Nothing Special   »   [go: up one dir, main page]

Tied Foundations-Portal Frame

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

Tied foundations - Design.

Introduction
Tied foundations are often adopted as a means of exploiting to advantage opposing forces. This
is achieved by linking them together via a tie or tie beam. The effect this has on the design is to
reduce the horizontal force requiring to be resisted by the ground (see Fig. 12.1 (a)).
The use of a tie can reduce the amount of movement likely to occur in developing the reaction
and reduce the cost of the foundation.

Fig. 12.1 Tied foundation.

Design decisions
In any situations where horizontal forces, such as thrusts from portal frames, etc., act in opposite
directions, consideration should be given to connecting the forces via a tie in order to reduce or
totally react a horizontal force. For example, if the forces are equal and opposite then the total
force can be reacted. On the other hand, if the forces are opposite and not equal, the smaller of
the two forces can be tied and the remainder left to be reacted by foundation 1 or, if a higher tie
force is used, foundation 2 can also be utilized, thereby reducing the force to be taken in passive

pressure (see Fig. 12.1 (b)).

Sizing the foundations


The main pad foundations are designed in the same way as those previously discussed in Chapter
11 but taking into account the tie force reaction in accordance with the above considerations. The
tie itself must be designed to resist the force H1 or H2, as the case may be, and must be detailed
to
transfer this force without excessive slip or failure between the bases of the stanchions.
This is usually achieved by designing a tie rod for the total force using appropriate permissible
tensile stresses for the steel and ensuring that suitable mechanical anchorage or bond anchorage
is achieved in the details between the stanchion and tie (see Fig. 12.2).
In detailing these ties, the detailer should ensure that the tie acts on the centreline of the
horizontal thrust force or that any eccentricity produced is designed into the foundation by the
designer. The tie rod itself could contain a turn-buckle for tensioning in order to reduce lateral
movement due to possible slackness in the rod, alternatively, if adjustment is not required, a
reinforced concrete tie beam as shown in Fig. 12.3 could be used. Care should be taken to
ensure axial tension across any connections which may be required in the tie by the use of turnbuckle or male/ female-type plate connectors. In the case of portal framed factories it is often
desirable to construct the oor slab after
erection and cladding of the building. In this case the engineer must ensure that all tie members
are constructed and covered prior to the erection of the steelwork, in order that the presence of
the tie members does not impede the construction process.

Fig. 12.2 Tie anchorage.

Fig. 12.3 Reinforced concrete tie beam.

You might also like