CPIM ECO Sample Test
CPIM ECO Sample Test
CPIM ECO Sample Test
1. What is the time for the production of a lot of Part A when the information of this calculation are as
the follows ?
2. Using the routing information of order A, when is appropriate for the working start date of operation 20
?
Total Clock Hours : 480 hours. Planned Labor Hours : 420 hours.
5. A work center, which has two machines, are given 400 hours for a specific customer order at the last
month. In the operation process, the following information are collected.
Preventive maintenance = 60 Hrs.
Absenteeism = 25 Hrs.
Late tools = 15 Hrs.
Active standard hours = 270 Hrs.
Hours of work per week = 40 Hours.
When jobs and each priority of the next period are as the follows, which jobs are possible to complete ?
1. Job M : 17 Hrs. 2. Job N : 9 Hrs. 3. Job O : 14 Hrs. 4. Job P : 14 Hrs.
5. Job Q : 21 Hrs.
A. M, N B. M, N, O C. M, N, O, P D. M, N, O, P, Q
6. In the above workcenter, what is the efficiency of the next week ?
A. 72% B. 75% C. 80% D. 90%
7. A company has 500 units of week demand and 8 days of transit lead time. In case of the product
price for this demand is $25 and carrying cost rate is 20%, how much cost reduction is expected when
decreasing transit lead time from 8 days to 5 days ?
A. $900 B. $1500 C. $7500 D. $12500
8. When using the below information, calculate the rated capacity if increasing 10% of the productivity.
No. of machines : 10.
No of shifts : 2.
Workers per shift : 1 shift - 8 workers. 2 shift - 5 workers.
Utilization = 80%.
Efficiency = 90%.
Working hours per week = 40 hours.
9. Which of the following technique can contribute to intensify visual control for a specific workcenter ?
A. Flexible workforce. B. Workplace organization.
C. Quality function deployment. D. Taguchi method.
A. , B. C. , , D. , , ,
: Execution & Control of Operation.
11. Which of the following is likely to most appropriate practice for WIP inventory accuracy ?
A. Increasing MRP system frequency. B. Inventory cycle counting.
C. Implementation of data redundancy system for only WIP. D. Daily reporting.
13. PLUSSTAR , power supply production company, has two product lines. One is made to contribute
part fabrication and another is used to assemble parts, but now the company have some problems for
second line - excess inventory and part shortage. Which of the following measures is the BEST choice for
improving this line ?
A. Delivery speed. B. Piece fill rate.
C. Revenue fill rate. D. Delivery to schedule.
14. If gateway work center is overloaded, what should be done for next operation by controller ?
A. Lot split. B. Line balance. C. Load leveling. D. Overlapping.
15. In general, statistical process control(SPC) is most useful to control quality. Which of the following
environment is likely to the most challenge of this technique ?
A. Intermittent. B. Repetitive flow.
C. Build-to-forecasting. D. Continuous flow.
16. is used to effectively control inventory transaction costs when organizing demand based
focused factory.
A. Backflushing system. B. Pre-deducted system.
C. Cycle counting system. D. Kanban.
17. If efficiency of a workcenter have just improved from 80% to 90% and other parameter affecting
workcenter capacity are the same, what is input having same queue ? (assuming the prior input is 680
units.)
A. 680 units. B. 725 units. C. 765 units. D. 785 units.
19. Among problem solving techniques, "Priority" is the closest relationship with
A. Brainstorming. B. Control Chart. C. PDPC. D. Pareto Chart.
A. , B. , C. , D.
23. All of the following result from long-term commitment between supplier and customer EXCEPT
A. Single source. B. Multiple source. C. Point of use. D. Empty bin.
: Execution & Control of Operation.
24. The process of work are sequential and processing time are 10 seconds, 30 seconds, 20 seconds, 40
seconds, 30 seconds, 20 seconds respectively. When the required production rate is one unit per minute,
How much workers are needed ?
A. 1 person. B. 2 person. C. 3 person. D. 6 person.
25. When a company select backflusing as inventory control system, a company have some problems
concerning to
A. Inventory accuracy. B. Staging and kitting.
C. Incoming inspection. D. Transaction cost.
27. All of the following concepts and techniques are included by Taguchi method EXCEPT :
A. Process variation. B. Tolerance Design.
C. Design of experiment. D. Quality loss function.
28. Among product costing techniques, which of the following require outputs during predetermined period
instead of investigating each activity of production ?
A. Job order costing. B. Process costing.
C. Activity-based costing. D. Throughput costing.
A. B. C. , D. ,
30. Velocity costing :
A. Use to lead time for allocating overhead costs. B. Is as the same as variable costing.
C. Use to labor hour for allocating overhead costs. D. Is avoidable cost.
32. Which of the following should be increased for reducing run time in the labor intensive workcenter ?
A. Efficiency. B. Utilization. C. Capacity. D. Throughput.
33. All of the following are used for determining no. of kanbans EXCEPT
A. Daily use. B. Lead time. C. Container size. D. Bill of materials.
34. What is the throughput time for producing 100 units in the below workcenter ?
36. When overhead costs are calculated as 200% of setup cost, calculate overhead cost using the
following information.
Setup cost : $10 per 1.5 setup time.
Setup time : 4.5 hours.
Efficiency : 33%.
37. Which of the following is (are) actual input source(s) in input/output control ?
. Planned order.
. Released order.
. Master production schedule.
. Dispatching.
A. B. , , C. D. ,
38. All of the following practices are appropriate for increasing capacity EXCEPT :
A. Overtime. B. Lot splits. C. Machine purchasing. D. Shifts increasing.
39. When performing cost variance analysis, which of the following affect on differences between planned
cost and actual cost ?
. Queue.
. Staging.
. Efficiency.
. Scrap.
A. B. , , C. , D. ,
40. In a firm using customer ordering system, customer orders are released once a week and average
throughput lead time are 2.5 weeks. What is the average delivery lead time in this firm ?
A. 2.5 week. B. 3 week. C. 3.5 week. D. Unknown.
41. Which of the following is closely related to overlapping ?
A. Capacity requirement planning. B. Input/output control.
C. Priority control. D. Preventive maintenance.
42. When increasing tolerance limits from ± 0.2 to ± 0.5, ultimately we can expect this results in :
A. Defectives are reduced, while process capability is increased.
B. Defectives are reduced, while process capability is decreased.
C. Defectives are enlarged, while process capability is increased.
D. Defectives are enlarged, while process capability is decreased.
44. Which of the following can be NOT accepted as the concept of backflushing ?
A. Facilitates the reduction of counting points.
B. Deduct the parent items when the components are produced.
C. Will be executed when assemblies are produced.
D. Use the bill of material of assembly item.
A. B. , C. , D. , ,
: Execution & Control of Operation.
47. Which of the following production systems have the closest relationship with synchronous production ?
. Just-in-Time.
. Pull system.
. Push system.
. Project production.
A. B. , C. , , D. , , ,
48. Which of the following is TRUE about calculating move time of MLT ?
A. It uses average time among workcenters.
B. It's calculation is engineering responsibility.
C. It is based on each workcenter queue time.
D. It is dependent on the distance between workcenters.
50. Due date information of shop order are storage in which of the following base ?
A. Job order file. B. Work ticket. C. Item master file. D. Routing file.
51. Which of the following actions is MOST likely to produce a high degree of sustained inventory data
integrity ?
A. Increasing frequency of cycle counts. B. Changing cycle counting methods periodically.
C. Making periodic physical inventories. D. Resolving problems exposed by cycle counting.
52. Which of the following BEST describes the results of total quality control ?
A. Statistical tests of production identify sources of defects.
B. The number of inspection stations is decreased in the production process.
C. The product is made right the first time.
D. The cost of scrap and rework is below budget.
54. In Plant X, flow of purchased parts is from receipt at dock to receiving/inspection to receipt at In the
MRP system, inventory on hand is increased when material is received at stores. Which of the following
are true about this situation ?
. A supplier delivery performance measurement should be based on actual receipts at dock versus
schedule.
. Purchase orders should be closed when all parts are received at stores.
. A resource constraint could cause parts to be received at the dock but not into the stores on
schedule.
A. I and II only B. I and III only C. II and III only D. I, II, and III
58. Inventory control can be improved by adopting which of the following storeroom practices?
. Calculating EOQs to determine quantities to issue
. Initiating a cycle-counting system
. Making the storeroom off-limits to all except storeroom personnel
. Maintaining parallel record systems to cross-check balances
A. I and II only B. II and III only C. III and IV only D. I, III, and IV only
59. The most significant factor affecting the difference between planned lead time and actual lead time for
a specific order or batch in a shop is
A. Priority B. Capacity C. Queues D. Component availability
63. When allocated on the basis of historical direct labor hours, overhead will be properly absorbed if
which of the following is TRUE ?
A. Total volume increases. B. Total volume decreases.
C. Total volume remains unchanged. D. Fixed costs decrease.
64. Pareto analysis is included in training so that employees may use it to identify which of the following?
A. The most frequently occurring defects. B. Out-of-control operations.
C. The customer base for marketing. D. The volume of work through the plant.
65. Under the group technology concept, which of the following is TRUE ?
A. Like machines should be grouped in clusters.
B. Machines should be grouped to produce parts of similar form.
C. Tape controlled machines are required.
D. Manufacturing departments should be laid out according to function.
: Execution & Control of Operation.
66. When expediting purchased parts that are needed from the supplier before the original due date, a
buyer should first try to do which of the following ?
A. Buy all the parts from an alternate source.
B. Offer to de-expedite another part that is needed later than the original due date.
C. Offer to pay a premium.
D. Increase safety lead time by one week.
67. Which of the following systems would be most appropriate for managing an inventory of solenoids
purchased by an appliance manufacturer for use in the assembly of several models of an automatic
dishwasher ?
A. Two-bin replenishment system.
B. MRP system.
C. Fixed order quantity, EOQ, reorder point system.
D. Fixed interval, periodic ordering system.
68. The value of work-in-process inventory is LEAST affected by which of the following?
A. Process time. B. Lot sizing. C. Queue time. D. MRP processing frequency.
69. In environments using backflush inventory relief, perpetual on-hand inventory counts are relieved when
A. Planned orders for the parent items are created by MRP.
B. A work order for the parent item is generated.
C. Production against the parent item is reported.
D. The parent item is shipped to a customer.
70. U-shaped cells that group dissimilar machines to perform various operations on a part result in
reduction of all of the following EXCEPT
A. Travel distances. B. Machine downtime. C. In-process inventory. D. Lead times.
71. Customer-oriented manufacturing performance measures include all of the following EXCEPT
A. Service parts availability. B. Cost variances.
C. Product quality. D. Delivery responsiveness.
74. In the implementation of Just-in-Time, which of the following is the MOST significant change for the
accounting function ?
A. Cellular processes no longer report every operation to accounting.
B. Budgeted scrap and rework costs that create variances are reduced.
C. Physical inventory of work-in-process inventory is more time-consuming.
D. Costs of incentive programs increase.
75. Under full absorption costing, overhead costs would be handled by which of the following methods ?
A. They would be subtracted from the variable margin for a net profit.
B. They would not be allocated to individual products.
C. They would be allocated to each product based on the overhead burden rate.
D. None of the above.
: Execution & Control of Operation.
Solution :