MOS-Post install Starter Bar
MOS-Post install Starter Bar
MOS-Post install Starter Bar
1
Contents
1. Introduction............................................................................................................................................................................. 4
2. Scope........................................................................................................................................................................................... 4
3. Technical Specification & Reference Details..............................................................................................................6
4. Materials.................................................................................................................................................................................... 7
5. Tools & Equipment............................................................................................................................................................... 7
6. Procedure.................................................................................................................................................................................. 8
5. Coring.......................................................................................................................................................................................... 8
6. Standard Installation Procedure for Post Fixing Rebar........................................................................................9
7. Safety........................................................................................................................................................................................... 9
8. Inspections................................................................................................................................................................................ 9
2
1. Introduction
Post-installed reinforcing bar connections are an increasingly important structural
element in repair or upgrading construction and gaining increasing popularity. They are a
reliable and economical means to strengthen or extend existing reinforced concrete
structures with the same performance characteristics comparable to cast-in reinforcing bars
under the assumption that anchoring mortars and reinforcing bars are selected, designed,
and installed by appropriately qualified and experienced personnel.
The connections between existing and new construction are made by installing
deformed reinforcing bars in boreholes drilled using diamond or hammer drilling in the
existing RC structure. The connection between the deformed reinforcing bar and existing
concrete is realized through bonding using a qualified anchoring mortar. Then the new
concrete member is cast. Typical applications include lap splice with existing reinforcement
or anchorage of the reinforcement in a slab, beam or foundation.
To simplify the installation of post-installed reinforcing bar connections and to avoid
improper installations, manufacturers of organic anchoring mortar injection systems provide
product dependent installation kits prepacked in boxes containing all equipment necessary
to clean the borehole and inject the anchoring mortar properly.
Lbd design value of development length, lsd design value of splice length.
(Grey hatch areas represent existing structural component)
Fig 1: Lap splices with existing and post-installed reinforcing bar
2. Scope
This method statement covers the step-by-step procedure and action refer to re-install
existing starter bar for 3rd floor stair 1B zone B2 (SB2 20X50) to be connecting to the 4th
floor beam (B6A 35x70) Zone B2, Grid X14. (As shown fig. 2).
This method statement covers the various requirements to be provided for preparation
like chipping and expose the existing rebar, marking to position the additional starter bar
location, reconnaissance to confirm and ensure that the existing rebar doesn’t get disturbed
and then do core drilling to required depth.
3
Fig. 2: 3rd Stair 1B zone B2 Layout plan
4
3. Technical Specification & Reference Details
1) Refer to the drawing approved by the consultant, Beam SB2-20x50, which provide main
bar 3DB20 both top and bottom rebar with a 2DB12, Contractor would like to request to
apply this method to comply with the design stated.
5
3) Hole depth will be a minimum 250 mm. Reference locations of beam starter rebar is
available for consultant review.
Fig. 3: Location and depth detail for SB2 20x50 connecting to B6A 35x70
4. Materials
6
6. Procedure
7
and the area
8
cleaned. Further normal drilling activity reinstated to continue drilling holes to the
required depth.
8. Standard Installation Procedure for Post Fixing Rebar
Attached to this submittal is a detailed method statement
to be submitted by using Sika -31CF Normal.
9. Safety
9.1 Work Permits should be obtained prior to starting
Work.
9.2 Check proper power supply phase and extension cable
condition prior to starting.
9.3 Close supervision by the contractor is required during
the entire operation.
9.4 Only experienced and skilled labor shall be engaged
for the job.
9.5 The people involved in the construction work
shall wear PPE such as safety helmets, safety shoes,
gloves safety glass, mask etc. as required.
9.6 Site supervisor/ engineer & Safety officer shall check
and ensure that all safety precautions are followed. After fixing