Civil Engineering Construction
Civil Engineering Construction
Civil Engineering Construction
Construction Technology
CRN : 31888
Credit Rating : 20 Credits
Level 4, Semesters 1 and 2
Date
Version
Nov-11
1.0
Revision
Initial print for 2011-12
Module Leader:
Neil Currie B.Eng(Hons), FIStructE, MICE, CEng
Newton Building, LG8, University of Salford, Greater Manchester, M5 4WT
Email: n.g.r.currie@salford.ac.uk
Civil Engineering website: www.cse.salford.ac.uk/civilengineering
Blackboard website: vle.salford.ac.uk
Forward
The entire module will be subdivided into 5 smaller sub-sections, with construction
techniques being one of these smaller sections. The other components are
engineering contracts, sustainability, health and safety and contract law.
Module Requirements
Recommended Reading
In order to acquire an understanding of construction design and technology you
must read wider than just this module handbook. This is because you will need to
experience a diversity of opinion and methods to fully understand the subject.
The Clifford Whitworth library (first floor) retains a large amount of high quality
material on this subject. Students should refer to texts listed in the references
section at the end of this handbook, many of which are held in the Clifford
Whitworth Library, there are also likely to be various blogs, wikis and online
guidance documents available, but care should be taken with regards verifying
the appropriateness of these sources.
Contents
3
4
5
1.1
Blackboard.
1.2
Weighting of the assignment
1.3
Key dates
Construction Techniques.
2.1
Order of construction
2.2
Permanent Works
2.3
Temporary Works
2.4
Types of activity
2.5
Temporary propping
2.6
Adjacent foundations
2.7
Highway construction
2.8
Basement construction.
What is superstructure?
What is substructure?
4.1
Substructure
Steel
5.1.1
What is steel?
5.1.2
Process
5.1.3
Simple Frames.
5.1.4
Portal frames
5.1.5
Trusses
5.1.6
Long span floors
5.1.7
Composite decking
5.1.8
Bi-steel
5.1.9
Modular construction
5.1.10
Example
5.2
Cranage
5.3
Lots
5.4
Phases
Concrete
6.1.1
What is concrete?
6.1.2
Types of concrete?
6.1.3
Designated
6.1.4
Designed
6.1.5
Self compacting
6.1.6
Super high strength
6.1.7
Pour sequence
6.1.8
Identity testing
6.1.9
Jointing
6.2
Process
6.2.1
Design
6.2.2
Drawings
6.2.3
RC Placement drawings
6.2.4
Bar bending schedules
6.2.5
Placement
6
6
6
7
7
8
8
8
9
9
10
11
12
14
14
17
17
20
21
22
22
23
24
25
25
27
29
29
30
31
31
31
32
33
33
34
34
35
36
37
37
37
38
39
39
6.2.6
Vibrating
6.3
Common defects
6.4
Formwork
6.4.1
Timber shuttering
6.4.2
Table forms
6.4.3
Steel forms
6.4.4
Cardboard
6.5
Tremie pipe
6.6
Concrete pump.
6.7
Tall buildings.
6.7.1
Table forms.
6.7.2
Cantilevers
6.7.3
Jump forming
6.7.4
Slip forming
7
Concrete (Alternate forms)
7.1
Edge protection
7.2
Debonding agent
7.3
Sealant
8
Masonry
8.1
What is masonry?
8.2
How are they made?
8.3
Common units.
8.4
Clay bricks
8.5
Facing bricks
8.6
Calcium Silicate Brick
8.7
Concrete block
8.8
Fair finished block
8.9
Terminology
8.10
Ties
8.11
Bond
8.12
How is it built?
8.13
Common defects
9
What is timber?
9.1
Forms of timber.
9.2
Origins of timber.
9.3
Softwoods
9.4
Considerations.
9.4.1
Hygroscopy
9.4.2
Hygroscopy
9.4.3
Propensity to creep under sustained load
9.5
Strength
9.6
Deflection
9.7
Creep relationships.
9.8
The anisotropic nature of timber strengths.
9.9
Processing timber.
9.10
Engineered Timbers.
9.11
Kerto
40
42
42
44
44
46
47
48
49
50
51
52
52
55
58
60
60
61
62
62
63
64
64
65
65
65
67
67
68
69
70
70
72
73
73
73
74
74
74
75
75
75
76
76
76
77
77
9.12
Plywood
9.13
Cross Laminated Timber (CLT)
9.14
Drying of timber
9.15
Air Drying
9.16
Kiln Drying
9.17
Grading of timber
9.18
Strength classes.
9.19
Sourcing timber.
9.20
Defects
10
Self based exercise.
10.1
Civil Structures
10.2
Buildings
10.3
Infrastructure
78
80
81
81
81
81
82
83
83
85
85
85
86
Table of figures.
Figure 2-1 Temporary propping to a concrete slab.
Figure 2-2 Section through an indicative highway.
Figure 2-3 Excavation with batter along the right hand edge.
Figure 3-1 Bridge superstructure
Figure 3-2 Skyscraper height comparison including Burj Khalifa
Figure 4-1 Leaning Tower of Pisa.
Figure 4-2 Cofferdam being used to construct bridge pier.
Figure 5-1 Steel sections
Figure 5-2 Plate Girder
Figure 5-3 Compound sections
Figure 5-4 Cell beams
Figure 5-5 Castellated Curved Rafters
Figure 5-6 A truss for No 1 Deansgate.
Figure 5-7 Weight restriction sign for a weak bridge.
Figure 5-8 Composite beam with fire protection.
Figure 5-9 Cross-section through a bi-steel panel.
Figure 5-10 Photograph of MoHo in Castlefield.
Figure 5-11 Mobile crane.
Figure 5-12 Eiffel tower construction sequence.
Figure 6-1 Reinforcement placement drawing from design and detailed.
Figure 6-2 Example of Shape Code 13 for RC Detailing.
Figure 6-3 Steel reinforcement being concreted.
Figure 6-4 Forwork for a column.
Figure 6-5 Formwork
Figure 6-6 Backpropping load distribution.
Figure 6-7 Carboard Formwork
Figure 6-8 Tremie pipe used in piled foundations.
Figure 6-9 Concrete pumping truck.
Figure 6-10 Concrete skip used on tall buildings.
Figure 6-11 Pier Luigi Nervi hangar roof using downstand beams.
Figure 6-12 Stability core at Media City formed using slip form.
Figure 7-1 Bubbledeck
Figure 7-2 Formwork for a viaduct.
Figure 8-1 Normalised block strengths from a manufacturer.
Figure 8-2 Coursing dimensions for brickwork.
Figure 8-3 Types of masonry units.
Figure 8-4 Forms of masonry wall construction.
Figure 8-5 Common Wall Ties
Figure 8-6 Common UK bond patterns.
Figure 9-1 Deflection of a timber beam.
Figure 9-2 Common sawing patterns.
Figure 9-3 Timber gridshell using engineered timber
Figure 9-4 Structure of ply.
9
10
11
12
13
14
16
18
18
19
19
20
22
23
24
25
27
29
29
38
39
41
43
45
46
47
49
50
51
52
55
59
60
63
64
67
68
68
69
76
77
78
79
82
84
1.1 Blackboard.
Each section of the course will be co-ordinated with Blackboard
and will require you to regularly log in and co-ordinate with the
reading programme. Within BlackBoard there will be a series of ongoing self-tests and self-based learning activities. These may form
part of your overall mark and will require you to achieve a minimum
mark in each section.
These tests will be taken within controlled conditions and each test
will be randomly taken from a pool of questions maintained within
the Blackboard database.
Once the self-based tests have been completed for all students, the
same pool of questions will be thrown open to allow you to study
and revise for your exams.
2 Construction Techniques.
One of the key requirements often overlooked by engineers when
designing a structure or a piece of civil engineering infrastructure is
how these components will be built, maintained and even
operated. This section of the module is intended to take the student
through some of the common techniques utilised within construction
within the UK.
This handbook will make reference to various articles linked into the
corresponding area on blackboard and the student will need to
ensure that these are also read in conjunction with reading this text,
the associated texts, attending lectures and tutorials.
http://www.communities.gov.uk/publications/planningandbuilding/partywall
10
Figure 2-3 Excavation with batter along the right hand edge.
11
Superstructure
3 What is superstructure?
Superstructure is a term used in civil engineering to identify a specific
area of a building or development. The phrase superstructure is
used in many other disciplines and is not exclusive to engineering,
ranging from psychology through to describing parts of Marxist
theory. They all share a common notion though in that it is used to
describe a thing that is supported by another.
In simple buildings, the superstructure can simply be thought of the
area of the building that sits above the foundations or basement
level. For bridges the superstructure is classed as the section that sits
upon the piers and abutments.
12
13
Substructure
4 What is substructure?
Substructure is a term used in civil engineering to identify a specific
area of a building or development. In its simplest form the
substructure can be imagined as something that provides support to
something above and is thus a critical component.
A common example of substructure is the humble foundation, the
first component typically constructed on a building site and
frequently one given the least amount of acknowledgement when
looking at large exotic structures, but without solid foundations,
buildings would sink into the ground or dangerously topple.
4.1 Substructure
The substructure is a key component within civil engineering, it is
typically the element of works that either sits in or beneath the
14
Pad foundations.
Strip footings.
Combined foundations.
Raft foundations.
Piled foundations.
Secant piles
CFA piles
CHD piles
Bottom driven piles
Top driven piles
Sheet Piles
Timber Piles
Nestled timber planks
15
16
Steel
5 Steel
18
19
5.1.2 Process
As with all elements of design, the design cannot start properly until
a brief has been determined. The brief can take different forms
depending on the nature of the design problem, for a simple beam
to form an aperture through a masonry wall this could simply be the
performance criteria for the beam (i.e. its span, limiting deflection
and load it must support).
20
For more complex buildings this could be simply how many square
metres of floor are required and that certain areas are not allowed
to have internal columns. It is at this point that the brief will start to
drive the potential solutions and start to attract costs for the design
of the scheme.
From the conception of the structural form, its critical that the
designers start to consider how these structures can and will be
constructed. Many schemes have never made it through to
construction stage due to them being impractical or the associated
costs of temporary propping or the shear number of cranes required
to lift them.
There are numerous families of structural forms that can be
constructed in steel and below are a selection of some of the more
common forms that engineers will be expected to understand,
identify and present the construction sequence for.
21
5.1.5 Trusses
Trusses are used to span long distances and are commonly used in
large span structures such as exhibition arenas, concert halls, large
lecture theatres and similar type buildings. As the trusses themselves
are typically longer than a standard trailer can transport, they are
brought to site in several sections and then bolted together to
create a complete truss. The positions where the trusses are bolted
back together are called splices and the number of sections that a
truss is subdivided into can be as a result of many governing factors
including the size of the fabrication shop, the length of the vehicles
delivering the components, low bridges en route, etc
22
Typically vehicles and their loads that are no wider than 2.9m and
no longer than 18.75m require no special measures to be
undertaken such as police escorts. However the planning of the
route needs careful consideration so as to avoid low bridges and
other sections of road that may not be suitable to support the axle
load from the wagons.
Clearly until the entire truss is bolted together it has no ability to span,
its incomplete and has no structural integrity. This may mean that
the truss is assembled on the floor and lifted into place as one piece,
or that the truss is assembled insitu using some form of crash decking
or temporary support decks.
Question: Where on a house would you see a truss?
Question: And how large are they and would they require special
permission and/or access requirements to be delivered?
23
Question: Why would you use a long span floor in a car park?
5.1.8 Bi-steel
Corus produced a product called Bi-steel which is essentially two
sheets of steel that are connected together using metal studs to
create a sandwiched panel.
The benefit of these panels is that they are comparatively light when
compared to a concrete wall and can be erected quickly to form
shear walls around lift cores and similar types of structures. Once
they have been erected then they can be filled with concrete if
necessary to increase their axial load carrying capacity.
26
5.1.10
Example
27
28
5.2 Cranage
Another of the key considerations of constructing steel frames is the
amount, positioning and location of any cranage that is necessary to
lift the steel elements into position. As steel elements are delivered to
site on the back of a trailer, they are lifted off and stored in sequence
to allow the frame to be assembled in a logical and systematic fashion.
5.3 Lots
The order that the steelwork is delivered is referred to as lots. Each
batch (or lot) of steel that is delivered to site is carefully planned so that
it maintains stability for itself whilst the rest of the frame is erected and is
frequently co-ordinated with the access for cranage and other site
access requirements. For taller buildings though, the allocation of lots is
determined by the logical construction sequence.
29
5.4 Phases
Larger steel frames are further sub-divided into phases or regions, with
each phase being an independent frame. Examples of this include
large shopping centres such as the Trafford Centre or the Lowry Outlet
Mall, the latter of which is subdivided into three sub-regions or phases.
30
Concrete
6 Concrete
6.1.1 What is concrete?
Concrete in its simplest form is a combination between cement,
coarse aggregate, fine aggregate and water. By varying the
different forms and ratios of these elements allows for concrete with
differing properties to be manufactured. Further amendments to
the mix such as the inclusion of fly ash, use of recycled aggregate or
various chemical admixtures can also reduce the amount of carbon
required to manufacture concrete.
The design requirements of concrete will vary dramatically
depending on its intended end use, the environment to which it is
intended, the method of construction, placement and climatic
conditions to name a few.
The following sections will cover some of the key criteria used when
designing and constructing in concrete and are intended to aid the
student develop an understanding of modern concrete
construction. It is fully intended that the student however will also
research the ideas contained within under their own initiative and
research the topic and construction techniques further.
ultra high strength mixes. The intention of this section is not to teach
teach you about the finer points of concrete and mix design, but to
instruct you on some of the basic principles associated with
concrete specification and construction to provide you with
information to aid with your future designs.
6.1.3 Designated
Designated mixes are typically the most common type of concrete
used in modern building and civil engineering construction. The
methodology behind designated mixes is that they are standardised
both in terms of their specification but also in their production and
provision from concrete suppliers.
In theory this should mean that each batch of concrete is uniform
and has been through the same quality control procedure and thus
will have the same mechanical properties.
Each batch of concrete will have a ticket when it leaves the factory
and should the concrete be amended in any way (including the
addition of water) between it leaving the factory and being placed
then the driver should note this on the batch ticket before the
concrete is placed. If the batch has been amended then the
customer does not necessarily have to accept delivery of the
concrete.
Not recording any alterations to the mix on the ticket can often
result in the person responsible being dismissed such is the risk to the
mechanical and chemical properties2 of the concrete mix.
One of the reasons toilets are often set up at regular intervals through the floors of tall
buildings to prevent workers urinating in the formwork. There have been cases where the
ammonia from the urine has adversely affected the performance of the concrete.
32
6.1.4 Designed
Every building is designed to respond to a certain set of criteria and
occasionally this will require the specification of a concrete mix that
is beyond the capability of a standard designated mix.
This may be because the client requires the inclusion of a specific
admixture, such as a colour to the concrete or a specific high
quality finish. These are outside the scope of a generic concrete
specification and mix design and will require the mix for the
concrete to be designed specifically.
High strength concretes above 60 N/mm often require the use of
designed mixes.
33
This has been noted on the exchange between the two mixes when
constructing hybrid structures such as twin wall, where voids have
been uncovered at the ends of panels.
34
35
6.1.9 Jointing
Where large areas of slab are required, these cannot be readily be
poured in a single pour for several reasons. Primarily there will be a
logistic limitation as to how much concrete can be delivered to site
and continually poured before the site must close for the day and
this must be factored into the construction sequence. Where pours
stop and start for the day are frequently called day joints.
Even if the amount of concrete required to pour a large floor slab
could all be delivered and placed in one day, the amount of
concrete involved may result in high quantities of heat being
generated within the concrete which can have an adverse affect
on its curing times and sequences. This is because concrete is
exothermic and consequently gives up large amounts of heat as it
cures, this effect is exacerbated for deep and large volume pours
such as mass concrete retaining walls and dams, where the amount
of heat generated can be quite considerable.
As concrete cures; it slowly gives up a portion of its water content as
it dries out and this giving up of water results in shrinkage of the
concrete. This can be problematic for large areas of slabs,
depending on their restraint conditions near large stability cores and
other stiff elements. The shrinkage of concrete slabs can be a
36
6.2 Process
The design, detailing and construction of insitu concrete buildings
passes through several key stages during the process. Some of the
key stages are outlined below but do not make reference to the
early conceptual design stages, merely in the production of
construction information through to the physical construction of the
building.
6.2.1 Design
The design of the structural element to be constructed will
determine the shape, form, strength of concrete, amount and
arrangement of the reinforcement. A good designer will always be
developing how the element can be constructed safely and
economically as well as ensuring that the design is safe and will not
deflect excessively in the permanent condition.
6.2.2 Drawings
To identify the overall shape of the element and its location within
the building a well drawn set of plans, sections, elevations and
details are likely to be required. These drawings will be produced by
the engineer at the appropriate design stage and will typically be
co-ordinated with the other disciplines such as the architect and
building services engineers to allow for a co-ordinated design to be
produced.
37
These drawings will give each piece of steel reinforcement their own
unique number for the project, this number is called the bar mark
and will be accompanied with a bending schedule.
38
13
A + 0.57B + (C)
(C)
12
Neither A nor B
(B)
Whilst reinforcing bar can be bent into any practical shape withinin Table 2
the limitations of its diameter and associated diameter, it is typically
A + (B) 0.43R
bent into predefined standardised shapes that are governed by a
British Standard3.
B shall not be l
Neither A nor C
in Table 2 nor l
See Note 3.
A
Key
Figure 6-2 Example of Shape Code 13 for RC Detailing.
1 Semi-circular
14
These rules also prevent reinforcing bars being bent to radii that are
A + (C) 4d
too tight and that might otherwise affect the strength of the
reinforcement through cold working of the steel reinforcement.
6.2.5 Placement
B
Neither A nor (
in Table 2. See
(C)
12
BS8666
39
cage that can be lifted up into place and position directly into the
formwork.
Reinforcing bar lengths are typically provided in either 6m or 12m
lengths, depending on the diameter and the designer should give
consideration as to how these bars will be physically picked up and
positioned on site whilst they are preparing their designs. If a
reinforcing bar cannot be position by the labourers then this can
frequently tie up valuable resources and crane time to lift and
position the reinforcing bar into place, plus it may not present a safe
and economical solution.
If a structural element is longer than the typical length of a
reinforcing bar, then this will require a lap in the reinforcement, this
lap can be formed by lapping the reinforcing bars next to each
other for a minimum length as described within the relevant
standards, by the inclusion of mechanical couplers or by positioning
the lap in a location where the reinforcement is no longer required
to form a beam design utilising lapless construction. Mechanical
couplers are frequently avoided in commercial applications given
the increase in costs and standard laps instead are prepared, in
nuclear construction though the bar diameters are typically large
and congested and in these instances couplers provide an
economical alternative to lapped reinforcement.
All debris should be removed from the bottom of the formwork prior
to concrete being placed, there is often clippings of tying wire
around the bottom of the formwork that can cause unsightly
staining to the underside of the concrete slab and any foreign
matter left on the bottom of the formwork can result in the cover to
the reinforcement being compromised.
6.2.6 Vibrating
Once the reinforcement is in place within the formwork and all
debris has been removed from the bottom of the forms, then the
concrete can be placed.
40
41
6.4 Formwork
Formwork is a key component of construction using concrete and
can take a variety of forms from the traditional timber formwork,
through to the introduction of permanent formwork through the use
of composite steel decking.
The costs associated with formwork and the complexity involved is
often overlooked by engineers during the design process, but
ultimately if you cant make the formwork, then you cant make the
structure.
42
43
45
ds careful consideration.
is responsible for
striking process safely.
bility of the Temporary
ator (TWC) to manage
striking. This will
ng detailed procedures
ements, which should
the safety officer and
ks Designer (PWD).
is to provide design
hat the construction
adversely affect the
the structure.
d managerial staff
ware of the implications
and procedures adopted.
striking and backures are given in Ref. 1.
on load
ons
Load No backprops
On slab
On slab
total
100%
100%
Falsework/formwork
wp
100%
In backprops
On slab
100%
65% w p
30% w p
30% w p
In props
100%
70% w p
w b1
In props
Two levels of
backprops
100%
100% w p
One level of
backprops
35% w p
23% w p
w b2
12% w p
12% w p
1. Assumes lower and supporting floors have been struck, have taken up their deflected
shape and are carrying their self-weight
n-situ concrete
e critical loading
lab is not necessarily
and becomes self-
46
Also worth noting is that the finished quality of the concrete and
accuracy of the formwork can be increased when compared to
timber formwork and steel forms are frequently used for columns
that are exposed and consist of a visual element of concrete.
Steel shuttering may also be more economical for tall complex pours
where large hydrostatic pressures are anticipated due to their
increased strength compared to timber forms.
6.4.4 Cardboard
The use of modern engineered cardboard formwork is a common
sight on UK construction sites due to its robustness and economical
benefits. Disposable cardboard formwork is bought in predefined
sizes and is more commonly used for columns where it can be
bought for circular, rectangular and square column profiles. The
formwork can only be used once and is designed to be cut from the
columns with a knife once the formwork has been struck.
47
The inside of the cardboard tubes is lined with high quality polished
cardboard which enables the formwork to give a high quality
surface finish with even standard designated mixes.
Whilst the formwork itself allows for high quality construction to be
completed, the nature that the tube will slide over the bars can
sometimes result in the inside of the formwork becoming snagged
and ripping on the reinforcement of the spacers.
To overcome this, the column is designed with a slightly greater
cover to accommodate tolerances within the cage construction
and special spacers can be used that spin to facilitate the
placement of the concrete tubes over the top of the reinforcement.
Another benefit is that once the column has been struck and
inspected, then the cardboard formwork can be placed back onto
the column and taped back on to offer some element of protection
to the concrete columns during the rest of the construction stages.
48
49
50
lower floors being smaller than the upper floors due to the increase
in axial load
As the construction work reaches higher and higher levels, it will
extend beyond the reach of a traditional concrete pump and a
different approach will be needed. Typically the concrete is lifted in
a skip via the tower cranes up to higher floors and either deposited
into a hopper for pouring or placed directly onto the relevant floor
slab.
strength. An upstand sits above the top of a slab, like a small wall
whereas a downstand sits below the slab like a beam.
Figure 6-11 Pier Luigi Nervi hangar roof using downstand beams.
6.7.2 Cantilevers
Cantilevers require special attention when assessing their
constructability, particularly in concrete, as concrete has no
inherent strength until it has cured for sufficient time. The formwork
therefore, provides all of the support to the cantilever until the
strength requirements have been met and it is this requirement that
can introduce great cost and complexity to the construction of
significant cantilevers, rather than just the fixed lengths of the
cantilever in the permanent condition.
52
53
Figure 6-12 Stability core at Media City formed using slip form.
57
Similar hybrid systems (such as Omnia Deck6) exist for concrete slabs
and follow a similar principle with a thin high strength concrete
http://www.precaststructures.com/TwinWall.asp
http://www.heidelbergcement.com
58
biscuit providing the load carrying capacity within the slab to allow
the support of the structural element in the temporary condition with
the additional weight of the wet concrete, but once the concrete
has cured then the slab will attain its permanent load carrying
ability. This method typically requires no additional reinforcement to
be included as longitudinal steel is included within the concrete
biscuit, however additional reinforcement can be included where
required on an ad hoc basis.
The weights of these panels can be considerably reduced through
the introduction of biaxial void formers such as Cobiax7 or
Bubbledeck8.
http://www.cobiax.ch/en
http://www.bubbledeck.com
59
7.3 Sealant
Concrete structures can produce large quantities of dust, even after
the concrete itself has long since cured and attained its 28 day
strength. This can be problematic in areas that require dust free
environments or even in car parks where the slabs are frequently
trafficked by vehicles.
To limit the amount of dust produced from the building, dust sealant
can be applied to the concrete elements in the form of a clear
paint. This paint suppresses the dust and prevents it leaving the
concrete and is frequently used on areas of exposed concrete such
as core walls and soffits of slabs.
Where additional toppings are to be applied to the tops of concrete
slabs then it may be required to omit the dust sealant so as to
provide a good key between the two surfaces. Each area should
be carefully assessed by its intended use and proposed finishes to
determine if dust sealant will be required. Frequently the sealant is
specified by the architect and included within their finishes
schedules.
61
Masonry
8 Masonry
8.1 What is masonry?
Masonry is one of the oldest materials still used today and has been
used in several of the iconic historic buildings still standing today
including the Great Wall of China and the Great Pyramids.
Masonry is an encompassing name for a variety of units, which
include stone, bricks and various man made blocks when it comes
to structural design and it is not uncommon for different units to be
mixed and matched. For example, on modern houses frequently
the internal skin is constructed using blockwork due to the speed at
which it can be erected, although traditional bricks are still
commonly used for the external skin because of the increased visual
quality that they present and also they perform well in external and
exposed environments.
One of the key things to remember when designing and
constructing masonry structures is that whilst it may have a small
tensile component, it is generally advisable to construct masonry
structures so that they work in compression. If as an engineer you
are ever unsure if a material is suitable to design to resist tension
forces, ask yourself a simple question
If I was in prison, would I make an escape rope from it?
If the answer is no, then the chances are, that its a poor material in
tension.
62
90mm
100mm
140mm
190mm
215mm
2.9
4.1
4.1
4.0
3.8
3.5
3.4
3.6
5.1
5.0
5.0
4.7
4.3
4.2
7.3
10.4
10.2
10.1
9.5
8.8
8.5
10.4
14.9
14.6
14.4
13.5
12.5
12.1
17.5
25.0
24.5
24.2
22.8
21.0
20.3
22.5
32.2
31.5
31.1
29.3
27.0
26.1
30.0
42.9
42.0
41.4
39.0
36.0
34.8
40.0
57.2
56.0
55.2
52.0
48.0
46.4
63
copper, polythene,
8.3 Common units.
courses of bonded
Fig. 5.5 Types of bricks: (a) solid; (b) perforated;
ed on Table 2,
There is(c)
anfrogged.
overwhelming range of masonry products available and
given the amount of time that theyve been used in the UK for
size ofthere
the brick,
i.e.standard
215 102.5
65 mm, plus
an
construction
is no real
size as frequently
specials
allowance
of for
10heritage
mm for and
the conservation
mortar joint work
(Fig.where
5.6).
are used,
especially
iety of materials
Clay bricks are also manufactured in metric moduperhaps the bricks were made by a local artisan originally.
and sand/flint),
lar format having a coordinating size of 200 100
However,
formm.
modern
construction,
commonly
adopted
ese, clay bricks
75
Other
cuboid and
special shapes
arebrick
also
d variety in the
available
(BS 4729).
dimensions
include:
241
There are a wide range of clay bricks within the UK, each with subtly
different finishes, colours and performance criteria that have been
developed over the years to suit the various uses and intended
locations of the bricks.
11/3/09, 11:11 AM
Clay bricks can be made by hand or within a factory and can have
a density ranging from anywhere between 22.5 to 28kN/m3.
64
Similarly as the units themselves are quite a bit larger than bricks, the
amount of wall that can be constructed in a day is much greater as
a bricklayer can effectively replace multiple bricks with a single
block.
There are a multitude of different types of concrete blocks, ranging
from lightweight blocks with a density of 5kN/m3 through to dense
blocks with a density of 20kN/m3.
Care should be taken when specifying the blocks, as it is possible to
get the same strength of block at a variety of densities and
depending on the use of the block this can affect how it performs
with regards its durability.
For example, hanging large heavy components such as boilers off a
wall constructed in lightweight block can sometimes cause
difficulties as the wall anchors are being installed as they can cause
lighter weight blocks to disintegrate and fall apart.
The solution isnt to specify the heaviest block possible, there are
limits on block weights that you can legally expect a brick layer to lift
continually through the course of the day and these are contained
within the CDM regulations.
Similarly, if the heaviest blocks are used, these can increase the
dead load that a floor needs to support which can have associated
ramifications on the cost of the building if larger floors, columns and
foundations are needed to support the extra weight of the masonry.
Common9 strengths of concrete blocks range between 3.6 to
22.5N/mm2.
http://www.tarmacbuildingproducts.co.uk/products_and_services1/blocks_and_mortar/
blocks/aggregate_blocks/topcrete_standard.aspx
66
8.9 Terminology
Masonry units have a strange terminology which may not be
apparent from the description given and engineers will need to be
familiar with these terms so that they are able to appropriately
communicate with contractors and anyone else that may need to
use 6:their
Eurocode
Designdrawings.
of masonry structures
Solid Unit
Frogged Unit
Table 10.4 shows the masonry mortar mixes recommended for use in the UK to achieve the appro-
8.10 Ties
COMPRESSION:
Gk
Qk
Wk
f
m
fk
N
NR
Masonry
leaves are knitted togetherthethrough
the
introduction
primary aim
of design
is to ensureof
an wall
adequate
characteristic dead load
margin of safety against the ultimate limit state
tiescharacteristic
that can imposed
take aload
variety of shapes
and
formed.
As ofbuilding
being
reached.
In the case
vertically loaded walls
characteristic wind load
this
is
achieved
by
ensuring
that the to
ultimate
efficiencies
and the requirement
to increase the cavity
partial safetyincrease
factor for load
design load (N ) does not exceed the design load
partial safety factor for materials
resistance
of thegreater
wall (NR ):and greater,
help
raise thecompressive
thermalstrength
performance
becomes
characteristic
of
masonry
N NR stronger (5.1)
so the
size of the cavity too will increase and this requires
ultimate design vertical load
ultimate
designwall
vertical
load resistance of
and
stronger
ties.
wall
Materials
FLEXURE:
fkx par
fkx perp
M
MR
Mpar
Mperp
Mk par
Mk perp
Fig. 5.3 Wall ties to BS EN 845-1: (a) butterfly tie; (b) double triangle tie; (c) vertical twist tie.
basic types,
deaddouble
loads, imposed
(or live)
the above
figure type
(a) are butterfly
ties,namely
(b) are
triangle
5.5InDesign
of vertically
loaded
loads and wind loads. Generally, the ultimate design
ties
and (c)walls
are half twist ties which load
are istypically
used
for the
obtained by
multiplying
thelarger
characteristic
masonry
(dead/imposed/wind) loads (Fk) by the appropriate
In common
with most modern codes of practice
cavities.
partial safety factor for loads ( )
dealing with structural design, BS 5628: Code of
Practice for Use of Masonry is based on the limit
N = fFk
(5.2)
246
Fig. 5.4 Damp proof courses: (a) lead, copper, polythene,
bitumen polymer, mastic asphalt; (b) two courses of bonded
slate; (c) two courses of d.p.c. bricks (based on Table 2,
9780415467193_C05
246
BS 5628: Part 3).
5.2.1 BRICKS
68
8.11 Bond
The pattern that the bricks are laid is called the bond pattern and in
the UK there are five commonly used bond patterns, although many
more patterns are available.
69
70
71
Timber
9 What is timber?
Timber is one of the oldest construction materials. It is biologically
produced by nature and further processed by man.
Timber is a commonly used construction material, with the ability for
taller and taller timber buildings continuing to develop with the
recently completed 9 storey Stadthaus10.
If appropriately sourced, timber can be a sustainable material and
there are a variety of forestry stewardship programmes that ensure
that as trees are harvested that a minimum number of trees are
planted for replacement.
There are numerous timber products available:
Solid timber (traditional sawn timber)
Glue Laminated timber (laminates planks of wood glued
together)
Laminated Veneered Lumber (2mm thick laminates glued
together)
Plywood (panel product of thin laminates glued together)
10
http://www.woodawards.com/the-stadthaus/
72
9.3 Softwoods
Various softwoods are commonly used within the UK for construction
purposes and for different purposes.
73
Douglas Fir
Scots Pine
European Spruce
Sitka Spruce
Pitch Pine
Parana Pine
Western Hemlock
Western Red Cedar
Hardwoods.
Beech
Iroko
Mahogony
Oak
Sapele
Teak
9.4 Considerations.
When compared with other structural materials, there are
peculiarities to the use of timber in construction. These are:
9.4.1 Hygroscopy
Propensity to creep under sustained load
Anisotropy
9.4.2 Hygroscopy
Timber is a natural product derived from trees. Since trees need
water to survive during their lifespan, timber, by its nature, is a
hygroscopic material it attracts water. The effect of hygroscopy is
not just true for living timber but also for dead timber. If, for example,
a structural timber element is taken from a dry timber merchant and
74
9.5 Strength
A piece of timber has an initial value of strength when a load is first
applied to it. If the load is sustained over a considerable period of
time it can be seen that the load carrying capability is significantly
reduced. Its strength after this time period is a fraction of its initial
strength value. Severe loss of strength could result in failure of the
timber or creep rupture.
9.6 Deflection
When a load is applied to a piece of timber it has an initial elastic
deflection. If the load is sustained the deflection steadily increases
even though there is not any increase in the magnitude of load. In
other words, the piece of timber is subjected to the effect of creep.
The deflection increases as time progresses until creep rupture
occurs.
75
uinst
ufin
ucreep
g. 2.6. Deformation.
Where it
e symbol used
in Figure 2.5.
Anisotropy
viceability
it is defi
(ii)
Eurocode 5 uses the limit state design philosophy. This means that
theloading
strength capacity
of the timber
to withstand
appliedthe
actions
When the
is immediately
applied;
this the
is called
instantaneous
at the ultimate limit state (ULS). Additionally, a check on
mation:isuchecked
inst .
the actual deflection under the applied actions is within an
After allacceptable
time-dependent
displacement (i.e. creep deformation, u creep ) ha
deflection limit is undertaken at the serviceability limit
place; this
is(SLS).
called the final deformation: u fin .
state
These deformations
shown
diagrammatically
in Figure
2.6grain
in relation to a
Timber is cutare
down
from whole
trunks and the direction
of the
upported beam
without
pre-camber.
aligns
with theany
longitudinal
axis of the trunk. Below is a diagram
which
shows some common
forms of cutting
timber
down intoon the creep beh
Deformation
is calculated
in two different
ways,
depending
useable planks and timber elements.
the structure:
Radial sawing
Through conversion
(plain sawing)
Through conversion
(billet sawing)
77
9.12 Plywood
Plywood is a wood product manufactured out of many sheets of
veneer, or plies, pressed together and glued, with their grains going
in opposite directions. Plywood tends to be extremely strong, though
not very attractive, and is treated in many different ways depending
upon its intended application. Because of the way in which plywood
78
1: PAB/RPW
P2: PAB
LUK117-Porteous
6, 2007
19:22
isOctober
constructed,
it also
20
Face ply
Back ply
(a) The structure of a three-ply plywood
(e) Laminboard
Figure
9-4 Structure
of ply.
Fig. 1.9. Examples of plywood and
wood
core plywood.
The plies that form plywood are generally cut on a rotary lathe,
1.7.2 Plywood
which cuts a continuous roll of wood while a log, called a peeler, is
turned against it. Rotary lathing is rapid and makes efficient use of
Plywood is a flat panel made by bonding together, and under pressure, a number of
the
while
turning
out veneers
highly
suitable Plywood
for plywood.
thinwood
layers of
veneer,
often referred
to as plies
(or laminates).
was the first
type oflathes
EWP toare
be invented.
Logsto
areexpose
debarkedmore
and steamed
or heated
in hotofwater
Some
designed
interesting
parts
the for
about
24
hours.
They
are
then
rotary-peeled
into
veneers
of
24
mm
in
thickness
wood grain, although they may be more wasteful of the wood. and
clipped into sheets of some 2 m wide. After kiln-drying and gluing, the veneers are
laid up lathed
with the veneers
grain perpendicular
one
another
and bonded under
pressure in an
Rotary
tend to tobe
dull
in appearance,
although
odd number of laminates (at least three), as shown in Figure 1.9a. The outside plies,
perfectly functional. After the veneers are cut, they are overlaid with
always made of veneer, are referred to as faces (face ply or back ply) and the inner
layers
of glue
together
untilordry
to formwood,
a flat,
laminates,
whichand
couldpressed
be made of
either veneers
sliced/sawn
are even,
called core.
Examples
of
wood
core
plywood
include
blockboards
and
laminboards,
as
shown
tight piece of plywood. Plywood is sturdier than regular sheets
or in
Figures 1.9c1.9e.
panels of wood, because the veneers are laid with their grains
Plywood is produced in many countries from either softwood or hardwood or a
opposing,
wood
product
tocommonly
resist warping
combinationwhich
of both.also
The causes
structuralthe
grade
plywoods
that are
used in the
United Kingdom
are as follows:
because
the grains
pull each other tight.
The!main
types
of Plywood
Sheets plywood
are Shuttering, WBP, Softwood,
American
construction
and industrial
!
CanadianInterior,
softwoodExterior
plywood and
and Douglas
fir plywood
Hardwood,
Marine.
Within these different types
! Finnish birch-faced (combi) plywood, Finnish birch plywood and Finnish conifer
there are then also different grades depending on the type of wood
plywood
that! isSwedish
used for
constructing
softwood
plywood. the wood laminates and the quality of
The plywood sheet sizes available sizes are 1200 mm 2400 mm or 1220 mm
79 with the longer side of the sheet except
2440 mm. The face veneer is generally oriented
for Finnish made plywoods in which face veneers run parallel to the shorter side.
Structural plywood and plywood for exterior use are generally made with waterproof
adhesive that is suitable for severe exposure conditions.
11 http://www.eurban.co.uk/
12 http://www.klhuk.com/
80
81
GS (C14), SS (C18)
GS (C16), SS (C24)
GS (C16), SS (C24)
GS (C16), SS (C24)
GS (C14), SS (C18)
GS (C14), SS (C18)
GS (C18), SS (C24)
measuring
the
stiffness of the timber when a load is applied to it by a
Timber
graded in accordance with BS 4978:1996; based on Table 1.2, BS 5268-2:2002.
strength grading machine.
the load to induce a known deflection) is then automatically measured and compared
withto
pre-programmed
which leads
the directof
grading
of the is
timber
section
The need
assess thecriteria,
strength
of atopiece
timber
usually
and marking with the appropriate strength class. An example of the grading marking,
requiredbased
where
timber is of
toBSbe
in a constructional
on the requirements
ENused
14081-1:2005,
is shown in Figure 1.7.or load
In general less material
rejected
machine graded; however,
timbertrusses.
is also visually
bearing capacity,
such isas
the ifmanufacture
of roof
inspected during machine grading to ensure that major, strength-reducing, defects do
not exist.
Kingdom with
BSbe
5268-2
in 1984.
Strength
classes offer a number
of advantages
Visual grading
can
and
is used
to determine
grades
for
both to the designer and the supplier of timber. The designer can undertake the design
constructional
it is more
usually
used
toofdetermine
the
without the use,
need toalthough
check on the availability
and price
of a large
number
species and
grades thaton
might
be used. Suppliers can supply any of the species/grade combinations
grade based
appearance.
PRODUCT
NBODY
M
CODE
DRY GRADED
C24
Key:
82
9.20 Defects
Timber can have many defects, most of which will be identified
within the grading process, but an awareness of some of the most
common types of defect is important to allow the engineer to
understand and recognise these defects on site.
13
14
15
83
10
Shake
Diagonal grain
Knot
Cross grain
Wane
Flat grain
Cupping
Springing
End splitting
Bowing
Honeycombing
Twisting
10.2 Buildings
Foundations
Shear cores
Jump form
Slip form
Traditionally formed stability cores.
85
10.3 Infrastructure
Rail
Roads
Drainage
Airports
Ports
Underground tunnels.
86