Large Diameter Steel Piping
Large Diameter Steel Piping
Large Diameter Steel Piping
TCE.M6-ME-590-424
SECTION: TITLE
SHEET (i) OF (iv)
REV. NO.
R0
R1
R2
ISSUE
INITIALS
SIGN.
INITIALS
SIGN.
INITIALS
PPD. BY
VBS
Sd/-
SMM
Sd/-
PV
CKD. BY
RKC
Sd/-
PV
Sd/-
VBS
APP. BY
SJB
Sd/-
SCM/RL
Sd/-Sd/-
PDG/RL
SIGN.
INITIALS
SIGN.
R2
DATE
19.04.1991
25.03.2000
29.01.2003
TCE FORM NO. 020R2
SECTION CONTENTS
CONTENTS
SL. NO.
DESCRIPTION
SH. NO.
1.0
INTRODUCTION
2.0
INPUT DATA
3.0
MATERIALS
4.0
HYDRAULICS OF PIPELINES
5.0
6.0
SUPPORTS
7.0
WATER HAMMER
8.0
ANCHORS
9.0
SPECIALS
10
10.0
PIPE JOINTS
12
11.0
14
12.0
PROTECTIVE COATING
14
13.0
REFERENCES
15
FIGURES
Fig.1, Fig. 2 a
TYPES OF SUPPORTS
16
TYPES OF SUPPORTS
17
OF
FORCES
IN
VARIOUS
18
19
ISSUE
R2
TCE FORM NO. 120 R1
SECTION CONTENTS
SHEET (iii) OF (iv)
20
Fig. 6
TYPES OF FLANGES
21
Fig.7
21
Fig. 8
22
Fig. 9
23
ISSUE
R2
TCE FORM NO. 120 R1
TCE.M6-ME-590-424
REVISION STATUS
REV. NO.
DATE
DESCRIPTION
R0
19.04.1991
--
R1
25.03.2000
R2
29.01.2003
ISSUE
R2
TCE.M6-ME-590-424
1.0
SECTION: WRITE-UP
SHEET 1 OF 23
INTRODUCTION
This design guide covers the criteria for design of large diameter steel
pipes > 400 NB for the benefit of practising water works Engineers.
2.0
INPUT DATA
The following input are required for the design of large diameter steel
pipelines for systems like cooling water, water supply etc :
3.0
(a)
Normal and maximum flow and flow for any future expansion
if any.
(b)
(c)
Design pressure
(d)
External pressure.
(e)
(f)
(g)
(h)
(i)
(j)
MATERIALS
Materials depend upon the type of fluid which is being handled.
Normally carbon steel pipes are used with internal lining, if applicable.
The normally used internal lining material is mortar. This is especially
applicable for service like sea water and in case of water supply
system. For details chapter on 'Protective Coating & Lining' in
AWWA Manual-M11 shall be referred.
4.0
HYDRAULICS OF PIPELINES
4.1
SELECTION OF DIAMETER
The criteria for design is that the pipeline should convey the required
quantity of water at the lowest capitalised cost i.e. the cost inclusive of
ISSUE
R2
TCE.M6-ME-590-424
SECTION: WRITE-UP
SHEET 2 OF 23
initial installation and cost loading for power. For preliminary sizing
of the piping, a velocity of 2 m/sec may be used. The recommended
velocity range is 1.25 m/sec to 3 m/sec. Additional flow requirement
in the line in future, if any, due to plant expansion shall be considered
for pipe sizing in consultation with the client.
4.2
DESIGN PRESSURE
The design pressure to be adopted for designing the pipelines will
depend on the following factors.
(a)
(b)
(c)
V
C
1.852
1
D
1.167
6.815 x
x L
where -
ISSUE
R2
SECTION: WRITE-UP
SHEET 3 OF 23
TCE.M6-ME-590-424
Bends, fittings and valves also constitute a major part of the friction
loss in the system. The loss in the system shall be calculated on the
following basis :
Friction loss =
k V2
2g
where k
The k value for different fittings shall be taken from the design guide
TCE-M6-ME-613-212 for "Calculation of Hydraulic Losses for Water
in Pipes, Fittings and Valves."
5.0
5.1
UNDERGROUND PIPING
5.1.1
5.1.2
Wall thickness shall be such that the compressive stress in the pipe
shell under external loads with the negative internal pressure is within
prescribed limit of allowable stress.Allowable deflection for various
lining and coating system that are often accepted as:
Mortar lined & coated
2% of pipe diameter
Mortar lined & flexible coated 3% of pipe diameter
Flexible lined & coated
5% of pipe diameter
ISSUE
R2
TCE.M6-ME-590-424
5.1.3
SECTION: WRITE-UP
SHEET 4 OF 23
Wall thickness shall be such that the tensile stress in the pipe shell
under external loads with the internal pressure, is within prescribed
limit of allowable stress.
The allowable stress in the pipe shell shall be related to yield stress (fy)
of pipe material making due allowance for weld efficiency of the joint.
(a)
Joint Efficiency %
100
90
80
85
5.2.1
Internal Pressure
The wall thickness of straight pipelines for internal pressure is found
using the following formula:
t
pd
2f
where t
=
ISSUE
R2
SECTION: WRITE-UP
SHEET 5 OF 23
TCE.M6-ME-590-424
External Pressure
Procedure outlined in paras UG-28, UG-29 and UG-30 of ASME
Section VIII Division 1 may be adopted for determining the wall
thickness and stiffening requirements for straight pipe under external
pressure.
5.3
GENERAL
5.3.1
5.3.2
Corrosion Allowance
Internal corrosion of unlined pipes depends upon the nature of water
carried. It is preferable to design the required wall thickness of pipe as
determined by above considerations, then select linings, coatings and
cathodic protection as necessary to provide the required level of
corrosion protection. However, if measures are not made to combat
the corrosion, a minimum corrosion allowance of 1.5 mm shall be
added to the net wall thickness found as per above paras 5.1 and 5.2.
5.3.3
TCE.M6-ME-590-424
SECTION: WRITE-UP
SHEET 6 OF 23
SUPPORTS
6.1
6.2
(a)
Fill load
(b)
(c)
(d)
Self load due to weight of pipe and its lining and coating.
6.2.1
Saddle Supports
The pipe shell carried on saddles can be divided into two classes :
6.2.2
(a)
(b)
TCE.M6-ME-590-424
SECTION: WRITE-UP
SHEET 7 OF 23
P loge
t2
R
t
where fL
=
6.2.4
Ring-Girder Construction
ISSUE
R2
TCE.M6-ME-590-424
SECTION: WRITE-UP
SHEET 8 OF 23
When large diameter steel pipe is laid above ground or across ravines
or streams, rigid ring girders spaced at relatively long intervals, have
been found to be very effective supports. Typical ring girder support
detail is given in Fig. 3. The stresses developed in shell as a result of
internal pressure and gravity load due to weight of shell and water are
as follows :
(a)
Hoop stress
(b)
(a)
For detail calculations for supports refer design guide no. TCE.M6CV-HS-G-010 - Design Guide For High Pressure Exposed Steel
Conduits.
7.0
WATER HAMMER
The problem of water hammer in a pipeline consists of containing the
pressure and dissipating the water flow energy. When the waterhammer wave loads the pipe wall, the strain in the wall increases
slightly faster than in strict proportion to stress within the elastic region
and on release of the loading, the reverse occurs. If the pressure rise in
the pipe is sufficient, the walls may be stressed into the plastic region
and experience a permanent set. The water hammer of the system shall
be worked out considering the characteristics of pumps, types and
valves used, distribution system details ,duration of valve closure etc.
The phenomenon of water hammer is extremely complex. Suitable
means like surge tank, surge damper or hydropneumatic chamber,
spring loaded check valve / zero velocity valve should be provided to
reduce the water hammer effect, if required. For further details refer
design guide for Water Hammer Analysis for Pumping Mains
TCE.M6-CV-HS-G-019.
8.0
ANCHORS
The necessity for anchors or thrust blocks arise at angle points, side
outlets, and valves and on steep slopes. When water transmission is
under internal pressure, unbalanced forces develop at these points.
These forces act in the direction bisecting the angle of bend, outwardly
causing development of stresses in pipe shell. The magnitude of the
thrust force for tees and bulk head is equal to the product of the
internal pressure and the cross sectional area of the pipe. At elbows or
bends, the resultant force is given by
ISSUE
R2
TCE.M6-ME-590-424
SECTION: WRITE-UP
SHEET 9 OF 23
2 PA sin
2
where T
The above forces are shown in Fig. 4. In addition there are also small
unbalanced forces at bends caused by the velocity of water flow within
the pipeline. In general this velocity is so low in transmission or
distribution system that its effect is negligible and the thrust force
caused by velocity is not considered.
The anchorages commonly used on pipelines are classified under
following four categories, viz.
(a)
(b)
(b)
(c)
(c)
(d)
(e)
Frame anchors are generally adopted for ring girder pipelines for
resisting unbalanced forces due to friction in expansion joints and at
supports. Anchor indicated in Fig. 5 g is used where the soil is hard or
the terrain is rocky.
Pipelines laid on slopes, particularly above ground, always have a
tendency to creep downhill. It is necessary to provide anchor blocks
placed against undisturbed earth at sufficiently frequent intervals on a
long, steep slope to reduce the weight of pipe supported at each
anchorage to a safe figure.
ISSUE
R2
TCE.M6-ME-590-424
9.0
SECTION: WRITE-UP
SHEET 10 OF 23
SPECIALS
Various types of fixtures adopted in pipeline for ensuring proper
functioning, such as, flanges, branches, expansion joints etc. The
design aspects of some of these fixtures are given in the ensuring
paragraphs.
9.1
FLANGES
Flanges commonly used on pipelines for fixing appurtenances, such as
valves, are of slip ring type or loose rings. These flange rings are
either of unsupported construction or of supported type as illustrated in
the Figs. 6 .
The standard flanges used for fixing appurtenances are of unsupported
type, generally conforming to the requirements of IS 6392 or BS 4504
(Part I), in regard to drilling pattern, number of bolts, diameter of bolts,
thickness, PCD etc. for different pressure ratings.
BRANCHES
For the purpose of dividing or combining flow in pressure pipelines,
branch assembly, such as, tees, wyes and headers are used. These
branches are often reinforced to take care of unbalanced forces
developed in the shell, due to removal of pipe shell portion at the
junction of the arms of the branch.
These branches are usually fabricated from thicker plates than those
required from hoop stress consideration. They are generally reinforced,
where required, with saddle type reinforcement.
In saddle type reinforcement, steel is added, if necessary, to make up
for the area lost in the cutting within the prescribed zone, equal to half
the diameter of opening on either side of main pipe, such that, the hoop
tension that would be taken by the metal lost in cutting would now be
taken by this reinforcement along with the spare thickness available in
the main pipe and the branch pipe, as shown in the Fig. 7.
Referring to Fig. 7, the area remo ved by the opening of the branch is
compensated by the spare area available in pipe shell and branch wall
in the figure as well as by saddle reinforcement and the welds. If
required, reinforcement pad calculation shall be carried out as per
ISSUE
R2
TCE.M6-ME-590-424
SECTION: WRITE-UP
SHEET 11 OF 23
EXPANSION JOINTS
Steel pipelines when laid above ground require expansion joints at
specified intervals to absorb the effect of expansion and contraction
taking place in the metal particularly when the pipeline is empty.
Expansion joints may be located midway between the anchors if the
pipeline is laid level. On slope, the joint is usually best placed adjacent
to or on the downhill side of the anchor point. If such expansion joints
are not provided, the pipeline when it expands is likely to shift away
from its alignment and if such lateral movement is prevented by
providing anchorages, the pipe shell is likely to be subjected to heavy
stresses necessitating the thickness of pipes being considerably
increased. Cost of pipes with thick shells and bulky anchorages would
be high as compared to installation of expansion joints at required
intervals. The most common type of expansion joint used in water
mains of telescopic construction, which accommodate the expansion
and contraction movement of the pipe by suitable displacement of
inner stake, Fig. 8 gives the details of telescopic expansion joints. It is
also recommended to provide guide support after the expansion joint
with the first guide at a distance not exceeding 4 times outside
diameter of pipe.
9.4
MANHOLES
For inspection and maintenance of the pipelines sufficient number of
manholes are to be provided. The most common type in water work is
circular, having a short, flanged neck and a flat, bolted cover.
Manholes will be most useful if located close to valves in the line and
sometimes close to the low points that might need to be pumped out
for inspection or repair. Manholes shall preferably be located at a
spacing of 300 to 500 m.
10.0
PIPE JOINTS
Steel pipe lengths can be joined together in the field by many different
methods to effect rigid or flexible connections, though this type of
joints are not normally used in our office, details are enclosed for
information only:.
Bell & Spigot Lap Welded Joint
Bell & Spigot rubber Gasket Joint
Butt Welded Joints
ISSUE
R2
TCE.M6-ME-590-424
SECTION: WRITE-UP
SHEET 12 OF 23
10.2
(b)
Bell and Spigot Rubber Gasket Joints simplify laying the pipe and
require no field welding. They permit flexibility, water-tightness,
lower installation costs, elimination of bell-holes, etc. Gaskets
conform to AWWA Standards. But these require anchors to prevent
opening out due to internal pressure.
10.3
BUTT-WELDED JOINTS
Butt-welded joints will develop full strength, but will require more
care in cutting and fitting up in the field if changes in alignment or
profile occur frequently. Where welded joints are used, the pipe should
be left bare a sufficient distance back from the ends to avoid damaging
the protective coating by the heat produced during welding. These
joints should be field coated after welding.
10.4
ISSUE
R2
TCE.M6-ME-590-424
10.5
SECTION: WRITE-UP
SHEET 13 OF 23
MECHANICAL COUPLINGS
Mechanical couplings provide ease of installation and flexibility and
are represented by the sleeve and clamp type of coupling.
10.6
FLANGED JOINTS
Flanged joints are not generally used for field joints on large diameter
steel pipe because of their high cost and lack of flexibility. They are
advantageous, however, for special conditions, such as connections to
flanged valves, bridge crossings walls etc.
10.7
11.0
12.0
PROTECTIVE COATINGS
Interior and exterior surfaces of both above ground and underground
pipes may get corroded depending on several factors. It is the duty of
the design engineer to know the principles and causes of corrosion and
adopt sufficient protective measures to combat the same.
12.1
12.1.1
12.1.2.
Buried Piping
Many factors influence underground soil corrosion. The single most
important factor, however, which is readily measured is the resistivity
of the soil.
Coatings have long been used to inhibit the corrosion process. The
American Water Works Association presently recognises two coatings
materials - coal tar enamel and cement mortar - for steel water pipes.
ISSUE
R2
TCE.M6-ME-590-424
SECTION: WRITE-UP
SHEET 14 OF 23
13.0
REFERENCES
The following literature can be referred if further details are require
with respect to large diameter piping:
(a)
(b)
AWWA - M11
ISSUE
R2
TCE.M6-ME-590-424
SECTION: WRITE-UP
SHEET 15 OF 23
(c)
AWWA C208
(d)
ISSUE
R2