INDUSTRIAL TRAINING REPORT

On
CONSTRUCTION OF OFFICE BULINDING FOR
DIRECTORATE OF CENSUS OPERATIONS
At

CPWD, DEHRADUN
Submitted for Partial fulfillment for the award of degree of Bachelor of Technology
In
Civil Engineering
BIPIN TRIPATHI KUMAON INSTITUTE OF
TECHNOLOGYDWARAHAT, ALMORA

Session 2024-2025

SUBMITTED BY: SUBMITTED TO:


AKASH SHARMA Mrs. RENU SINHA

210180107004 (HEAD OF DEPARTMENT )


IVTH YEAR (7th SEMESTER) ASSOCIATE PROFESSOR
SUBJECT CODE:- BCEP – 702
DECLARATION BY CANDIDATE

I, AKASH SHARMA hereby certify that I have successfully completed my Industrial Training
with “CPWD DEHRADUN” from JUNE 20, 2024 to JULY 24, 2024. This is to certifythat this
training is original product and no unfair means like copying etc. have been used for thistimely
completion.

NAME: AKASH SHARMA


SIGNATURE:

1
ACKNOWLEDGEMENT

No task is a single person’s effort, and same is with this project. I would like to extend my sincere thanks to all
those who have helped me in accomplishing my training successfully and satisfactorily.
I would like to thank Mr. V.K. KOHLI ( EXECUTIVE ENGINEER ) for the experience I could gain under his
valuable guidance
I cannot afford to forget the efforts put in by MR. PAWAN KUMAR for the helping hand she extendedfor the
completion of my project in EIL. She ceaselessly worked and cleared all my doubts and remained uncomplaining
about my constant visits for doubt sessions to her. I appreciate and regard her for framing a betterengineer out of
me.
My heartiest regards are extended to my TRAINING COORDINATOR Mr. A.K. AGGRAWAL
who helped me in broadening my horizons and see the world through the eyes of a civil engineer.
I would like to express my heartfelt thanks to the entire Structural Department of EIL for their valuable assistance
during my training.
This Industrial Training provided me with a platform to increase my intellect and empowered me with better
understanding of the real civil world scenario. And last but not the least my special thanks to “CPWD
DEHRADUN” which accepted me in spite of my inexperience in the field of engineering and gave me thisfruitful
opportunity and good working ambience to learn and work with them.

Date: July 25, 2024 AKASH SHARMA

2
TABLE OF CONTENTS

1. Introduction to CPWD
2. Reinforcement in column
2.1 Types of reinforcement
2.2 Design consideration
3. Laying of Admixture in batching and mixing
3.1 Understanding admixtures
3.2 Batching process
4.Casting of column
5.Formwork
5.1 Type of formwork
5.2 Design consideration
6. Shuttering of columns
6.1 Material used for shuttering
6.2 Removing of shuttering
7. Curing
7.1 Methods of curing
8. Jointing and finishing

9. Longitudinal and transverse reinforcement


10. Admixture

11. Workability
12. Design mix requirements

13. IS Code - 456:2000


14. Acceptance criteria of Limit state methods
15. Raft foundation
16. Pier cap
17. Footing in foundation
18. Water tank construction
19. Conclusion
20. Reference