FE Review for Engineering Economics

FE Review for Engineering Economics


http://ristroph.louisiana.edu/EngrEcon/Overhead/FEReview.pdf Present Economics
$ Revenue = ($/unit)X Profit = Revenue Total Cost Total Cost = Fixed Cost + Variable Cost Variable = ($/unit)X Cost Fixed Cost Breakeven X (units)

Total Cost

Breakeven Diagram

f(x) $

df(x) dx = 0

x*

x (units)

Nonlinear Revenue or Profit

8/17/08 J H Ristroph

FE Review for Engineering Economics

$ TC1 TC2 Method 1 Method 2 Breakeven x (units)

Alternative Production Methods

Expected Profit or Cost P(100) = 30% P(200) = 20% P(300) = 50% Expected value = 220 = 100(0.30) + 200(0.20) + 300(0.50)

Equivalence
Single Payments

E4 55
2 3 4 5

65

100 Single Cash Flows


E4 = -100(F|P,i,4-2) + 55(P|F,i,5-4) + 65(P|F,i,6-4)

8/17/08 J H Ristroph

FE Review for Engineering Economics

Uniform Series

E3

100

E20

20

Simple Series E3 = 100(P|A,i,20-3) E20 = 100(F|A,i,20-3)

E-2 E3

100

E20 E30
20 30

-2

Two Step Equivalents to 100 Series E-2 = E3(P|F,i,3-(-2)) E30 = E20(F|P,i,30-20)

E-2 E3

100

E20

E30

-6 -5 -4

-3

-2

20

30 31 32 33 34

Three Step Equivalents to 100 Series E -5 to -2 = E-2(A|F,i, -2-(-6)) E 31 to 33 = E30(A|P,i,34-30)

8/17/08 J H Ristroph

FE Review for Engineering Economics

Arithmetic Gradients

54 50 52

70

B = 50

=
20 9 10 11 12

+
20

G = +2 20 2 4

9 10 11 12

9 10 11 12

20

Linear Trend

Base Series Arithmetic Gradient Components of a Linear Trend

9 10 11 12

20

9 10 11 12

20

9 10 11 12

20

=
70

50 52 54

B = -50

2 4 20 G = -2

a) Negative Base Series and Negative Gradient 70 68 66

B = 70 50
20

9 10 11 12

9 10 11 12

20

9 10 11 12

20

b) Positive Base Series and Negative Gradient

4 20 G = -2

G = +2 20 2 4
9 10 11 12

20

9 10 11 12

20

9 10 11 12

20

66 70 68

50

B = -70 c) Negative Base Series and Positive Gradient

Types of Linear Trends

8/17/08 J H Ristroph

FE Review for Engineering Economics

Er = G (P | G, i, s-r ) (s-r-1)G G 2G
r r+1 r+2 r+3 s

Arithmetic Gradient Present Worth Factor

(s-r-1)G G 2G
r r+1 r+2 r+3 s

EU = G (A | G, i, s-r )

r r+1 r+2 r+3

Arithmetic Gradient Uniform Series Factor

Effective Interest
r = nominal rate, such as 12% per year compounded monthly P = number of short periods in the long period, such as 12 months in a year iP = r / P = rate per short period, such as a month ie = (1 + iP)P 1 = effective (or true) interest rate for the long period, such as a year Example: 18% per year compounded monthly P = 12 im = 1.5% per month = 18% / 12 = true monthly rate ie = (1 + 0.015)12 1 = 19.56% effective (or true) interest rate per year

8/17/08 J H Ristroph

FE Review for Engineering Economics

Example: 12% per year compounded monthly with quarterly cash flows => The monthly interest rate is 1%
Q M

Q3

M
4 5

Q6

Q33

Q36

0 1 2 12

0 1 2 3 6 31 32 33 34 35 36

i = 3.0301% / qr 1,000

i = 1% / mo 1,000 Monthly Rate, Quarterly Payments

If draw cash flow diagram on a quarterly basis, must use quarterly rate 3.0301% = (1 + 0.01)3 1 <= 3 months per quarter Q = 1000(A|P, 3.0301%, 12-0) If draw cash flow diagram on a monthly basis, get monthly payments Em = 1000(A|P, 1%, 36) , Step 1

Since lender only getting quarterly payments, then must pay interest on missed monthly payments Q3 = Em (F|A, 1%, 3-0), Q6 = Em (F|A, 1%, 6-3) --Q36 = Em (F|A, 1%, 36-33) In general, Q = Em (F|A, 1%, 3-0) Step 2 Continuous Compounding (P | F, r, n) = er n (F | P, r, n) = e r n $58.58 = 11 e 0.1(5-1.5) + 13 e 0.1(5-3) + 17 e 0.1(7-5) + 18 e 0.1(9.2-5)
E5

11 13
1.5 3

17 18
7 9.2

Continuous Compounding Factors

8/17/08 J H Ristroph

FE Review for Engineering Economics

Present Worth
All cost and benefits given: draw cash flow diagrams and compute PW. Equal lives not necessary. Only costs given: equal benefits or known difference in benefits must be assumed. Planning horizon can be truncated. For example, 3 and 4 year pumps can be compared over a 7 year planning horizon. Just draw the cash flows for the 7 years, compute the PC's, and choose the smallest. Planning horizon can be a common multiple with fully repeating, identical life cycles. For example, 3 and 4 year pumps can be compared over a 12 year planning horizon. Compute the EAC of the 3 year pump over its 3 year life life cycle, and the EAC of the 4 year pump over its 4 year life cycle. Then for each pump EACOver 12 years = EACLife Cycle PCOver 12 years = EACOver 12 years(P|A, i, 12-0) "Capitalized cost" means present cost, usually of an infinite series. (P|A, i, ) = 1/i Equivalent is one period before the first series flow

Equivalent Annual Worth


All cost and benefits given: draw cash flow diagrams and compute EAW. Equal lives not necessary, but compute all EAW's over same time period, usually the life of the longest alternative Only costs given: equal benefits or known difference in benefits must be assumed. Planning horizon can be truncated. For example, 3 and 4 year pumps can be compared over a 7 year planning horizon. Just draw the cash flows for the 7 years, compute the EAC's, and choose the smallest. Planning horizon can be a common multiple with fully repeating, identical life cycles. For example, 3 and 4 year pumps can be compared over a 12 year planning horizon. Compute the EAC of the 3 year pump over its 3 year life life cycle, and the EAC of the 4 year pump over its 4 year life cycle. Then for either pump
8/17/08 J H Ristroph

FE Review for Engineering Economics

EACOver 12 years = EACLife Cycle If the planning horizon is infinite (A|P, i, ) = i Equivalent series begins one period after original cash flow Heuristic: long and indefinite planning horizon with repeating life cycles: EACPlanning Horizon EACLife Cycle

Internal Rate of Return


Solve PW = 0. Reject if IRR < AMRR (MARR) If any alternatives left: Rank in order of increasing first cost On a pair-wise basis, compute Higher Cost Lower Cost cash flows Solve PWHigh Low = 0 to compute NIRR Choose High if NIRR AMRR (MARR) Choose Low if NIRR < AMRR (MARR) Comparing pure cost ventures, such as pumps, using NIRR Cannot compute IRR's, so skip that step Rank and do pairwise comparisons as above

Benefit Cost
Compute PB / PC. Reject if PB / PC < 1 If any alternatives left: Rank in order of increasing present cost On a pair-wise basis, compute

PB PB High Low NBC = PC PC High Low


Choose High if NBC 1 Choose Low if NBC < 1

8/17/08 J H Ristroph

FE Review for Engineering Economics

Special Topics for PW, EAW, or IRR


Bonds Redemption period or bond life is when its last payment is made Face, redemption, or par value is what owner receives at end of bond life Coupon rate or bond's rate is used to compute the periodic payment or coupon Coupon = Face Value x Coupon Rate Maximum to pay is present worth computed at buyer's discount rate Example: 10 year bond with 1,000 face value and 8% coupon rate. Buyer can earn 12% elsewhere Max = 1,000(0.08)(P|A, 12%, 10-0) + 1,000(P|F, 12%, 10-0) Example: Similar bond, but third payment just made Max = 1,000(0.08)(P|A, 12%, 10-3) + 1,000(P|F, 12%, 10-3) Example: "Zero coupon," 10 year $1,000 bond that makes no payments and current time is 3 Max = 1,000(P|F, 12%, 10-3) Stocks Estimate cash flows from dividends and sale of stock Max to pay = PW of those cash flows Sunk Costs Always ignore costs that have already occurred. Decisions can be made only regarding choice of present and future cash flows Loan Payoffs Suppose 10 year loan with yearly payments at 8%: Note = (Amount Borrowed)(A|P, 8%, 10) Suppose at time 3 and just made payment. Then discount remaining payments Amount Owed = Note(P|A, 8%, 10-3)

8/17/08 J H Ristroph

FE Review for Engineering Economics

10

Replacement
Cash Flows Defender: Initial cost is its current market value, not its book value or trade-in value. Yearly costs are operations and maintenance costs, and then salvage at end of life is usually a benefit but can be a cost Challengers: Initial cost of each challenger is its installed cost. It also has yearly O&M costs, and salvage at end of life Fixed planning horizon with at most one replacement Draw cash flow diagrams over planning horizon, compute either PC or EAC and choose best alternative Multiple replacements # Possibilities = (1 + # Challengers)n Try to find best possibilities using EAC and common sense Heuristic for keeping defender at least one more year or replacing today Assumes identical replacements with long, indefinite horizon For each alternative, compute its economic life. Use trial and error to compute the EAC's for several years. Economic life occurs where the EAC is the smallest. Call this value EAC*. Compare every EAC* and choose the smallest one. If it is a challenger, replace the defender today with that challenger. If it is the defender, keep it for at least one more year with exact timing determined using defenders marginal cost

Depreciation
BV0 = Installed Cost BVj = BV0 D1 D2 --- Dj BVj = BVj-1 Dj n = recovery period or depreciation life SV = legal salvage value

8/17/08 J H Ristroph

FE Review for Engineering Economics

11

Straight line Dj = (BV0 SV ) / n Declining Balance Declining balance rate = 100%, 125%, , 200% (double dec. bal.) p = DBR / n Dj = pBVj-1 until reach SV Optimal switch from DB to SL for SV = $0: first Dj using SL when j n /DBR + 1 Switch at time j 1 so SL is used during year j and first SL charge at time j MACRS Look up recovery rate rj in a table Dj = rj BV0 Early retirement: mid-year for personal and mid-month for real

Taxes
ATCF = BTCF Cash Flow for Taxes t = tax rate (depends on bracket) Always use rate for current bracket, never average rate Applied to taxable income Ordinary income taxes = Bracket Amount + t (Amount in Bracket) Business: Taxable Income = Revenue Expenses GLD Cannot deduct a purchase, only depreciation Personal: Taxable Income = Gross Income (includes GLDs) Adjustments Personal Exemptions Deductions Deductions = max(Itemized deductions, Standard deduction)

8/17/08 J H Ristroph

FE Review for Engineering Economics

12

Gain or loss on disposal laws are complex. If $0, then ignore. Effective Tax Rate = Federal Rate + State Rate (Federal)(State), state deductible from fed = (Fed + State 2FedState) / (1 FedState), if mutually deductible

Inflation
Nominal dollars in year j are the number of dollars: Nj Real dollars in year j refers their purchasing power relative to some earlier year: Rj Suppose that $100 dollar bills are required to purchase goods in 2010 that can be purchased for $60 in 2000. Then the $100 nominal dollars handed to the vendors in 2010 have a value of $60 real dollars relative to 2000. Inflation rate is the percentage increase in prices each year: f Nj = (1+f ) j Rj If inflation averages 5.24% from 2000 to 2010, how much will goods costing $60 in 2000 cost in 2010? Call year 2000 time 0, then 100 = (1+0.0524 )10 60 Real dollars can be computed using Rj = Nj / (1+f ) j If inflation averages 5.24% from 2000 to 2010, how many real dollars worth of goods relative to 2000 will $100 nominal dollars in 2010 purchase? 60 = 100 / (1+0.0524 )10 Economic measures Nominal or inflation adjusted discount rate is n = f +r + rf, where r is the real discount rate (AMRR based on real dollars) Real discount rate is r = (n f ) / (1 f ), where n is the nominal discount rate (AMRR based on nominal dollars)

8/17/08 J H Ristroph

FE Review for Engineering Economics

13

PWR = PWN Other measures: Use nominal rate on nominal dollars and real rate on real dollars. Multiple rates: use rates for each sector to compute net nominal and then deflate to real using general (CPI or PPI) deflator After tax analyses with inflation Estimate all BTCF cash flows as nominal dollars Remember that depreciation charges are fixed by law, so they do not change Gains or loses on disposal must be computed using nominal dollars Compute the ATCF as nominal dollars Deflate to real dollars (or directly discount the ATCF using the inflation adjusted discount rate)

Good luck! Let me know how you do when you take the FE Exam. Drop me an email and let me know the types of questions being asked so that this review can be kept current. ristroph@louisiana.edu