the
announcement of the bid evaluation report; however mere fact
of lodging a complaint shall not warrant suspension of the
procurement process.
IB.26 Examination of 26.1 Prior to the detailed evaluation of bids, the Employer will
Bids and determine whether each bid is substantially responsive to the
Determination of requirements of the Bidding Documents.
Responsiveness 6.2 A substantially responsive bid is one which (i) meets the
eligibility criteria; (ii) has been properly signed; (iii) is
accompanied by the required Bid Security; and (iv) conforms
to all the terms, conditions and specifications of the Bidding
Documents, without material deviation or reservation. A
material deviation or reservation is one (i) which affect in any
substantial way the scope, quality or performance of the
Works; (ii) which limits in any substantial way, inconsistent
with the Bidding Documents, the Employer’s rights or the
bidder’s obligations under the Contract; or (iii)
adoption/rectification whereof would affect unfairly the
competitive position of other bidders presenting substantially
responsive bids.
26.3 If a bid is not substantially responsive, it will be rejected by
the Employer, and may not subsequently be made responsive
by correction or withdrawal of the non-conforming deviation
or reservation.
IB.28 Evaluation and 28.1 The Employer will evaluate and compare only the Bids
Comparison of determined to be substantially responsive in accordance with
Bids Clause IB.26.
28.2 In evaluating the Bids, the Employer will determine for each
Bid the evaluated Bid Price by adjusting the Bid Price as
PAKISTAN ENGINEERING COUNCIL
16 Instructions to Bidders
follows:
(a) making any correction for errors pursuant to Clause
IB.27;
(b) excluding Provisional Sums and the provision, if any,
for contingencies in the Summary Bill of Quantities, but
including competitively priced Daywork; and
(c) making an appropriate adjustment for any other
acceptable variation or deviation.
28.3 The estimated effect of the price adjustment provisions of the
Conditions of Contract, applied over the period of execution
of the Contract, shall not be taken into account in Bid
evaluation.
28.4 If the Bid of the successful bidder is seriously unbalanced in
relation to the Employer’s estimate of the cost of work to be
performed under the Contract, the Employer may require the
bidder to produce detailed price analyses for any or all items
of the Bill of Quantities to demonstrate the internal
consistency of those prices with the construction methods and
schedule proposed. After evaluation of the price analyses, the
Employer may require that the amount of the Performance
Security set forth in Clause IB.32 be increased at the expense
of the successful bidder to a level sufficient to protect the
Employer against financial loss in the event of default of the
successful bidder under the Contract.
F. AWARD OF CONTRACT
IB.29 Award Critera 29.1 Subject to Clauses IB.30 and IB.34, the Employer will award
the Contract to the bidder whose bid has been determined to
be substantially responsive to the Bidding Documents and
who has offered the lowest evaluated Bid Price, provided that
such bidder has been determined to be eligible in accordance
with the provisions of Clause IB.3 and qualify pursuant to
Sub-Clause IB 29.2.
29.2 The Employer, at any stage of the bid evaluation, having
credible reasons for or prima facie evidence of any defect in
supplier’s or contractor’s capacities, may require the suppliers
or contractors to provide information concerning their
professional, technical, financial, legal or managerial
competence whether already pre-qualified or not:
Provided that such qualification shall only be laid down after
recording reasons therefore in writing. They shall form part of
the records of that bid evaluation report.
IB.30 Employer’s 30.1 Notwithstanding Clause IB.29, the Employer reserves the
Right to Accept right to accept or reject any Bid, and to annul the bidding
any Bid and to process and reject all bids, at any time prior to award of
Reject any or Contract, without thereby incurring any liability to the
all Bids affected bidders or any obligation except that the grounds for
rejection of all bids shall upon request be communicated to
any bidder who submitted a bid, without justification of
IB.36 Instructions not 36.1 Bids shall be prepared and submitted in accordance with
Part of Contract these Instructions which are provided to assist bidders in
preparing their bids, and do not constitute part of the Bid or
the Contract.
BIDDING DATA
13.1 Bidders to quote entirely in Pak. rupees but specify the percentages of
foreign currency they require.
14.1 Period of Bid Validity:
[Insert number of days after the deadline for Bid submission.]
LETTER OF BID
AND
APPENDICES TO BID
LETTER OF BID
Bid Reference No. ________________________
(Name of Contract/Works)
To:
_______________________________
_______________________________
Gentleman,
1. Having examined the Bidding Documents including Instructions to Bidders, Bidding Data,
Conditions of Contract, Specifications, Drawings and Bill of Quantities and Addenda Nos.
_________________________________for the execution of the above-named Works, we,
the undersigned, offer to execute and complete such Works and remedy any defects therein
in conformity with the Conditions of Contract. Specifications, Drawings, Bill of
Quantities and Addenda for the sum of Rs._______________________
(Rupees______________________________________________) or such other sum as may
be ascertained in accordance with the contract.
2. We understand that all the Appendices attached hereto form part of this Bid.
3. As security for due performance of the undertakings and obligations of this Bid, we submit
herewith a Bid Security in the amount of Rupees _______________________
(Rs. __________________________________) drawn in your favour or made payable to
you and valid for a period of ___________days beginning from the date Bids are opened.
4. We undertake, if our Bid is accepted, to commence the Works and to complete the whole of
the Works comprised in the Contract within the time stated in Contract Data.
5. We agree to abide by this Bid for the period of ______ days from the date fixed for receiving
the same and it shall remain binding upon us and may be accepted at any time before the
expiration of that period.
6. Unless and until a formal Agreement is prepared and executed, this Bid, together with your
written acceptance thereof, shall constitute a binding contract between us.
7. We do hereby declare that the Bid is made without any collusion, comparison of figures or
arrangement with any other bidder for the Works.
8. We understand that you are not bound to accept the lowest or any Bid you may receive.
Signature: ________________________
in the capacity of _____________________duly authorized to sign Bids for and on behalf of
___________________________________________________________________________
(Name of Bidder in Block Capitals)
(Seal)
Address:____________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
Witness:
Signature: _____________________________
Name: ________________________________
Address. _____________________________________
_____________________________________
Occupation____________________________________
A-1
Appendix-A to Bid
Total 1.00
Notes:
1) Indices, its source and base value are taken from Pakistan Institute of Cost and Contract
(PICC), a subsidiary of PEC. The base cost indices or reference prices, each of which is
applicable to the relevant tabulated cost element, shall be for the month falling on the day
28 days prior to the latest day for submission of bids. Current indices or reference prices for
period “n” is applicable to the relevant tabulated cost element and shall be for the month
falling on the day 49 days prior to the last day of the period (to which the particular
Payment Certificate relates).
2) Any fluctuation in the indices or prices of materials other than those given above shall not
be subject to adjustment of the Contract Price.
3) The Employer shall determine the weightings of non-adjustable portion considering only
those cost elements having cost impact of five (5) percent or more on the specific project.
The non-adjustable portion (0.35) indicated above is for example only and the actual shall
be worked out by subtracting sum of all adjustable weightings from (1.00) one. In case the
non adjustable portion works out to be less than 0.35, the Bidder / Contractor shall be
required to justify the amounts filled by the Bidder through analysis of his unit rates quoted
in the Bid; further in case the non adjustable portion works out to be less than 0.20 on the
basis of the justification provided by the Bidder, the non adjustable portion shall be taken as
0.20 and the weightings of adjustable items shall be adjusted proportionately to sum as 0.80
[Employers using this price adjustment provisions may add or delete any elements as deemed
appropriate to the project.]
A-2
Appendix-A to Bid
(i) Non- __ __ __ A:
adjustable
(ii) B:
(iii) C:
(iv) D:
(v) E: _____
Total 1.00
[Note: If the Bidder failed to provide information regarding Weightings, Base Value and Source
of Index, then it is deemed that the Contractor has foregone his right to claim price
adjustment in Foreign Currency.]
A-3
Appendix-A to Bid
TOTAL 100.00
[*The above Factors (Inputs) related to the requirement of respective currencies, are for
guidance only, and shall be indicated specific to the projectForeign Currency should be limited
to only those items which are not available in Pakistan to meet with the prescribed Specification
and are necesserally required to be incorporated provided that the Equipment which would be re
exported is an exemption like expatriate staff.]
A-4
Appendix-A to Bid
a b c d
Name of payment Amount of Rate of Local Percentage of
currency currency exchange currency Total Bid Price
(local currency equivalent (TBP)
per unit of c =a x b 100xc
foreign) TBP
FC1
FC2
B-1
Appendix-B to Bid
BILL OF QUANTITIES
A. Preamble:
1. The Bill of Quantities shall be read in conjunction with the Conditions of Contract,
Specifications and Drawings.
2. The quantities given in the Bill of Quantities are estimated and provisional, and are given
to provide a common basis for bidding. The basis of payment will be the actual quantities
of work executed and measured by the Contractor and verified by the Engineer and
valued at the rates and prices entered in the priced Bill of Quantities, where applicable,
and otherwise at such rates and prices as the Engineer may fix as per the Contract.
3. The rates, prices and amounts entered in the priced Bill of Quantities shall, except insofar
as it is otherwise provided under the Contract include all costs of Contractor’s plant,
labour, supervision, materials, execution, insurance, profit, taxes and duties, together
with all general risks, liabilities and obligations set out or implied in the Contract.
Furthermore all duties, taxes and other levies payable by the Contractor under the
Contract, or for any other cause, as on the date 28 days prior to deadline for submission
of Bids, shall be included in the rates and prices and the total Bid Price submitted by the
Bidder.
4. A rate or price*shall be entered against each item in the priced Bill of Quantities, whether
quantities are stated or not. For the items against which quantities are stated, their
amounts shall also be entered. The cost of items against which the Contractor will have
failed to enter a rate or price (of a Lump Sum item) or amount for unit rate item shall be
deemed to be covered by other rates, prices and amounts entered in the Bill of Quantities.
5. The whole cost of complying with the provisions of the Contract shall be included in the
items provided in the priced Bill of Quantities, and where no items are provided, the cost
shall be deemed to be distributed among the rates, prices and amounts entered for the
related items of the Works.
6. General directions and description of work and materials are not necessarily repeated nor
summarised in the Bill of Quantities. References to the relevant sections of the Bidding
Documents shall be made before entering rates, prices and amounts against each item in
the priced Bill of Quantities.
7. Provisional sums included and so designated in the Bill of Quantities shall be expended in
whole or in part at the direction and discretion of the Engineer in accordance with Sub
Clause 13.5, General Conditions of Contract.
8. The following abbreviations for units have been used in Bill of Quantities:
Units Abbreviations
Cubic Meter = Cu.M
Square Meter = Sq.M
Kilogram = Kg
Provisional Sum = PS
Lumpsum = LS
B-2
Appendix-B to Bid
BILL OF QUANTITIES
(Sample)
B. Work Items:
Daywork Schedule
B-3
Appendix-B to Bid
BILL OF QUANTITIES
Bill No. 1 General Items
Rate
Specs. Amount
Item Description Unit Quantity Rupees in Rupees in words
Ref. Rupees
figures
1 2 3 4 5 6 7
101 Insurances of the SP-31 PS
Works
109
B-4
Appendix-B to Bid
BILL OF QUANTITIES
Bill No. 2 Earthworks
Rate
Specs. Amount
Item Description Unit Quantity Rupees in Rupees in words
Ref. Rupees
figures
1 2 3 4 5 6 7
201 TS
202
203
204
205
206
B-5
Appendix-B to Bid
BILL OF QUANTITIES
Bill No. 3 Culverts and Bridges
Rate
Specs. Amount
Item Description Unit Quantity Rupees in Rupees in words
Ref. Rupees
figures
1 2 3 4 5 6 7
301 TS
302
303
304
305
306
B-6
Appendix-B to Bid
BILL OF QUANTITIES
Bill No. 4 Subsurface Drains
Rate
Specs. Amount
Item Description Unit Quantity Rupees in Rupees in words
Ref. Rupees
figures
1 2 3 4 5 6 7
401
402
403
404
405
406
B-7
Appendix-B to Bid
BILL OF QUANTITIES
Bill No. 5 Miscellaneous Items
Rate
Specs. Amount
Item Description Unit Quantity Rupees in Rupees in words
Ref. Rupees
figures
1 2 3 4 5 6 7
501
502
503
504
505
506
B-8
Appendix-B to Bid
BILL OF QUANTITIES
Daywork Schedule
C. Daywork
General
1. Reference is made to Sub-Clause 13.6 of the General Conditions of Contract. Work shall
not be executed on a day work basis except by written order of the Engineer. Bidders
shall enter basic rates for Daywork items in the Schedules, which rates shall apply to any
quantity of Daywork ordered by the Engineer. Nominal quantities have been indicated
against each item of Daywork, and the extended total for Daywork shall be carried
forward to the Bid Price.
Daywork Labour
2. In calculating payments due to the Contractor for the execution of Daywork, the actual
time of classes of labour directly doing the Daywork ordered by the Engineer and for
which they are competent to perform will be measured excluding meal breaks and rest
periods. The time of gangers (charge hands) actually doing work with the gang will also
be measured but not the time of foreman or other supervisory personnel.
3. The Contractor shall be entitled to payment in respect of the total time that labour is
employed on Daywork, calculated at the basic rates entered by him in the Schedule of
Daywork Rates for labour together with an additional percentage, payment on basic rates
representing the Contractor’s profit, overheads, etc., as described below:
a) the basic rates for labour shall cover all direct costs to the Contractor, including (but
not limited to) the amount of wages paid to such labour, transportation time, overtime,
subsistence allowances and any sums paid to or on behalf of such labour for social
benefits in accordance with Pakistan law. The basic rates will be payable in local
currency only; and
b) the additional percentage payment to be quoted by the Bidder and applied to costs
incurred under (a) above shall be deemed to cover the Contractor’s profit, overheads,
superintendence, liabilities and insurances and allowances to labour timekeeping and
clerical and office work; the use of consumable stores, water, lighting and power; the
use and repair of stagings, scaffolding, workshops and stores, portable power tools,
manual plant and tools; supervision by the Contractor’s staff, foremen and other
supervisory personnel; and charges incidental to the foregoing.
B-9
Appendix-B to Bid
BILL OF QUANTITIES
Daywork Schedule
I. Labour
Sub Total
Allow _____________ percent of subtotal for Contractor’s overhead, profit, etc, in accordance
with Paragraph 3(b) of Daywork Schedule ________________________
B-10
Appendix-B to Bid
BILL OF QUANTITIES
Daywork Schedule
Daywork Material
4. The Contractor shall be entitled to payment in respect of materials used for Daywork
(except for materials for which the cost is included in the percentage addition to labour
costs as detailed heretofore), at the basic rates entered by him in the Schedule of Daywork
Rates for materials together with an additional percentage payment on the basic rates to
cover overhead charges and profit, as follows.
a) the basic rates for materials shall be calculated on the basis of the invoiced price,
freight, insurance, handling expenses, damage, losses, etc., and shall provide for
delivery to store for stockpiling at the site. The basic rates shall be stated in local
currency but payment will be made in the currency or currencies expended upon
presentation of supporting documentation;
b) the additional percentage payment shall be quoted by the Bidder and applied to the
equivalent local currency payments made under Sub-Para(a) above; and
c) the cost of hauling materials used on work ordered to be carried out as Daywork from
the store or stockpile on the site to the place where it is to be used will be paid in
accordance with the terms for Labour and Constructional Plant in this Schedule.
B-11
Appendix-B to Bid
BILL OF QUANTITIES
Daywork Schedule
II. Material
D204 -------etc--------
Sub Total
Allow _____________ percent of subtotal for Contractor’s overhead, profit, etc, in accordance
with Paragraph 4(b) of Daywork Schedule ____________________
B-12
Appendix-B to Bid
BILL OF QUANTITIES
Daywork Schedule
6. In calculating the payment due to the Contractor for constructional plant employed on
Daywork, only the actual number of working hours will be eligible for payment, except
that where applicable and agreed with the Engineer, the travelling time from the part of
the Site where the constructional plant was located when ordered by the Engineer to be
employed on Daywork and the time for return journey thereto shall be included for
payment.
7. The basic rental rates for constructional plant employed on Daywork shall be stated in
Pakistani Rupees.
B-13
Appendix-B to Bid
BILL OF QUANTITIES
Daywork Schedule
D304 -------etc--------
Sub Total
B-14
Appendix-B to Bid
BILL OF QUANTITIES
Daywork Schedule
Summary
I. Labour
II. Materials
B-15
Appendix-B to Bid
BILL OF QUANTITIES
Summary
1. General Items
2. Earthworks
4. Subsurface Drains
5. Miscellaneous Items
Sub-Total of Bills
Daywork Schedule
Note: All Provisional Sums are to be expended in whole or, in part at the direction and
discretion of the Engineer in accordance with Sub-Clauses 13.5 and 13.6 of the
General Conditions.
C-1
Appendix-C to Bid
a) Whole Works
b) Part-A
c) Part-B
d) ___________
e) ___________
[The Bidder shall provide, the Construction Schedule in the bar chart (CPM, PERT or any other
to be specified herein) showing the sequence of work items and the period of time during which
he proposes to complete each work item in such a manner that his proposed programme for
completion of the whole of the Works and parts of the Works may meet Employer’s completion
targets in days noted above and counted from the Commencement Date(Attach sheets as required
for the specified form of Construction Schedule)]
D-1
Appendix-D to Bid
[The Bidder is required to submit a narrative outlining the method of performing the Work. The
narrative should indicate in detail and include but not be limited to:
1. Organization Chart;
Shall indicate head office and field office personnel involved in management and
supervision, engineering, equipment maintenance and purchasing.
2. Mobilization;
In Pakistan, the type of facilities including personnel accommodation, office
accommodation, provision for maintenance and for storage, communications, security
and other services to be used.
E-1
Appendix-E to Bid
The Bidder shall provide adequate information to demonstrate clearly that it has the capability to
meet the requirements for the major equipment listed in Sheet E-3.]
E-2
Appendix-E to Bid
a. Owned
b. To be
Purchased
c. To be arranged
on Lease
E-3
Appendix-E to Bid
Item of equipment
The following information shall not be applicable for equipment owned or to be purchased by the
Bidder
Address of owner
Fax Telex
F-1
Appendix-F to Bid
ORGANIZATION CHART
FOR THE
SUPERVISORY STAFF AND LABOUR
G-1
Appendix-G to Bid
LIST OF SUBCONTRACTORS
I/We intend to subcontract the following parts of the Work to subcontractors. In my/our opinion,
the subcontractors named hereunder are reliable and competent to perform that part of the work
for which each is listed.
Enclosed are documentation outlining experience of subcontractors, the curriculum vitae and
experience of their key personnel who will be assigned to the Contract, equipment to be supplied
by them, size, location and type of contracts carried out in the past.
H-1
Appendix-H to Bid
Bidder’s estimate of the value of work which would be executed by him during each of the
periods stated below, based on his Programme of the Works and the Rates in the Bill of
Quantities, expressed in thousands of Pakistani Rupees:
Quarter Amounts
(1,000 Rs)
1 2
Ist
2nd
3rd
4th
5th
6th
7th
8th
9th
Bid Price
I-1
Appendix-I to Bid
Note:
The Contractor shall be responsible for pumps, electrical power, water and electrical
distribution systems, and sewerage system including all fittings, pipes and other items
necessary for servicing the Contractor’s construction camp.
J-1
Appendix-J to Bid
INTEGRITY PACT
DECLARATION OF FEES, COMMISSION AND BROKERAGE ETC.
PAYABLE BY THE SUPPLIERS OF GOODS, SERVICES & WORKS IN
CONTRACTS WORTH RS. 10.00 MILLION OR MORE
Without limiting the generality of the foregoing, [name of Supplier] represents and warrants that
it has fully declared the brokerage, commission, fees etc. paid or payable to anyone and not given
or agreed to give and shall not give or agree to give to anyone within or outside Pakistan either
directly or indirectly through any natural or juridical person, including its affiliate, agent,
associate, broker, consultant, director, promoter, shareholder, sponsor or subsidiary, any
commission, gratification, bribe, finder’s fee or kickback, whether described as consultation fee
or otherwise, with the object of obtaining or inducing the procurement of a contract, right,
interest, privilege or other obligation or benefit in whatsoever form from GoP, except that which
has been expressly declared pursuant hereto.
[name of Supplier] certifies that it has made and will make full disclosure of all agreements and
arrangements with all persons in respect of or related to the transaction with GoP and has not
taken any action or will not take any action to circumvent the above declaration, representation or
warranty.
[name of Supplier] accepts full responsibility and strict liability for making any false declaration,
not making full disclosure, misrepresenting facts or taking any action likely to defeat the purpose
of this declaration, representation and warranty. It agrees that any contract, right, interest,
privilege or other obligation or benefit obtained or procured as aforesaid shall, without prejudice
to any other rights and remedies available to GoP under any law, contract or other instrument, be
voidable at the option of GoP.
Notwithstanding any rights and remedies exercised by GoP in this regard, [name of Supplier] agrees
to indemnify GoP for any loss or damage incurred by it on account of its corrupt business practices
and further pay compensation to GoP in an amount equivalent to ten time the sum of any commission,
gratification, bribe, finder’s fee or kickback given by [name of Supplier] as aforesaid for the purpose
of obtaining or inducing the procurement of any contract, right, interest, privilege or other obligation
or benefit in whatsoever form from GoP.
CONTRACT FORMS
BS-1
KNOW ALL MEN BY THESE PRESENTS, that in pursuance of the terms of the Bid and at the
request of the said Principal (Bidder) we, the Surety above named, are held and firmly bound
unto _________________________________________________________________
(hereinafter called the 'Employer') in the sum stated above for the payment of which sum well and
truly to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly
and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH, that whereas the Bidder has submitted
the accompanying Bid dated __________ for Bid No. _______________for
__________________________ (Particulars of Bid) to the said Employer; and
WHEREAS, the Employer has required as a condition for considering said Bid that the Bidder
furnishes a Bid Security in the above said sum to the Employer, conditioned as under:
(1) that the Bid Security shall remain in force up to and including the date 28 days after the
deadline for validity of bids as stated in the Instructions to Bidders or as it may be
extended by the Employer, notice of which extension(s) to the Surety is hereby waived;
(2) that the Bid Security of unsuccessful Bidders will be returned by the Employer after
expiry of its validity or upon signing of the Contract Agreement; and
(3) that in the event of failure of the successful Bidder to execute the proposed Contract
Agreement for such work and furnish the required Performance Security, the entire said
sum be paid immediately to the said Employer pursuant to IB-15 and 32 of the Instruction
to Bidders for the successful Bidder's failure to perform.
NOW THEREFORE, if the successful Bidder shall, within the period specified therefore, on the
prescribed form presented to him for signature enter into a formal Contract with the said
Employer in accordance with his Bid as accepted and furnish within twenty eight (28) days of his
being requested to do so, a Performance Security with good and sufficient surety, as may be
required, upon the form prescribed by the said Employer for the faithful performance and proper
fulfilment of the said Contract or in the event of non-withdrawal of the said Bid within the time
specified for its validity then this obligation shall be void and of no effect, but otherwise to
remain in full force and effect.
BS-2
PROVIDED THAT the Surety shall forthwith pay the Employer the said sum upon first written
demand of the Employer (without cavil or argument) and without requiring the Employer to
prove or to show grounds or reasons for such demand, notice of which shall be sent by the
Employer by registered post duly addressed to the Surety at its address given above.
PROVIDED ALSO THAT the Employer shall be the sole and final judge for deciding whether
the Principal (Bidder) has duly performed his obligations to sign the Contract Agreement and to
furnish the requisite Performance Security within the time stated above, or has defaulted in
fulfilling said requirements and the Surety shall pay without objection the said sum upon demand
from the Employer forthwith and without any reference to the Principal (Bidder) or any other
person.
IN WITNESS WHEREOF, the above bounden Surety has executed the instrument under its seal
on the date indicated above, the name and seal of the Surety being hereto affixed and these
presents duly signed by its undersigned representative pursuant to authority of its governing body.
WITNESS: Signature
1. Name
Title
Corporate Secretary (Seal) Corporate Guarantor (Seal)
2. ____ _______
________________________
Name, Title & Address
PS-1
PS-2
arguments and without requiring the Employer to prove or to show grounds or reasons for such
demand any sum or sums up to the amount stated above, against the Employer's written declaration
that the Principal has refused or failed to perform the obligations under the Contract which payment
will be effected by the Guarantor to Employer’s designated Bank & Account Number.
PROVIDED ALSO THAT the Employer shall be the sole and final judge for deciding whether the
Principal (Contractor) has duly performed his obligations under the Contract or has defaulted in
fulfilling said obligations and the Guarantor shall pay without objection any sum or sums up to the
amount stated above upon first written demand from the Employer forthwith and without any
reference to the Principal or any other person.
IN WITNESS WHEREOF, the above-bounden Guarantor has executed this Instrument under its seal
on the date indicated above, the name and corporate seal of the Guarantor being hereto affixed and
these presents duly signed by its undersigned representative, pursuant to authority of its governing
body.
WITNESS: Signature
1. Name
Title
Corporate Secretary (Seal) Corporate Guarantor (Seal)
2. ____ _______
________________________
Name, Title & Address
CA-1
THIS CONTRACT AGREEMENT (hereinafter called the “Agreement”) made on the _________ day
of __________ (month) 20_____ between ____________________________
___________________________________________________(hereafter called the “Employer”) of
the one part and __________________________________________________ (hereafter called the
“Contractor”) of the other part.
WHEREAS the Employer is desirous that certain Works, viz _______________ should be executed
by the Contractor and has accepted a Bid by the Contractor for the execution and completion of such
Works and the remedying of any defects therein.
2. The following documents after incorporating addenda, if any, except those parts relating to
Instructions to Bidders shall be deemed to form and be read and construed as part of this
Agreement:
a) The Letter of Acceptance;
b) Letter of Bid;
c) The Particular Conditions – Part A Contract Data;
d) The Particular Conditions – Part B Specific Provisions;
e) The General Conditions;
f) The Specifications - Special Provisions;
g) The Specifications - Technical Provisions;
h) The Drawings;
i) The Completed Appendices to Bid including Priced BBill of Quantity; and
j) any other Documents forming part of the Contract.
The addenda, if any, (Excluding part relating to Instructions to Bidders alongwith Bidding
Data) shall be deemed to have been incorporated at the appropriate places in the documents
forming the Contract”.
4. The Employer hereby covenants to pay the Contractor, in consideration of the execution and
completion of the Works as per provisions of the Contract, the Contract Price or such other sum as
may become payable under the provisions of the Contract at the times and in the manner
prescribed by the Contract.
CA-2
IN WITNESS WHEREOF the parties hereto have caused this Agreement to be executed on the day,
month and year first before written in accordance with their respective laws.
(Seal) (Seal)
Witness Witness
MG-1
AND WHEREAS, the Employer has agreed to advance to the Contractor, at the Contractor's
request, an amount of Rupees ___________________________________ (Rs _________ )
which amount shall be advanced to the Contractor as per provisions of the Contract.
AND WHEREAS, the Employer has asked the Contractor to furnish Guarantee to secure the
mobilization advance for the performance of his obligations under the said Contract.
NOW, THEREFORE, the Guarantor hereby guarantees that the Contractor shall use the advance
for the purpose of above mentioned Contract and if he fails and commits default in fulfilment of
any of his obligations for which the advance payment is made, the Guarantor shall be liable to the
Employer for payment not exceeding the aforementioned amount.
Notice in writing of any default, of which the Employer shall be the sole and final judge, on the
part of the Contractor, shall be given by the Employer to the Guarantor, and on such first written
demand, payment shall be made by the Guarantor of all sums then due under this Guarantee
without any reference to the Contractor and without any objection.
This Guarantee shall remain in force until the advance is fully adjusted against payments from the
Interim Payment Certificates of the Contractor or until _________________________whichever
is earlier. (Date)
The Guarantor's liability under this Guarantee shall not in any case exceed the sum of Rupees
______________________ (Rs ________________________________________________).
This Guarantee shall remain valid up to the aforesaid date and shall be null and void after the
aforesaid date or earlier if the advance made to the Contractor is fully adjusted against payments
from Interim Payment Certificates of the Contractor provided that the Guarantor
MG-2
agrees that the aforesaid period of validity shall be deemed to be extended if on the above
mentioned date the advance payment is not fully adjusted.
Guarantor
(Scheduled Bank/ Insurance Company*)
WITNESS: Signature
1. Name
Title
Corporate Secretary (Seal) Corporate Guarantor (Seal)
2. ____ _______
________________________
Name, Title & Address
CONDITIONS OF CONTRACT
CONDITIONS OF CONTRACT
The Conditions of Contract comprise General Conditions and Particular Conditions:
General Conditions
The General Conditions that follow are the FIDIC-MDB Harmonized Edition-2010 of the Conditions
of Contract for Construction prepared and copyrighted by the International Federation of Consulting
Engineers (Fédération Internationale des Ingénieurs-Conseils, or FIDIC), FIDIC 2010-All rights
reserved. Therefore, no part of this publication may be reproduced, translated, adapted, stored in a
retrieval system or communicated, in any form or by any means, whether mechanical, electronic,
magnetic, photocopying, recording or otherwise, without prior permission in writing from FIDIC.
The standard text of the General Conditions chosen must be retained intact to facilitate its reading and
interpretation by bidders and its review by the Employer. Any amendments and additions to the
General Conditions, specific to the contract in hand, should be introduced in the Particular Conditions.
The use of standard conditions of contract for construction works will ensure comprehensiveness of
coverage, better balance of rights or obligations between Employer and Contractor, general
acceptability of its provisions, and savings in time and cost for bid preparation and review, leading to
more economic prices.
Particular Conditions
The Particular Conditions (PC) complement the General Conditions (GC) to specify dates,
contractual requirements, and special circumstances related to the Works. The PC consists of two
parts, Part A, Contract Data and Part B, Specific Provisions:
Part A - Contract Data
Employer’s name and address 1.1.2.2 & 1.3 [insert Employer’s name and addres]
Engineer’s name and address 1.1.2.4 & 1.3 [insert Engineer’s name and address]
Time for access to the Site 2.1 No later than the Commencement Day,
except for the following parts (if
applicable, with detailed description of
parts concerned: ________ days after
Commencement Date.
Delay damages for the Works 8.7 & Rs. _____ for each day of delay in
14.15(b) completion of Works
[If Sections are to be used, refer to Table:
Summary of Sections below]
Bonus for early completion 8.13 Rs.____ for each day of early completion
of Works.
(PCC Part B)
[If Sections are to be used, refer to Table:
Summary of Sections below]
Minimum Amount of Interim 14.6 [One third of the average value of Interim
Payment Certificates Payment Certificate on linear scale of
Time for Completion]
Minimum amount of third 18.3 [insert for injury, death and damage to
party insurance property e,g. Rs. 200,000 in case of injury
for each occurrence and Rs. 1,000,000 in
case of death for each occurrence, number
of occurrences unlimited, and up to ten
percent (10%)of the Accepted Contract
Amount for damage to property as
determined by the Engineer.]
Particular Conditions
Part B - Specific Provisions
1.5 Priority of The documents listed at (a) through (i) of this Sub-Clause are
Documents deleted and substituted with the following:
(a) The Contract Agreement;
(b) The Letter of Acceptance;
(c) Letter of Bid;
(d) The Particular Conditions – Part A Contract Data;
(e) The Particular Conditions – Part B Specific Provisions;
(f) The General Conditions;
(g) The Specifications - Special Provisions;
(h) The Specifications - Technical Provisions;
(i) The Drawings;
(j) The Completed Appendices to Bid including Priced Bill
Of Quantity; and
(k) any other Documents forming part of the Contract.
The addenda, if any, (Excluding part relating to Instruction to
Bidders along with Bid Data) shall be deemed to have been
incorporated at the appropriate places in the documents
forming the Contract.
1.16 Shop Drawings The Contractor shall submit to the Engineer for review 3 copies
of all shop and erection drawings applicable to this Contract as
per provision of relevant Sub-Clause of the Contract.
Review and approval by the Engineer shall not be construed as
a complete check but will indicate only that the general method
of construction and detailing is satisfactory and the Engineer’s
review or approval shall not relieve the Contractor of any of his
responsibilities under the Contract.
1.17 As-Built Drawings At the completion of the Works under the Contract, the
Contractor shall furnish to the Engineer 6 copies and one
reproducible of all drawings amended to conform to the Works
as built. The price of such Drawings shall be deemed to be
included in the Contract Price.
2.5 Employer’s Claims In the second last line of last paragraph, after words ‘Payment
Certificate’, the following is added:
“or from the encashment of Performance Security or from other
assets of the Contractor”
3.1 Engineer’s Duties The following Sub-Paragraphs are added after the sub-paragraph
and Authority (D) in the sixth paragraph:
(E) Any action under Sub-Clause 4.2 “Performance Security”
and Clause 18 “Insurance”.
(F) Consenting to the subcontracting of any part of the Works
under Sub-Clause 4.4-”Subcontractors”.
(G) Any action under Sub-Clause 8.7 “Delay Damages” or
Payment of Bonus for Early Completion of Works (PC
Sub-Clause 8.13).
(H) Any action under Sub-Clause 8.8 “Suspension of Work”,
Sub-Clause 8.9 “Consequences of Suspension”, Sub-
Clause 8.10 “Payment for Plant and Materials in Event of
Suspension” and Sub-Clause 8.11 “Prolonged
Suspension”.
(I) Issuance of “Taking Over Certificate” under Sub-Clause
10.1“Taking Over of the Works and Sections”.
(J) Issuing the “Performance Certificate” under Sub-Clause
11.9.
(K) Agreeing or determining cost under Sub-Clause 12.4.
(L) Certifying release of retention money under Sub-Clause
14.9.
(M) Issuing Final Payment Certificate under Sub-Clause
14.13.
(N) Agreeing or determining any extension of the Time for
Completion and/or any additional payment under Sub-
Clause 20.1
3.2 Delegation by The following text is added at the end of this Sub-Clause:
the Engineer The Employer shall ensure that the Engineer is a “Registered
Professional Engineer”, defined in the Pakistan Engineering
Council Act 1975 (V of 1976).
4.8 Safety Procedures The following text is added at the end of this Sub-Clause:
In the event of work being carried out outside the normal
working hours and in the event of work being carried out at
night, the Contractor shall at his own cost, provide and maintain
such good and sufficient light as will enable the work to proceed
satisfactorily and without danger. The approaches to the Site and
the Works where the night work is being carried out shall be
sufficiently lighted. All arrangement adopted for such lighting
shall be to the satisfaction of the Engineer.
4.17 Contractor’s The following text is added at the end of this Sub-Clause:
Equipment
With a view to securing, in the event of termination under Clause
15, the continued availability, for the purpose of executing the
Works, of any hired Contractor’s Equipment, the Contractor
shall not bring on to the Site any hired Contractor’s Equipment
unless there is an agreement for hire thereof (which agreement
shall be deemed not to include an agreement for hire purchase)
which contains a provision that the owner thereof will, on
request in writing made by the Employer within 7 days after the
date on which any termination has become effective, and on the
Employer undertaking to pay all hire charges in respect thereof
from such date, hire such Contractor’s Equipment to the
Employer on the same terms in all respect as the same was hired
to the Contractor and that the Employer shall be entitled to
permit the use thereof by any other Contractor employed by him
for the purpose of execution and remedying any defects therein
under Clause 15.
The Contractor shall, upon request by the Engineer at any time
in relation to any item of hired Contractor’s Equipment,
forthwith notify the Engineer in writing the name and address of
the Owner of the equipment and shall certify that the agreement
for the hire thereof contains a provision in accordance with the
requirement set forth above
6.1 Engagement of Staff The following new paragraph is added at the end:
and Labour
“The Contractor shall be required, to the extent practicable and
reasonable, to employ maximum technical and non-technical
staff with appropriate qualifications and experience, from the
country, where the Site is located. However, the Contractor shall,
in any case be obliged to prefer to employ unskilled labour from
the towns/villages effected by the Works. “
6.7 Health and Safety The following text is added after 3rd paragraph:
According to the Pakistan regulations, the adultery, alcohol and
drugs are prohibited legally.
In order to provide for the safety, health and welfare of persons,
and for prevention of damage of any kind, all operations for the
purposes of or in connection with the Contract shall be carried
out in compliance with the Safety Requirements of the
Government of Pakistan with such modifications thereto as the
Engineer may authorize or direct and the Contractor shall take or
cause to be taken such further measures and comply with such
further requirements as the Engineer may determine to be
reasonably necessary for such purpose. In case of any fatality or
serious accident, the Contractor shall, in addition, notify the
Engineer immediately by the quickest available means.
Paragraphs-4 to 6, commencing from “HIV-AIDS prevention
……..……..the related specification” are deleted.
6.8 Contractor’s The following text is added at the end of this Sub-Clause:
Superintendence
The Contractor’s authorized representative and his other
professional engineers working at site shall possess registration
with the Pakistan Engineering Council.
The Contractor’s authorized representative at Site shall be
authorized to exercise adequate administrative and financial
powers on behalf of the Contractor so as to achieve completion
of the Works as per the Contract.
6.25 Epidemics In the event of any out-break of illness of epidemic nature, the
Contractor shall comply with and carry out such regulations,
orders and requirements as may be made by the Government or
the local medical or sanitary authorities for the purpose of
overcoming the same.
7.9 Use of Pakistani The Contractor shall, so far as may be consistent with the
Materials and Contract, make the maximum use of materials, supplies, plant
Services and equipment indigenous to or produced or fabricated in
Pakistan and services, available in Pakistan provided such
materials, supplies, plant, equipment and services shall be of
required standard.
8.13 Bonus for Early The Contractor shall in case of earlier completion for either
Completion of whole or part(s) of the Works pursuant to Sub-Clauses 10.1 and
Works 10.2 respectively of the General Conditions, be paid bonus [upto
a limit of and at a rate of 50% of the relevant limit and rate of
delay damages prescribed in “Contract Data”. ”] as inserted in
the Contract (Data).
14.2 Advance Payment At the end of 3rd paragraph the following is added:
“A reputable bank” is a “Scheduled Bank” and “a financial
institution” includes “an Insurance Company” having at least AA
rating from PACRA/JCR.
The text of last line in paragraph-5, commencing from “as
follows” and Sub paras (a) and (b) are deleted.
The mode of payment of Advance and its repayment are given
inn the Contract Data”
14.8 Delayed Payment In the first paragraph, second line, the words “compounded
monthly” are deleted.
The text of 2nd paragraph is deleted and substituted with the
following:
“The Employer shall pay to the Contractor compensation at the
rate of KIBOR+2% for local currency and LIBOR+1% for
foreign currency per annum upon all sums unpaid within the
period specified in Sub-Clause 14.7 [Payment].”
14.15 Currencies of The word “and” at the end of Sub-Para (ii) of paragraph (a) is
Payment deleted and the word “and” at the end of Sub-Paragraph (iii) is
added.
The following paragraph is added after sub paragraph (iii):
(iv) In case of Provisional Sum Item, payment will be
made in the specified Contract currencies according to
the actual expenditure in Local and Foreign currencies.
15.2 Termination by Replace the text of sub-paragraph (d) with following:
Employer “subcontracts the whole or part of the Works or assigns the
whole or part of the Contract without required agreement and
consent of the Employer,”
At the end of first paragraph, add the following new sub-
paragraph (g):
(g) fails to achieve the work progress and lag in progress of
work from the programme submitted as per Sub-Clause 8.3.
In the second paragraph, second line, after the words ‘expel the
Contractor from the Site’, the following text is added:
“without thereby voiding the Contract, or releasing the
Contractor from any of its obligations or liabilities under the
Contract, or affecting the rights and powers conferred on the
Employer or the Engineer by the Contract”
In between the first and second paragraphs insert the following
paragraph:
“In case of Joint Venture each partner shall be required to
execute the Works in accordance with its JV share. In case of
finding or determination of any proxy JV partner (having
allowed use of his name for execution of Works to other
partners) the Employer shall be entitled to terminate the
Contract.”
15.4 Payment after The following text is added at the end of Sub-Clause 15.4(c):
Termination
The Employer shall be entitled to sell any of the Contractor’s
Equipment, Temporary Works and unused materials and apply
the proceeds of sale towards payment of any debt due from the
Contractor to the Employer under this Clause including any
outstanding payments to the sub-contractors.
16.1 Contractor’s In the first paragraph, fourth line, the period of notice of ‘21
Entitlement to days‘ is changed to “56 days”.
Suspend Work
16.2 Termination by The sub paragraph (h) of first paragraph and 3 rd paragraph are
Contractor deleted in its entirety.
17.4 Consequences of In sub paragraph (b), the text appearing in first to last lines
Employer’s Risks reading “In the case ----------also be included.” is deleted.
18.1 General In the 2nd paragraph, the text appearing in first and second lines
18.5 Insurance Company The Contractor shall be obliged to place all Insurances relating to
the Contract from Insurance Company, which is operating and
acceptable to the Employer. subject to compliance with NIC Act.
20 Claims, Disputes The text “Dispute Board” is replaced with “Adjudicator” and
and Arbitration “Dispute Board Decision” with “Adjudicator’s Decision” in
this Clause 20.
The Sub Clauses 20. 2 to 20.4 are replaced with the following:
20.4 Obtaining If a dispute (of any kind whatsoever) arises between the Parties
Adjudicator’s in connection with, or arising out of, the Contract or the
Decision execution of the Works, including any dispute as to any
certificate, determination, instruction, opinion or valuation of the
Engineer, either Party may refer the dispute in writing to the
Adjudicator for its decision, with copies to the other Party and
the Engineer. Such reference shall state that it is given under this
Sub-Clause.
Both Parties shall promptly make available to the Adjudicator all
such additional information, further access to the Site, and
appropriate facilities, as the Adjudicator may require for the
purposes of making a decision on such dispute. The Adjudicator
shall be deemed to be not acting as arbitrator.
Within 84 days after receiving such reference, or within such
other period as may be proposed by the Adjudicator and
approved by both Parties, the Adjudicator shall give its decision,
which shall be reasoned and shall state that it is given under this
Sub-Clause. The decision shall be binding on both Parties, who
shall promptly give effect to it unless and until it shall be revised
in an amicable settlement or an arbitral award as described
below. Unless the Contract has already been abandoned,
repudiated or terminated, the Contractor shall continue to
proceed with the Works in accordance with the Contract.
If either Party is dissatisfied with the Adjudicator’s decision,
then either Party may, within 28 days after receiving the
decision, give a Notice of Dissatisfaction to the other Party
indicating its dissatisfaction and intention to commence
arbitration. If the Adjudicator fails to give its decision within the
period of 84 days (or as otherwise approved) after receiving such
reference, then either Party may, within 28 days after this period
has expired, give a Notice of Dissatisfaction to the other Party.
In either event, this Notice of Dissatisfaction shall state that it is
given under this Sub-Clause, and shall set out the matter in
dispute and the reason(s) for dissatisfaction. Except as stated in
Sub-Clause 20.7 [Failure to Comply with Adjudicator’s
Decision] and Sub-Clause 20.8 [Expiry of Adjudicator’s
The Sub Clauses 20. 6 to 20.8 are replaced with the following:
20.6 Arbitration Any dispute between the Parties arising out of or in connection
with the Contract not settled amicably in accordance with Sub-
Clause 20.5 above and in respect of which the Adjudicator’s
decision (if any) has not become final and binding shall be
finally settled by arbitration, specified in the Contract Data.
20.7 Failure to Comply In the event that a Party fails to comply with a final and binding
with Adjudicator’s Adjudicator decision, then the other Party may, without
Decision prejudice to any other rights it may have, refer the failure itself
to arbitration under Sub-Clause 20.6 [Arbitration]. Sub-Clause
20.4 [Obtaining Adjudicator’s Decision] and Sub-Clause 20.5
[Amicable Settlement] shall not apply to this reference.
SPECIFICATIONS
SPECIAL PROVISIONS
SP-6 Drawings
[Note:
The above Sections of Spicification, are for guidance only, and shall be indicated appropriate
to the work/project.
The User may adopt the above format. However, if any section is not applicable, it may be
mentioned as “Not Used”. ]
SPECIFICATIONS
TECHNICAL PROVISIONS
DRAWINGS
Sr.
Documents
Nr.
13. Standard Form of Bidding Documents for Procurement of Works on BOT Basis
14. Standard Form of Bidding Documents for Operation and Maintenance Contracts