ECN-OP-PRP-00079 Process Control of Safety Critical Valves Blinds Procedure
ECN-OP-PRP-00079 Process Control of Safety Critical Valves Blinds Procedure
ECN-OP-PRP-00079 Process Control of Safety Critical Valves Blinds Procedure
tro
on
nc
C
op
y
ECN-OP-PRP-00079
Table of Contents
2
1.0
Purpose
2.0
Scope
3.0
4.0
5.0
Control
5.1 OOP Control and Risk Assessment
5.2 Valve Identity
5.3 Key Transfer
5.4 Anomalies
5.5 OOP Process and Risk Assessment
6.0
7.0
Reference Documentation
10
8.0
Abbreviations
10
on
tro
lle
C
op
y
Distribution List
6
6
6
6
6
7
8
8
8
9
11
12
13
nc
4
4
4
4
5
Note: Details of the amendment history of this document are maintained and available in the
Document Management System.
Page 1 of 13
Uncontrolled if printed.
ECN-OP-PRP-00079
Distribution List
Location
01
Nexen House
nc
on
tro
lle
C
op
y
Copy
Page 2 of 13
Uncontrolled if printed.
1.0
ECN-OP-PRP-00079
Purpose
The purpose of this procedure is to set out the requirements for control of all safety critical
valves and blinds.
2.0
Scope
C
op
y
The valves are of the manual type which, under normal circumstances, remains either
open or closed, otherwise, they might create a safety hazard. This includes valves fitted
with a key-operated interlock device.
Typical examples are:
Upstream and downstream manual isolation valves for Pressure Safety Valves (PSVs)
Downstream isolation valves for all PSVs. Status is Locked Open (LO), one to provide
a relief flow path if the PSV is online, but also due to the fact that pressure rating
specification change occurs immediately downstream of the PSV
Blowdown valves downstream isolation valves.
blowdown flow path
lle
Spectacle blinds at drain points on high pressure systems, where a specification break
occurs downstream of a spectacle blind
Implementation of the procedure will ensure that the design integrity of the Installation is
maintained at all times and is not compromised in any way.
tro
3.0
on
The basis of this procedure is maintaining a live Valve Status Register showing the
status of valves and spectacle blinds.
nc
The Register is retained in the Scott Central Control Room (CCR)/Buzzard Main Control
Room (MCR). The individual Master Control Sheets are available via the Company
electronic document management system.
Page 3 of 13
Uncontrolled if printed.
4.0
4.1
ECN-OP-PRP-00079
C
op
y
Production Supervisor
lle
4.2
tro
Delegating his authority to the Production Lead Technician (PLT)to release operational
interlock keys and change over a PSV in a system where there are both duty and
standby valves
PLT and ensuring
on
Maintaining the Register of OOPs (both current and historical) and numbering new
issues. Archiving completed OOPs for 6 months from completion of work
nc
4.3
Page 4 of 13
Uncontrolled if printed.
ECN-OP-PRP-00079
Ensuring that the operational compliance checks for valves and blinds are carried out,
as described in Paragraph 6.0 Compliance and Assurance, and updating the
installation Compliance Record
Using the Register of valves and blinds to determine when the position of an
anomalous valve or blind was changed, and by whom
Verifying that the movement of any valves and blinds is correctly recorded on the OOP
Authorisation Form
4.4
Production Technicians
Operations Technicians are responsible for:
C
op
y
Issuing and accepting operational interlock keys to and from the Production Technician
and recording the transfer in the sign-in/sign-out log book. Note that authority only
exists for operational keys, as master keys are controlled by the PS
Ensuring that P&IDs are used at the planning stage to identify valves and blinds that
need to be repositioned and using this information to complete the first part of an OOP
Authorisation Form
lle
tro
Ensuring that an OOP Authorisation Form is obtained before moving a valve or blind
Recording the movement of any valve or blind in the Register
on
Accepting from, and returning operational interlock keys to, the PLT and recording the
transfers by signing the sign-in/sign-out log book
nc
As a result of engineering changes resulting in the creation of a new P&ID and associated
Register control sheet, ensuring that in addition to the above, the PS is requested to add
the sheet to the compliance checking programme.
Page 5 of 13
Uncontrolled if printed.
5.0
ECN-OP-PRP-00079
Control
The essential aspects of the control procedure are graphically presented in Figure 2.
5.1
5.2
C
op
y
The PLT and the Production Technician who is to manipulate the valve or change the
position of a blind must comply with the above requirement.
Valve Identity
All valves must have a tag attached. The tag will clearly identify the status of the valve ie
locked open or locked closed.
Key Transfer
lle
5.3
tro
Where the operation of a valve involves the use of an interlock key, the operational
interlock key will be released to the Production Technician by the PLT and recorded in the
sign-in/sign-out log book under both their signatures. The return of the interlock key to the
PLT will also be recorded in the sign-in/sign-out log book under their signatures.
on
Use of a Master interlock key can only be approved by the PS after carrying out a suitable
and sufficient risk assessment and an OOP Authorisation Form. The PS will then release
the key to the PLT and the transfer will be entered in the sign-in/sign-out log book under
both their signatures. The return of the master interlock key will similarly be recorded in
the sign-in/sign-out log book under both signatures.
nc
5.4
Anomalies
Where a valve or blind is found to be in the incorrect position and cannot be identified by an
OOP Authorisation Form and an entry on the control sheet within the Register, the
Production Technician who discovers the situation will immediately bring it to the attention
of the PLT.
After a suitable and sufficient risk assessment has been carried out by the PLT, PS and
OIM, the Production Technician will return the valve or blind to its correct position then tag
and secure it.
Page 6 of 13
Uncontrolled if printed.
ECN-OP-PRP-00079
The PLT will try to determine when the position of the valve or blind was changed, and by
whom. The PLT will inform the PS of the anomaly and discussion will be held between
the OIM and PS to determine any further action required.
5.5
C
op
y
The PS will review the OOP request and carry out suitable and sufficient risk assessment.
At this point, the PS will answer the four questions covered within section 3 of the form.
System in which LO/LC points are contained does not constitute an HP/LP interface at the
LO/LC point? If the LO/LC valve is an HP/LP interface then a HAZAN must be completed.
Integrity of system boundary (isolation) in which LO/LC points are contained has been/will
be proven by pressure build up test? Although the plant may be isolated, the isolation
must be proved to ensure that no pressure ingress can occur. If integrity of isolation
cannot be proved or does not meet the criteria given by the fluid ranking table, then a
HAZAN must be carried out.
lle
All sources of internal energy, if applicable (compressors/pumps etc) will be isolated prior
to movement of LO/LC points? If sources of pressure are not isolated then a HAZAN
must be carried out.
tro
Sources of external pressure will not be introduced whilst LO/LC devices are out of
position? This applies to pressure testing etc where overpressure protection may not
exist or the spec blind may be open exposing lower rated pipe to system pressure. If the
above criteria cannot be achieved then a HAZAN must be carried out.
on
Only if the answer to ALL four questions above is YES, thus assuring that risks are As
Low As Reasonably Practicable (ALARP), may the PS proceed without the requirement to
carry out a more formal risk assessment using a HAZAN.
An ESSoW Isolation Control Certificate (ICC) shall accompany ALL LO/LC valve
movements and identify each LO/LC valve.
nc
In circumstances where the associated isolation is considered not to meet with company
standard, a HAZAN shall be carried out and the appropriate checkbox in the ICC checked
NO. This ICC HAZAN shall be the required OOP HAZAN if the answer to any of the
above four questions is NO.
If a HAZAN is required, a HAZAN Team will be formed. Only if risks are deemed ALARP
will work be permitted to proceed.
Each OOP Authorisation form has a unique reference number.When LO/LC valves are
returned to normal position, collect all copies of the forms and retain the original in the
folder in the Production Supervisors office.
The PLT will then discuss the work with the Production Technician(s) and the team will
implement any control measures specified.
Page 7 of 13
Uncontrolled if printed.
ECN-OP-PRP-00079
The PLT will then initial the control sheet to verify that it is permitted to move the
valves/blinds to an out-of-normal position. The original copy of the authorised OOP Form
shall be inserted into the front of the Register. The second (blue) copy of the OOP form
shall be held by the OIM for the duration of the OOP movement and the third (pink) copy
held with the ICC in the isolation lock out box.
The Production Technician then signs the control sheet to confirm the valve has been
physically moved OOP.
C
op
y
On completion of the work and after the valves and/or blinds have been returned to the
normal operating position, the Production Technician will initial the control sheet and
request verification by the PLT who will then initial the sheet to verify.
When all LO/LC valves are returned to their normal operating positions all copies of the
OOP form shall be collected and signed off by the PS. The completed OOP form shall
then be archived.
6.0
6.1
Compliance Checking
lle
The physical checking of valves and blinds will be carried out in accordance with a rolling
compliance checking schedule. The programme will schedule checks of different control
sheets each week thereby ensuring that the entire system is physically checked at least
once a year.
tro
Each week number shall be defined within a compliance checking programme (Ref 3).
The PS is responsible for maintaining the programme such that on notification from the
Engineering Technical Authority, Process that a new control sheet has been issued due to
modifications, he shall ensure it is included within the checking programme.
on
Physical status checks will also be performed after completion of major maintenance work
on individual systems carried out during a shutdown.
Reviews
6.2.1
nc
6.2
Every week, the Operations Technicians will complete a weekly compliance check. A
system with a defined amount of valves/blinds (defined on the checksheet) will have to be
physically checked on-site to ensure the valves and blinds are in their normal position as
per the Register and that they are securely locked and tagged. If they are OOP, they
must be marked up within the Register, including the authorised OOP Form. Any noncompliance shall be reported to the PLT and the results of the check recorded on the
Compliance Record Form, which should be passed to the OIM on completion.
Page 8 of 13
Uncontrolled if printed.
6.2.2
ECN-OP-PRP-00079
Production Supervisor
In accordance with the LO/LC Compliance Schedule ( Ref 3), every second week the PS
will review any live OOP Authorisation Forms within the Register and satisfy himself that
the work described within the form is still ongoing, the current status of the Register is
up-to-date and no activities are currently underway that have not been subject to the
controls specified within this procedure. The OIM will be informed on completion of the
check and any anomalies will be brought to his attention and appropriate corrective action
taken.
C
op
y
Every fourth week, the PS will select at least five (5) LO/LC points at random and check
that the valves and blinds are in their normal position as per the Register and that they are
securely locked and tagged. If they are OOP, they must be marked up within the Register,
including the authorised OOP Form.
The results of both checks shall be recorded on the Compliance Record Form, which
should be passed to the OIM on completion.
6.2.3
Audit
tro
6.3
lle
Every month, the OIM shall check the compliance schedule completion against target to
ensure that the checks are being carried out and being documented. He will also review
any close-out/remedial actions completed, based on the findings of the compliance
checks. He will also check the Register within the CCR to satisfy himself that any live
OOP Authorisation Forms are still ongoing, the current status of the Register is up-to-date
and no activities are currently underway that have not been subject to the controls
specified within this procedure.
nc
on
Page 9 of 13
Uncontrolled if printed.
ECN-OP-PRP-00079
[2]
[3]
Add New Compliance Schedule Form reference ESSoW Procedure (Electronic Safe System
of Work), ECN-HS-PRP-00048.
[4]
[5]
[6]
[7]
Abbreviations
as low as reasonably practicable
CCR
HAZAN
hazard analysis
LO
locked open
LO/LC
LPT
MCR
OIM
OOP
P&ID
lle
tro
out of position
Production Supervisor
nc
PS
ALARP
on
8.0
C
op
y
[1]
PSV
Page 10 of 13
Uncontrolled if printed.
ECN-OP-PRP-00079
nc
on
tro
lle
C
op
y
Page 11 of 13
Uncontrolled if printed.
Ops Tech
ECN-OP-PRP-00079
Production Supervisor/OIM
Requirement identified
for movement of
LO/LC valve/blind
YES
Carry out HAZAN
(HAZAN Team)
YES
NOPRAS
required?
NO
lle
Carry out
NOPRAS
NO
C
op
y
HAZAN
required?
on
tro
Risks are
ALARP
Carry out
TRIC
Implement
control measures
Verify permission to
move valve/blind
nc
On completion of work,
valve/blind returned
to normal position
Request LPT
verification
Production Supervisor
signs off OOP Form
and inserts copy into file
ECSOPPRP00008_002.ai
Page 12 of 13
Uncontrolled if printed.
ECN-OP-PRP-00079
OIM
PRODUCTION
SUPERVISOR
OPERATIONS
TEAM
TARGET
2
2
2
11
12
13
14
15
16
17
18
19
20
21
22
lle
26
27
28
tro
29
30
31
32
33
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
40
41
42
43
nc
39
on
34
38
OIM to check
status of register
25
37
Production Supervisor to
physically check 5 valves in field
24
36
Production Supervisor to
check status of register
23
35
Weekly Status PM
(Production Technician/
Lead Production Technician)
C
op
y
9
10
ACHIEVED
44
45
46
47
48
49
50
51
52
2
ECSOPPRP00008_003.ai
Page 13 of 13
Uncontrolled if printed.