FPM1300 Layout and Spacing
FPM1300 Layout and Spacing
FPM1300 Layout and Spacing
Abstract
This section discusses plant layout and facility and equipment spacing to minimize
the potential for fire to spread to adjacent facilities. Figure 1300-1 and 1300-2 at the
end of this section offer guidelines for plant-to-plant and plant-to-equipment
spacing.
This section covers layout and spacing requirements for process plants. Requirements for other types of facilities are covered in Sections 3100 to 4100. Drainage is
discussed in Section 1400. Location and protection of critical controls are discussed
in Section 1700. Tank spacing is discussed in the Tank Manual.
Contents
Page
1300-3
1311 General
1312 Legal Requirements
1313 Design for Local Conditions
1314 Layout Objectives
1315 Block Layout and Roads
1316 Drainage
1320 Plant Spacing
1300-6
1300-9
Chevron Corporation
1300-1
January 1997
January 1997
1300-11
1300-11
1360 References
1300-12
1300-2
Chevron Corporation
Chevron Corporation
1300-3
January 1997
Separation of Facilities
Protect Company personnel and equipment by separating independent elements,
such as process units, storage tanks, and control houses. This helps to prevent fire,
explosions, radiant heat, spills, etc. in one element from significantly affecting adjacent elements.
Meteorological Conditions
Consider general climatic, meteorological, and related conditions such as direction
of prevailing winds, maximum storm wind velocities, frequency of thunderstorms,
maximum and minimum temperatures, and the occurrence of earthquakes.
January 1997
1300-4
Chevron Corporation
PIM-EF-580
PIM-EF-883
Security
Plant location and degree of public access may indicate that plant borders and
entrances should be supervised and protected.
Evacuation
Evacuation routes should take into account the location of potential releases,
prevailing winds, drainage patterns, etc.
Chevron Corporation
1300-5
January 1997
Restricted roads should not be used for routine plant travel of operations and maintenance vehicles.
Traffic on restricted roads can be closely controlled by installing barriers and signs
at the entrance to the facility, and by requiring procedures such as hot work permits
for vehicles that must enter the facilities. This usually requires that the operators
test for combustibles in the area prior to vehicular entry.
Unrestricted roads are those roads located more than 25 feet from release sources.
They do not require traffic control.
1316 Drainage
In process units, area drainage prevents spills from accumulating under vessels or
piping. Drainage design requirements are described in the Civil and Structural
Manual, Section 500, and in Section 1400 of this manual. Firefighting water
requirements are determined by the size of fire that could occur and the fire control
techniques and equipment likely to be used.
Plant to plant
Plant to property line
Plant to equipment
Equipment to equipment
These guidelines have been developed through Company experience and industry
standards. Where special circumstances allow less spacing, the facility or project
team should document the rationale and mitigation efforts. Following are examples
for using the spacing tables.
Figures 1300-1 and 1300-2 are foldouts located at the end of this section.
Refer to Figure 1300-1, sheet 1 for your situation. Sheet 1 gives the codes to use on
sheet 2 to locate the minimum spacing.
Example: Spacing of control house to high pressure plant.
From Figure 1300-1, sheet 1, the code is B13. B on the diagonal and 13 on the horizontal gives you 50 feet accompanied by Note 16.
January 1997
1300-6
Chevron Corporation
Spacing between process units is based on the estimated hazard of one or both facilities.
Once the overall risk is agreed upon, it is important to determine what effect a fire
or explosion would have on the surroundings. This effect is a function of the degree
of explosive violence possible in the process and/or the rate of flow, total volume,
volatility, temperature, and toxicity of the liquid or vapors that might be accidentally released. This determination should further help to establish the justified
spacing between units.
Close spacing of operating units permits shorter runs of transfer pipe, more centralization of plant control, and more compact electrical supply systems. Close spacing
Chevron Corporation
1300-7
January 1997
minimizes surge between plants and has other tangible economic benefits.
However, close spacing increases the likelihood of fire spreading between units,
increases the problems of major maintenance work, and may hamper firefighting
activities.
Each foot of separation costs money, and there is a point at which additional separation may increase the fire hazard, especially if control is highly automated and
centralized. Leaks may go undetected and operators may be restricted in their
visual observation of the unit.
In general, spacing between major process units should not be less than 75 feet
between equipment setback lines. Spacing greater than 200 feet, except for specialized operations such as emergency high capacity flare systems, provides little
decrease in risk and may actually increase the overall hazard.
It is acceptable for an overhead or grade-level pipe rack to cross a segregation space
transversely. A pipe rack may also be routed longitudinally along a segregation
space, provided that it does not occupy the full width. At least 20 feet (6 meters) of
the segregation space should be left clear of the pipe rack as a firebreak and to
permit fire fighting access.
The likelihood of future expansion of any major process unit should be considered
in the spacing layout. The minimum spacing between units should not be viewed as
a location for possible unit expansion.
January 1997
1300-8
Chevron Corporation
Keep fired equipment away from equipment and portions of the plant where a flammable vapor release might occur. Where possible, locate furnaces on the outside
edge of plants, upwind of other equipment.
General spacing recommendations are shown in Figure 1300-2.
Chevron Corporation
1300-9
January 1997
Locate pumps at least 25 feet from furnaces; both are sources of ignition
should a pump leak occur.
Locate pumps along the outer edge of the plot limit, outboard of columns and
vessels, and with no equipment installed overhead. If it is necessary to locate
such pumps alongside in-plant overhead pipeways, the process ends should be
10 feet outside the extremities of the overhead pipeway. Where desirable to
further reduce risk of fire loss, a pump may be separated from its spare by
another pump or by increased spacing.
You should discuss any exceptions to these guidelines with the CRTC Fire &
Process Safety Team.
January 1997
Spacing between the control house and process equipment (See Figure 1300-1).
1300-10
Chevron Corporation
Where vents and relief valves are piped to a closed system, locate the relief
line away from fire hazardous equipment. If it is located onplot, it should be
properly supported or have fireproofed supports.
Place instruments, instrument leads, and critical power cables out of the fire
hazard area. If this is not possible, protect them or place them underground as
discussed in Section 1700.
Chevron Corporation
Stage 1 of the study will identify each building at the facility, verify potential
hazards, and screen out buildings based on occupancy levels and function
during an emergency.
During Stage 2, the buildings that met the previous screening criteria are evaluated with consequence modeling for vapor cloud explosion and toxic release
1300-11
January 1997
hazards; and they are evaluated against current Company design standards for
fire hazards. If the team determines that a building(s) has a sufficient hazard,
then a Stage 3 is justified.
During the Stage 3, the study team identifies and analyzes the frequency of
potential scenarios either qualitatively or quantitatively. Recommendations are
then developed to mitigate the risks where appropriate. This is the final evaluation step in the API RP 752 facility siting assessment methodology. Specific
guidance and criteria for such a study are in CRTC's "Building Siting Assessment: Supplemental Guidelines for API RP 752", and is included in Appendix
H of this manual.
1360 References
American Petroleum Industry (API)
API 500
API 2510
API RP 752
Chevron References
Civil and Structural Manual
Electrical Manual
Tank Manual
January 1997
NFPA 30
NFPA 50A
NFPA 58
NFPA 59
1300-12
Chevron Corporation
Chevron Corporation
1300-13
January 1997
Chevron Corporation
1300-15
January 1997
Chevron Corporation
1300-17
January 1997