1823973
1823973
1823973
Ron Basu is based at Henley Management College, Henley Business School, Gerrards Cross, UK. Chris Little and Chris Millard are both based at BAA Capital Programmes, Heathrow Airport, Hounslow, UK.
Summary Purpose The purpose of this paper is to present a case study of the Heathrow Terminal 5 project and to illustrate a customised application of the Balanced Scorecard in a major infrastructure project with multiple stakeholders. Design/methodology/approach The research methodology applied in this work was based on the case study methodology. The focus was on how questions and exploratory analysis of primary and secondary data supported in-depth interviews with members from both the project team and suppliers. Findings The application of the concept of the Balanced Scorecard by Kaplan and Norton in project management is less frequent in comparison with operations management. The study has established a proven application of the Balanced Scorecard in managing quality in a major infrastructure project. Practical implications For practitioners of major projects the paper gives implications for implementing the theoretical and customising requirements of the Balanced Scorecard involving key stakeholders. Originality/value The paper illustrates that metrics can be customised for major projects within the framework of the Kaplan and Norton Balanced Scorecard and that suppliers should be empowered to own the monitoring and improvement process using their performance data. Keywords Balanced scorecard, Stakeholders, Suppliers, Partnership, Performance measurement (quality) Paper type Case study
1. Introduction
Heathrow Terminal 5 opened on 27 March 2008 with high expectations. It represents a major step in the transformation of Heathrow and it is now a major gateway to the UK. From the start T5 was different and it needed to be due to its size, complexity and proximity. Despite some teething problems on opening, T5 was a catalyst for new and improved ways of working. One such initiative is the application of a Balanced Scorecard approach in managing quality in major projects. For nearly two decades organisations in both the manufacturing and service industries have been working arduously at trying to bring the power, discipline and rigour of performance measurement into their organisations based on the Balanced Scorecard. The concept of a Balanced Scorecard by Kaplan and Norton (1996) is a strategic measurement system organised in four perspectives (nancial, customer, internal processes, and learning and growth) that aims to establish tangible performance indicators in all functions of the business. One of the proven virtues of this system is that it proposes a balance between concepts that could be contradictory to managers. For example, it aims to balance between short-term and longer-term objectives, nancial measures versus operational measures, internal performance versus external performance, enabling indicators versus results indicators and between leading and lagging indicators.
PAGE 22
VOL. 13 NO. 4 2009, pp. 22-33, Q Emerald Group Publishing Limited, ISSN 1368-3047
DOI 10.1108/13683040911006765
As might be expected, it is soon recognised (Zagrow, 2003; Project Management Institute, 2004) that the same benets an organisation as a whole can derive from the deployment of a Balanced Scorecard based performance measurement system can also be acquired by a projects management. Performance measures enable project managers to track whether the projects they are managing are moving in the right direction. Furthermore, projects do not only provide nancial benets: many of the outcomes of a project are intangible in nature. Project leaders are beginning to come out of the box of traditional project objectives, such as time, cost, risk and safety, and are moving towards the softer issues of project quality (Basu, 2008). This also means that many traditional performance measurement tools do not capture these benets. The Balanced Scorecard approach enables us to identify the intangible drivers and project outcomes. So the application of the Balanced Scorecard in project management is becoming attractive to project managers. However, a customised application of a performance management system based on the concept of the Balanced Scorecard in Heathrow Terminal 5 Project has created a fresh approach to involve all key stakeholders, including major consultants and contractors, to move towards a project quality culture.
set new standards in delighting the traveller at T5; develop and deliver T5 to new industry standards of health safety and security; earn the proactive support and trust of key stakeholders; achieve exceptional performance to ensure value for money, on time delivery and an efcient and productive T5; and leave behind a legacy of quality.
The need of supplier partnerships in line with the T5 Agreement (Little, 2005) and the complexity of rail, road, construction and systems requirements of the project were additional drivers. To achieve these audacious targets in money and programme BAA had to consider a novel contracting and procurement strategy supported by a performance management system. Suppliers signing up to BAA agreements are expected to work in integrated teams and display true partnering behaviours and values akin to partnering. Before embarking on the Terminal 5 (T5) programme of works, BAA looked at a number of major UK construction projects to ascertain lessons learned, particularly where they had gone wrong. BAA decided that they had to have an agreement that could deal with an adaptable and dynamic approach dealing with the uncertainties and embracing integrated teams. So BAA wrote its own bespoke agreement or contract. The same conditions of contract applied to all key
suppliers irrespective of type or usual position as a subcontract. And to support the governance of the project in line with this agreement a Balanced Scorecard based performance management system was developed for the T5 project.
the KPIs give everyone a clear picture of what is important; the KPIs enable the project leadership team to view all projects at a glance in a consistent way; and the KPIs complement the measurement of nancial performance.
However, the need of supplier partnerships and stakeholder management in line with the T5 Agreement and the complexity of rail, road, construction and systems requirements of the project also generated collaborative (Basu, 2001) secondary drivers of customising the Balanced Scorecard in the T5 performance management system. It aimed to address some key management questions:
B
Do we have adequate measures to monitor interface arrangements with key stakeholders? Do the design solutions have the required technical and functional approvals? Have we agreed what to inspect and test and who will verify compliance? Have we benchmarked the quality standards? Are aiming to do it right rst time? Is the work complete, reliable and maintainable at handover?
B B B B B
5 10 37
KEY MEASURES
PERFORMANCE DATA
Table I The relationships between key performance indicators, key measures and performance data
Number of performance measures
Key performance indicators 1. Verications planned and work supervised 2. Benchmarks agreed 3. Inspected and protected
Objectives Plan to get it right rst time Making quality standards visible and achievable Keep work free from error and damage
Key performance measures 1. Inspection and test plan agreed 2. Supervisors RFT trained 3. Samples/benchmarks agreed
6 4
4. Compliance assured
4. Inspections meeting benchmarks and quality standards 5. Checks showing that work and assets are protected Provide team assurance that the 6. Non-conformance resolution and cost brief is met (NCRs) 7. Team certicates of compliance issued Ensure that assets are fully 8. Handovers accepted integrated and maintainable 9. O&M manuals accepted 10. Maintenance work plans accepted
13
12
Table II Guidance notes for the Verications Planned & Work Supervised KPI
Performance measures (data table heading) Inspection & test plans scheduled Inspection & test plans due Inspection & test plans agreed Guidance notes Enter the total number of plans required Enter the cumulative number of plans due to date Enter the cumulative number of plans agreed by team. Refer to CP4 and T5- XXX-QA-00002 for details Enter the cumulative number of supervisors mobilised Enter the cumulative number of supervisors right-rst-time-trained R: ITP or Training . 6 weeks late A: ITP or Training 0-6 weeks late G: ITP & Training Meeting Target for Work in Progress
Supervisors mobilised Supervisors RFT trained Verications planned & work supervised RAG status
leader either as an individual or as a team was aware of the role as a sponsor (responsible), owner (accountable), contributor (consult) or participant (inform). Table IV shows an example of RACI for key performance indicators.
Inform
Production leader Project leader Design manager Technical manager Supplier Principal point of contact (PPOC) Programme ofce Quality leadership Group leaders
1. the T5 Agreement; and 2. a four-tiered approach of quality culture. The T5 Agreement was agreed between BAA and the major consultants and rst tier contractors. Under the terms of this T5 Agreement, BAA took a single insurance policy to cover the multi-billion pound project. And because BAA had shouldered the risk, it expected the consultants and suppliers to work together. People from all stakeholders were encouraged to raise issues at the earliest opportunity. This helped the reporting and discussions on performance and non-conformance issues. When you align peoples objectives, stuff happens. The agreement has allowed us to work with our consultants and suppliers in a refreshing new way, says Andrew Wolstenholme, T5 Project Director. As shown in Figure 2, an inter-related four-tier approach (Millard, 2005) of embedding quality culture to project team members and suppliers was introduced in 2005. This four-tier approach is an on going process and is primarily driven by focussed discussion groups and workshops. The stakeholder engagement and commitment process is supported by the project executives commitment to engage with project leadership and suppliers (principals) to introduce a right rst time quality concept and get their buy-in and commitment. The culture and behaviour change process has been iterative, comprising
regular workshops, brieng, awareness and feedback on quality KPIs and right rst time behavioural change programme. This is further supported by the third-tier communication campaign, which includes quality logo branding, quality commitment workshops, quality booklets, quality walkabout, quality awards and posters. The fourth tier on quality best practice started with research and interviews with experts to establish best practices and align them with quality KPIs. This was followed by supervisor training and workshops to ensure understanding and ownership from supervisors. 5.2 Monitoring and Improvement Each project team (such as aireld, baggage, rail, TTS, etc.) record, measure and monitor each performance measure, and on a monthly basis the ten key performance measures are reported as a Balanced Scorecard. Table V shows an example of a Balanced Scorecard. The overall T5 results for Key Performance Measures are also presented graphically as the quality management prole shown in Figure 3. The key performance measures provide a snapshot of the performance of each project team, which are also highlighted by RAG (red, amber, green) colour codes according to their status with regard to targets. However improvement projects are acted upon more by individual performance measures at the specic project level. The most signicant contributors to improvement projects are non-conformance reports (NCRs). There are nine performance measures related to NCRs as part of one KPI, viz. compliance assured. These measures enable the quantication of a part of COPQ (cost of poor quality) given by estimated cost of NCRs. Root cause analyses by type of non-conformance and supplier lead to continuous improvement in design and processes and savings. Figure 4 shows an example of NCR report analysis. Overall, circa 6,000 non-conformance reports were raised on T5 and the cumulative cost of non-conformance was only 0.6 per cent of the budget. Analysis of the data showed that 70 per cent of the total cost of non-conformance resulted from just 150 reports. A no-blame culture resulted in speedy and effective resolution of all issues.
Project team 100 74 100 100 100 100 99 100 86 100 100 100 100 99 98 87 88 76 100 73 87 98 78 72 100 100 71 86 97 92 92 83 100 62 92
Maintenance integration work plans accepted 100 100 0 100 100 0 100
Handovers accepted 100% Team Certificates of Compliance Issued 99% NCRs Closed 92%
Inspections Meeting Benchmark & Quality Standards 87% Checks Showing Work is Protected 86%
7. Learning points
It is evident from the preceding analysis that the fundamental principles of the Balanced Scorecard have been gainfully adopted and customised to the performance management systems of T5 meeting the specic requirements of this complex major project. The best practices of project performance management arising from this case study include:
B
encouraging supplier partnership and proactive involvement of contractors in monitoring and improving project quality and conformance to standards;
CUSTOMER
To achieve our vision, how should we appear to our customers?
Objectives Measures Targets Initiatives
To satisfy our shareholders and customers, what business process must we excel at?
Objectives Measures
Targets
Initiatives
To achieve our vision, how will we sustain our ability to change and improve?
Objectives Measures
Targets
Initiatives
Note: T5 KPIs are shown in bold italics Source: Kaplan and Norton (1996)
Internal processes
providing indicators and measures in three main themes as enablers, monitoring progress and showing results along the project life cycle right up to the handover and completion of work; the metrics and processes are validated and then embedded by extensive discussions with stakeholders followed by documentation, communication campaign and training workshops; and the ongoing reporting of non-conformance reports (NCRs) supported by the estimation of cost of non-conformance and improvement projects based on root cause analysis is a strong point of the process and opens the opportunities for Six Sigma and innovation.
The application of the T5 Balanced Scorecard over a few years has also focused on areas of further renement. These include:
B
incorporate Six Sigma training and methodology in the project quality strategy and link them with NCR-related measures; explore and then extend a Balanced Scorecard approach and metrics to the design phase (including conceptual and preliminary engineering) of a major project (this is now in place for BAA major capital projects); and align the key performance indicators and measures to a formal self-assessment of EFQM (European Foundation of Quality Management) type excellence process.
In Kaplan and Nortons Balanced Scorecard the enabling or leading indicators are learning and growth. In the T5 Balanced Scorecard the enabling indicators are Benchmarks Agreed and Verications Planned & Work Supervised.
References
Basu, R. (2001), New criteria of performance management: a transition from enterprise to collaborative supply chain, Measuring Business Excellence, Vol. 5 No. 4, pp. 7-12. Basu, R. (2004), Implementing Quality, Thomson, London. Basu, R. (2008), A third dimension of project quality, Quality World, May, pp. 34-8. Kaplan, R.S. and Norton, D.P. (1996), The Balanced Scorecard, Harvard Business School, Boston, MA. Little, C. (2005), BAA Terminal 5, paper presented to IQA Conference, Bali, 18 May. Millard, C. (2005), Make T5 quality, internal BAA document, February. Project Management Institute (2004), A Guide to the Project Management Body of Knowledge (PMBOK Guide), 3rd ed., Project Management Institute, Newtown Square, PA. Zagrow, H.W. (2003), Applying the Balanced Scorecard in project management, AllPM Project Manager Project Management, November.
Further reading
Yin, R.K. (2003), Case Study Research: Design and Methods, Sage Publications, London.
To purchase reprints of this article please e-mail: reprints@emeraldinsight.com Or visit our web site for further details: www.emeraldinsight.com/reprints