WHAT IS HORIZONTAL DIRECTIONAL DRILLING

Horizontal Directional Drilling (HDD) is a method of installing underground pipelines, cables and
service conduit through trenchless methods. It involves the use of a directional drilling machine, and
associated attachments, to accurately drill along the chosen bore path and back ream the required
pipe.

General description of the technology

Horizontal Directional Drilling is based on using the drilling equipment. The general technology of
puncturing comes to the following manipulations:

 Project documentation with calculations is prepared for accurate horizontal drilling in the
soil.
 The projects are compliant with local authority and landowners.
 Two basins are digged out at the site of works start and communications exit in the location,
where the drilling will take place.
 Laying of necessary pipelines are carried out with the help of drilling tools.
 Completion of work, removal of basins, restoration of sites at their location if necessary.

The above description is brief, currently several types of HDD have been developed. The application
of a certain type of horizontal drilling is carried out depending on the soil type, laying
communication lines and other factors.
Drilling equipment

Various drilling tools are used in drilling technology:

 Drilling machine. It is an industrial equipment run on diesel fuel. Operation and movement
are carried out by the operator. Drilling is based on functional components of such machines
as carriage, hydraulic power station, control panels.
 Accessory tools. Various tools are used for the soil puncturing and punching as hoses,
reamers, pumps, screw elements with thread and so on. Based on type and stages of the
works carried out, the team set a different tool on the drilling rig.
 Navigation system. It is important to observe the trajectory of transmitter housing (drill
head) passing, the accuracy of outlet (output) at the second basin during HDD works. In
order to do that, a probe is mounted into the transmitter housing, and the workers follow
the movement of the tool with the help of a locator.

Each part of industrial equipment for HDD takes on an important role, requires professional handling
and routine maintenance.

Directional drilling is a three stage process:

Pilot Hole

The first stage consists of drilling a small diameter pilot hole. Drilling fluid is pumped
through the drill pipe to the drill bit where high pressure jets and the bit will grind the soils
ahead of the drill stem. The drilling fluid will also carry the cuttings back to the entrance pit
at the drill rig. Tracking of the pilot hole can be done in several ways depending on the size
and complexity of the shot. There is a transmitter or steering tool located near the drill head
which sends a signal to the location engineer giving the exact coordinates of the drill stem.
Readings are constantly taken which check the depth, alignment and percent slope of the
drill head.
Corrections will be made by the operator and locator to keep the pilot hole along the
predetermined bore path. The speed of the pilot hole will vary upon existing soil conditions
and the amount of steering which is required. Upon reaching the exit point, the beacon
housing and bit is detached and replaced with a reamer.

Pre-Reaming

The second step is to pre-ream the pilot hole and enlarge it to a size sufficient to safely
install the product lines. A reamer is pulled back and rotated while pumping drilling fluid to
cut and remove solids to enlarge the hole. Pre-reaming speeds will vary depending on
existing soil conditions and the amount of cuttings that are removed from the hole.
If required Additives are being used to ensure a clean and stable hole. Bentonite may be t9
used to create a “cake layer” around the outside of the hole during pre-reaming. This will
help with the stability of the bore hole and with fluid loss or infiltration. Additives such as
polymers are used to help break up the clay soils. A more evenly mixed drilling fluid will
prevent any blockages inside of the bore hole.

Pipe Pullback

The final step is the pullback of the pipe within the pre-reamed hole. The drill rod and
reamer will be attached to a swivel, which is utilized between the product line and the
reamer to prevent any torsional stress from the rotating drill string being transferred to the
product pipe. As the product pipe is pulled into the drill hole, drilling fluid is pumped
downhole to provide lubrication to the product pipe.

Advantages
 Less waste of resources, finance, labour and time
 Costs for laying communications are reduced due to the lack of the need to restore
the environment.
 You can work in any areas, including historical places, high-voltage stations,
unfavourable climatic conditions;
 The soil structure is preserved; the fertile soil layers are not disturbed;
 The usual urban rhythm is also not disturbed, there is no need to stop the road
traffic.

Why Choose MEC for Execution –

 Huge Fleet of Equipment and highly skilled and experienced staff having experience
in laying of underground Pipe Line for various utilities.
 Proven experience of 20 years, technocrats and the experienced human resources.
 Management team is an interfusion of leaders having an experience of 30 - 40 years,
and young budding leaders having graduated from one of the best Business Schools
of the Globe & Highly Trained, Experienced Project Managers.
 Having Experience of completion of Various crossing for laying pipeline of various
DIA staring from 200 MM to 600 MM .
 All required equipment are company owned , no dependency on any external agency