Daily Work Report

ITB02-011C45-7020

AMAALA
General Information
Program Name AMAALA Triple Bay Central Project Code 1TB02011 Project Name Rosewood Resort and Branded Residence

Contract ref. ITB02-011C45-7020 Package Hardscape Works


Contractor Saudi SALCO Contracting Co. Report No. 272
Contract No. ITB02-011C45-7020 Report Date 3-Sep-2024

To the Engineer Mr Shamiullha Basha, Mr Mohamed Mahmoud Ali Contract 12-Jul-23


Weather sunny Humidity Medium
Prepared By Adel ALRAADI Temperature 33-37.°C
General Description of Work Activities

. Personnel on Site
Equipment Qty. Personnel Qty.
Dozer 1 Direct Labor 107
Grader General Foreman 3
Excavator 2 Carpenter 12
Wheel Loader (Shovel) 1 Mason 7
Backhoe Loader (JCB 1 Tiler 6
Self Loader (HIAB) 1 Rigger 2
Forklift Steel Fixer
Skid Loader / Bobcat 2 Welder
Trailer / Truck 4 Driver Light Duty 3
Fuel Truck 1 Driver Heavy Duty 12
Roller Compactor 2 Machine Operators 18
Plate Compactor 4 Helper / Labour 44
Bus 2 Store Labour
Others/ equipment Supervisor /technician
Light Vehicle / SUV / Car 6 Indirect Labor 0
Water Tank 1
1 Ton Pick Up 5 Direct Staff 49
Ambulance 1 Project Director 1
Mobile Crane Project Manager 1
Dyana 2 Facility Manager 1
Technical Manager 1
landscape Architect/site 2
Technical Engineer(irrigation,Environmental ) 3
Draftsman 1
Controls Engineer-planning 1
Document Controller 1
Contracts Manager 0
Accountant 1
Procurement Eng./Officer 1
Storekeeper / Timekeeper 1
Safety Manager 1
Safety Officer 7
Quantity Surveyor 1
Land Surveyor Manager 2
Land Surveyor 4
Assistant Surveyor 2
HR Administrator/Logistics 1
QA/QC Manager 2
QA/QC Officer 4
Nurse 1
BIM Modeler/coordinator /Others 4
Construction Manager 3
Mechanical Engineer-maintenance 2
Indirect Staff
Total number of Equipment 36
Total man hours for the day 1248
Total Man Hours Worked Since Last DPR Report 158792
Total man hours from the start of the project 160040
Section Event
Health and Safety
Environment
Inspections
Material Delivery
Note:
Activities and Tasks
Task Description (%) Complete Start Date Forecast Finish/ Date
1 Concret -pathway 3G 1st part 76% 2-Sep-2024
2 Road backfilling Granular A for 3F 81% 25-Aug-2024
3 Grading at 3H 49% 1-Sep-2024
4 Limestone paving at RB08 interance 94% 26-Aug-2024
5 Tensar work for WA/2-1 5rd layer 93% 27-Aug-2024
6 Parking RC05 sub base granular B 62% 28-Aug-2024
7 Concrete for blinding WC/1-1 100% 2-Sep-2024
ITB02-011C45-7020

Progress Photo

parking backfilling

Grading at 3H

Concrete for blinding WC/1-1