RG 1.160 r2 Maintennace
RG 1.160 r2 Maintennace
RG 1.160 r2 Maintennace
May 2012
Revision 3
REGULATORY GUIDE
OFFICE OF NUCLEAR REGULATORY RESEARCH
philosophy. Maintenance is also important to ensure that design assumptions and margins in the original
design basis are maintained and are not unacceptably degraded. Therefore, nuclear power plant
maintenance is important to protecting public health and safety.
In 10 CFR 50.65(a)(1), the NRC requires that power reactor licensees monitor the performance or
condition of SSCs against licensee-established goals in a manner sufficient to provide reasonable
assurance that such SSCs are capable of fulfilling their intended functions. Such goals are to be
established commensurate with safety and, where practical, take into account industrywide operating
experience. When the performance or condition of an SSC does not meet established goals, appropriate
corrective action must be taken. For a nuclear power plant for which the licensee has submitted the
certifications specified in 10 CFR 50.82(a)(1) (i.e., plants undergoing decommissioning),
10 CFR 50.65(a)(1) applies only to the extent that the licensee must monitor the performance or condition
of all SSCs associated with storing, controlling, and maintaining spent fuel in a safe condition, in a
manner sufficient to provide reasonable assurance that such SSCs are capable of fulfilling their intended
functions.1
In 10 CFR 50.65(a)(2), the NRC states that monitoring as specified in paragraph (a)(1) is not
required when it has been demonstrated that the performance or condition of an SSC is being effectively
controlled through the performance of appropriate preventive maintenance, such that the SSC remains
capable of performing its intended function.
In 10 CFR 50.65(a)(3), the NRC requires that performance and condition monitoring activities
and associated goals and preventive maintenance activities be evaluated at least every refueling cycle
provided the interval between evaluations does not exceed 24 months. The evaluations shall take into
account, where practical, industrywide operating experience. Adjustments shall be made where necessary
to ensure that the objective of preventing failures of SSCs through maintenance is appropriately balanced
against the objective of minimizing unavailability of SSCs due to monitoring or preventive maintenance.
In 10 CFR 50.65(a)(4), the NRC requires that before performing maintenance activities
(including but not limited to surveillances, postmaintenance testing, and corrective and preventive
maintenance), the licensee shall assess and manage the increase in risk that may result from the proposed
maintenance activities. The scope of the assessment may be limited to SSCs that a risk-informed
evaluation process has shown to be significant to public health and safety.2
In 10 CFR 50.65(b), the NRC states that the scope of the monitoring program specified in
10 CFR 50.65(a)(1) is to include safety-related and nonsafety-related SSCs as follows.
(1) Safety-related structures, systems, and components that are relied upon to remain
functional during and following design basis events to ensure the integrity of the
reactor coolant pressure boundary, the capability to shut down the reactor and
maintain it in a safe shutdown condition, or the capability to prevent or mitigate the
consequences of accidents that could result in potential offsite exposure comparable
to the guidelines in 50.34(a)(1), or 50.67(b)(2), or 100.11 of this chapter, as
applicable.3
The specific requirements for decommissioning plants became effective on August 28, 1996 (Ref. 4).
This paragraph (a)(4) of the maintenance rule was added on July 19, 1999 (Ref 5).
This paragraph (b)(l) of the maintenance rule was changed in the final rulemaking for Reactor Site Criteria Including
Seismic and Earthquake Engineering Criteria for Nuclear Power Plants (Ref. 6).
(2)
(ii)
Whose failure could prevent safety-related structures, systems,
and components from fulfilling their safety-related function; or
(iii)
Whose failure could cause a reactor scram or actuation of a
safety-related system.
In 10 CFR 50.65(c), the NRC states that licensees are to implement the rule provisions no later
than July 10, 1996.
The NRC issues regulatory guides to describe to the public methods that the staff considers
acceptable for use in implementing specific parts of the agencys regulations, to explain techniques that
the staff uses in evaluating specific problems or postulated accidents, and to provide guidance to
applicants. Regulatory guides are not substitutes for regulations and compliance with them is not
required.
This regulatory guide contains information collection requirements covered by 10 CFR Part 50
and 10 CFR Part 52 that the Office of Management and Budget (OMB) approved under OMB control
number 3150 0011 and 3150-0151, respectively. The NRC may neither conduct nor sponsor, and a
person is not required to respond to, an information collection request or requirement unless the
requesting document displays a currently valid OMB control number. This regulatory guide is a rule as
designated in the Congressional Review Act (5 U.S.C. 801-808). However, the NRC has determined this
regulatory guide is not a major rule as designated by the Congressional Review Act and has verified this
determination with the OMB.
The International Atomic Energy Agency (IAEA) has established a series of safety guides and
standards constituting a high level of safety for protecting people and the environment. IAEA safety
guides present international good practices and increasingly reflects best practices to help users striving to
achieve high levels of safety. Pertinent to this regulatory guide, IAEA Safety Guide NS-G-2.6,
Maintenance, Surveillance, and In-service Inspection in Nuclear Power Plants, issued October 2002,
provides guidance and recommendations on maintenance, surveillance and in-service inspection activities
to ensure that safety related SSCs are available to perform as designed. This regulatory guide
incorporates a similar philosophy to maintenance of nuclear power plants in the United States and its
guidelines are consistent with the basic safety principles provided in IAEA Safety Guide NS-G-2.6.
Page
A. INTRODUCTION .................................................................................................................................. 1
B. DISCUSSION ......................................................................................................................................... 5
Objective .......................................................................................................................................... 5
Development of Industry Guideline, NUMARC 93-01 ................................................................... 5
Definition of Maintenance ............................................................................................................... 6
Timeliness ........................................................................................................................................ 6
Plant, System, Train, and Component Monitoring Levels ............................................................... 6
Use of Existing Licensee Programs ................................................................................................. 7
Use of Reliability-Based Programs .................................................................................................. 7
Safety Significance Categories ........................................................................................................ 7
Safety-Significance Ranking Methodology ..................................................................................... 7
Use of Probabilistic Risk Assessments ............................................................................................ 7
Applicability of Appendix B to 10 CFR Part 50 .............................................................................. 8
Maintenance Risk Assessments ....................................................................................................... 8
Switchyard Maintenance Activities ................................................................................................. 8
Emergency Diesel Generators.......................................................................................................... 8
C. STAFF REGULATORY GUIDANCE ................................................................................................. 10
1. NUMARC 93-01 .................................................................................................................... 10
2. Consideration of Risk from Internal Fires in Maintenance Rule (a)(4) Activities ................. 14
3. Other Documents Referenced in NUMARC 93-01................................................................. 14
4. Inclusion of Electrical Distribution Equipment ....................................................................... 14
D. IMPLEMENTATION ........................................................................................................................... 14
REFERENCES ........................................................................................................................................... 17
B. DISCUSSION
Objective
The objective of 10 CFR 50.65 (referred to hereafter as the maintenance rule or the rule) is to
require monitoring of the overall continuing effectiveness of licensee maintenance programs to ensure
that (1) safety-related and certain nonsafety-related SSCs are capable of performing their intended
functions, and (2) for nonsafety-related equipment, failures will not occur that prevent the fulfillment of
safety-related functions, and failures resulting in scrams and unnecessary actuations of safety-related
systems are minimized.4 Additional objectives of the maintenance rule are to require that (1) licensees
assess the impact of equipment maintenance on the capability of the plant to perform key plant safety
functions, and (2) licensees use the results of the assessment before undertaking maintenance activities at
operating nuclear power plants to manage the increase in risk caused by those activities.5
failures to perform adequate assessments before maintenance activities. Partly because of these
inspection findings, the Commission approved an amendment to the maintenance rule, adding a new
paragraph (a)(4) to ensure that licensees assess and manage increases in risk associated with maintenance
activities.
In a series of public meetings, the NRC staff met with industry representatives to discuss the
change in the rule in relation to proposed revisions to Section 11, Assessment of Risk Resulting from
Performance of Maintenance Activities, of NUMARC 93-01 (Ref. 12). In May 2000, the NRC staff
issued Regulatory Guide 1.182, which endorsed the February 2000 revision to Section 11 of NUMARC
93-01.
From December 2009 to March 2011, the NRC staff met with industry representatives in a series
of public meetings to discuss additional revisions to NUMARC 93-01 that would improve
implementation of the maintenance rule throughout the industry. Revision 4A to NUMARC 93-01
resulted from those meetings.
Definition of Maintenance
As discussed in the Federal Register notice, Final Commission Policy Statement on
Maintenance at Nuclear Power Plants, dated March 23, 1988 (Ref. 13), maintenance is defined as the
aggregate of those functions required to preserve or restore safety, reliability, and availability of plant
SSCs. Maintenance includes not only activities traditionally associated with identifying and correcting
actual or potential degraded conditions (i.e., repair, surveillance, diagnostic examination, and preventive
measures) but extends to all supporting functions for the conduct of these activities.6 The activities that
form the basis of a maintenance program are also discussed in Final Commission Policy Statement on
Maintenance at Nuclear Power Plants.
Timeliness
NUMARC 93-01 states that activities such as cause determinations and moving SSCs from the
10 CFR 50.65(a)(2) to the (a)(1) category must be performed in a timely manner. Some licensees have
requested that the NRC staff specify a period that would be considered timely. To be consistent with
the intent of the maintenance rule to provide flexibility to licensees, the NRC staff does not consider
providing a specific timeliness criterion appropriate. Licensees should undertake and accomplish
activities associated with the maintenance rule in a manner commensurate with the safety significance of
the SSC and the complexity of the issue being addressed.
Emergency diesel generator unavailability values were also assumed in plant-specific individual
plant examination analyses. These values should be compared to the plant-specific emergency diesel
generator unavailability data regularly monitored and reported as industrywide plant performance
information. These values could also be used as the basis for a goal or performance criterion under the
maintenance rule. In addition, in accordance with 10 CFR 50.65(a)(3), licensees must periodically
balance the unavailability and reliability of the emergency diesel generators.
NUMARC 93-01
Revision 4A to NUMARC 93-01 (Ref. 1) provides methods that are acceptable to the NRC staff
for complying with the provisions of 10 CFR 50.65 with the following provisions and clarifications.
1.1
NUMARC 93-01 states that performance criteria for SSCs of high safety significance should be
established to ensure that reliability and availability assumptions used in the plant-specific safety analysis
are maintained or adjusted. NUMARC 93-01 further allows the use of maintenance-preventable
functional failures (MPFFs) as an indicator of reliability. The maintenance rule requires that the
performance of SSCs be monitored commensurate with safety; however, the maintenance rule does not
require that the assumptions in the safety analysis be validated. Licensees who choose to use their safety
analyses as described in NUMARC 93-01 must be able to demonstrate how the number of MPFFs
allowed per evaluation period is consistent with the assumptions in the risk analysis. For standby SSCs,
this would require, at a minimum, a reasonable estimate of the number of demands during that period.
If a licensee desires to establish a reliability performance criterion that is not consistent with the
assumptions used in the risk analysis, adequate technical justification for the performance criterion must
be provided. For some SSCs, an MPFF performance criterion may be too small to be effectively
monitored and trended as required by the rule. In these cases, the licensee should establish performance
or condition monitoring criteria that can be monitored and trended so that the licensee can demonstrate
that maintenance is effective.
1.2
Monitoring Structures
The maintenance rule does not treat structures differently from systems and components.
Experience with the rule and NUMARC 93-01 during the pilot site visits and the initial period following
the effective date of the rule indicated that specific guidance for monitoring the effectiveness of
maintenance for structures was needed, as structures present a different situation than do systems and
components. The primary difficulty in implementing the rule for structures using NUMARC 93-01 was
in establishing appropriate criteria for performance and monitoring structures under 10 CFR 50.65(a)(1)
instead of (a)(2).
The effectiveness of maintenance can be monitored by using performance criteria or goals, or by
condition monitoring. Although it is acceptable to use performance criteria or goals, most licensees have
found it more practical to use condition monitoring for structures. With certain exceptions (e.g., primary
containment), structures do not have unavailability, and rarely have demands placed on their safety
significant functions (e.g., maintain integrity under all relevant design basis events), which makes
reliability monitoring impractical.
In accordance with the rule, structural monitoring programs must provide reasonable assurance
that in scope structures are capable of fulfilling their intended functions. An acceptable structural
monitoring program for the purposes of the maintenance rule should have the attributes discussed in
Section 9.4.1.4 of NUMARC 93-01. Structures monitored in accordance with 10 CFR 50.65(a)(1) would
continue to be monitored until the degradation and its cause have been corrected. For these structures,
there would be additional degradation-specific condition monitoring and increased frequency of
assessments until the licensees corrective actions are completed and the licensee is assured that the
Rev. 3 of RG 1.160, Page 10
structure can fulfill its intended functions and will not degrade to the point that it cannot fulfill its design
basis.
Consistent with the intent of the rule, licensees should use their existing structural monitoring
programs (e.g., those required by other regulations or codes) to the maximum extent practical.
1.3
Definition of Standby
In NUMARC 93-01, standby SSCs of low safety significance must have SSC-specific
performance criteria or goals, similar to SSCs of high safety significance. NUMARC 93-01 provides a
definition of standby. Some licensees have improperly interpreted this definition to mean that SSCs that
are energized are normally operating. As stated in NUMARC 93-01, if the SSC performs its intended
function only when initiated by either an automatic or manual demand signal, the SSC is in standby.
Normally operating SSCs are those whose failure would be readily apparent (e.g., a pump failure
results in loss of flow that causes a trip). Standby SSCs are those whose failure would not become
apparent until the next demand, actuation, or surveillance. Only those SSCs of low safety significance
whose failure would be readily apparent (because they are normally operating) should be monitored by
plant-level criteria.
SSCs may have both normally operating and standby functions. To adequately monitor the
effectiveness of maintenance for the SSCs associated with standby functions, licensees should develop
SSC-specific performance criteria or goals, or condition monitoring.
1.4
1.4.1
Cause Determinations
For all SSCs that are being monitored using plant-level performance criteria (i.e., normally
operating SSCs of low safety significance), the NRC staffs position is that a cause determination should
be performed whenever any of these performance criteria are exceeded (i.e., failed) in order to determine
which SSC caused the criterion to be exceeded or whether the failure was a repetitive MPFF. As part of
the cause determination, it would also be necessary to determine whether the SSC was within the scope of
the maintenance rule and, if so, whether corrective action and monitoring (tracking, trending, goal setting)
under 10 CFR 50.65(a)(1) should be performed.
1.4.2
The maintenance rule requires that licensees monitor the effectiveness of maintenance for all
SSCs within the scope of the rule. NUMARC 93-01 allows licensees to monitor SSCs of low safety
significance with plant-level criteria. NUMARC 93-01 notes that some normally operating SSCs of low
safety significance cannot be practically monitored by plant-level criteria. Licensees should ensure that
the plant-level criteria established do effectively monitor the maintenance performance of the normally
operating SSCs of low safety significance, or they should establish SSC-specific performance criteria or
goals or use condition monitoring.
For example, a licensee determined that the rod position indication system and the spent fuel pool
pit cooling system were within the scope of the maintenance rule because they were safety-related at the
licensees site. None of the three plant-level performance criteria described in NUMARC 93-01
(unplanned scrams, unplanned capability loss factor, or unplanned safety system actuations) would
monitor the effectiveness of maintenance on these systems. Therefore, licensees should establish
additional plant-level performance criteria or system-specific performance criteria.
1.5
Clarification of Maintenance Preventable Functional Failures Related to Design
Deficiencies
The third paragraph of Section 9.4.5 of NUMARC 93-01 provides guidance on the licensees
options following a failure and on whether, as a result of the licensees corrective actions, subsequent
failures would be considered MPFFs. In particular, this paragraph addresses failures caused by design
deficiencies. Ideally, licensees would modify the design to eliminate the poorly designed equipment.
However, if the licensee determines that such an approach is not cost effective (e.g., the cost of
modification is prohibitive), the licensee has two options:
(1)
Replace or repair the failed equipment and adjust the preventive maintenance program as
necessary to prevent recurrence of the failure. Subsequent failures of the same type that are
caused by inadequate corrective or preventive maintenance would be MPFFs, and could be
repetitive MPFFs.
(2)
Perform an evaluation that demonstrates that the equipment can be run to failure (as described in
Section 9.3.3 of NUMARC 93-01). If the equipment can be run to failure, the licensee may
replace or repair the failed equipment, but adjustments to the preventive maintenance program are
not necessary and subsequent failures would not be MPFFs.
1.6
NUMARC 93-01 provides guidance to licensees on the scope of hazard groups to be considered
for the 10 CFR 50.65(a)(4)assessment provision during power operating conditions. Section 11.3.3 of
NUMARC 93-01 specifically considers internal events, internal floods, and internal fires for assessment.
Section 11.3.4.2 of NUMARC 93-01 also considers weather, external flooding, and other external impacts
if such conditions are imminent or have a high probability of occurring during the planned out-of-service
duration. The NRC staff considers these two sections of NUMARC 93-01 to encompass the scope of
hazards that licensees should consider during power operation in order to perform an adequate assessment
of the potential impact of risk that may result from proposed maintenance activities.
1.7
NUMARC 93-01 provides guidance to licensees on the scope of hazard groups to be considered
for the 10 CFR 50.65(a)(4) assessment provision during shutdown conditions. Section 11.3.6 of
NUMARC 93-01 specifically considers internal events for assessment as well as weather, external
flooding, and other external impacts if such conditions are imminent or have a high probability of
occurring during the planned out-of-service duration. The NRC staff considers this section of NUMARC
93-01 to encompass the scope of hazards that licensees should consider during shutdown conditions in
order to perform an adequate assessment of the potential impact of risk that may result from proposed
maintenance activities.
1.8
The last paragraph of Section 11.3.3.1 of NUMARC 93-01 states that some fire scenarios have no
success paths available. The NRC does not agree with this statement within its context in NUMARC 9301. Each plant is required by 10 CFR 50.48, Fire Protection to identify one train of safe-shutdown
capability free of fire damage, such that the plant can be safely shut down in the event of a fire. When
Rev. 3 of RG 1.160, Page 12
maintenance activities are conducted on the protected train, the staffs position is that licensees should
follow the guidance in Section 11.3.4.3 of NUMARC 93-01.
1.9
In Section 11.3.7.2 of NUMARC 93-01, the authors suggest the value 10-3/year as a ceiling for
configuration-specific core damage frequency. At this time, the NRC neither endorses nor disapproves of
the 10-3/year value.
1.10
In 10 CFR 50.65(a)(1), the NRC requires that goal setting and monitoring be established for all
SSCs within the scope of the rule except for those SSCs whose performance or condition is adequately
controlled through the performance of appropriate preventive maintenance as described in 10 CFR
50.65(a)(2). NUMARC 93-01 initially places all SSCs under 10 CFR 50.65(a)(2) and only moves them
to consideration under 10 CFR 50.65(a)(1) if experience indicates that the performance or condition is not
adequately controlled through preventive maintenance, as evidenced by the failure to meet a performance
criterion or by experiencing a repetitive MPFF. Therefore, the 10 CFR 50.65(a)(1) category could be
used as a tool to focus attention on those SSCs that need to be monitored more closely. It is possible that
no (or very few) SSCs would be handled under the requirements of 10 CFR 50.65(a)(1). However, the
rule does not require this approach. Licensees could also take the approach that all (or most) SSCs would
be handled under 10 CFR 50.65(a)(1) and none (or very few) would be considered under 10 CFR
50.65(a)(2). Licensees may take either approach.
During the pilot site visits, licensees asked whether the NRC would consider a large number of
SSCs monitored under 10 CFR 50.65(a)(1) as an indicator of poor maintenance performance. The NRC
staff assured the licensees that NRC management would not use the number of SSCs monitored under 10
CFR 50.65(a)(1) as an indicator of maintenance performance nor would it be used in determining the
systematic assessment of licensee performance grade in the maintenance area. The staff continues to
assert that the number of SSCs monitored under 10 CFR 50.65(a)(1) will not be used as an indicator of
licensee performance under the Reactor Oversight Process. The number of SSCs monitored under 10
CFR 50.65(a)(1) can vary greatly because of factors that have nothing to do with the quality of the
licensees maintenance activities. For example, two identical plants with equally effective maintenance
programs could have different numbers of SSCs monitored under 10 CFR 50.65(a)(1) because of
differences in the way system boundaries are defined (e.g., a system with three trains may be defined as
one system at one plant while the same system may be defined as three separate systems at an identical
plant) or because of differences in the way performance criteria are defined at the two plants (e.g., a
licensee that takes a very conservative approach to monitoring against the performance criteria would
have more SSCs in the 10 CFR 50.65(a)(1) category). The NRC staff also cautioned licensee managers
that they should not view the number of SSCs in the 10 CFR 50.65(a)(1) category as an indicator of
performance because that attitude might inhibit the licensees staff from monitoring an SSC under 10
CFR 50.65(a)(1) when a performance criterion has been exceeded or a repetitive MPFF has occurred. If
there is some doubt about whether a particular SSC should be monitored under 10 CFR 50.65(a)(1) or
(a)(2), the conservative approach would be to monitor the SSC under 10 CFR 50.65(a)(1).
1.11
Licensees may use methods other than those provided in Revision 4A to NUMARC 93-01 to
meet the requirements of the maintenance rule. The NRC will determine the acceptability of other
methods on a case-by-case basis.
Rev. 3 of RG 1.160, Page 13
1.12
NUMARC 93-01 contains references to the language in 10 CFR 50.65. These references are not
exact quotations of the regulations. Since the rule language has been updated (e.g., to include licensees
under 10 CFR 52), licensees should reference 10 CFR 50.65 for exact regulatory language.
2.
Previous versions of NUMARC 93-01 provided no guidance on how licensees should consider
the risk from internal fires in the conduct of maintenance rule (a)(4) activities unless these fires were
imminent or were considered to have a high probability of occurring during the planned out-of-service
duration. During public interactions, the staff and industry agreed that additional guidance was necessary
to adequately assess and manage the risk from internal fires in the conduct of activities required by 10
CFR 50.65(a)(4). Consequently, industry included guidance in Revision 4A to NUMARC 93-01, which
states methods licensees can use to identify equipment which is important to mitigation of risk of core
damage from fire initiators, describes approaches to developing and implementing appropriate risk
management actions, and discusses the tools for effective implementation of the guidance.
In developing this guidance, the industry evaluated and identified the specific efforts essential to
ensure effective implementation of the activities necessary to appropriately consider the risk from internal
fires in (a)(4) assessments. Specifically, industry identified a project plan and associated timeline for
piloting and implementing the guidance. This project plan identifies December 1, 2013 as the date by
which all licensees shall have fully implemented the changes necessary to effectively consider the risk
from internal fires in the conduct of maintenance rule (a)(4) activities. The staff has reviewed the project
plan and concluded that it is an acceptable approach for adequately considering the risk from internal fires
in maintenance rule (a)(4) activities. Licensees should consider the risk from internal fires upon
completion of the specific efforts necessary to ensure effective implementation of the industry guidance,
but no later than December 1, 2013.
3.
The NRCs endorsement of NUMARC 93-01 should not be considered an endorsement of other
documents referenced in NUMARC 93-01.
4.
The monitoring efforts under the maintenance rule, as defined in 10 CFR 50.65(b), encompass
those SSCs that directly and significantly affect plant operations, regardless of which organization
actually performs the maintenance activities. Maintenance activities that occur in the switchyard can
directly affect plant operations; as a result, electrical distribution equipment out to the first intertie with
the offsite distribution system (i.e., equipment in the switchyard) should be considered for inclusion as
defined in 10 CFR 50.65(b).
D. IMPLEMENTATION
The purpose of this section is to provide information on how applicants and licensees may use
this guide and information regarding the NRCs plans for using this regulatory guide. In addition, it
describes how the NRC staff complies with the Backfit Rule (10 CFR 50.109) and any applicable finality
provisions in 10 CFR Part 52.
NRC policies and procedures governing backfitting. Accordingly, the issuance of this regulatory guide
by the NRC staff is not considered backfitting, as defined in 10 CFR 50.109(a)(1), nor is it deemed to be
in conflict with any of the issue finality provisions in 10 CFR Part 52.
REFERENCES1
1.
2.
3.
Regulatory Guide, 1.182, Assessing and Managing Risk before Maintenance Activities at
Nuclear Power Plants, U.S. Nuclear Regulatory Commission, Washington, DC.
4.
5.
6.
61 FR 65157, Reactor Site Criteria Including Seismic and Earthquake Engineering Criteria for
Nuclear Power Plants, Federal Register, Volume 61, Number 239, p. 65157, Washington, DC,
December 11, 1996.
7.
8.
9.
NUREG-1526, Lessons Learned from Early Implementation of the Maintenance Rule at Nine
Nuclear Power Plants, U.S. Nuclear Regulatory Commission, Washington, DC, June 1995.
Publicly available NRC published documents are available electronically through the NRC Library on the NRCs
public Web site at: http://www.nrc.gov/reading-rm/doc-collections/. The documents can also be viewed on-line or
printed for a fee in the NRCs Public Document Room (PDR) at 11555 Rockville Pike, Rockville, MD; the mailing
address is USNRC PDR, Washington, DC 20555; telephone 301-415-4737 or (800) 397-4209; fax (301) 415-3548; and
e-mail pdr.resource@nrc.gov.
All Federal Register notices listed herein were issued by the NRC, and are available for inspection or copying for a fee
from the NRCs PDRoom at 11555 Rockville Pike, Rockville, MD; the PDRs mailing address is USNRC PDR,
Washington, DC 20555; telephone (301) 415-4737 or (800) 397-4209; fax (301) 415-3548; e-mail
pdr.resource@nrc.gov. Many are also available electronically through the Federal Register Main Page of the public
GPOAccess Web site, which the U.S. Government Printing Office maintains at
http://www.gpoaccess.gov/fr/index.html.
This document is available for inspection or copying for a fee in the NRC PDR at 11555 Rockville Pike, Rockville,
MD; the mailing address is USNRC PDR, Washington, DC 20555; telephone 301-415-4737 or (800) 397-4209; fax
(301) 415-3548; and e-mail pdr.resource@nrc.gov.
10.
11.
12.
13.
14.
15.
16.
Draft Regulatory Guide 1020, Monitoring the Effectiveness of Maintenance at Nuclear Power
Plants, U.S. Nuclear Regulatory Commission, Washington, DC, November 1992.
17.
Draft Regulatory Guide 1082, Assessing and Managing Risk before Maintenance at Nuclear
Power Plants, U.S. Nuclear Regulatory Commission, Washington, DC, December 1999.