Method Statement For Construction of LPG Mounded Storage Bullets
Method Statement For Construction of LPG Mounded Storage Bullets
Method Statement For Construction of LPG Mounded Storage Bullets
JOB NUMBER
XXXX
Pages 1 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
Contents
1.0 PURPOSE .................................................................................................................................................................. 4
Pages 2 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
Pages 3 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
1.0 PURPOSE
The purpose of this document is to follow proper procedure to describe the Execution of Civil,
Mechanical, Electrical and other associated works for construction of LPG mounded storage
Bullets. This procedure covers the detailed civil works, Fabrication, Erection of Steel tanks for
LPG Storage Capacity Expansion Project, EIPL Terminal, Visakhapatnam.
2.0 SCOPE
This documents cover the methodology to be followed during Civil Foundation works,
Fabrication and Erection of all Steel structures and Tanks, Pipe Racks, Technological
Structure, Paving, Platforms including Gratings/Handrails etc. at Site Works Area pertaining
to Contract and Project Approved Drawings/Specification.
For the purpose of this document, the term “Shall” indicates a mandatory requirement and
“Should” indicates a recommended practice.
In preparation of this procedure, the following documents in totality or in part shall from the
reference document:
a) IS 5121 (1969) Safety Code for Piling & other deep foundations.
d) IS 4014-2-1962 Code of Practice for Steel Tubular Scaffolding, Part II: Safety
Regulations for Scaffolding
f) IS 7969- 19974 Safety code for handling and storage of building materials
h) BIS CODES: IS: 2062, 800, 801, 802, 816, 818, 819, 822, 919, and 1024,
1261, 1323, 1477, 1852, 2074, 7205, 7215, 7307, 7310, 7318, 9595 & other
relevant IS Codes.
Pages 4 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
Amunra Infratech and Agritech Pvt Ltd is dedicated to ensure that the safety, health, and
environmental aspects are respected. To begin with, every personnel is compelled to attend
safety meetings and tool box talks which take place every morning on site before the
commencement of any activity. Secondly, all tools and equipment shall be regularly maintained
and properly calibrated to ensure the quality of the work results. Moreover, Personal Protective
Equipment (PPE) must be worn on site by all personnel at all time.
6.0 RESPONSIBILITIES
Following are the responsibilities and reporting structure of Personnel involved in the scope
of this Procedure:
PROJECT HOD
a) Shall be responsible for providing resources for the implementation of the method
statement.
b) Maintain good communication with all employees involved in this process.
c) To ensure that all the equipment, tools and tackles required to execute the works
according to approved construction Schedule are available in good condition and
provide any additional equipment as required.
d) To ensure all the equipment/vehicles are handled by licensed/ skilled operators.
e) To provide all necessary support to his construction team and ensure that the works
are carried out as per the approved Method Statements/procedures.
Pages 5 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
f) Co-ordinate with site engineer, Surveyors, Safety Engineer, Quality Engineer, and
frontline supervisors for safe & proper execution of the works.
g) To ensure that, checked levels shall be entered in level books as per the approved
formats & requirements on daily basis.
h) To ensure that levels are jointly being signed by the contractor and Client
representative.
i) To continuously check the progress of works as per schedule/ programs.
j) To ensure Client approval on all checklists / permission as and when required.
MANAGER
ENGINEER IN CHARGE
QA/QC MANAGER
QC ENGINEER/INSPECTOR
a) Ensure that Raw Material is as per approved make and traceability maintained.
b) Ensure required training and induction provided to all workers/supervisors.
c) Ensure fabrication procedure is as per approved Fabrication Method Statement.
d) Ensure all testing performed, witnessed and verified by Inspection agency.
Pages 6 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
FIELD ENGINEER/SUPERVISOR
a) Understanding the drawings prior to start of work and all details are provided to execute
the work. If not, then take clarification from Client.
b) Compliance to EHS and QA/QC requirements prior to commencement of work.
c) Engaging workmen in work according to plan.
d) Cross checking the activities intermittently during day’s work and ensuring the activity is
done within tolerance limits.
e) Mobilizing the materials required for work prior to start of work.
f) Giving Instructions to workmen working under him highlighting the risk involved in the
task.
g) To ensure safety of workmen working in his area. To ensure proper working platform
with access to keep materials.
h) To ensure all working and checking tools are available at site with working team before
start of work.
i) To ensure proper housekeeping at site at the end of day’s work.
j) Understanding EHS requirements of project from EHS plan, EHS management systems,
EHS Manual & following the same in execution of work.
k) Marking legibly grid reference/ Date of construction.
l) Ensuring implementation of proper work methodology for all activities.
m) Preparation of all checklists and certification of works from Client.
ADMIN INCHARGE
a) Ensure availability of all statutory documents related to safe use of all construction
equipment and vehicles such as dumpers, excavators, and passenger vehicles (if any).
b) To facilitate site team for all enabling work to carry out works safely without any
interruption.
STORES INCHARGE
a) EPCC store personal will collect invoices and MTCs of all material received at Fabricator’s
end.
b) Maintain the record of incoming materials from Fabricators and dispatch record.
EQUIPMENT OPERATOR
Pages 7 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
e) Maintain a safe working distance away from any mobile equipment while work is in
progress.
f) Be aware of traffic and pedestrians and make sure the equipment operator knows
when equipment or a vehicle is approaching
QUALIFIED RIGGER.
a) Shall inspect in maintaining safe working environment & conditions and compliance to
Project EHS Plan. Shall facilitate in EHS Risk analysis and ensure required preventative
measures.
b) Identify potentially unsafe acts, areas and practice and educate people.
c) Monitor EHS practices, persuade to minimize non compliance
d) Report incidents beyond control and unsafe occurrences.
e) Issue stop work notice for unsafe work.
f) Investigate unsafe occurrences and initiate preventive steps.
g) Discuss near miss accidents with staff and workmen
h) Conduct safety training programs and celebrations
i) Review Health & Environment related aspects as per the norms.
Pages 8 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
fabrication drawings and submit to TPI/EIPL for approval. Only based on approved for
construction drawings, work will be executed.
8.0 METHODOLOGY
Each section shall be marked for identification and each lot should be accompanied by
manufacturer's quality certificate, conforming the specifications, for mechanical items
chemical analysis and mechanical characteristics. All sections shall be checked, sorted out,
straightened, and arranged by grades and qualities in stores. Any instruction given by
Safety Officer in this respect shall be strictly followed.
Structural steel with surface defects such as pitting, cracks, laminations etc. shall be
rejected if the defects exceed the allowable tolerances specified in relevant standards. All
such rejected material shall be kept in designated quarantine area & subsequently
removed from store/site.
Pages 9 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
a) Boring and piling zone should have barricading to prevent unauthorized access/entry.
b) 5 m. Exclusion zone around the rig should be done.
c) Piling rig should be tract into position under the supervision of competent person.
d) Unauthorized entry should be restricted into hazardous zone.
e) One dedicated person should be deployed to prevent unauthorized entry.
f) In an interruption of piling occurred the chisel needs to be removed, it should
Pages 10 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
8.4.2 Sop for Bar Cutting, Bending, Fixing, Welding And Gas Cutting.
Pages 11 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
d) The yard should be proper house kept to prevent hazards like falling, slipping, tripping.
e) Welding activity should be done by the competent person and earthing should be
done for welding machines.
f) The electrical connection should be routed through 30mA sensitivity RCCB. Bare cable
insertion is strictly banned. Only industrial purpose plug sockets shall be used. Only
double insulated cable shall be used.
g) Gas cutting should be done under the competent supervision; IS standard flash back
arrester should be used to prevent accident like fire and explosion. Pressure gauge
shall be in working condition.
h) Gas cylinder should be handled safely & always stored in upright position. Oxygen & DA
cylinders shall be stored separately at least 6m away. Never roll cylinders on ground.
i) Fire extinguishers & sand & water buckets shall be kept nearby hot work area.
j) Poster should be displayed relating to the relevant hazards.
k) Everyone inside the yard should wear relevant PPEs like safety shoe, safety helmet,
face shield, ear plugs, and shoulder pads.
l) Mechanical handling inside the yard should be done under competent supervision.
m) Bar bending & cutting equipment’s shall have emergency stop button & adequate
guarding for rotating parts?
n) Only IS certified & tested cutting blades shall be used for bar cutting.
o) Gas cutters/ welders, bar benders/cutters shall be provided with ID cards to
prevent unauthorized operation.
8.4.3 Sop for Placing and Handling of Reinforcement Cage and Liner.
Pages 12 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
Fabrication shall be in accordance with IS 800:2007 Section 17. Fabrication shall be done
as per “Approved for Construction” fabrication drawings adhering strictly to work points
and work lines on the AIAPL same. The connections shall be welded or bolted as per
design drawings. Work shall also include fabricating built up sections. Prior to
commencement of structural fabrication, undulations in the fabrication yard, if any shall
be removed and area levelled and paved by AIAPL. Any defective materials used shall be
replaced by AIAPL at his own expense, care being taken to prevent any damage to the
structure during removal. Any faulty fabrication pointed out at any stage of work by
TPI/TPI/EIPL/Owner, shall be made good or replaced by AIAPL. Tolerance for fabrication
of steel structures shall be as per IS: 7215. Frequency of NDE shall be as per applicable
Coad &specifications.
Demarcate Bullet Fabrication area and clear the jungle by cutting off Trees & Bushes and
Fence by Temporary Barricading up to 3 Mtrs height all around.
Pages 13 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
b) Due to higher thickness of plates, Distortion will take place while continuous welding
process will going on to arrest all the distortion it is very essential to make suitable
heavy support platform has to be placed at 1meter distance to prevent distortion due to
weld heat inputs so as to keep plates in perfect level and sequence shall be carried out
before start the welding.
c) Before start of welding, the entire member is locked properly by using extra support to
avoid distortion. After completion of welding, when the welded members cool down in
normal/room temperature the extra support will be removed.
d) For fit up of every new member, cutting edges of the web will be removed and the
fabrication platform needs to be cleaned properly by removing all the
spatters/slag/previous welding spot.
b) Flame cut edges shall be cleaned to remove slag. Uneven edges shall be dressed by
grinding.
c) Gas cuts shall be smooth and regular in contour.
d) Cutting of plates by pug machine needs skilled and experienced operators to maintain
proper cutting edge. Also after one cut the next cut will be started in other side of the
plate to avoid distortion in cutting zone.
e) Marking on steel shall be done in accordance of shop drawing and cutting plan.
f) Code of marking over fabricated member shall be as follows-
Drg. No. / Mark No. / Part No. / Weight / Heat No.
This marking on members shall be done by hard punch.
g) Every separate member shall be plainly and permanently marked with paint to show
position and direction as necessary for each identification and correct placing.
h) Loose pieces of connection shall be attached to their respective members.
Pages 14 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
also record the name of the fitter(s) for feedback, improvement and skill level
assessment.
d) IQC-Fit Up shall carry out inspection as per the drawing (drawing should have good for
manufacturing stamping by PPC/PMG- to ensure that that it is pertinent issue of the
drawing).
e) IQC shall prepare dimensional report and record dimensions, orientation of the child
parts, correct weld preparation etc.
f) After completion of rectification, assembly/sub-assembly shall be cleared/moved to
welding section.
g) Welding supervisor shall carry out welding using qualified welders and the procedures
which are appropriate to achieve desired welding quality.
a) Before work can commence, properly complete all Checks, work permits, safety tool
box meetings.
b) Equipment inspections will be completed by qualified personnel.
c) Establish the scope of work, and ensure everyone knows their specific job duty.
d) Spotter will maintain a safe buffer zone and inform the operator that it is safe for
work to commence.
e) Using proper lifting devices, supporting personnel will begin to rig up to the joint of
steel pipe.
f) The joint of steel pipe will be transported to established welding area.
g) Welder and helper will adjust pipe to make sure it is level and square.
h) Welders will begin to make their welding passes steel pipes. After each pass the
Welder’s Helper will grind and dress out the weld as needed. Once the last welding
pass is completed, the Welders Helper will use a buffing wheel to buff down the
weld.
8.5.7 Pre-heating
a) Fit-ups of members will be carried out by qualified fitters under the supervision of Fit-up
supervisors as per ITP/QAP/TS/Dwg.
Pages 15 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
8.5.9 Transportation
a) After final shop acceptance and marking, the item shall be loaded for
transportation. Fabricated items must be protect during loading and unloading.
Proper lifting devices shall be used for loading, in order to protect items. Loading
and transportation shall be done in compliance with transportation rules.
b) The small parts such as fin-plates, gussets etc. shall be securely tied with wire to
their respective parts. Bolts, nuts and washers shall be packed and transported in
crates, marked in at least 2 places with water resistant paint.
a) Before start of erection all crane & Hydra & other lifting equipment's shall be ensured
of having proper test certificates/Checklist so that it can work safely for the required
load of the member.
Pages 16 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
b) Checklist must be filled by operator regular basis. Operating area of Crane shall be
barricading.
c) Storing & Handling of bullet shall courses shall be done in a controlled manner to
avoid excessive stress & any damage.
d) Proper safety precautions shall be taken before & during the erection work each
worker shall be trained for precaution taken for erection jobs.
e) The framework must be sufficiently braced to prevent wind damage.
f) Steelwork shall be hoisted and erected in position carefully, without any damage to
itself, other works and injury to workmen.
g) During erection, the steelwork shall be securely bolted or fastened. Wherever
necessary temporarily braces shall be provided for all loads to be carried by the shell
during erection, including those due to erection equipment and its operation.
h) All field assembly and welding shall be executed in accordance with the requirement
for shop assembly and welding.
i) A “Fit for Use” notice will be present on the scaffold. Damaged scaffolding is not to be
used.
j) Scaffolding higher than 2 meters must be bonded/ fixed to the building.
k) Scaffolding must have bottom stand plates. Scaffolding higher than 2 meters must
have handrails around.
l) All scaffolding material shall be stored in an orderly manner and the storage area
shall be properly house kept.
m) The handrails will be at least 900mm high and Guard rails must be installed to
prevent workers from falling if it is not reasonably practical to use Personal Protective
Equipment.
n) Toe plates of at least 100mm high must be installed if scaffolding is higher than 2
meters.
o) Cross support must be used on scaffolding. No tools or equipment is allowed to be
thrown/passed from one level to the next.
p) A safe barricade must be put up if scaffold is higher than 3 meters.
q) Scaffolding shall be erected on the request for erection from the contractor and shall
be kept in place for the entire duration of works and shall be dismantled after request
for dismantle from the contractor.
r) All scaffolding must be inspected before use and after rain.
s) The Construction Manager or his nominated sub ordinate will conduct weekly
inspections on scaffolding.
The method of inspection shall be according to the relevant applicable codes & standards
and to be carried out during all stages of fabrication & erection, to check the conformity
with the relevant specifications and IS codes / standards. Defects & faults occurring at the
surface such as blow holes, exposed porosity, unused welds, surface cracks in the weld
metal etc, profile defects like excessive convexity or concavity, overlapping, incomplete
Pages 17 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
filled grooves, excessive penetration heads, root grooves etc. Distortion due to welding
i.e. local shrinkage, camber, bowing, twisting, rotation etc. & other dimensional errors,
eccentric angular & rotational miss.
a) After completion of the erection, welding and NDT the following points shall be
checked before testing.
b) All the mechanical activities completion in respect of the drawing, Specification and
code requirements.
c) Finally mechanical clearance from the Engineer-In-Charge shall be taken before Hydro
test in approved format.
a) Clearance of QC In charge also shall be taken in the approved format.
b) Each bullets shall be hydro tested as per the hydro test procedure, the testing medium
shall be clean water.
c) During testing, inspection report shall be filled and TPI/EIPL signatures shall be taken.
d) After completion of test water shall be emptied out as per the hydro test procedure.
Storage of Paints
a) Paints shall be stored in accordance with any local laws or regulations, or both. In
principle, paints shall be stored in an independent warehouse/container. However, only a
short period of outdoor storage may be allowed when provisions for weather protection
and provisions for cover from direct sun light are made.
b) Paint shall not be stored together with other dangerous and inflammable materials.
c) All paints shall be stored in a tightly sealed condition, and never stored in, or exposed to
the open air.
d) The oldest paints shall be used first after they have been delivered from the
manufacturer’s warehouse.
e) Material Safety Data Sheets shall be kept in “MSDS” Box available with the paint container.
Paints and Thinners shall be stored in well ventilated building at storage temperature as
recommended in manufacturer’s data sheet.
f) Temperature of inside the Paint container must be maintained as per MSDS.
g) A paint storage container shall be with good ventilation, air conditions, temperature
reading device and its log sheet/book, fire extinguisher, warning signs such as “ No
Smoking”, “No Open Flames” and “Storage of Flammable Materials”, etc.
h) Storage condition of paint materials should be monthly jointly inspected with client.
Pages 18 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
Surface Blasting
Application of Paint
Pages 19 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
a) After completion of the mechanical works and retaining Wall the spaces left in the pits and
trenches shall be cleared of debris, brickbats, mortar droppings etc. prior to the start of
backfilling.
b) When directed by the engineer Incharge/Project Manager coarse river/crushed sand shall also
be used filling material. Soils such as black cotton soil, clay and mixtures having excessive
swelling characteristics shall not be used as filling material.
Pages 20 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
c) Filling material shall be spread in layers of thickness approx. 200 mm and compacted by 4
passes of 10 T vibratory roller. Water shall be sprinkled intermittently.
d) Each layer shall be compacted before laying the succeeding layer. Surface voids in each layer
shall be filled by crusher dust/Sand.
e) When instructed by the Engineer-in –Charge, controlled backfilling shall be done. Material
shall be spread in un compacted layers of thickness approx. 200 mm and rolled by
adequate number of passes of a 10T vibratory roller so as to achieve 90% of the maximum
Proctor density of the fill material.
f) Each compacted layer under controlled backfilling shall be tested for degree of
compaction. One test per 100 sq. m of compacted area shall be done for determining field
dry density of the compacted layer. Alternate layers shall be tested as per Modified
Proctor Density Test and Sand Replacement Method respectively. Records of field density
test shall be maintained in the format approved by Engineer-in-charge.
g) Sand filling shall be continue up to top of bullets as specified in the construction drawings.
h) Once the Filling reaches to the desired height necessary HDPE/PVC, Geo textile sheets and
Drain Pipes shall be laid and further filling shall be done by following the steps given in
mound GA drawing.
i) Finally Paving shall be done through the surface of Mound as per the construction drawing.
Whenever a section of the work is completed the area will be cleaned and all waste
immediately removed from site.
Pages 21 of 21
METHOD STATEMENT FOR CONSTRUCTION OF LPG
MOUNDED STORAGE BULLETS.
Doc No: 2023-24/PID-40/AMUNRA/EIPL/MB/MS-01, R.0
Proper PPE is to be used by the involved person. All measuring, lifting and test equipment
and materials used must be well maintained.
Pages 22 of 21