Nothing Special   »   [go: up one dir, main page]

Water Distribution System Rehabilitation

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

UNACCOUNTED FOR WATER (UFW) REDUCTION & CONTROL

AND
WATER DISTRIBUTION SYSTEM REHABILITATION (WDSR)

Mr. Takeru Tsuchiya


Engineer, Advisor, Division 3, Sector Strategy Development Department
Japan Bank for International Cooperation
1. Background
Bangalore Water Supply and Sewerage Board (BWSSB) proposes to draw the final
installment of allocated water from River Cauvery under Cauvery Water Supply
Scheme(CWSS) Stage Ⅳ , Phase Ⅱ . Government of Karnataka (GoK) in India has
allocated 1,469 Mld of Cauvery Water to BWSSB. Under CWSS Stages Ⅰ, Ⅱ, and Ⅲ,
BWSSB is drawing about 614 Mld of raw water. OEFF funded, now known as Japanese
Bank for International Cooperation(JBIC), CWSSB Stage Ⅳ, Phase Ⅰat the final stages of
completion. Water supply components have been already commissioned and an additional
315 Mld is being drawn from Cauvery river. Under CWSS Stage Ⅳ Phase Ⅱ, BWSSB
proposes to draw the balance 540 Mld.
Bangalore, the capital city of Katnataka state, is one of the fastest growing cities in India.
The present population of about 5,7 million is expected to increase to over 7 million by the
year 2011 and the area covered by the city is projected to increase from the present 446 km2
to 594 km2 in the same period.

Meanwhile, the major problem BWSSB is facing at present is the high level of
unaccounted-for water (UFW). UFW rate is estimated at approximately 50 % of water supply.
These high losses increase the cost of supply and contribute to the substantial operating
subsidies required from GoK. As a consequence of high UFW, especially due to leakage,
consumers are not able to obtain sufficient quantity of water with adequate pressure for their
needs. The water supply duration in the project area is around 6 hours on alternative days.
Hence it is essential that UFW levels be reduced to acceptable levels as rapidly as possible.
The additional revenue generated because of reduced leakage/UFW will improve financial
status and ensure sustainability of waterworks.

BWSSB has taken up a pilot project in UFW and the estimated cost of the works is
about Rs 480 Millions. In addition to CWSSB Stage Ⅳ, Phase Ⅰ, JBIC has also funded
this project , specifically valves, meters and leak detectors, and the consulting services as
technical assistance.

1
2. Description of the Works

Table. Statistics of the Pilot Project Area


Pilot Project Area Bangalore
Area 30 km2 1,279 km 2

(565 km2 Urban, 714 km2 Greenbelt)


Population 400,000 4.84 million
Water supply volume 70 MLD 850 MLD
No. of connections 32,000 380,000
Length of mains 302 km -

The scope of the work includes carrying out UFW survey and remedial measures for
about 35,000 service connections and 302 km water of Distribution network. The work
comprises establishment of District Meter Areas (DMAs) within the pilot area for the purpose
of monitoring of UFW and detection of leakage. Provide bulk meters to measure water
consumption, inspection of all
Shut
Shut! ! Shut
Shut! !
consumer meters, fixing of new meters
on unmetered water connections or on
connections where meters are not
working, testing of meters for accuracy,
recording of consumptions on revenue M
meter to measure water supplied to
the consumers. The difference
DMA
DMA
between the input into DMA and water
Valve Boundary Valve
supplied to consumers is the total loss
of water in the DMA. Decide Pipe M District Meter
DMA is established with boundary valves which make DMA
permissible loss to get target levels
hydraulically isolated and limit inflow/outflow points of DMA.
and carryout leak detection survey, At limited inflow/outflow points, district meter will be installed
identify leaks, repair leaks and retest to measure inflow volume of DMA accurately. UFW can be
calculated as shown below.
the DMA till loss of water is reduced to UFW = [Inflow to DMA] – [Consumption in DMA (billed
target leakage level. amount)]
Figure. Concept of DMA
Also, carryout condition
assessment survey of water distribution network in the DMA / pilot area and rehabilitate
water pipelines prone to leaks.

Work also includes renewals/replacement of service connections using MDPE pipes where
necessary.

2
Design of DMA shall be done with the aid of computer network models, high level model
covering the project area and low level models for each DMA to ensure and demonstrate
that the proposed DMA establishment works will be able to maintain adequate hydraulic
capacity of the DMA under 24 hours satisfied demand conditions as well as ensuring no
unacceptable detrimental impact on supplies to areas adjacent to the DMA. The boundary of
the DMA shall be watertight.

Circulating valves, i.e. those


valves that are closed in order to
remove all loops from within the DMA
thus producing a tree-like mains
layout, shall be identified and new
valves installed where necessary,
which will make leakage detection
works more easily and efficiently.

The size and extent of areas


within the DMA that can be
progressively isolated in order to
identify leakage levels across the
DMA shall be determined to minimize
the need for step valves
commensurate with best step-testing Figure. DMA
practice. New step valves shall be installed where necessary.

3. Current Status of the Project


Progress of the project is about 60 % as of the end of May. 2004. The current result is
encouraging. In progressed DMA (DMA-3A), UFW has been reduced down to 53% of initial
volume. Besides in DMA-1, UFW has been reduced down to 54%. And in DMA-3C, UFW
has been reduced down to 70%. The status of the project is based on the data prepared by
BWSSB and its consultant team.

3
Leakage Restructuring distribution networks
UFW rate is estimated at 50% of water supply volume Based on the hydraulic analysis, restructuring work
such as re-connection etc, is being done so as to
ensure optimal water pressure within DMAs.

Installation work of DM (district meter) Installation work of DM


Bulk meters, called district meter, are installed at inlet Water flow meter (right) and Pressure gauge (left)
points of DMAs to measure supply volume to
eachDMA.

Revenue meter box


To prevent physical damage, water meter is installed
with meter box.

4
Site survey
Confirm the data on existing facilities such as location
Data logger box
of valves, junctions of distribution pipes, house
connections, etc.
Monitoring actual water flow and pressure, DMA
design is reviewed.

Listening stick Pressure gauge


Checking watertight of boundary valves of DMA. Pressure gauges are installed at strategic points of
DMA should be hydraulically isolated. DMA in order to know water supply condition. Logged
data is used for computer simulation model and design
review.

You might also like