Standard Terms & Conditions of Sale Pre-Engineered Buildings
Standard Terms & Conditions of Sale Pre-Engineered Buildings
Standard Terms & Conditions of Sale Pre-Engineered Buildings
Pre-Engineered Buildings
Pre-Engineered Buildings
1. Placing Orders
Orders are normally placed after Zamil
Steel submits a written proposal (also
known as quotation or offer) to its customers.
Quotations may be revised until all technical and commercial matters are agreed
upon by both the customer and Zamil Steel.
Once all matters are agreed upon and are
included in a final, revised Zamil Steel
proposal, both the customers authorized
representative and Zamil Steels authorized
representative must sign a standard
contract. This standard document is provided with and attached to all Zamil Steel
proposals.
2. Acceptance of Orders
Only orders accompanied by signed and
dated contracts are accepted by Zamil Steel.
Orders are reviewed and determined to be
complete with all required information. Accepted orders are entered in a sales register
maintained by the Order Management Department while orders that are incomplete
are placed on hold until the appropriate
corrective action is taken. Customers are
informed of the On Hold status of their
orders by the responsible Zamil Steel Area
Office.
Pre-Engineered Buildings
Pre-Engineered Buildings
Other Terms:
a.
WAR RISK is not covered under land insurance
b.
Partial shipment is allowed.
c.
L/C must be valid for shipment for ninety (90) days from opening date.
d.
L/C expiry date shall be twenty one (21) days after L/C shipping date.
e. All L/C opening and amendment charges are for openers account.
Please arrange to transmit the full text of the L/C by SWIFT, being the operative instrument, to enable the beneficiary to ship our material at an early date and advise the beneficiary through telephone to collect the L/C from the advising bank.
Pre-Engineered Buildings
Other Terms:
a. WAR RISK is not covered under land insurance
b Partial shipment is allowed.
c. L/C must be valid for shipment for ninety (90) days from opening date.
d. L/C expiry date shall be twenty one (21) days after L/C shipping date.
e All L/C opening and amendment charges are for openers account.
Please arrange to transmit the full text of the L/C by SWIFT, being the operative instrument, to enable the beneficiary to ship our material at an early date and advise the beneficiary through telephone to collect the L/C from the advising bank.
Pre-Engineered Buildings
Other Terms:
a. Partial shipment is allowed.
b. L/C must be valid for shipment for ninety (90) days from opening date.
c. L/C expiry date shall be twenty one (21) days after L/C shipping date.
d. All L/C opening and amendment charges are for openers account.
Please arrange to transmit the full text of the L/C by SWIFT, being the operative instrument, to enable the beneficiary to ship our material at an early date and advise the beneficiary through telephone to collect the L/C from the advising bank.
Pre-Engineered Buildings
Other Terms:
a.
Partial shipment is allowed.
b.
L/C must be valid for shipment for ninety (90) days from opening date.
c.
L/C expiry date shall be twenty one (21) days after L/C shipping date.
d.
All L/C opening and amendment charges are for openers account.
Please arrange to transmit the full text of the L/C by SWIFT, being the operative instrument, to enable the beneficiary to ship our material at an early date and advise the beneficiary through telephone to collect the L/C from the advising bank.
Pre-Engineered Buildings
Pre-Engineered Buildings
Packing list.
Commercial invoice.
Packing list.
Additional Terms:
a) Partial shipments must be
permitted.
c)
Pre-Engineered Buildings
5.
Design Calculations
(Optional)
d)
Column reactions.
Pre-Engineered Buildings
6. Design Certificates
7. Change Orders
7.1 Once a contract is signed and
accepted, any subsequent changes to
the order require a change order letter,
prepared by Zamil Steel and signed by
the customer. This letter will, describes
the specific change(s) and indicate the
impact these changes may have on
price and/or delivery of the project. No
further action will be taken by Zamil
Steel until the change order has been
signed as accepted by the customer.
7.2 The cost of any fabricated components
that are rendered useless by a change
order initiated after the start of fabrication, will be charged to the customers
account.
8. Jobs on Hold
8.1 All costs that are incurred by Zamil Steel
when a job is placed On Hold by the
customer, after the start of manufacturing, will be charged to the customers
account.
8.2 A job that is not released for production
within 90 days from the date of its entry
in the sales register, for whatever reason
(including lack of technical clarification),
will be put On Hold. Zamil Steel
reserves the right to adjust the price of
such a job according to the price rates
that are valid at the time of release from
its On Hold status.
9. Material Dispatch
9.1 The material dispatch commitment
period is measured, in weeks, from the
latest date of receipt and acceptance by
Zamil Steel offices of all of the following
job related documents:
Signed contract.
10
Pre-Engineered Buildings
Pre-Engineered Buildings
11
12
Pre-Engineered Buildings
Pre-Engineered Buildings
13
in their open yards, any or all the materials for a contract for a period not
exceeding 10 days from the scheduled
dispatch date.
24.2 Should a customer delay dispatch of
goods for a period exceeding 10 days
after the originally scheduled dispatch
date, STORAGE CHARGES will be
levied by Zamil Steel, at the rate of
0.1% of the ex-works selling price (of
the unshipped material) per day up to
a maximum of 5%.
24.3 Zamil Steel shall not be held
responsible for damage caused to the
exposed steel after it has been stored
longer than 10 days. Such damage
may include deterioration of the paint
coating.
25. Warranty
25.1 Zamil Steel warrants the materials it
manufactures for a period of one year
from the date of material dispatch.
This warranty extends only to failure
due to defective materials or workmanship, and covers only products
that are utilized in the intended manner.
25.2 Zamil Steel warrants that the structure
will support the loads described in
Zamil Steels drawings and contract
when properly erected, as part of a
complete structural system designed
by Zamil Steel and made up only of
parts made by Zamil Steel, provided
that the structure is used in the manner and purpose for which it was
designed.
25.3 No warranties are expressed or implied other than those described in
these Terms and Conditions of Sale.
24. Storage
14
Pre-Engineered Buildings
the building maintenance is warranted for 12 months from the date of provisional acceptance by the customer.
Zamil Steel shall not be held accountable for delays in material dispatch or
delivery (after dispatch) resulting from
circumstancesoutside its control, such
as strikes, acts of war, revolution, riot
or civil disturbance, trade sanctions or
restrictions, occurrences of meteorological or geophysical nature, etc., to
the extent that these affect transport,
communications, manufacturing and/
or erection by Zamil Steel, its suppliers
and its subcontractors.
Pre-Engineered Buildings
15
Pre-Engineered Buildings
11
March 2012