Work Program - RIVER - Kurigram

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Construction of Primary School cum Flood Shelter with Solar PV Nano Grid, Street Light, tightening Protection &

Connecting Roads, Bridge/Culvert at Kurigram District.


Package No. :: LGED/RJVER/KURI/21-22/NW-011
ID Task Name Duration Start Finish Predecessors Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026
J M M J S N J M M J S N J M M J S
0 Summary of Work Plan PS cum FS Kurigram_RIVER 900 days Sun 3/3/24 Thu 8/27/26
1 Pre-construction and Substructure works 355 days Sun 3/3/24 Fri 2/28/25
2 Site Development 90 days Sun 3/3/24 Wed 6/5/24
3 Layout 75 days Thu 6/6/24 Thu 8/22/24 2
4 Materials equipment mobilization stacking Works90 days Thu 6/6/24 Fri 9/6/24 2
5 Earth Works 120 days Sat 8/3/24 Sat 11/30/24 3FS-20 days
6 Foundation works 200 days Tue 8/13/24 Fri 2/28/25 5SS+10 days
7 Super Structure Works (55 nos. Shelter) 510 days Thu 9/12/24 Tue 2/3/26
8 RCC Works 390 days Thu 9/12/24 Mon 10/6/25
9 RCC Ground Floor 90 days Thu 9/12/24 Tue 12/10/24 6SS+30 days
10 RCC 1st Floor 90 days Wed 12/11/24 Mon 3/10/25 9
11 RCC 2nd Floor 90 days Tue 3/11/25 Sun 6/8/25 10
12 RCC 3rd Floor 60 days Mon 6/9/25 Thu 8/7/25 11
13 RCC Roof Floor 60 days Fri 8/8/25 Mon 10/6/25 12
14 Brick Work (55 nos. Shelter) 465 days Sun 10/27/24 Tue 2/3/26
15 Brick work Ground Floor 180 days Sun 10/27/24 Thu 4/24/25 9FS-45 days
16 Brick work 1st Floor 60 days Mon 6/9/25 Thu 8/7/25 15,11
17 Brick work 2nd Floor 60 days Fri 8/8/25 Mon 10/6/25 12,16
18 Brick work 3rd Floor 60 days Tue 10/7/25 Fri 12/5/25 17
19 Brick work Roof Floor 60 days Sat 12/6/25 Tue 2/3/26 18
20 Electrical & Mechanical Works (Electric Works, 800 days Sun 3/3/24 Tue 5/19/26
Solar Power and lightning Arrester)
21 Finishing Works (55 nos. Shelter) 145 days Wed 2/4/26 Sun 6/28/26
22 MS & SS work 40 days Wed 2/4/26 Sun 3/15/26 19
23 Plaster works 60 days Wed 2/4/26 Sat 4/4/26 22SS
24 Tiles works 60 days Sat 2/14/26 Tue 4/14/26 23SS+10 days
25 Wooden 60 days Wed 2/4/26 Sat 4/4/26 22SS
26 Aluminium works 45 days Thu 2/19/26 Sat 4/4/26 22SS+15 days
27 Roof Top works 30 days Wed 2/4/26 Thu 3/5/26 23FS-60 days
28 Sanitary & Plumbing pipe works 60 days Wed 2/4/26 Sat 4/4/26 22SS
29 Painting 60 days Sun 4/5/26 Wed 6/3/26 27,28
30 Furniture and Misc. Items 25 days Thu 6/4/26 Sun 6/28/26 29
31 Connecting Roads, Culvert, Solar and Other 875 days Sun 3/3/24 Sun 8/2/26
32 Permanent Bench Mark (BM.) 200 days Sat 8/3/24 Tue 2/18/25 5SS
33 Internal Road 400 days Sat 8/3/24 Sat 9/6/25 5SS
34 Electric Works, Solar Power and lightning Arrester 120 days Fri 3/6/26 Fri 7/3/26 27
35 Deep Tube well / Submersible Pump 90 days Fri 3/6/26 Wed 6/3/26 27
36 Environmental Enhancement Works 850 days Sun 3/3/24 Wed 7/8/26 2SS
37 Solar PV Nano Grid Power System 150 days Fri 3/6/26 Sun 8/2/26 27
38 Solar Street Light 200 days Sun 9/7/25 Wed 3/25/26 33
39 Connecting Road & Slope Protection Work 450 days Sat 8/3/24 Sun 10/26/25 5SS
40 RCC. Box Culvert 300 days Sat 8/3/24 Thu 5/29/25 39SS
41 Field Raising 600 days Sat 8/3/24 Wed 3/25/26 39SS
42 Site Cleaning & Handover 60 days Mon 6/29/26 Thu 8/27/26 21,20,7
43 Finish 0 days Thu 8/27/26 Thu 8/27/26 42 8/27

Submitted By: PE:Ptroject Director, LGED, RIVER


MJCL – STANDARD JV
Note: Starting Date shall varry upon NOA and Time for access to the site. During contract JV shall again provide a detailed Work Program with WBS considering all the issues said in Section III- EQC, Page-79 of Vol-1.