ABC and Standard Costing
ABC and Standard Costing
ABC and Standard Costing
P 88.64.
P123.64.
P135.00.
None of the responses are correct.
____
2. Refer to Smithson Company If total overhead is assigned to A and B on the basis of units
produced, Product B will have an overhead cost per unit of
a.
b.
c.
d.
P84.00.
P88.64.
P110.64.
None of the responses are correct.
____
3. Refer to Smithson Company If total overhead is assigned to A and B on the basis of direct
labor hours, Product A will have an overhead cost per unit of
a.
b.
c.
d.
P51.32.
P205.28.
P461.88.
None of the responses are correct.
____
4. Refer to Smithson Company If total overhead is assigned to A and B on the basis of direct
labor hours, Product B will have an overhead cost per unit of
a.
b.
c.
d.
P51.32.
P76.98.
P510.32.
None of the responses are correct.
____
5. Refer to Smithson Company If total overhead is assigned to A and B on the basis of
overhead activity hours used, the total product cost per unit assigned to Product A will be
a.
b.
P86.32.
P95.00.
c.
d.
P115.50.
None of the responses are correct.
____
6. Refer to Smithson Company If total overhead is assigned to A and B on the basis of
overhead activity hours used, the total product cost per unit assigned to Product B will be
a.
b.
c.
d.
P115.50.
P73.32.
P34.60.
None of the responses are correct.
Phelps Company
Phelps Company produces 50,000 units of Product Q and 6,000 units of Product Z during a period. In
that period, four set-ups were required for color changes. All units of Product Q are black, which is the
color in the process at the beginning of the period. A set-up was made for 1,000 blue units of Product
Z; a set-up was made for 4,500 red units of Product Z; a set-up was made for 500 green units of
Product Z. A set-up was then made to return the process to its standard black coloration and the units
of Product Q were run. Each set-up costs P500.
____
7. Refer to Phelps Company. If set-up cost is assigned on a volume basis for the department,
what is the approximate per-unit set-up cost for Product Z?
a.
b.
c.
d.
P.010.
P.036.
P.040.
None of the responses are correct.
____
8. Refer to Phelps Company. If set-up cost is assigned on a volume basis for the department,
what is the approximate per-unit set-up cost for the red units of Product Z?
a.
b.
c.
d.
P.036.
P.111.
P.250.
None of the responses are correct.
____
9. Refer to Phelps Company. Assume that Phelps Company has decided to allocate overhead
costs using levels of cost drivers. What would be the approximate per-unit set-up cost for the blue units
of Product Z?
a.
b.
c.
d.
P.04.
P.25.
P.50.
None of the responses are correct.
____ 10. Refer to Phelps Company. Assume that Phelps Company has decided to allocate overhead
costs using levels of cost drivers. What would be the approximate per-unit set-up cost for the green
units of Product Z?
a.
b.
c.
d.
P1.00.
P0.25.
P0.04.
None of the responses are correct.
Physical flow of
Costs
Driver Units
P50,000
1,000 accounts
Process deposits
36,000
400,000 deposits
Process withdrawals
15,000
200,000 withdrawals
Process loan
applications
27,000
900 applications
The above activities are used by the Jennings branch and the Crowley branch:
Jennings
Crowley
200
400
Deposits
40,000
20,000
Withdrawals
15,000
18,000
100
160
New accounts
Loan applications
____ 11. Refer to Lafayette Savings and Loan. What is the cost per driver unit for new account
activity?
a.
b.
c.
d.
P0.09
P0.075
P30.00
P50.00
____ 12. Refer to Lafayette Savings and Loan. What is the cost per driver unit for the deposit
activity?
a.
b.
c.
d.
P0.09
P0.075
P30.00
P50.00
____ 13. Refer to Lafayette Savings and Loan. What is the cost per driver unit for the withdrawal
activity?
a.
b.
c.
d.
P0.09
P0.075
P30.00
P50.00
____ 14. Refer to Lafayette Savings and Loan. What is the cost per driver unit for the loan
application activity?
a.
b.
c.
d.
P0.09
P0.075
P30.00
P50.00
____ 15. Refer to Lafayette Savings and Loan. How much of the loan application cost will be
assigned to the Jennings branch?
a.
b.
c.
d.
P3,000
P4,800
P7,800
P27,000
____ 16. Refer to Lafayette Savings and Loan. How much of the deposit cost will be assigned to the
Crowley branch?
a.
b.
c.
d.
P1,800
P3,600
P5,400
P36,000
____ 17. Refer to Lafayette Savings and Loan. How much of the new account cost will be assigned
to the Crowley branch?
a.
b.
c.
d.
P10,000
P20,000
P30,000
P50,000
Hazel Company uses activity-based costing. The company produces two products: coats and hats.
The annual production and sales volume of coats is 8,000 units and of hats is 6,000 units. There are
three activity cost pools with the following expected activities and estimated total costs:
Activity
Cost Pool
Activity 1
Activity 2
Activity 3
____
a.
Estimated
Cost
P20,000
P37,000
P91,200
Expected
Activity
Coats
100
800
800
Expected
Activity
Hats
400
200
3,000
Total
500
1,000
3,800
18. Refer to Hazel Company. Using ABC, the cost per unit of coats is approximately:
P2.40
b.
c.
d.
____
a.
b.
c.
d.
P3.90
P6.60
P10.59
19. Refer to Hazel Company. Using ABC, the cost per unit of hats is approximately:
P2.40
P3.90
P12.00
P15.90
Kan Co.
Kan Co. produces two products (A and B). Direct material and labor costs for Product A total P35 (which
reflects 4 direct labor hours); direct material and labor costs for Product B total P22 (which reflects 1.5
direct labor hours). Three overhead functions are needed for each product. Product A uses 2 hours of
Function 1 at P10 per hour, 1 hour of Function 2 at P7 per hour, and 6 hours of Function 3 at P18 per
hour. Product B uses 1, 8, and 1 hours of Functions 1, 2, and 3, respectively. Kan produces 800 units of
A and 8,000 units of B each period.
____ 20. Refer to Kan Co. If total overhead is assigned to A and B on the basis of units produced,
Product A will have an overhead cost per unit of
a.
b.
c.
d.
P 88.64.
P123.64.
P135.00.
none of the above.
____ 21. Refer to Kan Co. If total overhead is assigned to A and B on the basis of units produced,
Product B will have an overhead cost per unit of
a.
b.
c.
d.
P84.00.
P88.64.
P110.64.
none of the above.
____ 22. Refer to Kan Co. If total overhead is assigned to A and B on the basis of direct labor hours,
Product A will have an overhead cost per unit of
a.
b.
c.
d.
P51.32.
P205.28.
P461.88.
none of the above.
____ 23. Refer to Kan Co. If total overhead is assigned to A and B on the basis of direct labor hours,
Product B will have an overhead cost per unit of
a.
b.
P51.32.
P76.98.
c.
d.
P510.32.
none of the above.
____ 24. Refer to Kan Co. If total overhead is assigned to A and B on the basis of overhead activity
hours used, the total product cost per unit assigned to Product A will be
a.
b.
c.
d.
P86.32.
P95.00.
P115.50.
none of the above.
____ 25. Refer to Kan Co. If total overhead is assigned to A and B on the basis of overhead activity
hours used, the total product cost per unit assigned to Product B will be
a.
b.
c.
d.
P115.50.
P73.32.
P34.60.
none of the above.
JJ Corp.
JJ Corp. produces 50,000 units of Product Q and 6,000 units of Product Z during a period. In that period,
four set-ups were required for color changes. All units of Product Q are black, which is the color in the
process at the beginning of the period. A set-up was made for 1,000 blue units of Product Z; a set-up
was made for 4,500 red units of Product Z; a set-up was made for 500 green units of Product Z. A setup was then made to return the process to its standard black coloration and the units of Product Q
were run. Each set-up costs P500.
____ 26. Refer to JJ Corp. If set-up cost is assigned on a volume basis for the department, what is the
approximate per-unit set-up cost for Product Z?
a.
b.
c.
d.
P.010.
P.036.
P.040.
none of the above.
____ 27. Refer to JJ Corp. If set-up cost is assigned on a volume for the department, what is the
approximate per-unit set-up cost for the red units of Product Z?
a.
b.
c.
d.
P.036.
P.111.
P.250.
none of the above.
____ 28. Refer to JJ Corp. Assume that JJ Corp. has decided to allocate overhead costs using levels of
cost drivers. What would be the approximate per-unit set-up cost for the blue units of Product Z?
a.
b.
P.04.
P.25.
c.
d.
P.50.
none of the above.
____ 29. Refer to JJ Corp. Assume that JJ Corp. has decided to allocate overhead costs using levels of
cost drivers. What would be the approximate per-unit set-up cost for the green units of Product Z?
a. P1.00.
b. P0.25.
c. P0.04.
d. none of the above.
Kingston Company
The following July information is for Kingston Company:
Standards:
Material
Labor
Actual:
Production
Material
Labor
____ 30. Refer to Kingston Company. What is the material price variance (calculated at point of
purchase)?
a.
b.
c.
d.
____
a.
b.
c.
d.
____
a.
b.
c.
d.
____
P2,700
P2,700
P2,610
P2,610
U
F
F
U
F
F
U
U
U
F
U
F
a.
b.
c.
d.
P1,875 U
P938 U
P1,875 U
P1,125 U
Timothy Company
Timothy Company has the following information available for October when 3,500 units were produced
(round answers to the nearest peso).
Standards:
Material
Labor
Actual:
Material purchased
12,300 pounds @ P4.25
Material used
11,750 pounds
17,300 direct labor hours @ P10.20 per hour
____
a.
b.
c.
d.
____
a.
b.
c.
d.
F
F
U
U
F
U
U
F
____ 36. Refer to Timothy Company. What is the material price variance (based on quantity
purchased)?
a.
b.
c.
d.
____
a.
b.
c.
d.
P3,075
P2,938
P2,938
P3,075
U
U
F
F
____ 38. Refer to Timothy Company. Assume that the company computes the material price
variance on the basis of material issued to production. What is the total material variance?
a.
b.
c.
d.
P2,850
P5,188
P5,188
P2,850
U
U
F
F
Batt Manufacturing
The following March information is available for Batt Manufacturing Company when it produced 2,100
units:
Standard:
Material
Labor
Actual:
Material
Labor
____
a.
b.
c.
d.
____
a.
b.
c.
d.
____
a.
b.
c.
d.
____
a.
b.
c.
d.
U
F
U
F
F
F
U
U
Redd Co.
Redd Co. uses a standard cost system for its production process and applies overhead based on direct
labor hours. The following information is available for August when Redd made 4,500 units:
Standard:
Actual:
____
a.
b.
c.
d.
____
a.
b.
c.
d.
____
a.
b.
c.
d.
____
a.
b.
c.
d.
____
2.50
P1.75
P3.10
P21,875
P38,750
10,000
P26,250
P38,000
43. Refer to Redd Co. Using the one-variance approach, what is the total overhead variance?
P6,062.50
P3,625.00
P9,687.50
P6,562.50
U
U
U
U
44. Refer to Redd Co. Using the two-variance approach, what is the controllable variance?
P5,812.50
P5,812.50
P4,375.00
P4,375.00
U
F
U
F
45. Refer to Redd Co. Using the two-variance approach, what is the noncontrollable variance?
P3,125.00
P3,875.00
P3,875.00
P6,062.50
F
U
F
U
46. Refer to Redd Co. Using the three-variance approach, what is the spending variance?
P4,375 U
P3,625 F
P8,000 U
P15,750 U
47. Refer to Redd Co. Using the three-variance approach, what is the efficiency variance?
a.
b.
c.
d.
____
a.
b.
c.
d.
P9,937.50
P2,187.50
P2,187.50
P2,937.50
F
F
U
F
48. Refer to Redd Co. Using the three-variance approach, what is the volume variance?
P3,125.00
P3,875.00
P3,875.00
P6,062.50
F
F
U
U
____ 49. Refer to Redd Co. Using the four-variance approach, what is the variable overhead spending
variance?
a.
b.
c.
d.
P4,375.00
P4,375.00
P8,750.00
P6,562.50
U
F
U
U
____ 50. Refer to Redd Co. Using the four-variance approach, what is the variable overhead
efficiency variance?
a.
b.
c.
d.
P2,187.50
P9,937.50
P2,187.50
P2,937.50
U
F
F
F
____ 51. Refer to Redd Co. Using the four-variance approach, what is the fixed overhead spending
variance?
a.
b.
c.
d.
P7,000 U
P3,125 F
P750 U
P750 F
____ 52. Refer to Redd Co. Using the four-variance approach, what is the volume variance?
a. P3,125 F
b. P3,875 F
c. P6,063 U
d. P3,875 U
MULTIPLE CHOICE
1. A
Total Overhead
Product A
Function
Product B
Hourly
Rate
10
Hours
2
18
108
Totals
135
Hourly
Rate
10
Hours
1
10
Function
56
18
18
Totals
10
84
135
800
108,000
84
8000
672,000
Total OH
Proportion
Total
P 780,000
0.090909091
(800/8800)
780,000
Allocated
OH
Units
Produced
OH per
Unit
800
P 88.64
70,909.09
2. B
See #70 for Total Overhead Computations
P 780,000
PTS:
Allocated
OH
0.909090909
(8000/8800)
DIF:
3. B
Product
DL Hrs/Unit
Moderate
Total
Units
Produced
Proportion
20
OH/Unit
Total OH
Total
Units
OH per
Produce Unit
d
709,090.91
8000
P 88.64
OBJ:
5-3
Units Produced
800
1.5
8000
Total DL
Hours
3200
12000
15200
Total OH
P
Proportion
780,000
Allocated
OH
0.210526316 P
Units
Produced
164,210.53
OH per
Unit
800
205.28
(3,200/15,200)
4. B
See #72 for Direct Labor Computations
Total OH
P
Proportion
780,000
Allocated
OH
0.789473684
Units
Produced
615,789.47
OH per
Unit
8000
76.98
(12,000/15,200)
PTS:
DIF:
Moderate
5. C
Total OH
Proportion
P
780,000
0.082568807
OBJ:
Allocated
OH
P
64,403.67
5-3
Units
Produced
800
OH per
Unit
P 80.50
Units
Produced
OH per
Unit
DM and
DL/Unit
P
35.00
Total
P 115.50
(7,200/87,200)
6. D
Total OH
P 780,000
Proportion
Allocated
OH
0.917431193 P 715,596.33
(80,000/87,200)
7. B
Total setup cost: P500 4 = P2,000
P2,000/56,000 = P0.0357
8. A
Total setup cost: P500 4 = P2,000
P2,000/56,000 = P0.0357
9. C
Setup cost for blue units = P500.00
Number of blue units produced = 1,000
8000 P
89.44
DM and
DL/Unit
P
22.00
Total
P 111.44
P500/1,000 = P.50
10. A
Setup cost = P500.00
Units produced = 500
P500.00/500 = P1.00/unit
11. D
P50,000/1,000 = P50.00 per account
12. A
P36,000/400,000 = P0.09
13. B
P15,000/200,000 = P0.075
14. C
P27,000/900 = P30.00
15. A
P30.00 100 = P3,000
16. A
P0.09 * 20,000 = P1,800
17. B
400 * P50 = P20,000
18. C
Activity
Cost Allocation
1
2
3
6.60
19. D
Activity
Cost Allocation
1
2
3
15.90
20. A
21. B
22. B
23. B
24. C
25. A
26. B
27. B
28. C
29. A
30. A
31. D
32. C
33. B
34. B
35. A
36. D
37. A
38. C
39. B
40. C
41. B
42. D
43. C
44. A
45. B
46. C
47. B
48. C
49. C
50. C
51. D
52. D