Section VI Technical Specification
Section VI Technical Specification
Section VI Technical Specification
CONTENTS
SECTION VI - I DRAWINGS
1.1 This document and specification calls for the manufacture, testing at
manufacturer’s works, supply and delivery, storage, erection, testing and
commissioning of the works required for the Project.
Any appended drawings of the required equipment /works form part of this
specification.
Detailed scope of the works is as per the BOQ and specifications of the
bidding documents.
1.4 Language
The English language shall be used in all Contract documentation and in all
correspondence between the Contractor and the Employer.
All Equipment and the Works under this Specification shall conform to the
latest editions of the International Electrotechnical Commission (IEC) or
Bureau of Indian Standards (BIS) Specifications.
1.7.1 Elevation
1.7.3 Access
Insulation levels
a) 1 minute power
70 28 28 2
frequency kVrms
b) 1.2/50 microsecond
impulse kVp 170 75 75 6
No. of phases 3 3 3 3
Frequency Hz 50 50 50 50
The above are the values for 1000 m altitude and shall be corrected based
on the elevation of the site for which the equipment shall be designed.
The bidder shall attach the spares, special tools and/ or appliances which are
recommended apart from Schedule “D”.
The Employer may order all, none or any of the recommended items. Those
ordered shall be delivered not later than the date of receipt of the last shipment
of the associated item of plant. The price of the items shall be subject to the
same price conditions as the associated item of plant.
All spares shall be interchangeable with the original parts. They shall be
treated and packed for long term storage under the climatic conditions of site.
Each item shall be clearly and permanently labeled on the outside of its
container with its description and purpose. When several items are packed in
one case, a general description of the contents shall be given on the outside of
Section IV – Technical Specification
the case. Spare parts shall not be shipped in the same cases as components,
which are used for erection. The cases shall be clearly labeled to indicate that
they contain spare parts or tools and each tool or appliance shall be clearly
marked with its size and purpose.
All case containers or other packages are liable to be opened for inspection
and checking on site.
The cost of recommended spares, special tools (other than those specified in
the BOQ) will not be taken into consideration when comparing bids.
a) Power Supplies
Power supplies for plant and equipment shall be:
c) Instruments
All electrical instruments and meters shall comply with IEC 60051 and
IEC 61010 and, unless otherwise specified, shall be of industrial grade
accuracy. Three-phase power measuring instruments shall be of the
three-phase unbalanced load pattern wherever the current and Voltage
references permit. Energy meters shall be three phase four wire having
maximum demand indicator, RS485 port and optical port.
Instrument dials for analogue meter if any shall be white with black
markings. A red line shall be drawn on each scale to represent rated
conditions. Bezels shall have uniform semi-gloss black high-grade
finish.
Section IV – Technical Specification
The movements of all electrically actuated instruments shall be of the
deadbeat type. Instruments shall be provided with a readily accessible
zero adjustment wherever possible.
d) Terminals
Unless otherwise specified, all the terminal blocks except the terminal
blocks for CTs shall be suitable for connecting minimum two 2.5
sq.mm copper conductors of the external cables at each connecting
point. The terminal blocks for CTs and PTs shall be suitable for
connecting minimum of 4.0 sq. mm and 2.5 sq. mm copper conductors
respectively.
All spare contacts and terminals of the panel mounted equipment and
devices shall be wired to terminal blocks.
The terminal assemblies shall give the required number of ways plus
20% spare with a minimum of 5 terminals. These shall be uniformly
distributed on all rows of terminal blocks.
e) Panel Wiring
All wiring shall be carried out with 1100 V grade, single core, stranded
copper conductor wires with FRLS PVC insulation and shall be
Vermin, rodent proof. The minimum size of the stranded copper
conductor used for panel wiring shall be as follows:
a) All circuits except CT circuits : 2.5 mm2 per lead.
b) CT Circuit : 4 mm2 per lead.
Section IV – Technical Specification
The minimum number of strands per conductor shall be seven. Extra
flexible wires shall be used for wiring of devices mounted on moving
parts such as swinging panels and doors.
Colour Purpose
Red R-phase connections in current and Voltage
transformer circuit only
Yellow Y-phase connections in current and Voltage
transformer circuits only
Blue B-phase connections in current and Voltage
transformer circuits only.
Green with Connections to earth
Yellow Stripes
AC neutral connections, earthed or unearthed,
Black connected to the secondary circuits of current
and Voltage transformers.
Any other AC connections other than those above.
Colours
The ends of every wire and every cable tail shall be fitted with
numbered ferrules of white with alpha numbers clearly engraved in
black. The ferruling should be as per BEBS-S12 (1964).
Double pole switches shall be used to break dc supplies, one pole for
the positive line and one pole for the negative.
l) Batteries
Electronic equipment shall not use local internal batteries unless the
approval of the Engineer has been obtained. Where approval is given,
batteries used inside equipment shall be of the totally sealed, leak-
proof type, lithium and rechargeable type.
m) Earthing
All structural metal work and metal chassis shall be connected to earth.
Earthing conductors shall be at least equal in cross-sectional area to the
supply conductors and shall be capable of carrying the fault current for
1 second.
n) Anti-Condensation Heaters
p) Rubber Mats
1.11.1 General
Unless otherwise provided for in the Contract, all materials, fixtures, fittings,
and supplies furnished (hereafter called "materials") shall be new and of
standard first grade quality. All assembly and construction work shall be done
in a neat and professional manner. Materials shall be free of defects. Materials
shall be brought to site only after inspection and issuance of proper dispatch
clearance. The dispatch clearance shall be issued within three working days
after the inspection from the BPC head office. The local materials like bricks,
sand aggregates shall be tested in the local laboratories before bulk supply.
The cube test for the concrete shall be to the contractor account and tested in
the local laboratory for the major concrete works.
In choosing materials and their finishes, due regard shall be given to the harsh
climatic conditions which can occur in the area. Some relaxation of the
following provisions may be permitted where equipment is hermetically
sealed, but weatherproof materials should be used wherever possible.
All structural members, nuts and bolts shall be galvanised and shall conform
to the requirements indicated in clause 1.12 of this section.
The paint shall be obtained from a reputed manufacturer. The formulation and
application procedure shall be as recommended by the manufacturer for the
appropriate exposure conditions.
Section IV – Technical Specification
All the equipment shall be painted with shade RAL 7032 (exterior) and
glossy white (interior). Poles shall be painted with silver paint.
Coatings shall not be applied before Vessels and chambers have passed
pressure or Vacuum tests. Precautions shall be taken to prevent corrosion
occurring in the period of time between cleaning of the steel and commencing
the painting.
Suitable amounts of each type and colour of finish coat as applied to the major
equipment items shall be provided for "touch-up" purposes.
All substation structural members shall be secured by means of nuts and bolts
with approved flat steel washers. Nuts and heads of all bolts shall be of the
hexagonal type and of uniform outline dimension.
Minimum size of bolts for all structural connections shall be 12-mm diameter
in mild steel. All bolts shall conform to IS 12427- 1988, property class 5.6.
All bolts washers and screwed rods shall be galvanized including the threaded
portions. All nuts shall be galvanized with the exception of the threads, which
shall be oiled. All bolts attaching insulator set droppers, U bolts and earth
conductor clamps to the towers shall be provided with extra thread length to
accommodate two nuts and a washer in an approved manner. The screwed
thread of any bolts or studs shall not form part of a shearing plane between
members.
All washers shall be included under this Contract, including locking devices
and anti-vibration arrangements, which are to be subject to the approval of the
Engineer. The washers shall be of adequate thickness to abridge the projection
of the shaft and the commencement of the threaded portion. Taper washers
shall be fitted where necessary.
Nuts shall be finger tight on the bolt and will be rejected if they are, in the
opinion of the Engineer, considered to have an excessively loose or tight fit.
Bolts re-threaded after galvanizing will be rejected.
The Contractor shall allow for the supply of surplus bolts, nuts and washers in
excess of the exact amount measured to allow for shortages due to loss,
misappropriation etc.
Bolts of a single diameter only shall be used for a given tower/structure type,
and as far possible for all tower/structure types. Only in exceptional cases
different diameter bolts shall be used with the prior approval of the Engineer.
But even in the latter case, for each tower/structure type, all the bolts used
shall be of the same diameter.
All castings shall be free from blowholes, flaws and cracks as far as is
practicable. No welding, filling or plugging of defective parts shall be done
under any circumstances. All cast-iron shall be of close-grained quality
approved by the Engineer.
1.14 Welding
All joints shall be bolted joints and welded joints shall not be permitted either
during the design stage or the construction stage. However, during erection in
case of additional unforeseen requirements by the Employer, if welding needs
to be resorted to, the same shall be done with prior approval of the Engineer,
and shall conform to BIS specifications. In such a case, the Contractor shall
specifically indicate the location and purpose along with the proposed
methodology for welding for the Engineers' approval. The wielding shall be
carried out by a certified welder who have undergone minimum of certificate
level training in this trade.
a) Works Tests
The Engineer may at the Employer's discretion witness the works tests described in
the following Technical Specification and may also make Visits to monitor progress.
The Contractor shall give minimum of two weeks notice to the Employer/Engineer
with a copy to Engineer, in case they desire to witness the tests, indicating date and
place of Inspection.
The test equipment, meters, instruments etc. used for testing shall be calibrated at
recognised test laboratories at regular intervals and Valid certificates shall be made
available to the Employer's representatives at the time of testing. The calibrating
instruments used as standards shall be traceable to Indian/International standards.
c) Engineer's/Employer's Authority
Inspection and witnessing of tests shall be carried out in accordance with the
Conditions of Contract. The Engineer will be responsible for advising the Contractor
of acceptance or rejection. The Inspector has the authority to delay delivery of any
items of equipment, which have not been tested and proved in accordance with the
Contract.
All wood and other materials used in packing cases shall be insect free.
Adequate protection and precautions are to be taken to exclude termites and
other vermin, noxious insects, larvae or fungus from the packing materials or
plant. All contents are to be clearly marked for easy identification against the
packing list.
Bolts and nuts shall be double bagged and crated for shipment. Crating of
dissimilar metals is not acceptable.
Packing cases where used, shall be strongly constructed and in no case shall
timber less than 25 mm in thickness be used. The contents of packing cases
shall be securely bolted or fastened in position with struts or cross battens.
Cross battens supporting weight in any direction shall not rely for their support
on nails or screws driven lengthwise into the grain of the wood, but shall be
supported by cleats secured from inside.
HT cables shall be delivered in the steel cable drums while LT and control
cable shall be delivered wound on strong wooden drums treated to an
approved International Standard by Vacuum impregnation with copper-
chrome-arsenate (CCA) preservative to resist rotting, termite and fungus
attacks. Contractor may take back the steel cable drums. However, incase
contractor has to handover the HT cables to BPC, the same shall be handed
over properly rolled in the steel drums. Drums with an outside diameter
exceeding 2.5 metres and an outside width exceeding 1.4 metres shall not be
used except with the Engineer's approval. The central hole of the drums shall
be reinforced with a steel plate of thickness not less than 10 mm to fit an axle
size 95-mm diameter. The interior of the conductor drums shall be lined with
bituminous paper to prevent the conductor from being in contact with timber.
Waterproof paper and felt lining shall overleap at seams by at least 20 mm and
the seams shall be sealed.
The thread of bolts used to strengthen the cable drums shall be peened in such
a way that the nut can be tightened but cannot be readily removed.
Labels shall be made of non-rusting metal or 3-ply lamicoid. Labels shall have
white letters on black or dark blue background. The lettering size shall be 6
mm for panel designation and minimum 3 mm for device labels. The label
inscriptions shall be subject to the Employer’s approval.
1.19 Locks
Provision shall be made for the locking of mechanism boxes, indoor and
outdoor equipment to limit access or for the safety of personnel. The locks
shall be rust proof and shall be provided as a part of the equipment.
The Bidder shall submit in the tender an outline of the quality assurance
practices that will be applied to all aspects of the manufacturing process.
Within one month of receipt of a letter of acceptance (LOA) under this for
equipment specification and civil works, the Contractor shall submit a detailed
Quality Assurance Manual, which conforms generally to the requirements of
ISO 9002. Approval to proceed with manufacture of equipment within this
Contract will not be given until this Quality Assurance Manual has been
received and approved by the Engineer. Delays to the Contract completion
date due to non-compliance with this specification requirement will be the
Contractor's responsibility.
i) Adequate procedures are planned for corrective action in the event that
quality checks show that performance is not satisfactory.
All dwellings and buildings existing or erected for any purpose by the
Contractor shall comply with local regulations in regard to construction, water
supply, sanitation and other requirements. The Contractor is responsible for
seeking approval from concerned authority whenever required to take up
infrastructure works like construction of site office, labour camps, site stores,
etc. Temporary construction camps are to be provided with proper sanitation
and other necessary facilities. All temporary accommodation shall be removed
by the Contractor when no longer required and before the granting of the Final
Certificate. After the removal of accommodation the ground shall be left in a
clean and tidy condition.
The Employer will not provide these and the Contractor shall make his own
arrangements where these services may be required for his staff.
The Contractor is to bear all expenses in connection with the transport to Site
of all plant, material and things needed for the purpose of the Contract
including warehouse rent, handling and other charges, which may occur. The
Contractor is to observe any regulations, which limit loads on roads and
bridges over which material may be conveyed.
The handling and storage of any plant at the Site will be the responsibility of
the Contractor. The Contractor shall arrange for suitable lay-down areas. The
Contractor is to advise on the protection of all material against corrosion, theft,
and mechanical damage during storage and erection at the Site.
Only galvanised structural steelwork may be stored in the open. Plant sensitive
to climatic conditions must be stored in closed buildings protected from dust
and humidity.
1.21.7 Access
Contractor shall make his own arrangements for construction power supply
and pay the requisite charges/fees to the BPC.
All power and lighting circuits shall be constructed with due regard for
personnel safety and shall comply with recognised codes of practice and local
regulations. All circuits shall be fitted with earth leakage systems.
Once any section of the plant has been made alive; the Contractor, the
Engineer and the Employer shall establish and agree to a system for ensuring
the safety of personnel and equipment. While the plant is under the control of
the Contractor, the Contractor shall be primarily responsible for the safety
precautions.
It will be mandatory under this contract to provide at least safety helmets and
gumboots to all the personnel working at the site.
The Contractor shall be responsible for the behavior on site of all personnel
employed by him.
The Contract shall include for the training of the Employer's employees in the
areas corresponding to installation and commissioning of 33 & 11 kV
breakers, Package substations, testing and commissioning of UG cables and
general O&M of the substation at the site for period of 4 days at the respective
site.
The Contractor shall submit to the Engineer a weekly return detailing for each
portion of the works separately, the numbers of the various classes of
workmen employed by him on the Site, the Contractor's equipment on site, or
any other information that may reasonably be required.
The Contractor shall attend regular formal site progress review meetings with
the Engineer where progress and construction-related issues will be reviewed.
The Contractor shall prepare for issue the day before the meeting, detailed
schedules showing separately the erection, fixing, concreting, commissioning,
or other work activities planned for the next two weeks as well as progress
achieved over the preceding week.
The Contractor shall also be required to attend other meetings from time to
time as required for the project and the person representing the contractor shall
be fully empowered to take decisions at such meetings.
The Contractor shall liaise with local authorities on matters concerning the
impact of his operations on the local communities. Any problems that cannot
be resolved by the Contractor shall be referred to the Employer through the
Engineer.
The Contractor shall ensure that construction does not negatively impact the
natural beauty, the function, the amenities, or the ecosystems of the area and
care shall be taken to prevent permanent damage.
The Contractor shall provide drainage facilities at each substation site, and
shall revetate the surface where necessary to prevent erosion and consequent
weakening of the foundations.
The Contractor shall as far as possible, protect the flora within the work sites.
If areas are disturbed beyond the designated work boundaries, the Contractor
shall reinstate the ground and re-establish suitable Vegetation as directed by
the Engineer at no extra cost to the Employer. Such re-establishment shall take
place as soon as practicable after the Engineer's request.
The Contractor and his employees shall protect all faunas living within the site
area and shall ensure that hunting, shooting, bird nesting, egg collecting, or
trapping does not occur. Permits to cut any trees shall be obtained from the
relevant authorities through the Employer.
The Contractor shall as far as possible, restrict the dust pollution due to
digging activities. Special care shall be taken to reduce the pollution by
spraying water at regular intervals as per the directives of engineer or
supervisor so that the effects of dusts and inconvenience to the public are
minimized.
The contractor shall not dig and leave the place open for a maximum period of
7 days. The cable laying and foundation etc shall be so planned that as soon as
digging is done the work is carried out and covered up. As a safety measure,
the Contractor shall also barricade the working area with the warning tapes
and bamboos.
Contractor shall mobilize the workforce, equipment and start the work only
after getting environmental clearance from National Environment
Commission. BPC shall process for theses clearances and hand over to the
contractor at as early as possible after signing of the contract agreement.
The work site shall be kept neat and clean at all the times. Proper house
keeping of the site and store shall be done as directed by the engineer in
charge as per the directives at the site without any extra cost to the employer.
1.23 Documentation
1.23.1 General
1.23.2 The following essential drawings and information shall be submitted for
approval after signing of the contract agreement before the work is put in
hand.
The Contractor shall submit to the Engineer for approval a summary table of
tests and inspections to be carried out in the manufacturer’s works and at site
at least 2 months before the first scheduled activity.
The schedule shall include:
Raw materials test and inspections;
Workshop tests and inspections;
Site tests and an inspection, including pre-commissioning and
commissioning tests.
The Contractor shall submit detailed procedures for the site tests for approval
at least one month in advance of the corresponding activities, including:
Descriptions of the inspection and test methods;
Test or inspection sheets with dimensions and blank spaces for
entering of measured values;
Proposed dates and locations of tests and inspections.
The Contractor shall submit all final test and inspection reports to the Engineer
for approval, in the case of manufacturer’s works activities, before shipment
of the corresponding plant items.
The Contractor shall supply consignment notes bearing the reference number
of each dispatch, and a list of the contents of each crate, identification
numbers, dimensions, net and gross weights and where necessary, any special
instructions regarding storage and the type of packaging/ handling.
1.1.4.1 If measured losses exceed the guaranteed figures; penalties will be levied on
the Contractor at the rates given in Clause 1.1.3.1 above, within tolerable
limits.
Each 2 MVA transformers shall have the following fittings and accessories,
including but not limited to:
1.1.7 Windings
1.1.7.2 Materials used in insulation and assembly shall be insoluble, non-catalytic and
chemically inactive in the hot transformer oil and shall not soften or otherwise
be affected under operating conditions.
1.1.7.3 Leads from winding to the terminal board and bushings shall be rigidly
supported to prevent injury from vibration.
1.1.8 Core
1.1.8.1 The magnetic circuit shall be constructed from high grade, cold rolled, non-
ageing, grain oriented silicon steel laminations. Each sheet shall have an
insulating coating resistant to the action of hot oil.
1.1.8.2 The insulation structure for the core to bolts and core to clamp plates shall be
such as to withstand a voltage of 2000 V for one minute. The framework and
clamping arrangements of core and coil shall be securely earthed inside the
tank by a copper strap connected to the tank. The core clamping structure shall
be designed to minimise eddy current loss. The core shall be provided with
lugs suitable for lifting the complete core and coil assembly. The framework
and clamping arrangements shall be securely earthed.
1.1.9 Tank
1.1.9.1 The transformer tank shall be made from high-grade sheet steel, suitably
reinforced by stiffeners made of structural steel sections. All seams, flanges,
lifting lugs, braces, and other parts attached to the tank shall be welded. The
1.1.9.2 Tank together with radiators, conservator, bushings and other fittings shall be
designed to withstand without permanent distortion the following conditions:
1.1.9.3 Tank shall be provided with a pressure release device, which shall operate at a
pressure below the test pressure for the tank and radiators. The device shall be
rainproof after blowing and shall be provided with a device visible from
ground to indicate operation. An equaliser pipe connecting the pressure relief
device to the conservator shall be supplied. The device shall be provided with
potential free contacts for alarm and tripping. Alternatively, a separate
pressure relay shall be provided for this purpose.
1.1.9.4 The tank cover shall be bolted type and not welded, sealed type. The tank
cover shall be removable and shall be suitably sloped so that it does not retain
rainwater.
1.1.10 Bushings
1.1.10.2 The angle of inclination of oil filled bushing to vertical shall not exceed 30°.
1.1.10.3 Bushings rated 72.5 kV and above shall be of the oil-filled condenser type
with a central tube and draw-in conductor, which shall be connected to the
connector, housed in the helmet of the bushings. The pull through lead shall
be fitted with a gas bubble deflector.
1.1.10.4 Bushings shall be equipped with oil level indicators and means for sampling
and draining the oil. Condenser type bushings shall be equipped with the
following additional features:
1.1.10.5 All applicable routine and type tests as stated and specified in the applicable
standards shall be carried out.
1.1.11.2 Radiators shall be of detachable with bolted and gasket flange connections.
1.1.12.1 OFF CIRCUIT Tap Changer (OCTC) shall be provided. This handle shall be
suitable for operation by a man standing at ground level.
1.1.13.1 The marshalling box shall be tank mounted /free standing, weather proof,
sheet steel (2.5 mm thick minimum), enclosed and with hinged door having
padlocking facility. Door and gland plate shall be fitted with neoprene
gaskets. Bottom shall be atleast 600 mm from grade level. Top surface shall
be sloped. The degree of protection shall be atleast IP55.
1.1.13.3 All contacts for alarm, trip and indication circuits shall each be electrically
free, designed for the auxiliary DC supply of 110 V (as available at the site)
and brought out to separate terminals in the marshalling box. Terminals shall
be rated for 10 A. Disconnecting/ shorting type terminal block shall be used
for CT circuits.
1.1.14.1 Primary and Secondary side cable boxes shall have sufficient space for
segregating the cable cores and for adequate clearance in air between bare
conductors at the terminals. Cable boxes shall be complete with necessary
glands, lugs and armour grips.
1.1.14.2 Air filled cable boxes shall be of adequate dimensions and designed in such a
manner that they can be opened for inspection without disturbing the gland
plate or incoming cable. Disconnecting chamber shall be provided for
disconnecting and moving away the main transformer, without removing the
cables or the cable box.
1.1.14.2 Provision shall be made for earthing the body of each cable box.
1.1.15 Tests
1.1.15.1 All auxiliaries and accessories such as bushing CTs, Temperature Indicators,
Buchholz and pressure relays shall be tested as per the applicable standards
and test certificates shall be furnished to the Engineer for approval.
1.1.15.2 Bends, pressure test for leakage, noise level and heatrun for 1 transformer of
each rating shall be carried out without any additional cost implication and
shall be included in the transformer cost.
1.1.15.3 Type test for each transformer rating carried out within 5 years shall be
submitted during the detail engineering.
1.1.16 Rejection
1.1.16.1 The Employer may reject the transformer if anyone of the following
conditions arises:
1.1.16.2 Employer reserves the right to have the transformer replaced or repaired by the
Contractor within reasonable period to Employer's satisfaction at no extra cost
to the Employer. The Contractor shall also bear the costs, including but not
limited to, incurred by the Employer in re-inspection/re-testing such as travel
and incidental expense, etc. The Contractor shall note that any delay in
completion time due to such repair/replacement shall be subject to liquidated
damages as specified in the Conditions of Contract.
1.1.17 Inclusions
1.1.17.1 The following items shall also be included in the Contractor's scope:
2.1 SCOPE
2.1.1 The scope shall be for the design, engineering, manufacture, assembly, testing at
manufacturer's works before dispatch and services for supply, insurance,
transportation, delivery at project site, handling, storage and preservation at store/site,
transport to place of installation, complete work of site assembly, erection, testing at
site and commissioning of 36 kV SF6 Gas Insulated Switchgear (GIS). The
equipment shall comprise of:
a) Circuit Breakers
b) Bus Bars – Single bus
c) Current Transformers
d) Voltage Transformers
e) Transition between SF6 GIS and XLPE Cable terminations, operating
mechanism for each equipment
g) SF6 Gas
h) Supporting steel structures
i) Complete earthing system etc.
k) Any other item which is not covered above and but required for the operation
of the switchgear shall be supplied.
2.1.2 Any other equipment not explicitly mentioned herein/in the schedule of requirements
but is necessary for completeness of works specified shall also be included in the
scope without any extra cost. The equipment shall be suitable for climatic conditions
and altitude as mentioned in the technical specifications.
The following 33kV indoor GIS shall be provided at DPH-II 33/11kV substation:
The switchgear shall be in two bus sections, each catering to 1 incomer and 1
outgoing (transformer feeder) with bus section breaker. In addition to the bus PTs on
each bus section, the incomers shall be provided with line side PTs. For the incomer
feeders and bus-section, the breaker control circuit shall incorporate following
suitable control schemes (LILO):
(a) Looping out the power to Olakha substation at the same time charging the
transformers (2x5 MVA, 33/11 kV)
(b) Closing of incomer-2 feeder breaker (see SLD) when incomer-2 line is dead, at
the same time feeding the transformers.
(c) Synchronizing two sources (i.e when feeding from RICB substation and
Olakha substation) through closing of bus coupler breaker.
2.3 STANDARDS
2.3.1 The GIS switchgear shall comply with the latest amendments/revision of the
following standards or equivalent:
2.3.2 If there are, in the opinion of the bidder, any contradictions between the above
standards and these specifications, such contradictions shall be brought to the
attention at the time of bidding.
2.4 RATINGS
2.4.1 The ratings and general characteristics of the GIS shall be as follows:
(The ratings applicable to specific items of equipment are indicated in the applicable
sections dealing with the equipment).
(k) Rated short circuit withstand current at Not less than 25 kA rms
rated maximum voltage for three second (symmetrical)
2.4.2 All current carrying components of the equipment specified shall be capable of
continuous operation at the specified rated current without exceeding the maximum
temperature rise specified in the relevant IEC/IEEE standards.
2.5.1 The switchgear shall be single busbar, SF6 insulated capable of continuous operation
under the climatic condition and altitude at the site.
2.5.2 The panel shall be of extendable type. The design shall be such as to enable bay
extension at either end with the minimum of disturbance to the installed equipment
and without complete shutdown of the switchboard.
2.5.3 The switchgear units shall be divided into several gas-filled compartments. The
equipment and connections will be arranged in such a way to allow ready removal and
replacement of any section with minimum isolation and disruption of adjacent
pressurized sections. This feature should also permit erection and testing of extension
units with the equipment in service with the minimum of outage time required.
2.5.4 The pressurized compartments shall be designed to minimize the risk of damage to
adjacent sections and protection of personnel in the event of a failure occurring within
the compartments. Individual compartments shall be equipped with pressure relief
devices.
2.5.6 The gas loss per annum should be not more than 0.5% in any single gas compartment.
In case of extensive gas leakage during the defect liability period, BPC has the right to
request the contractor to replace the parts of the assembly which caused the leakage
without any cost implication to BPC.
2.5.7 The switchgear, which shall be of modular design, shall be fully gas insulated, all
Medium Voltage parts shall be insulated with SF6 gas. The conductors and the live
parts shall be mounted on high graded epoxy resin insulators. These insulators shall
be designed to have high structural strength and electrical dielectric properties and
shall be shaped so as to provide uniform field distribution and to minimize the effects
of particle deposition either from migration of foreign particles within the enclosures
or from the by-products of SF6 breakdown under arcing conditions.
2.5.8 The connecting points for the gas monitors shall also include connectors for
evacuation and gas filling.
2.5.9 Gas barrier insulators shall be provided so as to divide the GIS into separate
compartments. They shall be suitably located in order to minimize disturbance in case
of leakage or dismantling. They shall be designed according to IEC 62271-200 6.103.
The switchgear design shall confirm IAC AFLR. Gas section barriers shall be gas
tight and capable to withstand the maximum pressure differential that could occur
across the barrier. The support insulators and section barriers shall be of sufficient
strength to ensure that spacing and clearances are maintained when short circuit faults
occurs.
2.5.10 The material and thickness of the enclosures shall be such as to withstand an internal
flash over without burn through for a period long enough 1000ms till the backup relay
protection clears the fault. The material shall be such that it has no effect of
environment as well as from the by-products of SF6 breakdown under arcing
condition.
2.5.11 The material used for manufacturing the switchgear equipment shall be of the type,
composition and have physical properties best suited to their particular purposes and
in accordance with the latest engineering practices. All the conductors shall be
fabricated of copper bars of cross sectional area suitable to meet the normal and short
circuit current rating requirements. The finish of the conductors shall be smooth so as
to prevent any electrical discharge. The conductor ends shall be silver plated wherever
required to confirm the ratings as per IEC. The contacts shall be of sliding type to
allow the conductors to expand or contract axially due to temperature variation
without imposing any mechanical stress on supporting insulators.
2.5.12 The switchgear line-up when installed and operating under the ambient conditions
shall perform satisfactorily and safely under all normal and fault conditions. Even
repeated operations upto the permissible servicing intervals under 100% rated and
fault conditions shall not diminish the performance or significantly shorten the useful
2.5.13 Bracings shall be provided for all mechanical components against the effects of short
circuit currents. The arc faults shall be positively confined to the originating
compartment and shall not spread to the other parts of switchgear.
2.514 The switchgear shall be of the free standing, self-supporting with easy accessibility to
all the parts during installation and maintenance, dead front design with all high-
voltage equipment installed inside gas-insulated metallic and earthed enclosures,
suitably sub-divided into individual arc and gas-proof compartments at least for:
(i) Busbars.
(ii) Circuit breakers.
2.5.15 The arrangement of the individual switchgear bays shall be such so as to achieve
optimum space-saving, neat and logical arrangement and adequate accessibility to all
external components.
2.5.16 It should be impossible to unwillingly touch live parts of the switchgear or to perform
operations that lead to arcing faults without the use of tools or brute force. All
mechanical operations shall be done with the door closed.
2.5.17 A comprehensive interlocking system shall be provided to ensure reliable and safe
operation of the substation. All interlocks that prevent potentially dangerous mal-
operations shall be constructed such that they cannot be operated easily, i.e. the
operator must use tools or brute force to over-ride them. Within one panel,
mechanical interlocking has to be provided and the three position switch must have
facilities to be operated manually.
2.5.18 The actual position of circuit breakers must be positively displayed by mechanical
indicators visible from the operating position. It shall be possible to remove the CB
without having to switch off the BB.
2.5.19 In general the contours of energized metal parts of the GIS and any other accessory
shall be such, so as to eliminate areas or points of high electrostatic flux
concentrations. The surfaces shall be smooth with no projection or irregularities,
which may cause visible corona.
2.5.20 The fabricated metal enclosures shall be of stainless steel and have high resistance to
corrosion, low electrical losses and negligible magnetic losses. All joint surfaces shall
be machined and all castings shall be spot faced for all bolt heads or nuts and washers.
All screws, bolts, studs and nuts shall conform to metric system.
2.5.21 Wherever required, the heaters shall be provided for the equipment in order to ensure
the proper functioning of the switchgear at specified ambient temperatures. The
heaters shall be rated for 230V AC supply and shall be complete with thermostat,
control switches and fuses, connected as a balanced 3-phase, 4-wire load. The
possibility of using heaters without thermostats in order to achieve the higher
reliability may be examined and accordingly decided during detailed design stage but
it shall be ensured that the temperature rise of different enclosures where heating is
2.5.22 The sealing provided between flanges of two modules/enclosures shall be such that
long term tightness is achieved.
2.5.23 All earthing systems will be designed to ensure safety and protection of all operating
and maintenance personnel during all normal and fault conditions.
2.6.2 The circuit breakers being supplied shall be suitable for operation with Transformers
and 33 kV Sub-transmission lines.
2.6.3 The CB shall be spring operated, motor charged and manually released spring closing
mechanism with three pole simultaneous operations. The speed of the closing
operation shall be independent of the hand-operating lever. The indicating device
shall be mechanical type directly linked to the mechanism and shall show the OPEN
and CLOSE position of the breaker visible from front of the cubicle without opening
any doors or covers
2.6.4 The “TRIP” and “CLOSE” coils shall be of reliable design and low consumption.
Anti-pumping relays and T-N-C switch/PB shall be provided for each panel.
2.6.5 Vacuum Type circuit breaker shall conform to IEC-56 and have the following
performance characteristics and ratings, in addition to those stated in Clause 4.0 of
this document.
(xiv) Total break time for any current Not exceeding 60ms
upto the rated breaking current
2.7.1 CTs and VTs shall have polarity marks indelibly marked on each transformer and at
the associated terminal block. Facility shall be provided for short circuiting and
earthing the CT secondary at the terminal blocks.
2.7.2 CT's shall be easily accessible and interchangeable.
2.7.3 The CT ratios shall be furnished during detail engineering after the award of the work.
All the breakers including bus couplers are to be provided with the CTs.
2.7.4 Identification labels giving type, ratio, output and serial numbers shall be provided for
CTs and VTs.
2.7.5 VTs shall be of the single-phase type.
2.7.6 VT shall be connected by using isolators.
2.8.1 Disconnecting and earthing switches shall permit safe maintenance of any section of
the equipment when the remainder is live.
2.8.2 The disconnecting switch and earthing switch shall be of motor driven mechanism.
For safe isolation of the busbars and feeders, high speed fault making spring driven
disconnector/earth switch shall be provided. They will also have facilities for manual
operation and necessary operating handles shall be provided. The mechanical
operation of the disconnector switch must be possible with door closed for operator
safety.
2.8.3 All earthing switches shall be fully interlocked with associated circuit breaker and
disconnecting switches.
Any fittings, accessories or apparatus which may not have been specifically
mentioned in these specifications but are necessary for completeness of the equipment
shall be deemed to be included and shall be supplied without any extra charges to the
Employer. All plants and equipments shall be complete in all respects even if the
details regarding all the items are not mentioned in these specifications.
2.13 SPARES
BPC shall have option to order recommended essential spare parts as per the terms
and conditions of the contract. The spare parts shall be interchangeable and shall be of
same quality as that of original components.
The relay shall be provided as per Section 7. The meters shall be provided as per
Section 6. The control wiring, indicating instrument, control and selector switches,
indicators, push buttons, termination and other equipment shall be as per Section 3.
CT’s and PT’s requiring special manufacturing and consideration for the use in GIS
shall be provided.
2.15 DRAWINGS/DOCUMENTS
3.1 33 kV and 11 kV indoor switchboards shall comply with latest revision / amendments
of the following International Standards, including those referred to therein.
Rated Insulation Levels given below is upto 1000 m (shall be corrected as per
altitude)
Constructional Requirements
Minimum thickness of sheet Frame & LT Frame & LT
steel in mm Cold rolled mm Compartment Compartment Doors–
(Frame/Enclosure/Covers) Doors– 2.5 2.5
Other Doors/Covers Other Doors/Covers –
Degree of protection of IP-4X IP-4X
enclosure
Colour finish shade - Interior RAL 7032 RAL 7032
& Exteriors
Cable connection Bottom entry and Bottom entry and exit
exit
Circuit Breakers
Type Vacuum Vacuum
Rated current inside the cubicle A 630 630
under design ambient
temperature at 40C
Rated operating sequence O–3 sec–CO-3 Min-CO
PROTECTIVE RELAYS
Type Numerical Numerical
Auxiliary supply V 110V DC 110V DC
Details of protective relays As per specification As per specification
METERS
Type Multi-Function Multi-Function
As per As per specifications.
specifications. 3 . 3 phase 4 wire with
Details of meters phase 4 wire with RS 485 port and
RS 485 port and optical port.
optical port.
** Note:
a. 11 kV switchgear shall have provision of extension from both sides.
b. Interlocking shall be provided based on the system operation which will be discussed
during detail engineering.
3.3 Busbars
3.3.1 Material of main and tap off busbars shall be of electrical grade and be of Copper.
3.3.2 Busbars shall be rated in accordance with the service conditions and the rated
continuous and short time current ratings specified in technical particulars/data Sheet.
Maximum temperature of the main busbars and busbar connections, under operating
conditions, when carrying rated normal current at rated frequency shall not exceed 90
Deg. C for joints/connections. Busbar temperature limits shall be adhered to without
forced cooling method. For tap off busbars, the current rating shall be at least equal to
corresponding breaker(s) rating.
3.4.1 Circuit breakers shall be Vacuum type. Circuit breaker along with its operating
mechanism shall be mounted on a wheeled carriage moving on guides, designed to
align correctly and allow easy movement. Plugs and sockets for power circuits shall
be silver faced and shall be insulated with suitable insulating material shrouds. All
corresponding components of circuit breaker cubicles of same rating shall be
interchangeable with one another.
3.4.2 There shall be ‘Service’, ‘Test’ ‘Fully withdrawn’ positions for the breakers. In the
‘Test’ position the circuit breaker shall be capable of being tested for operation
without energizing the power circuits, i.e. the control circuits shall remain undisturbed
while the power contacts shall remain disconnected. Separate limit switches, each
having a minimum of 2 ‘NO’ + 2 ‘NC’ contacts, shall be provided for both ‘Service’
and ‘Test’ positions of the circuit breakers for future use.
3.4.3 Electrical tripping shall be performed by shunt trip coils. “Local/Remote” selector
switch lockable with keys in “Local” position shall be provided on the cubicle door.
`Red’ and `Green’ indicating lamps shall be provided on cubicle door to indicate
breaker close and open positions. Breaker “Service” and “Test” positions shall be
indicated by separate indicating lamps on the cubicle door. Indicating lamps shall be
provided for “R”, “Y” “B” phase indication, trip circuit healthy indication and spring
charged indication for circuit breaker.
3.4.4 Connection of the control / interlocking circuits between the fixed portion of the
cubicle and the breaker carriage shall be preferably by means of plug socket
arrangement.
c) The tripping spring shall be charged by the closing action, to enable quick
tripping. Closing of the circuit breaker shall automatically initiate recharging
of the springs to enable the mechanism to be ready for the next closing stroke.
Charging time for the springs shall not exceed 30 seconds. It shall be possible
to manually charge the springs in an emergency. Transfer from motor to
manual charging shall automatically disconnect the charging motor. All
operating mechanisms shall be provided with "ON" - "OFF" mechanical
indication. The charging mechanism shall be provided with mechanical
indicators to show "charged" and "discharged" conditions of the spring.
Failure of any spring, vibration or mechanical shock shall not cause tripping or
closing of the circuit breaker.
e) The circuit breaker mechanism shall make one complete closing operation,
once the push button (PB) or control switch has been operated and the first
device in the control scheme has responded, even though the PB or control
switch is released before the closing operation is complete, subject to the
condition that there is no counter- impulse for tripping.
f) Means shall be provided to manually open and close the breakers slowly,
when the operating power is not available, for maintenance and adjustments.
A local manual trip device shall also be provided on the operating mechanism.
d) The circuit breaker carriage shall be earthed before the circuit breaker reaches
the test position from fully withdrawn position. In case of breakers with
automatic disconnecting type of auxiliary disconnects, the carriage shall be
earthed before the auxiliary disconnects are made and the carriage earthing
shall break only after the auxiliary disconnects break.
3.5.1 CTs and VTs shall have polarity marks indelibly marked on each transformer and at
the associated terminal block. Facility shall be provided for short circuiting and
earthing the CT secondary at the terminal blocks.
3.5.3 VTs shall be of the single-phase type and mounted on a drawout trolley. VTs shall be
protected on their primary sides by 3A HT fuses. MCB having auxiliary contact shall
be provided on secondary. Primary side fuses shall be replaceable only in the de-
energised position.
3.5.5 Identification labels giving type, ratio, output and serial numbers shall be provided for
CTs and VTs.
3.5.6 The CT ratios shall be furnished during detail engineering after the award of the work.
All the breakers including bus couplers are to be provided with the CTs.
3.6.1 Switchboard manufacturing shall be CNC machine based. Switchboard design shall
comprise metal enclosed, fully compartmental execution having separate sections for
each circuit. Compartments with doors for access to operating mechanism shall be so
arranged as not to expose high voltage circuits. Switchboard cubicle shall be provided
with hinged door on the front with facility for locking door handle.
3.6.2 Switchboard shall be dust and vermin-proof and shall have a degree of protection of
enclosure of IP 4X.
3.6.3 All removable covers shall be gasketed all around with neoprene or superior gaskets.
3.6.4 Instruments, relays and control devices shall be flush-mounted on hinged door of the
metering compartment located in the front portion of cubicle. The metering
compartment shall be properly shielded to prevent mal-operation of electronic
equipment such as numerical / static relays due to electro-magnetic fields. Separate
signal earth shall be provided for such devices, if necessary.
3.6.5 Each switchboard cubicle shall be fitted with a label on the front and rear of the
cubicle. Each switchboard shall also be fitted with label indicating the switchboard
designation, rating and duty. Each relay, instrument, switch, fuse and other devices
shall be provided with separate label. The labels shall be of Anodized Aluminum.
3.6.6 Sheet steel used for fabrication of switchboards, control cabinets, marshalling boxes,
etc shall be cold rolled.
3.6.7 All panels, cabinets, kiosks and boards shall comprise rigid welded/bolted structural
frames made of structural steel sections or of pressed and formed cold rolled sheet
steel of thickness not less than 2.5 mm. Stiffeners shall be provided wherever
necessary.
3.6.8 All removable covers, gland plates, etc. shall be of at least 2 mm thickness and shall
be gasketed all round the perimeter. All the doors shall be of 2.5 mm thickness.
3.6.12 The fully draw-out modules shall have all the circuit components mounted on
withdraw-able type steel chassis. All power and control connections shall be of the
draw-out type. It shall be possible to withdraw the chassis mounted circuit
components without disconnecting any connections. All draw-out contacts shall be of
silver plated copper.
3.6.15 After isolation of the power and control connections of a circuit, it shall be possible to
carry out maintenance in a compartment safely, with the busbars and adjacent circuits
alive.
3.6.16 Compartments with doors for access to operating mechanism shall be so arranged as
not to allow access to high voltage circuits. Switchgear cubicle shall be provided with
hinged door on the front with facility for padlocking door handle.
3.7 Earthing
3.7.1 A earthing bus of 50 x 6 sq.mm copper shall be provided and extended throughout the
length of the switchboard. It shall be bolted to the framework of each unit and brazed
to each breaker earthing contact bar. It shall be located at the bottom of the board.
3.7.2 The earth bus shall have sufficient cross section to carry the momentary short circuit
and short time fault current for at least 1 second without exceeding maximum
allowable temperature rise. The earth bus shall be properly supported to withstand
stresses induced by the momentary short circuit current.
3.7.3 Suitable clamp type terminals at each end of the earth bus shall be provided to suit the
size of the earthing conductors.
3.7.4 Bolted joints, slices, taps, etc. to the earth bus shall be made with at least two bolts.
3.7.5 Positive earthing of circuit breaker frame shall be maintained when it is in the
connected position and in all other positions whilst the auxiliary circuits are not
totally disconnected.
3.7.6 Hinged doors shall be earthed through flexible earthing braid of adequate cross
section.
3.7.7 All non-current carrying metal work of the switchboard shall be effectively bonded to
the earth bus.
3.7.8 Positive connection of the frames of all the equipment mounted in the switchboard to
the earth busbar shall be maintained through insulated conductors of size equal to the
earth busbar or the load current carrying conductor, whichever is smaller.
3.7.9 All instrument and relay cases shall be connected to earth busbar by means of
650/1100 V grade, green coloured, PVC insulated, FRLS stranded, copper, 2.5 sq.
mm conductor looped through each of the earth terminals.
3.8.1 It shall be possible to connect each circuit or set of 3 phase busbars of the switchboard
to earth through earthing switches.
3.8.2 Earthing switches / earthing devices shall be mechanically interlocked with the
associated breakers to prevent accidental earthing of live circuit or busbars.
3.8.3 In case the earthing facility comprises earthing trucks to be inserted in place of circuit
breakers, separate earthing trucks shall be supplied for each type / size of breaker
without any cost implication to BPC.
3.8.4 The earthing facilities proposed to be provided by the Bidder shall be clearly detailed
in the Bid and shall be subject to Employer's approval.
3.8.5 Auxiliary contacts (min. 2 NO + 2 NC) shall be provided on each earth switch /
earthing device and shall be wired to the terminal block for interlocking purpose.
3.9 Instruments
3.9.1 All electrical instruments and meters shall comply with IS 722.
3.9.2 All indicating and recording instruments shall be flush mounted in dust proof cases
complying with IEC 60068 and dimensions to IEC 61554.
3.10.1 Control and instrument switches shall be rotary type, provided with escutcheon plates
clearly marked to show operating position and suitable for semi-flush mounting with
only the switch front plate and operating handle projecting out. The connections shall
be from the back. The contact assembly at the back of the switch shall be enclosed in
dust tight removable covers.
3.10.2 Contacts of the switches shall be spring assisted and contact faces shall be of silver /
silver alloy. Springs shall not be used as current carrying parts. Contact rating and
configurations of the switches shall be adequate for the functions desired.
3.11.1 Cluster type LED lamps of 22 mm dia. of suitable voltage shall be provided.
The following indication shall be provided: Service positions, Test position, PT Fuse
fail, Auto Trip, TC Healthy, Spring charged, breaker off and breaker on.
3.12.1 Push buttons shall be of momentary contact type with rear terminal connections. All
push buttons shall have independent, potential free, 2NO + 2NC contacts. The contact
faces shall be of silver / silver alloy. The contacts shall be rated 10A and capable of
breaking inductive load of 1A at 110V DC.
3.12.2 Push button for emergency tripping of the circuit breaker shall be provided.
3.13.1 Adequately rated anti-condensation space heaters shall be provided for each
switchboard / cubicle.
3.13.2 Space heater shall be of the industrial strip continuous duty type of rating 100 W
(minimum), rated for operation on a 230 V, 1 phase, 50 Hz, AC system.
3.13.3 Space heater shall be provided with a single pole MCB with overload and short circuit
release, a neutral link and a thermostat.
3.14.1 Each cubicle shall be provided with interior lighting by means of 11 W CFL lighting
fixture. An MCB shall be provided for the lighting circuit. The lighting fixture shall
be suitable for operation from a 230 V, 1 ph, 50 Hz, AC supply.
3.14.2 A 230 V, 1 phase, AC receptacle (socket) plug point shall be provided in the interior
of each panel with an MCB.
3.15.1 Terminals for power connections shall be complete with adequate phase segregating
insulating barriers, shrouds and suitable crimping type of lugs for terminating the
cables.
3.15.2 Double compression type glands with armour and bonding clamps for the termination
of all solid dielectric multicore cables shall be provided.
3.15.3 Cable terminations for MV cables shall be heat shrinkable type. Adequately sized
shrouds / bolts shall be provided at connections to completely cover the terminations.
3.16.1 All low voltage wiring for control, protection and indication circuits shall be carried
out with 650/1100 V grade, PVC insulated cable with stranded, copper conductor of
minimum 1.5 sq. mm size. The size of conductor for CT circuits shall be minimum
2.5 sq. mm.
3.16.2 All wiring shall be run on the sides of panels and shall be neatly bunched and cleated
without affecting access to equipment mounted in the panel.
3.16.3 The wiring shall be bound and supported by clamping, roughing or lacing. Spiral
wrapping will not be accepted. Wireways shall not be more than 50% full. Adequate
slack wire shall be provided to allow for one restripping and reconnection at the end
of each wire. screened cables or wires are necessary, an insulating sheath shall be
included.
3.16.5 Wiring shall only be jointed or teed at terminals. Terminals of the clamp type shall not
have more than two wires connected.
3.17.1 Engraved core identification ferrules, marked to correspond with the wiring diagram,
shall be fitted to each wire and each core of multicore cables terminated on the panels.
The ferruling must be as per BEBS-S12 (1964).
3.17.2 Moisture and oil resisting insulating material shall be used. The ferrules shall be of
the interlocking type and shall grip the insulation firmly without falling off when the
wire is removed.
3.17.3 All wires forming part of a tripping circuit shall be distinctively marked.
3.17.4 Spare auxiliary contacts of electrical equipment shall be wired to terminal blocks.
3.18.1 Terminal blocks shall be of 1000 V grade and stud type. Brass stud of at least 6 mm
dia. with fine threads shall be used and securely locked within the mounting base to
prevent turning. Each terminal shall comprise two threaded studs, with a link between
them, washers, and matching nuts and locknuts for each stud. Connections to the
terminals shall be at the front.
3.18.3 Terminals for circuits with voltage exceeding 110 V shall be shrouded. Terminal
blocks at different voltages shall be segregated into groups and distinctively labeled.
3.18.4 Terminals used for connecting current transformer secondary leads shall be
‘disconnecting and shorting’ type with a facility for earthing the secondary.
3.18.6 Separate terminal stems shall be provided for internal and external wiring
respectively.
3.19.1 Electronic equipment shall be capable of withstanding randomly phased transient over
voltages of either polarity on the power supply or interruptions of the power supply
without damage or impairment to the equipment's subsequent performance. In the
case of controls, no mal-operation shall occur.
3.19.2 Where manufacturers require that electronic equipment supplied under this Contract
should not be subjected to insulation resistance tests ('Meggering'), suitable warning
notices shall be provided and installed in appropriate locations. When specified by
manufacturers, separate shield / signal earthing shall be provided.
3.19.3 It shall be possible to remove / replace cards from / to electronic equipment without
damage and without interfering with the operation of the rest of the equipment or
system. If necessary, consideration should be given to switching off the supplies
locally to a card to prevent inadvertent interference to the equipment or system during
removing / replacing a card.
a) All equipment shall be provided with sufficient easily accessible test points to
facilitate setting-up and fault location together with maintenance aids such as
extension boards, jumper leads and special maintenance tools.
i. MCBs
The rating and the circuit identification of each fuse shall be marked
adjacent to the MCBs base.
iii. Connectors
c) Test points shall be individually marked with the diagram reference number.
Test terminal blocks, if any, shall be provided for secondary injection and testing of
relays/meters.
3.21 MCBs
Each control panel shall be provided with the necessary arrangement for receiving,
distribution and isolation for DC and AC supply for various control, signaling and
lighting. It is proposed to have MCBs only instead of fuses. An indication for the PT
MCB failure shall be provided.
The relay provided shall be as mentioned below. Besides, numerical relay for primary
Protection, Master Trip relay (Numerical) and Trip Circuit Supervision relay shall be
provided.
a) The price of the bid shall include whether explicitly mentioned or not,
all the elements necessary to coordinate and assure the correct
functioning of the protection, high reliability, selectivity, very short
fault clearance time, and precisely dimensioned to the protected objects
these tender specifications and scope of work.
i) The relay shall have remote communication facility. The interface shall
ensure high dependability for genuine tripping signals and high
security against spurious trip signals necessary in protection
applications even if communication channel is disturbed.
k) Additional potential free contacts for all the Relay output i.e. trip as
well as alarm signals shall be provided for connection to SCADA in
the future.
l) The modules shall have transmit and receive counters for each
command such that the counter is incremented by actual output
command. This shall help in analysis of problems. The counter
information shall be in a non-volatile memory. Resetting the counter
shall be possible only with authorized access.
4.4 The DC distribution system which feeds the protection shall be proper so that,
the rating of the up-stream MCBs shall be chosen higher than that for the
down- stream ones and the coordination between the up-stream MCBs with
the down-stream ones shall exist. DC supply to trip coils shall be separately
fused in case of single DC supply. Two independent feeders from the
independent batteries shall be provided. An auto-changeover facility shall be
provided so that in case of failure of one power source, other shall cut in
automatically.
4.5 Both positive and negative of the auxiliary voltage shall be switched when trip
or close operation is executed in the substation switchgear.
4.6 The external protection circuits shall use the standard available substation
battery voltages. The voltage of the protection DC/DC converters shall never
be used for external protection circuitry.
4.7 The new protection system shall be completely wired, tested and inspected at
the factory. The only work to be performed at site shall be the connection to
external devices, the commissioning procedure and site tests.
4.8 The continuity of all tripping circuits shall be continuously supervised for both
close and open breaker status. The failure of any component of the supervision
shall lead to trip the breaker. The lock out relays shall also be supervised.
4.9 No time delay for the tripping contacts will be acceptable. Where a master trip
relay, lock-out relay or any auxiliary relay is utilized, it shall have a maximum
tripping time equal to or less than 10 ms. To avoid the additional time delay of
the above relay on the total tripping time of the main protection, an
arrangement shall be made so that the main protection shall perform the circuit
breaker tripping along with energizing the lock-out relay in a parallel circuit
arrangement.
4.11 All relays shall have clear identification on the associated panel by well-
written inscription plates. Where indications are provided by flag relays or
LEDs, these shall also be specifically identified by permanently fixed
inscription adjacent to them.
4.12 The supervision relays shall indicate an alarm and also a visual indication in
the case of trip operation of the relay, DC supply failure, DC/DC converter
failure, interruption in the trip circuit wiring and all alarm signals of the relay.
4.13 The tripping contacts of the protection relays shall reset automatically if no
further fault conditions are present, whereas the signaling and blocking close
order of the circuit breaker remains until the operator resets the relay
manually.
4.14 Each indicator, whether of the electrical or mechanical type shall be capable of
being easily reset by hand without special tools, opening the relay cover,
bridging of some back/internal terminals or drawing-out the relay.
4.15 Before starting with the wiring diagrams, the contractor shall supply block
diagrams in one drawing for each type of feeder and protection. These
drawings shall include information concerning control circuits, tripping
scheme, interlocking scheme, secondary circuits of voltage and current
transformers, DC power supply, supervisory alarms and tele-protection
circuits. These block diagrams shall be updated during the factory testing,
erection and commissioning phases.
4.16 The contractor shall supply the setting data sheets of the supplied protection
equipment showing the coordination with the rest of the network one-month
before commissioning.
a) This protection shall trip for all the phase and earth faults inside the zone and
shall have to be stable for all faults outside the zone limited by the current
transformers. This protection shall have restrained inrush-proof feature, which
shall never prevent operation for tripping in case if a real fault exists within
the relay zone during energization of the power transformer.
b) This protection shall be immune to the zero sequence current, which may
circulate, during certain conditions through the neutral of only one side of the
transformer. It shall be a modern phase segregated relay of low burden with
absolute stability at switchgear designed short circuit current rating and
tripping time of not more than 25 m.sec, at flow of one side current equal to
twice the nominal current. The tripping contactor of the relay shall have
sufficient number of contacts of suitable switching capacity to trip all the
c) The setting of bias and basic setting must be adjustable in steps in order to
cover the maximum mis-match between the HV and LV due to error of the
CT's and range of regulation of the tap changer.
e) It shall have a visible annunciator, which will be reset by push button and shall
be located on the relay.
f) Although the CT ratio and vector diagram correction for the input currents to
be performed within the relay itself. External interposing current transformers
is not required.
a) The restricted earth fault relay shall be operated from a completely separate
core of line and neutral current transformers. The dedicated CTs shall be of
class PS or X and have same magnetization characteristics with a knee emf
value higher than the highest possible setting of the relay. Intermediate CTs
for ratio correction are not acceptable. CT sizing shall be matched with
requirements from the relay.
b) For this protection, 1-phase high impedance relay will be provided and all the
aspects regarding stability of the protection, dimensioning of current
transformer, considering the peak short circuit current, etc. and all the
auxiliary equipment such as non-linear VDR resistor for voltage limiting, filter
for harmonics and DC component suppression and variable shunt resistor for
sensitivity adjustment if required shall be considered for the tender. The total
fault clearing time shall not exceed 20 m.sec. at 3IN.
c) Tripping of this protection shall activate all the circuit breakers surrounding
the power transformer and all the material such as surge-proof inter-tripping
relays if necessary, cables, test terminals, erection work, etc. is part of the
scope of this protection.
a) This relay not only monitors the pre-conditions for synchronising, but also
activates on-line correction signals, if necessary, to satisfy the conditions for
synchronising.
b) Phase current range shall cover at least 50-300% of-IN in steps of not more
than 10% while the earth current range shall cover at least 5-100% of IN in
steps of not more than 5%.
c) The time setting range of the definite time mode shall not be less than 5
seconds in steps each of 0.1 second.
d) The time multiplier setting for the inverse time-current characteristic modes
shall have a range not less than 0.05- 1.6 in steps each < 0.05.
e) Overcurrent and earth fault relays shall have separate timers and operation
indicators.
f) The high set element shall have a range of 2 - 15 times the nominal current at
least in steps of 1 IN shall be of low transient overreach, with a tripping time of
less than 25 ms and possible to be selected on "blocked" position. Reset time
shall be not more than 50 ms for both elements.
g) The relays, which shall be installed on the transformer neutral side, shall be
from single-phase version, but they shall have the same characteristics as the
phase ones. The transformer neutral earth fault relay shall trip both
transformer breakers.
b) Voltage operated relays with sufficient contacts to initiate alarm and data
logging for various alarm functions for transformers, etc. shall be provided.
Each relay shall have four (4) normally open self-reset contacts. The auxiliary
relay for Buchholz alarm shall be slugged to have delay on drop off at 100 ms.
The relays shall have hand reset operation indicator.
4.21 Tests
All routine tests shall be carried out on the assembled switchboard / panel during
inspection at the manufacturer’s works as per applicable standards. Test reports for
bought out items shall be presented for review/acceptance during testing. The bidder
shall submit type test reports during the detail engineering which is less than 5 years
old. In case the type tests reports are of the tests conducted earlier than five (5) years
prior to the date of Bid opening, the Contractor shall repeat these test(s) at his cost.
Multifunctional meter for functions as shown in the single line diagram/specifications shall
be provided. It shall be 3 phase 4 wire with RS 485 port and optical port. It shall be provided
with separate 3 phase 4 wire type test blocks for the testing of meters without disturbing the
CT and VT secondary connections. The accuracy of the meters shall be 0.5 or better and
capable of displaying maximum demand (kW/kVA). The detail specifications of meter are as
follows:
The bidder shall supply Fully Static Intelligent Energy Meter with GSM/GPRS support.
The static meter shall be manufactured and tested in accordance with the latest edition of
the following standards:
a. IEC 60687: Alternating current static watt-hour meters for active energy (classes
0.2 S and 0.5 S)
b. IEC 61036: Alternating current static watt-hour meters for active energy (classes 1
and 2)
c. IEC 61268: Alternating current static var-hour meters for reactive energy (classes
2 and 3)
d. IEC 61107: Data exchange for meter reading, tariff and load control direct local
data exchange
The static meter (The meter) shall be dust-proof type and installed in a cabinet, and
suitable for operation under the following conditions:
Altitude : up to 2,400 m above sea level
Ambient air temperature : from -10 up to 40C
Average Daily Ambient Air Temperature : 25C
Relative humidity : from 20% – 100%
Climatic condition : Varied, from tropical to severe winters
Average Annual Rainfall (mm) :1390 mm
The overall climate condition is moderately warm, dusty and humid, conducive to rust
and fungus growth.
The register unit shall be an all solid-state microprocessor based register with internal
memory of programmable and reprogrammable type. The internal memory shall be non-
volatile semi-conductor type.
The register display shall be at least 6-digit LCD display with three (3) decimal points
for power and two (2) decimal points for energy (programmable). The dimension of
LCD display and number on LCD display shall be as per IEC standard.
The register unit shall be able to process data in at least two (2) following programmable
modes:
(i) To display the real time data and check the status of the meter
(ii) To store and display the billing data for at least 60 days and the same shall be
retained in case of power failure.
The register unit shall have the following display operating modes:
(i) Scroll mode
The selected display data such as kW, kVar etc. shall be continuous sequence to
display each data automatically for a programmable display scroll time up to 15
seconds.
(ii) Manual operating mode
The push button/switch on the panel shall be used to start the display sequence
and to display the various stored data.
The display sequence and identified code can be independently specified by the user
(programmable). The identified code shall be at least three (3) digits.
The display shall have symbols for indicating the operation of the meter, and also
both import and export direction of measured active and reactive energy.
The display shall be able to indicate a unit of measure and the symbol of Electricity
Rates.
The meter shall be able to indicate defects, by displaying on LCD display, as follows:
a) In case the meter is damaged or has internal defects (e.g. clock fail, memory fail,
etc.).
b) In case the meter measures in reverse direction, or energy flows in reverse
direction.
c) In case the voltage at any phase is lost or under the setting value.
d) In case of low battery
The meter shall have an internal real time clock and/or a crystal-controlled time clock,
supplied from the Lithium back-up battery in case of power supply failure, for
providing calendar functions (i.e. the time of day, date, weekday, weekend, holiday,
year). The Lithium back-up battery shall be socket type.
The auxiliary power supply for the meter shall be derived from PT & CT.
The meter shall be able to record load profile data of no less than two (2) channels,
kW and kVar demand, every 15 minutes for at least 40 days in each channel. Load
profile data shall not be effected when the power is lost.
The meter shall have at least three (3) following groups of accessible password:
i. Group 1: Password for administrators to write the software and set the system
of the meter.
ii. Group 2: Password for programmers to program the operating functions of the
meter
iii. Group 3: Password for readers to read the stored data, including to correct the
time of the meter
Each meter shall have at least two (2) following communication systems:
i. Optical port, easily accessed through the front of the meter cover, for data
retrieval and program of all major operating characteristics of the meter.
ii. RS485 for connecting with modem.
5.13 CT Ratios
Meters should have dual CT ratio of 1/5 Amps. The change in the CT ratio can be
made only through a software and password authentications.
The meter shall pass the manufacturer’s standard routine tests. The following type
tests shall be in accordance with the latest relevant IEC or ANSI:
Test of insulation properties:
- impulse voltage test
- A.C. voltage test
Influence of short-time over currents
Influence of heating:
- windings, if any
- external surface
Electromagnetic compatibility (E.M.C.):
- radio interference measurement
- fast transient/burst test
- immunity to electromagnetic HF field test
- immunity to electrostatic discharge test
Others according to manufacturer’s standard
Heating (permissible temperature rise) of:
- windings, if any, in K
- external surface in K
The acceptance inspection shall be according to the latest relevant IEC or ANSI
a) Rated voltage
i. HV cables : 33 kV/ 11 kV
ii. LV power and control cables : 1.1 kV
iii. Lighting wires in conduits : 300/ 500 V
b) Installation:
i. In air or buried in ground.
ii. Depth of laying in ground for directly buried 33 kV cables:
1050 mm and 11 kV cables: 900 mm & for LV cables:
750 mm
iii. In conduit: space factor not more than 40 %.
iv. In trays: single layer, touching.
The above sizes are tentative and shall be decided during detail engineering.
6.4 The cable lengths indicated in price schedule shall be considered for
evaluation. However, it is Contractor's responsibility to provide the cable
schedule based on unit rates furnished during bidding. The contractor is to
procure the cables/cable termination only after finalizing the cable
schedule and not based on the BOQ in order to minimize the stores and
spares.
6.5 LT and DC cables shall be sized taking into consideration maximum voltage
drop of 2%.
6.6 33 and 11 kV cables shall be supplied in steel drums. The contractor may take
back the steel drum after completion of the works.
6.7 Tests
6.7.1 Cables shall be subjected to routine tests as per the applicable standards.
Cable tray supports such as angles, channel, etc shall be of GI/MS type.
6.8.2.1 For power cables, cable trays of MS ladder type shall be used. Accessories
such as tees, elbows, reducer, etc. shall be fabricated out of minimum 2 mm
thick sheet of hot dip galvanised type. Cable tray supports shall be at 1000
mm interval. If at the time of execution it is found that the cable trays sag, it is
Contractor’s responsibility to provide additional supports at no extra cost.
6.8.2.2 For Instrumentation and control cables, perforated type Aluminium cable trays
of minimum 5 mm thick sheet of hot dip galvanised type shall be used. The
outdoor cable trays if exposed to sun also shall be covered with the cover.
6.9.1 Terminals for power connections shall be complete with adequate phase
segregating insulating barriers, shrouds and suitable crimping type of lugs for
terminating the cables.
6.9.2 Double compression type glands with armour and bonding clamps for the
termination of all solid dielectric shall be provided. They shall be designed to
secure the armour wires to provide electrical continuity between the armour
and the threaded fixing component of the gland and to provide watertight seals
between the cable outer sheath and gland and between the inner sheath and
threaded fixing component. The gland shall preferably project above the gland
plate to avoid entry of moisture.
6.9.3 Earthing connectors between cable armour and earth shall be routed outside
the cable gland in an approved manner. Gland insulation shall be capable of
withstanding test for appropriate high voltage for one minute.
6.9.4 Cable terminations and jointing for HV/LV cables shall be carried out with
heat shrinkable type termination kits. Adequately sized shrouds/bolts shall be
provided at connections to completely cover the terminations.
7.1.1 Applicable Standards: IEC 60083, 60598, 60669, 60884, 60906 and
60947/IS1913
7.1.2.1 Lighting system equipment shall cover lighting panel, lighting fixtures,
switches, receptacles with switches, outdoor lighting inclusive of outdoor
lighting masts, street lighting poles, etc.
7.1.2.2 Normal and emergency lighting for indoor and outdoor areas shall be
provided. Separate lighting panels shall be provided for indoor and outdoor
areas.
7.1.2.4 Each lighting panel shall have facility for feeding the circuits, which would
operate on emergency supply.
7.1.3.1 Lighting panels shall be of wall/floor mounting type and fabricated out of 1.6
mm thick cold rolled sheet steel. Incomer circuit shall be controlled by a load
break type, triple pole switch or an MCB with a link in the neutral circuit.
Outgoing circuits shall be controlled by single pole MCBs of minimum 6A for
light points and 16 A for power points. Breaking capacity of MCBs shall not
be less than 10 kA. Residual current circuit breakers shall be provided on all
lighting and receptacle circuits.
7.1.3.2 The incomer circuit shall have bottom cable entry. It shall be possible to take
out outgoing circuits from top and bottom. Knockout for cable/conduit entries
for all the outgoing circuits shall be provided. Separate circuit for control of
lighting fixtures and receptacle shall be provided. Each phase shall have at-
least one spare circuit.
7.1.3.3 The panel shall be provided with 3 phase and neutral copper busbar adequately
rated to cater to the requirement of all the outgoing circuits. Two earthing
terminals shall be provided external to the panels for terminating the external
earthing conductor.
7.1.3.4 The panel shall be internally wired using colour coded, stranded copper
conductor, PVC insulated wires of 1100 V grade 2 nos. voltage relays suitable
for connection on 240 V, 1 phase power supply and one contactor suitable for
operation on 110 V DC shall be incorporated for sensing failure of AC supply
and energizing emergency lighting circuit.
7.1.3.4 Day timers shall be provided for automatic switching off outdoor lighting.
7.1.4.1 Lighting fixtures for illumination of outdoor and indoor area shal1 be
supplied. Fixtures for outdoor/semi-outdoor installation shall be of
weatherproof design with degree of protection of at least IP67.
7.1.4.2 Fixtures shall be complete with internal wiring, lamp, power factor correcting
capacitors, starter, holder, ballast, reflector, louvres/perspex, etc. as required
for their satisfactory operation.
b) Gate post lights - Top canopy spun from aluminium sheet and vitreous
enameled. Aluminium fins shall be fixed on the canopy at top and
spigot at bottom. Spigot shal1 be made of die-cast aluminium and
vitreous enameled. Fixture shall be suitable for 45 W LED lamp.
c) Decorative type LED fixtures - Housing made from mild steel sheet
and stove enameled white. Reflector assembly made from
electrochemically brightened anodized aluminium sheets secured to
housing with spring loaded triggers and suitable for 2 nos. 36 watt .
These fixtures shall be used in switchgear room and other areas where
false ceiling is provided. Fixtures shall be suitable for recessed
mounting in false ceiling.
7.1.4.4 The capacitor in the lighting fixture shall have adequate value of capacitance
to correct the power factor to 0.95 lag.
7.1.4.5 Each fixture shall be complete with a four way terminal block for connection
and looping of incoming and outgoing cables. Each terminal shall be able to
accept two 2.5 sq. mm stranded copper conductors.
7.1.4.6 Each lighting fixture shall be provided with an earthing terminal suitable for
connecting 16 SWG stranded copper conductor.
7.1.5.1 Lighting system shall be installed to achieve the average maintained levels of
illumination as indicated below. The Contractor shall be required to measure
the actual levels and carry out necessary modifications to accomplish specified
levels. It is to be noted that the values measured after installation will exceed
those specified by a factor that is equal or greater than the reciprocal of
maintenance factor. Measurement shall be carried out after 100 burning
hours.
7.1.5.2 The illumination system shall be so that the uniformity factor is of acceptable
level and that the glare is within limits. The ratio of maximum to minimum
illumination levels shall not exceed 20 in outdoor area within the fence.
7.1.5.3 The following values of maintenance factors shall be considered for design:
7.1.5.4 The Contractor shall furnish detailed design calculations along with a contour
map of illumination levels for outdoor area and control room, uniformity
factors, ratio of maximum to minimum illumination levels, ratio of average to
minimum illumination levels, glare indices, etc. for approval. Detailed
characteristics of various types of fixtures including but not limited to,
illumination curves and tables shall also be furnished for review during detail
engineering.
7.1.6.1 Receptacles of 5A and 15A rating with switches suitable for operation on 240
V AC, 1 phase, 50 Hz supply shall be provided as detailed below:
7.1.7 Switches
7.1.7.1 Decorative/ industrial type switches of 5A/10A rating shall be provided for all
indoor areas. Switches shall be provided to control a group of lighting fixtures
in various areas. Switches shall be housed in galvanized steel boxes.
7.1.8 Tests
7.1.8.1 Lighting panels, fixtures, receptacles and other accessories shall be subjected
to routine and acceptance tests as per the applicable standards.
7.2.2.1 Following material and sizes of earthing conductors, electrodes and shield
wire shall be used for various purposes:
7.3.1 33 and 11 kV Incoming and outgoings from the 33/11 kV switchgear shall be
by 33/11 kV grade earthed cables. The cables shall be terminated on a take-
off structure.
7.4.1 Applicable Standards: IEC 120, IEC 305, IEC 372, IEC 383, IEC 575,
IEC 1109, ANSI C29.6, and ANSI C29.4
7.4.2 Pin Insulators
c) Each pin insulator shall be supplied complete with a hot dip galvanised
forged steel pin, complete with nut, lock nut and spring washer. The
ultimate mechanical strength of the pin insulator assembly shall be equal
Section IV – Technical Specification
to the above cantilever strength. Pin insulators shall be supplied with
pins to fit on crossarms.
a) The string (tension disc) insulators shall be the ball and socket type
conforming to IEC 305 and IEC 120.
b) Each disc of the string insulators shall have the following minimum
characteristics.
CHARACTERISTICS UNIT
Designation (IEC 305) U 80 BL
Mechanical failing load kN 70
Nominal diameter mm 255
Nominal spacing mm 145
Nominal creepage distance mm 25 mm/kV
Puncture voltage kV 105
145
Minimum power frequency flashover
voltage Dry kV 78
Wet kV 45
c) Each string assembly shall consist of one (for 11 kV) or three (3 nos. for
33 kV) tension disc insulators, ball and socket couplings (16 mm to IEC
120), and a deadend clevis thimble suitable for preformed terminations
of 150 mm2 or 100 mm2 or 50 mm2, ACSR conductors.
7.6 Tests
7.6.1 Certificates of type tests carried out on arresters, insulators and hardware of
similar type shall be furnished during detail engineering.
7.6.2 Routine tests and acceptance tests as per the applicable standards shall be
carried out on the arrester, insulators and hardware in the presence of
Employer's representative.
1 m (l) x 0.75 m (w) x 0.003 m (t) rubber mat of black colour shall be installed
in front of each ACDB, DCDB and 33 kV and 11 kV switchgear.
1.0 General
1.1 This specification covers the general requirements with supply of all materials and
construction of civil related works and fabrication of structural steel works.
1.2 The contractor shall perform the works to meet the requirements of this
specification, the attached bid drawings and the relevant articles of this Contract
Document.
2.1 All materials, design, fabrication, galvanising and tests under these specifications
shall conform to the latest applicable Indian Standards, codes or their equivalent
established and approved in the country of manufacturer, and approved as equal by
Engineer.
2.2 Any details not specifically covered by these standards and specifications shall be
subjected to approval by Engineer. In the event of contradictory requirements
between the standards and the specifications requirements, the terms of the
specifications shall apply.
2.3 The Contractor may propose equivalent standards, specifications, materials etc.
which shall be equal in every aspect as specified. If the Contractor for any reason
proposes equivalents to or deviations from the above standards, he shall state the
exact nature of the change or the reason for making the change and shall submit
complete specifications of the materials as well as copies of pertinent standards for
the approval of Engineer and decision of Engineer in the matter of acceptability
will be the final.
3.0 Materials
All materials shall be as per the specifications and shall be approved by the
Engineer before use in the works. Samples of materials, fittings etc. shall be
submitted by the contractor for approval of the Engineer before bulk supplies are
brought on the site of works. The samples so approved shall be kept in the custody
of Engineer till the completion of works. When required by the Engineer, the
contractor shall supply for the purpose of testing, samples of any materials
proposed to be used in the works.
Samples whether submitted to govern bulk supplies or required for testing before
use shall be tested and the testing charges, if any, shall be borne by the contractor.
Testing of materials like concrete, brick, sand, aggregates, reinforcement and any
other civil materials may be done as and when instructed by the engineer. Any
materials failing from the test will be not allowed to use at site
Any finds at the time of excavation such as relics of antiquity, coins, fossils or
other articles of value shall be delivered by the contractor to the Engineer and shall
be the property of the Government. Any materials obtained from the excavation
which in the opinion of the engineer is useful, shall be stacked separately in regular
stacks as directed by the engineer aand
nd shall be the property of the Government.
Temporary site bench mark shall be constructed at the construction site, where so
required by the Engineer.
The materials and workmanship shall be of the the best of their respective kinds and
shall be to the approval of the Employer or his representative on Site, the Engineer.
The contractor shall carry out modifications in the procedure of work, if found
necessary, as directed by the Engineer during inspection.
inspection. Substandard quality of
work shall be rectified/redone at the contractor’s own cost, and defective
work/material shall also be removed from the site of works by the contractor at his
own cost.
The Engineer may ask to carry out the field/Laboratory tests mentioned in the
specification and the cost of carrying out such tests which include equipment
charges, tools, materials, labour and incidentals to perform tests and other
operations of quality control according to the specification requirements shall
sha be
deemed to be incidental to the work and no extra payment shall be made for the
same. Sampling and testing procedure to be used shall be as approved by the
Engineer and his decision shall be final and binding on the contractor.
51
DHI Group – Standard Bidding Document for Works
If these specifications do not cover these items then the relevant IS codes shall be
applicable. Where no reference is found in the above specifications for an item of
work then sound engineering practice as decided by the Engineer shall be
applicable and the decision of the Engineer in respect to all such matters relating to
specifications shall be final and binding on the contractor.
10.0 Signboards
The Contractor shall erect signboards in prominent positions adjacent to the works
to the satisfaction of the Engineer/in line with the requirement of CDB.
The contractor shall locate the Contractor Camp away from settlements, drinking
drink
water supply intakes, landslides or flood prone areas. This will help to avoid social
conflicts and the pollution of such sites and unsanitary waste disposal.
The scope of works for civil works, architectural, structural and foundations
ndations shall
include preparation of ground, supply of all materials to site including insurance
and storage, provision of all labor, qualified supervisory personnel, instruments,
tools, erection of plant and equipment, fixtures, fittings and all temporar
temporary and
permanent works necessary, whether or not such items are specifically stated
herein for satisfactory completion of the job in all respects in accordance with the
specification or as mentioned in the BoQ.
Site be graded
ed to the required level by cutting & filling. In case of filling, the
excess depth be brought to the required level by using cement concrete of M-10M
Grade. Area shall also be cleared of Jungle, bushes, vegetation, trees including its
roots etc. and stacking
ng of serviceable materials and disposal of other material as
directed by engineer. Filling in the excavated areas shall be done with sand.
15.0 Excavation
15.1 Earthwork in excavation for various foundations can be carried in all types of soil
including
ng soft/fissured/hard rock. The work shall also include dewatering in case
52
DHI Group – Standard Bidding Document for Works
confronted in any area. The scope of work also covers disposal of surplus
excavated material after filling back of foundation.
15.3 If any drainage system exists in the vicinity of excavation, Contractor shall control
the grading in the vicinity of all excavations so that the surface of the ground will
be properly sloped to prevent surface water from running into the excavated areas
during construction.
15.4 When machines are used for excavation, the last 300 mm before reaching the
required
red level shall be excavated by hand or by such equipment that shall leave the
soil at the required final level in its natural condition.
15.5 When excavation requires shoring, bracing etc. contractor shall submit to engineer
drawing g showing arrangement and details of proposed installations and shall
proceed only after getting approval from Engineer.
15.6 Excavated material suitable for use as backfill shall be deposited by contractor in
storage piles at the area approved by Engineer. However, surplus aand/or
nd/or unsuitable
excavated materials shall be hauled and transported to the disposal area designated
by Engineer.
16.0 Backfill
16.1 Contractor shall place and compact the backfill materials to the lines, grade and
dimension shown on approved drawings.
16.2 Prior to backfilling, all forms, temporary shoring, timber etc. shall be removed and
clean all trash, debris, perishable/organic materials and shall be approved by
engineer. The material to be used for backfill, the amount thereof and the manner
of depositing
epositing the materials shall be approved by Engineer.
17.0 Cement
53
DHI Group – Standard Bidding Document for Works
All stones shall be wetted before use. Masonry shall be laid truly in plumb or to
required batter where so specified. Height of construction in a day shall not exceed
1m so as to avoid excess load on fresh mortar.
22.0 Plaster
The joints shall be raked out properly. Dust and loose mortar shall be brushed out.
Efflorescence if any shall be rem
removed
oved by brushing and scraping. The surface shall
then be thoroughly washed with water, cleaned and kept wet before plastering is
commenced. In case of concrete surface, if a chemical retarder has been applied to
the formwork, the surface shall be roughened by wire brushing and all the resulting
dust and loose particles cleaned off and care shall be taken that none of the retarder
is left on the surface. The joints of masonry shall be raked out properly so that the
plaster is well keyed with the masonry.
23.0 Water
Water used for mixing mortars and concrete shall be clean and reasonably free
from injurious quantities of deleterious such as oil, acids, alkalis, salts and
vegetable growth. Generally portable/drinkable water shall be used. Water found
satisfactory
tory for mixing is suitable for curing concrete. However, the water used for
curing should not produce any objectionable stain or deposit on the concrete
surface.
Stone shall be hard, sound, free from decay, weathering and defects like
lik cavities,
cracks flaws, sand holes, veins patches of soft or loose materials etc. It shall be
54
DHI Group – Standard Bidding Document for Works
obtained from an approved quarry. Where required by the Engineer the stone shall
be got tested for water absorption determined as per IS: 1124, the stone boulders
boulde
shall not have round surfaces. The stone using for RRM works should be in blocks
of size 150 x 150 x 900 mm unless directed otherwise by Engineer or stated.
These shall be crushed or broken from hard stones. It shall be hard, strong, dense
and durable, clean and free from soft, friable, thin, flat, elongated or laminated,
flaky pieces and shall be roughly cubical in shape. While stock piling, the
aggregates shall not form pyramids resulting in segregation of different sized
materials and
nd height shall not exceed 1.5 m. The tests must be carried out for the
stone aggregates to check their conformance to the requirements of the
specifications.
Gravel/Shingle can be from the river beds or pits. It shall be sound, hard, clean,
suitably graded in size as specified without broken fragments. It shall be free from
flat particles of shale, powdered clay, silt, loam and other impurities. However, pit
gravel shall have to be washed.
27.0 Sand
Not more than 10% shall be retained on 4.75 mm IS Sieve. The sum of the
percentage of all deleterious materials shall not exceed 5%. It shall not contain
harmful organic impurities in any form or quantities which will adversely affect the
strength and durability of concrete or mortar. It shall not contain any acidic
material, which is likely to attack steel reinforcement. The tests must be carried out
for the fine aggregates to check their conformance to the requirements of the
specifications. The fineness modulus of sand to be used in plaster sshall
hall be between
1.0 and 1.5. The fineness modulus of sand to be used in concrete and for mortar
required for masonry shall be between 2.0 and 3.1. The maximum quantity of silt
shall not exceed 8%. Quantity passing through 150 microns IS Sieve shall not be
more than 10%.
28.0 Bricks
The bricks shall be hand or machine moulded. They shall be free from cracks and
flaws and nodules of free lime. The tests must be carried out for the brick to check
their conformance to the requirements of the specifications.
Bricks
cks required for brick work in cement mortar shall be adequately soaked in
stacks, before use, by profusely spraying with clean water at regular intervals for a
period of not less than six hours so as to keep them wet to the satisfaction of the
Engineer. Bricks
ricks required for masonry with mud mortar need not be soaked.
Brickwork shall be laid in English bond unless otherwise specified. Half or cut
bricks shall not be used except where necessary to complete the bond. Closures, in
such cases, shall be cut to the
the required size and used near the ends of the walls.
55
DHI Group – Standard Bidding Document for Works
In exposed brickwork, selected bricks shall be used for the face work.
It shall be of approved brand. The material shall not contain any harmful
constituents, which are llikely
ikely to impair the strength of cement. It shall conform to
the specification of IS 2645.
These shall conform to IS: 9103. Admixture is a material other than water,
aggregate, and hydraulic cement and additives like pozzolana or slag and fibre
reinforcement used as an ingredient of concrete or mortar and added to the batch
immediately before or during its mixing to modify one or more of the properties of
concrete in the plastic or hardened state. The different types of admixture are as
follows:
a) Accelerating admixtures,
b) Retarding admixtures
c) Water-reducing
reducing admixtures
d) Air entraining admixtures, and
e) Superplasticizing admixtures.
The chloride content in the admixture shall be declared by the manufacturer. Super
plasticizers
asticizers are expected to be chloride free. Admixtures that contain relatively
large amounts of chloride may accelerate corrosion of prestressing steel. Where
corrosion of such steel is of major concern, compliance with requirement of the
specification of IS 9103 does not constitute assurance of acceptability of the
admixture for use in prestressed concrete. In case of reinforced concrete, to
minimize the chances of deterioration of concrete, the total chloride content in the
concrete should be limited as specified in IS 456: 2000.
Protective coating and warnings shall remain undisturbed until final acceptance,
immediately prior to final inspection, temporary protection covering or coating
shall be removed and surfaces shall be washed with a suitable thinner and left in a
finished condition having approved uniform appearance and free from all marks
and blemishes. Wash and polish glass on both faxes.
All finished steel shall be well and cleanly rolled to the dimensions and weight
specified subject to permissible tolerances as per IS 1852. The finished material
shall be reasonably free from cracks, surface flaws, laminations, rough and
imperfect edges, and all other harmful defects.
defects. Steel sections, shall be free from
excessive rust, scaling and pitting and shall be well protected. The decision of the
Engineer regarding acceptability of the any steel section shall be final and binding
on the contractor. The mechanical and chemical pproperties
roperties of the structural steel
shall be as per Tables 3.6 and 3.7 respectively. The following varieties of steel
shall be used for structural purposes: -
56
DHI Group – Standard Bidding Document for Works
Foundation construction works includes excavation in all types of soil and backfill,
back
shoring and pumping out water if required, conducting required tests, necessary
embedment, curing and everything required for the satisfactory completion of
works.
Water, Cement, fine aggregate and coarse aggregate shall conform to material
specifications. Concrete can be specified by proportions or by nominating the
required strength.
57
DHI Group – Standard Bidding Document for Works
Before cutting and laying of the reinforcement for any RCC work, contractor need
to submit the bar bending schedules and get the approval from the Engineer in
charge. This shall be checked by the engineer at the site before implementing.
Daily work plan need to be maintained at the site in proper register. The work plan
for next
xt day need to be discussed in the evening and need to follow as recorded.
Contractor need to submit the monthly targeted work plan to the Project Office for
the proper monitoring purposes.
38.0 Miscellaneous
“No changes
es shall be made without the written approval of Engineer
Engineer”
40.2 Materials
Steel shall conform to IS: 226/IS: 2062 (tested quality) for mild steel and IS: 961
for high tensile steel.
58
DHI Group – Standard Bidding Document for Works
The minimum diameter of bolts shall be 16 mm. for members carrying calculated
stress and minimum 12 mm. for other members.
59
DHI Group – Standard Bidding Document for Works
1.0 GENERAL
1.1 The scope shall cover complete installation of plant items and accessories as indicated
in various parts of the specification. Requirements/ guidelines/ information/
parameters/ instructions etc. specified in this part shall apply to all the parts.
1.2 Installation work pertaining to plant items and systems such as cabling, lighting,
earthing and lightning protection systems, etc. shall comply with the applicable
standards, safety codes etc.
1.3 Installation shall be carried out strictly in accordance with the approved drawings.
Changes, modifications, if any, required to suit site conditions, shall be carried out
only with the prior approval of the Engineer. All such changes shall be incorporated
in the "As built" drawings to be furnished by the Contractor.
1.4 All tools, welding equipment, crane, scaffolding, rigging materials, ladders,
consumables, hardware etc. required for installation shall be provided by the
Contractor.
1.7 The Contractor shall ensure that all substations under erecti
erection
on as well as the work area
and the project site are kept clean to the satisfaction of the Engineer. In case the
Engineer is not satisfied about the site cleanliness, he will have the right to carry
out the cleaning operations and expenditure incurred in this regard will be to
Contractor's account, which will be deducted from the bills bills.. Packing cases and
packing material, except for spares shall be cleared from sites.
1.8 In order to avoid hazards to personnel moving around the equipment such as
switchgear etc.
tc. which is kept charged after installation before commissioning, such
equipment shall be cordoned off by suitable barriers to prevent accidental injury.
1.9 Switchgear and control/relay panels shall be installed on finished surfaces or concrete
or steel sills.
ls. Proper aligning, joining of various vertical shipping sections, busbar
connections, inter panel wiring etc. will be the responsibility of Contractor.
1.10 The Contractor shall take utmost care in handling instruments, relays and other
delicate mechanisms. Wherever the instruments and relays are supplied separately,
they shall be installed only after erection of switchgear/ relay panels is complete.
60
DHI Group – Standard Bidding Document for Works
2.1 All apparatus, connections and cable work shall be designed and arranged to
minimisee risk of fire and any damage, which might be caused in the event of a
fire.
2.2 Cables shall be laid directly buried in earth, on cable trays in built-up
built trenches,
in conduits/pipes along walls/structures/foundations/ceilings, etc. The
Contractor's scope of work includes unloading, excavation, laying, backfilling,
fixing, bending and terminating the cables. The Contractor shall supply the
necessary material and accessories required for installation and termination of
the cables which shall include but not be limited to items such as glands, lugs,
terminating accessories, hardware, consumables, saddles/spacers, GI
conduits/pipes, cable identification tags, protective bricks, civil materials, etc.
2.3.2 Directly buried cables shall be laid on a 75 mm thick sand bed. The cables
shall then be covered on top and at their side with sand to a depth of about 150
mm. This shall then be gently pulled down to a depth of about 100 mm above
the top of uppermost cable to provide bedding for the protective concrete cable
covers, which shall be placed centrally over the cables. The protective cable
covers shall be of reinforced concrete. The RCC covers shall have one hole at
each end to tie them to each other with GI wires to prevent displacement. The
trench should be then backfilled with the excavated soil after removal of
stones and boulders and well rammed in successive layers of not more than
300 mm thick, with the trenches being watered to improve consolidation,
wherever necessary. To allow for subsidence, a crown of earth not less than
50 mm in the center and tapering towards the sides of the trench should be
provided.
2.3.3 All cables to be routed along any particular route shall be laid at one time to
avoid repeated excavation, etc. Cable route markers shall be provided for
directly buried cables at an interval of 30 m and at every bend on the route in
the buried cable trench.
2.3.4 Where groups of HV, MV, LV and control cables are to be laid along the same
route, suitable metallic barriers to segregate them physically shall be
61
DHI Group – Standard Bidding Document for Works
2.4.2 In case of laying on cable trays/racks, power and control cables shall be laid in
separate cable trays, the order of laying of various cables being as given
below:
2.4.3 Ladder type GI cable trays and painted rack support shall be installed in cable
trenches for power cables. Perforated trays shall be used for control and
instrumentation cab
cables.
les. Embedded flats for fixing cable tray supports shall be
provided in cable trenches to support the cable trays during civil works.
Where such flats cannot be used, the fixing of cable trays shall be done using
anchor fasteners.
2.5.1 Standard cable grips and reels shall be utilised for cable pulling. If unduly
difficult pulling occurs, the Contractor shall check the pull required and
suspend pulling until further procedure has been approved by the Engineer's
Representative. The maximum
maximum pull tension shall not exceed the recommended
value for the cable measured by the tension dynamometer. In general, any
lubricant that does not injure the overall covering and does not set up
undesirable conditions of electrostatic stress or electros
electrostatic
tatic charge may be
used to assist in the pulling of insulated cables in conduit / pipes and ducts.
2.5.2 After pulling the cable, the Contractor shall record cable identification with
date pulled neatly with waterproof ink in linen tags/aluminum tag and shall
securely attach such identification tags. Identification tags shall be attached to
each end of each cable with non-corrosive
non corrosive wire. The wire must be nonnon-ferrous
material on single conductor power cable. Tags may further be required at
intervals on long
ng runs of cables on cable trays and in pull boxes. Cable and
joint markers and RCC warning covers shall be provided wherever required.
2.6 Each cable shall be pulled into the particular conduit/pipe. In hand holes, pull
boxes or junction boxes having any dimension over 1000 mm, all conductors
shall be cabled and / or racked in an approved manner. Care shall be taken to
avoid sharp bending or kinking cables, damaging insulation or stressing cable
beyond manufacturer's recommendations in pulling. Cable shall shall be protected
at all times from mechanical injury and from absorption of moisture at
62
DHI Group – Standard Bidding Document for Works
unprotected ends. The bending radius for various types of cables shall not be
less than 15 times the overall diameter of the cable for armoured cables and 20
times the overall diameter of the cable for unarmoured cables.
2.7 Cables on cable racks and in conduits/pipes shall be formed to avoid bearing
against edges of trays, racks, conduit / pipes or their supports upon entering or
leaving racks or conduit/pipes.
2.8 Cables
ables splices shall not be used except where permitted by the Engineer's
Representative. Splices shall be made by Contractor for each type of wire or
cable in accordance with the instructions issued by cable manufacturers and
the Engineer's Representative.
Representative. Before splicing, insulated cables shall have
conductor insulation stepped and bound or penciled for recommended distance
back from splices to provide a long leakage path. After splicing, insulation
equal to that on the spliced conductors shall be appli
applied
ed at each splice.
2.9 At cable terminal points, where the conductor and cable insulation will be
terminated, terminations shall be made in a neat, skillful and approved manner
by specially trained staff. Terminations shall be made by the Contractor for
each type of wire or cable in accordance with instructions issued by cable
manufacturers and / or the Engineer's Representative.
2.10 Control cable termination shall be made in accordance with wiring diagrams,
using proper colour codes for the various con
control circuit.
2.11 When control cables are to be fanned out and corded together with a cord, the
Contractor shall make connections to terminal blocks, and test the equipment
for proper operation before cables are corded together. If there is any doubt
about
out correctness of connection, the Contractor shall make a temporary
connection with sufficient length of cable so that the cable can be switched to
another terminal without splicing. After correct connections are established,
cables shall be cut to their correct lengths, connected to terminals in the
specified manner, and corded together where necessary to hold them in place
in a skillful manner. Jointing of cables shall be in accordance with relevant
Standards and manufacturer's instructions. Materials and tools required for
cable jointing work shall be supplied by the Contractor. Cables shall be firmly
clamped on either side of a ‘straight through joint’ at a distance of not more
than 300 mm away from the joints. Identification tags shall be provided at
each joint at all cable terminations.
2.12 Where cables pass through floor or wall openings or other partitions, suitable
bushes/pipe sleeves of GI shall be provided by the Contractor. The Contractor
shall seal the cables at the bushes/pipe sleeves using
using fire resistant material.
2.13 Cable seals shall be examined to ascertain if they are intact and that cable ends
are not damaged. If the seals are found to be broken, the cable ends shall not
be jointed until after due examination and testing under supervision
supervision of the
Engineer's Representative. Before jointing is commenced, insulation
resistance of both sections of cables to be jointed shall be checked by megger.
63
DHI Group – Standard Bidding Document for Works
2.14 In each cable run, some extra length shall be kept at a suitable point to enable
one or two straight
straight-through
through joints to be made, should the cable develop fault at
a later date.
2.15.1 Where cable trench is not available, cables shall be laid in GI conduits / pipes
routed along walls / columns / beams / steel structures
structures or buried in concrete
slabs, etc. to suit site conditions. Supply and installation of GI conduits / pipes
(minimum 20 mm diameter), their accessories such as bends, tees, couplers,
etc., saddles, spacers, junction / marshalling boxes and GI hardware rrequired
for installation shall be included in the Contractor's scope. Interval between
supports shall not exceed 1000 mm.
However, at the time of actual execution, if it is found that the cable trays (2.5
mm thick) sag, it shall be contractors responsibility
responsibility to provide additional
supports at no extra cost.
2.15.2 Non-metallic
metallic conduits / pipes shall be used for single core cables of a 3 phase
circuits.
2.15.3 The conduits and pipes shall be properly sealed by the sealing compound/with
Hessian cloth dipp
dipped in bitumen.
64
DHI Group – Standard Bidding Document for Works
3.1 Lighting panels, receptacles, light control switches, etc. shall be installed at the
following
owing heights from finished floor / ground level, unless otherwise
specified.
3.2 All light control switches and receptacle units (connected on the same phase)
at one location (such as room entrance), shall be hhoused
oused in one common box.
3.3 All wiring shall be concealed inside the control room. Within the control
room building, casing caping wiring shall be carried out. Space factor (ratio of
total cable cross
cross-section
section to internal area of conduit or casing) for
conduit/casings
onduit/casings wiring shall not exceed 40%. Size of wire chosen shall be
such as to limit the voltage drop to within 2%. Wires with minimum 2.5 sq.
mm. stranded copper conductor shall be used for lighting and 4 sq. mm. for
power sockets. For outdoor are
areas
as minimum 2.5 sq. mm. armoured cable with
stranded copper conductor shall be used. Current density in all cables shall
not exceed 2.5 A/sq. mm. Wires shall be colour coded. Generally, not more
than 8 to 10 lighting points shall be wired in one circuit.
circuit. For calculating
connected loads of various circuits, losses in the ballast shall be considered.
Maximum connected load on any circuit shall be 2500 VA for outdoor areas
and 2000 VA for indoor areas. In large rooms, the lighting system shall be
distributed
uted over three phases.
65
DHI Group – Standard Bidding Document for Works
3.4 Circuits for wiring of receptacles and lighting fixtures shall be separate and
wiring for the same shall be done in different conduits/casings. Switches /
receptacles wired on different phases shall be separated by a minimum
distance of 1.8 m.
3.5 Separate conduits shall be used for normal and emergency lighting circuits.
Also wires of different phases shall not be run in the same conduit. However,
different lighting circuits of same phase shall run in the same conduit. Ev
Every
phase wire shall have a separate neutral wire. Neutral wire shall not be
looped.
3.6 For street lighting, steel tubular poles complete with fixing brackets shall be
used. These poles shall be coated with bituminous preservative paint on the
inside ass well as on the embedded outside surface. Exposed outside surface
shall be painted with one coat of red oxide primer. After completion of
installation, two coats of aluminium paint shall be applied. Contractor shall
supply and erect the poles (including
(including foundation work), mount the assembled
fittings, and install the necessary cabling. The Contractor's scope includes
supply and installation of cables required between lighting panel and junction
box mounted on the street lighting pole and between junction
junction box and metal
enclosed controlgear box. Height and type of pole shall be subject to the
Engineer’s approval.
3.7 Conduits, fixtures, junction boxes etc. shall be bonded to the earthing system
by 16 SWG diameter copper wire looped from lighting panel earth ea bus
onwards. Outdoor lighting poles, junction boxes etc. shall be earthed by 8
SWG GI wire.
4.2 Tap connections (earthing leads) of more than 500 mm long from main
earthing grid to equipment shall be embedded in the floor by the Contractor
together with associated civil work such as chipping / chasing, concreting and
surfacing,
ing, etc. The concrete cover over the conductor shall not be less than 50
mm.
66
DHI Group – Standard Bidding Document for Works
4.6 The work of embedment of earthing conductor in RCC floors / walls along
with provision of earth plate inserts / pads / earth risers shall be done by the
Contractor preferably before the floors / columns / walls are cast. ca The
embedded conductors shall be connected to reinforcing rods wherever
necessary.
4.7 The scope of installation of earthing leads to the equipment and risers on steel
structures / walls shall include laying the conductors, brazing / cleating at
specified
d intervals, brazing to the main earth grids, risers, bolting at equipment
terminals and coating brazed joints by bituminous paint.
4.8 Earthing and lightning protection system conductors along their run on walls /
columns, etc. shall be cleated at an interva
interval of 750 mm.
4.9 Main earthing conductor shall be buried below the trench at crossing points.
4.10 Metallic frames of all electrical equipment shall be earthed by two separate
and distinct leads and then connected with earthing system.
4.13 An earthing mat shall be provided under the operating handle of the
disconnector. Operating handle of the disconnector
disconnector and the supporting
structure shall be bonded together by a flexible connection and connected to
earth grid.
4.14 Metal pipes and cable conduits shall be effectively bonded and earthed by
earthing clamps efficiently fastened to the conduit at both ends.
4.15 Neutral
ral connection shall never be used for equipment earthing.
67
DHI Group – Standard Bidding Document for Works
4.16 A separate earth electrode shall be provided for each lightning arrester and for
each lightning conductor down comer.
4.17 Cable sheaths and screen shall be bonded to the earthing system.
4.18 Armour of multicore cables shall be bonded to earthing system at both ends,
while that of single core cables shall be earthed at source end only. The size
of conductor for bonding shall be appropriate with the system fault current.
4.20 Street light pole and junction box shall be earthed with 12 SWG copper wire
tapped off from the 25 x 3 mm copper earthing conductor to be laid along the
street lighting cable.
4.21 All metallic parts such as transformer, fence, gate, etc. shall be properly
earthed.
4.23 All connections in the main earth conductors buried in earth / concrete shall be
brazed type. Connections between main earthing conductor and earth leads
shall also be of brazed type. Connection between earth leads
leads and equipment
shall be by two bolts.
4.25 The lightning protection air termination rods and / or horizontal air
termination conductors shall be fixed in a fi
firm
rm manner. The necessary
accessories such as cleats, clamps, brazing materials, bolts, nuts, shall be
supplied by Contractor.
4.27 All joints in the down conductors shall be of brazed type. All metallic
structure within 1 metre of down conductors shall be bonded to lightning
protection system.
68
DHI Group – Standard Bidding Document for Works
4.28 Every down conductor shall be provided with a ‘test link’ mounted on wall /
column at about 1000 mm above ground level housed in a 16 SWG GS
enclosure. The test joint shall be directly connected to the earth electrode.
4.29 The lightning protection system shall not be in direct contact with
underground metallic serv service
ice ducts, cables, cable conduits and metal
enclosures of electrical equipment. However, all metal projections, railings,
vents, tanks, etc. above the roof shall be bonded together to form a part of roof
grid.
4.30 Lightning protection system down conductors shall not be connected to other
earthing conductors above ground level. In addition, no intermediate earthing
connection shall be made to lightning arresters and transformer, whose
earthing leads shall be directly connected to electrode pit.
4.32.1 Treated earth pits shall comprise of treatment material such as salt and
charcoal
oal or any other conductivity enhancing compound. Treatment material
placed around the electrode shall be finely graded, free from stones and other
harmful mixtures. Backfill shall be placed in 150 mm thick uniformly spread
and compacted layers. If excavated
excavated soil is found unsuitable for backfilling, the
Contractor shall arrange for a suitable soil from outside.
4.32.5 Treated earth pits shall be treated with suitable treatment material mentioned
above, if average electrical resistivity of soil is more than 20 ohm metre.
69
DHI Group – Standard Bidding Document for Works
5.0 SCOPE
5.1 The Contractor shall carry out commissioning tests/completion checks in the
presence of a engineer appointed by the Employer/Enginee
Employer/Engineer. The
commissioning engineer may verify any commissioning tests/completion
checks to satisfy himself that the plant is fit and sound. The evaluation of test
results and decision passed by the commissioning engineer regarding the test
results will be final
final and binding on the Contractor. Any additional tests or
repetition of tests to establish satisfactory operation of any equipment shall be
carried out by the Contractor if so desired by the commissioning engineer at
no extra cost. The test report needs to to be signed by the engineer appointed by
the employer, which shall be submitted during handing/taking over.
5.2 The commissioning tests/completion checks to be carried out shall include, but
not be limited to, those described in subsequent paragraphs, as applicable to
the individual equipment / system.
In general, the following tests shall be carried out on all the equipment /
systems, as applicable.
70
DHI Group – Standard Bidding Document for Works
6.3 Among other commissioning tests, the following shall be carried out at site
after completion of installation. Contractor shall ensure use of calibrated test
equipment having valid calibration test certificates from standard laboratories
traceable to National Standards / International Standards. All tests shall be
carried out in the presence of Engineer’s representatives.
6.3.1 Transformers
71
DHI Group – Standard Bidding Document for Works
Power frequency high voltage test, insulation resistance test, operation tests.
Open delta test with low voltage, wherever required, measure core loss from
LV side, Voltage ratio measurement with low voltage
6.3.10 Relays
6.3.11 Cables
All cables shall be tested for insulation resistance before and after terminating
/ jointing.
72
DHI Group – Standard Bidding Document for Works
7.1 No item of the entire Works will be certified for 'Taking over' unless it has
passed all the tests.
7.2 A 'Taking Over' Certificate for Works will be issued only after the requisite
requisi
documentation of commissioning tests are duly compiled and approved by the
Employer / Engineer.
73
DHI Group – Standard Bidding Document for Works
1.0 DRAWINGS
1.1 General
1.1.1 Separate drawings shall be prepared and submitted for each equipment.
1.1.3 A blank space of size 100 mm x 100 mm shall preferably be provided for the
Engineer's's approval stamp and provision shall also be made by way of a block
for details of revisions to be recorded. The drawing no. shall be marked with a
subsequent revision no. every time the drawing is revised. The drawing title
shall also identify name of the substation/site.
1.1.4 The equipment and systems, which are to be bought out from the sub
sub-vendors,
are also required to be approved by the Engineer prior to manufacture. The
relevant technical literature and drawings pertaining to such equipment and
systems shall be submitted for approval.
1.1.5 Three copies (One original and two copies) of the drawings shall be submitted.
Contractor shall ensure that the contents on copies of drawings are legible and
are complete with all details. Drawings that are not legible
legible or are incomplete
will not be reviewed.
1.2.1 The Contractor shall submit to the Engineer all equipment data and detailed
drawings. These shall include general arrangement, details of equipment,
74
DHI Group – Standard Bidding Document for Works
1.2.2 Minimum details required on drawings of different categories are given below:
(The activities for each of the items shall essentially cover time-table
time for
activities such as placement of order with sub-vendors,sub vendors, engineering,
submission of drawings, review and approval by the the Engineer, manufacture,
inspection, delivery, erection, testing and commissioning. All events shall be
represented in a proper sequence of occurrence with due consideration for
inter-dependent
dependent activities and all periods shall be counted from the start date).
d
In addition to the above, the Contractor shall also submit adequate copies of
all relevant supporting literature/catalogues.
75
DHI Group – Standard Bidding Document for Works
76
DHI Group – Standard Bidding Document for Works
e) 11 kV indoor switchgear:
j) Lighting system
Lighting layout drawings for indoor and outdoor areas showing layout
of lighting fixtures, conduit/cables, ligh
lighting
ting circuit distribution scheme,
complete bill of material, locations of control switches, receptacles,
etc. and mounting details for fixtures, switches and receptacles as well
77
DHI Group – Standard Bidding Document for Works
l) Miscellaneous systems
systems:
m) A schematic-wiring
schematic diagram and general-arrangement
angement drawing of the
AR offered.
1.5.2 All other drawings shall be submitted progressively thereafter within a period
of 90 days. Sequence of drawings to be submitted within the above period
shall be finalised with the Engineer in advance.
2.1.1 Type test certificates for the following items shall be furnished after the award
of the contract and finalizing the vendor:
a) MV and LV Cables
b) 33 kV and
nd 11 kV switchgear, battery & battery charger.
d) All Transformers, OCTC,
OC etc.
2.1.2 Type test certificates shall be furnished for tests carried out on similar
type/design of equipment.
2.2.1 Routine test certificates for all the plant items and accessories shall be
furnished.
2.2.2 Routine test certificates shall be furnished in addition to test reports, which
will be collected
ected at the time of inspection.
2.2.3 Routine test certificates shall be furnished for review by the Engineer within
seven (7) days after completion of inspection of relevant item or as instructed
by the Engineer in case of items for which witnessing of tests is waived.
3.4 Contractor shall note that the documents mentioned above shall be made
available along with relevant drawings (listed in Clause 1.4.2 above) of plant
items/accessories/componen
items/accessories/componentsts etc. as supporting documents to facilitate
expeditious review of such drawings.
4.1 The Contractor shall provide five (5) bound sets of approved manuals. All
descriptive leaflets, instruction sheets, charts, listlists,
s, pamphlets and other
documents that are used in compiling each manual shall be contained in one or
more binders designed to prevent loss of contents. Each binding shall be titled
with the name of the Employer, the name of the project, the Contract number,
numbe
the name of the Contractor and with information to identify the subject matter
and shall include a detailed index to all the literature contained therein.
4.2 The manuals shall be initially approved in draft form by the Engineer and shall
cover all items
ms of the Works. For this purpose, three (3) draft copies shall be
submitted to the Engineer. Final submission of manuals shall be done after
satisfactory completion of commissioning tests. A mere collection of
manufacturers' descriptive leaflets will not
not be acceptable in satisfaction of this
Clause. Information pertaining to items selected for this project shall be
clearly indicated in such leaflets. The manuals shall comprise both operating
79
DHI Group – Standard Bidding Document for Works
4.3 A separate section of a manual shall be devoted to each size and type of
equipment.. It shall contain a detailed description of its construction and
operation and shall include all relevant pamphlets and a list of parts with
procedure for ordering spares. Operation of electrical equipment shall be
described step by step giving the comp complete
lete sequence of operation. The
detailed sections of the manual, if necessary, shall contain further maintenance
instructions and fault location charts.
4.4 The manuals shall be printed on A4 size sheets and shall be bound. Reduced
copies of record draw
drawings shall also be included in the manuals.
4.5.1 Step by step directions on setting the plant to work, listing all adjustments and
settings necessary for the correct functioning of the plant.
4.5.2 List of plant alarms giving possible causes for alarm initiation and sequence of
remedial actions to be taken.
4.5.3 Instructions on monitoring of plant performance and sample log sheets for
each plant item, to be filled by operators on a routine ba
basis.
4.5.4 "Do's" and "Don'ts" in plant operations. Operators' attention shall be drawn to
all operations considered to be dangerous to operators or likely to cause
damage to the plant.
4.6.1 Checking, testing and replacement procedures to be carried out on all plant
items on a daily, weekly and monthly basis or at longer intervals to ensure
trouble-free
free operation.
4.6.2 Fault locations and remedy charts to facilitate tracing the cause of
o
malfunctions or breakdown and correcting faults.
4.6.3 A 'spares schedule' which shall consist of a complete list of itemised spares for
all plant items with ordering references and part numbers.
80
DHI Group – Standard Bidding Document for Works
4.6.6 Part-list
list and drawings or exploded diagrams for such items of plant showing
manufacturing tolerances, matching clearances between machined components
at the time of supply, maximum wear and clearances permitted to facilitate
replacement.
4.6.7 Complete list of recommended lubricants and lubricating chart, insulating oil
and insulation checking/ replacement chart.
81
DHI Group – Standard Bidding Document for Works
The Contract Organisation shall have a written health and safety policy issued
by the Chief Executive of the Organisation; appropriate to the scale and nature
of the risks involved
ved in the contract works. A copy of the Policy shall be made
available to the Employer at the time of contract in evidence of Contractor’s
commitment to management of employee's health and safety and compliance to
Statutory and regulatory requirements. ThThee Policy along with its Component
operation procedures shall be evidenced as working document publicised
among Contractor's and his Sub-contractors'
Sub contractors' employees through appropriate
language/s. All Contractors’ employees shall be familiar with the Safety Policy
Poli
and their role and obligations in its implementation. The Policy shall meet the
relevant statutory and regulatory requirements and the requirements of the
Employer. The Policy shall periodically be reviewed for updating with respect
to new and emerging legal and other requirements.
The contractor shall also BPC safety instructions which will be given
successful contractor.
a) Contractor shall ensure full involvement of all his employees recognising their
right to consultation on health and safety matters. The safety appointees of the
various areas, in conjunction with the SR shall be responsible for ensuring
employees' involvement through routine safety inspections, hazard and risk
assessment in new and changed works and their control. Contractor shall
maintain appropriate operating procedures to guide these requirements.
c) Contractor shall
hall communicate to the employees regularly on job hazards
applicable to their tasks in hand. Safety Appointees (SA's or any of SR's
nominees) shall hold 'Toolbox talks' for this purpose on a routine basis before
undertaking any safety critical and / or no
non-routine
routine activities. Weekly meetings
of the Contractor and his Subcontractor attended by the SR and SA's shall
include safety as a key item in the agenda to discuss hazards and risk
assessments, Job safety analysis, control procedures and to review accide
accidents
and incidents (Near-miss)
(Near miss) for remedial measures to prevent such occurrence.
The minutes of the meeting shall be submitted to the Employer / Contractor.
SR shall maintain the records.
FREQUENCY=
= NUMBER OF LOST TIME INJURY X 1000000
MANHOURS WORKED
Contractor
ntractor shall arrange to display the safety statistics and the cumulative plot
of severity and frequency of accidents mentioned above painted in a board
prominently displayed, as a means of encouragement and assurance to all
interested parties and for pub
publicising the safety achievements.
"Accident" for the purpose of this clause is defined as "Undesired event giving
health, injury, damage or other loss" and "Incident" is defined
rise to death, ill-health,
as “Event that gavegave rise to an accident or had the potential to lead to an
accident”. An accident where no ill health, injury, damage or other loss occurs
also referred to as "near-miss".
"near Incident includes near miss.
83
DHI Group – Standard Bidding Document for Works
a) personal injury,
b) property damages,
c) Fires,
d) spills and
e) Near misses.
c) The first-aid
aid refresher training shall be provided at least once in a year and all
employees shall be encouraged to undergo first-aid
first aid training. A record shall be
kept of all first aid
aid treatments with particulars of treatment and personnel
providing the treatment.
Employer shall arrange for an ambulance room and an ambulance van directly
or outsource the facilities meeting the governing statutory needs
needs for prompt
transportation of serious cases of accident and or sickness to the Hospital. Such
facilities shall be maintained in good repair and equipped with facilities such as
dry powder type extinguishers, flashlights Portable Oxygen Unit, self- self
containeded breathing apparatus, etc as prescribed by the governing statute.
84
DHI Group – Standard Bidding Document for Works
receive effective
ctive training and periodic refresher training on the operation
control procedures specific to their tasks designed to control the job job-safety
risks. A booklet of such operation control procedures and safety rules with
need based pictorial illustrations shall
shall be made available to all employees who
are to learn and be familiar with such procedures. All training shall be
monitored for effectiveness as per established procedures. Contractor shall
maintain records of all training.
Safety posters, banners and slogans displayed for safety promotion shall be
rotated at frequent intervals. The Contractor is encouraged to have safety
promotion as an item in the safety committee agenda. Contractor
Contractor is encouraged
to include safety promotion programmes such as safety bulletins, magazines,
competitions in slogan and poetry writing on safety, screening of safety films,
celebration of national safety and environmental day, safety suggestion
schemes and safety library, etc.
85
DHI Group – Standard Bidding Document for Works
a) Contractor shall ensure that his key personnel and safety personnel are trained
to be competent in hazard identification, risk assessment and risk control
processes. Contractor shall on a routine basis identify, evaluate and control all
health and safety risks especially in the hazardous work activities and also to
validate the previous risk assessments. Elements such as hazard identification,
evaluation of risks with existing control measures in place and estimate of
tolerability of the residual risks shall be an ongoing process. Any additional /
new control measures shall be designed based on this process on need basis.
86
DHI Group – Standard Bidding Document for Works
Should the existing operation control procedures prove inadequate and the
residual risks are higher than tolerable levels, SR shall
shall initiate hazard and risk
assessment / analysis and consultations with Safety Committee to deploy
appropriate remedial measures and improved operation control procedures.
Periodic inspection reports and proposed remedial measures shall be submitted
to the
he Employer. Records of changes in processes; consultations with Safety
Committee and revision of Operational controls shall all constitute objective
evidence of the existence of established procedures.
87
DHI Group – Standard Bidding Document for Works
2.1 Mechanical
echanical Safety
b) Contractor shall provide only good quality handtools and ensure control of
condition, storage, routine inspection and use of such hand-tools.
hand tools. Unsafe tools
such as with cracked or broken handles, mushroomed chisels and punches,
worn screwdrivers, hardened hammerheads; power tools withwith unsafe resistance
to earth or without safety guards shall be prohibited.
c) All safety ladders, scaffolding and access equipment shall meet requirements of
IS 3696 and IS 4014:1967 and any such standards that the Employer / Engineer
may stipulate. The safety
safety work permits shall be issued only after ensuring that
all safety requirements of access equipment are complied with. Access
equipment shall be inspected on a routine basis to prevent injuries caused by
falls.
88
DHI Group – Standard Bidding Document for Works
a) Contractor shall provide only such equipment for work that is electrically safe
to work. Contractor shall have a procedure to identify and recordrec all his
electrical equipment in a register, with provisions to record his periodic
inspections of such equipment. Inspection shall cover cables, extension leads,
all electrical equipment drawing power from socket outlet. He shall identify
and maintain in good working order all electrical installations such as
distribution panels and major switchgear ensuring safe accessibility. A clear
area shall be maintained around Panels and switchgear. The installed
equipment shall be periodically inspected by qualified
qualified personnel to ensure their
continued safe operating condition. Inspection shall include earth polarity
checks, continuity checks and earth resistance checks. Contractor shall ensure
use of flameproof and explosion proof switchgear and lighting fittings where
required as per governing codes.
d) Contractor shall arrange displaying signages under Indian Electricity Act 1910,
such as :
f) Contractor shall ensure lighting circuits are not used for hand
hand-tools. No
electrical equipment shall be overloaded. Tools and test equipment used on
electrical systems shall be insulated.
a) Contractor shall prevent all injuries, illnesses and damage to property or the
environment caused by any article or substance, which proves to be hazardous.
hazardou
The code of practices of construction, operation, maintenance and control
procedures shall meet required statutory and regulatory requirements.
Personnel shall be trained on use, handling, storage and disposal of emergency
spillage procedures.
b) Contractor
or shall detail and deploy Operational controls to reduce hazardous
wastes and their disposal as required by the statute “ Hazardous Waste
(Management and handling) Rules 2000”. Oil wastes, used oils, soil and cotton
soaked in oil consequent to handling operations,
operations, grease, many class of paints,
asbestos sheets and gaskets are typical hazardous wastes.
Contractor shall provide his employees required PPE meeting the requirements
of the statedd IS Specifications and Guidelines or equivalent International
Standards as may be prescribed by the Engineer from time to time. Contractor
shall have instituted good working procedures and practices in providing PPE,
maintenance, issue and training on the
their
ir use. All PPE shall be periodically
checked to ensure worn so that damaged equipment are replaced expeditiously.
90
DHI Group – Standard Bidding Document for Works
Employees shall be responsible for PPE issued to them. Contractor shall meet
requirements
ents of IS 8519: 1977 titled “Guide for selection of Industrial safety
equipment for body protection” or any equivalent International Specification
that the Employer / Engineer may prescribe.
b) Head Protection:
Eye protection shall be worn during all operations by operators and people in
the vicinity, where there is a danger
danger of flying particles of metal such as
generated during use of hand tools such as chisels, grinding, welding and
cutting lathe work on brass and cast iron acid and alkali splash, and high
pressure jet cleaning or insulation removal from heights using high pressure
jets. Contractor shall meet the requirements of IS 8540:1978 titled ”Guide for
selection of Industrial safety equipment for eye and face protection".
d) Footwear:
Safety shoes boots and gumboots fitted with steel toecaps of approved quality
conforming
ing to prescribed Indian or International standards shall be used.
Wearing of unsafe safety shoes such as jogging shoes, tennis shoes, slippers
and sandal etc. shall be prohibited. Contractor shall meet the requirements of IS
10667:1983 titled ”Guide for sselection
election of Industrial safety equipment for
protection of foot and leg".
e) Protective clothing
clothing:
f) Hand Protection:
91
DHI Group – Standard Bidding Document for Works
i) Hearing conservation
conservation:
Contractorr shall ensure reasonable precautions are taken to avoid injury to the
hearing of the employee. All noise levels shall be controlled within 85 dBA.
Contractor shall identify noise areas where noise levels exceed prescribed safe
level for arranging for appropriate
appropriate Engineering revision. Where this is not
feasible, appropriate Earmuffs or protectors shall be provided to workmen
ensuring those wear them exposed to noise levels beyond safe levels. Periodic
hearing acuity tests shall be conducted on such persons exposed to high noise
levels to ensure that they do not suffer any hearing impairment` as per
requirements of IS 8520: 1977
92
DHI Group – Standard Bidding Document for Works
d) The location of fire fighting equipment shall quickly and easily be identifiable
identifi
especially in emergencies in a conspicuous manner painted as high as possible
to identify the location of the extinguisher to prevent it from being obscured by
machinery and goods stacked in front and to return the equipment to its
location after emergency
emergency use in other locations. In order to ensure this, "Keep
Clear" area shall be demarcated and maintained. Location plans of
extinguishers and fire
fire-fighting
fighting equipment shall be prominently displayed when
desired by the Employer.
g) A clear written procedure for action in the event of fire should be produced.
Fire teams and Hose teams shall be identified and their responsibilities during
emergencies shall be detailed in writing. Personnel shall be trained on their fire
duties and use of fire-fighting
fire fighting equipment. Regular drills shall be conducted to
test procedures and to validate them.them. Fire instructions and emergency
procedures shall be displayed throughout the premises. Emergency response
procedures are detailed below under Clause 5.0.
93
DHI Group – Standard Bidding Document for Works
h) A means of escape shall be provided in all work areas and storages and
maintained and kept free from obstruction. All exits shall be clearly marked
and kept unlocked whilst the premises are in use. Escape routes shall be
protected from fire.
4.2 Security :
b) Where
ere the project is located where a number of other companies are in
operation, Contractor shall plan for mutual assistance programmes in cases of
emergencies, as are practiced in the area in conjunction with Employer.
a) Contractor shall plan to deal with emergencies (ER) specific to the job site. ER
shall be written and communicated to all employees. ER shall identify for the
potential and responses to incidents and emergency situations and for
preventing and mitigating the likely illness and injury that may be associated
with them.
b) The Contractor shall review his emergency preparedness and response plans
and procedures in particular after occurrence of incidents or emergency
operations.
c) Contractor shall designate his emergency team with their duties during
emergencies defined, including those of the hose teams, medical personnel,
first-aiders
aiders and security. Contractor shall maintain a proce
procedure
dure as to how his
emergency organisation shall liaise with Employer's representatives in ER.
e) The emergency Response Plan of the Contractor shall be under the control of
the SR who shall be able to coco-ordinate
ordinate with Employer for liasing with
Government agencies, neighbouring industries and com
community
94
DHI Group – Standard Bidding Document for Works
f) The plans shall be designed to allow people to work under disaster conditions
when normal services such as telephone, water, light, power, transport and
sanitation are not available and first aid and fire fighting facilities are not able
to cope with
ith sudden demand on services.
95
DHI Group – Standard Bidding Document for Works
a) Contractor shall ensure stacked material is bonded on a stable and level footing
capable of carrying
arrying the mass of the stack. Adequate clearances shall be
provided between the sides of the stack and top to facilitate unimpeded access
to service equipment like overhead wiring, cranes, forklifts, fire fighting
equipment and hoses. Circular items shall be sufficiently choked with wedges
and not with odd bits of materials. Freestanding stacks of gunny bags and sacks
such as cement bags shall be stacked to prescribed safe-stack
safe stack heights with
layers formed for stable bonding, preventing slippage causing accidents.
acc
Stacking against walls shall not be permissible.
b) Contractor shall maintain the premises and surrounding areas in clean and clear
manner with safe access and egress. There shall be sufficient and adequate
storage racks, shelving, bins, pallets and material handling equipment to stack
his construction materials such as pipes, structures and his construction
enabling materials. Unwanted materials shall be promptly moved away for
efficient material movement.
a) Hazardous materials shall be stored on solid bases. Solid bases shall include
compacted earth, pallets, concrete or asphalt platforms or paving. Hazardous
materials shall be stored, stacked and secured to prevent toppling, spillage or
other unintended dislodgement. Aisles and clearances shall be as detailed under
6.6 above. Hazardous materials shall be stacked in such a manner that an
observer standing in the aisle can read their labels and legends
c) Hazardous materials which if brought in contact with each other could react or
pose equal or greater hazard than either material stored
stored alone shall be stored at
a distance not lesser than twenty feet apart.
96
DHI Group – Standard Bidding Document for Works
Employer. The Containers and storages shall display quantities stored with
name of the hazardous material and the UN Hazard classification label in
prescribed colour code prominently painted in a conspicuous manner.
b) Storage facilities for flammable liquids such as Petrol, Diesel, Kerosene and
Lubricants as well as the quantities stored shall meet the legal and statutory
requirements. They shall be stored in approved fire-resistant
resistant rooms with a
sump of sufficient volume to contain any spillage.
Compressed gas cylinders shall be stored and secured in the upright position at
safe distances shielded from welding and cutting operations. Compressed gas
cylinders in storage shall be shut off and torches,
torches, hose and manifolds removed
and capped. Cylinders shall be periodically checked for leakages. Storage shall
meet requirements of Gas Cylinder Rules 1981. Compressed gas storages shall
be provided with safety relief valves, safety valves and rupture disc to protect
them from overpressures and shall be appropriately designed to ensure their
continued availability in the face of process changes.
Contractor shall ensure that he has sufficient waste bins that are identified
ide for
different wastes and maintained in clearly demarcated areas. Wastes with oily
or other ignitable materials such as Oily cotton wastes and Hand gloves shall
be stored separately with covers to prevent fires and shall be made of metal.
Different Wastes shall be segregated and stored separately and disposed off.
They shall be emptied at routine intervals to prevent that they do not overflow
with wastes.
97
DHI Group – Standard Bidding Document for Works
98
DHI Group – Standard Bidding Document for Works
5.0 Relays
7.0 HV Cables
99
DHI Group – Standard Bidding Document for Works
11.0 Substation
ubstation Hardware Fittings
13 Ventilation Fan
100
DHI Group – Standard Bidding Document for Works
15.0 Battery
18.1. Vitreous China Sanitary Ware: Payrryware, Hindustan Saitary Ware, Neycer,
Cera
18.2. White Glazed Fire Caly Sink: Sanfire Cera, Neycer
18.3. Stainless Steel Sink: AMC, Orient, Sunag
18.4. Plastic Seat Cover of WC: Commander, Bestolite, Diplomat
18.5. Geyser: Venus Spash, Usha Lexus
18.6. CP fittings mixers, Piller taps Washer: Gem, Parko Kingston
101
DHI Group – Standard Bidding Document for Works
18.7 Sand Cast Iron Pipes & fittings: RIF, NECO, BIC
18.8 GI Pipes & MS Pipe: GST,
G Jindal, Kalinga, Tata, Bansal, Imperial
18.9. GI fittings: Kohhi, VI, Umk, MAC
18.10 Gunmetal Valves:Zoloto Leaser, Sant, Kohhi.
18.11. Brass stop & Bib cocks: Zalato, Sant, L&K
18. 12 Ball valve with float: Zaloto Leader, Sant
18.13 Stoneware pipes & Gully traps: Perfect, Burn Hind
18.14 RCC Pipes: IS marked pipes
18.15 CI Manhole Cover: RIF, NECO, BIC
18.76 Water Tank: Sintax, Polycon, Uniplas
18.17 Mirror Golden fish, Atul Jolly, Modi
18.18 Teak Ply/Commercial: National, Kitply, Novapan, Bhutan
18.19 Mosaic Tiles: Nitco
18.20 Locks: Godrej, Harison, Acme-4C(25mm)
Acme
18.21 Flooring & Wall Tiles: Somany, Argil, Kajaria
22 Air Conditioners:
ioners: Blue Star, Electrolux, Carrier, Hitachi
23 Note: All the material supplied in this contract shall be Class A materials and
shall be delivered to the site after the proper testing/approval of the samples
in case of civil works materials.
102
DHI Group – Standard Bidding Document for Works
Section
tion VI - H – Bid Purpose Drawings
103
LEGEND
SYMBOLS
FIG. INDICATES NO. OF CTs/VTs
VOLTAGE TRANSFORMER
R-RELAYING
CURRENT TRANSFORMER I-INSTRUMENTATION
CIRCUIT BREAKER
INSOLATOR
LIGHTNING ARRESTER
HT HRC FUSE
SOURCE (GENERATOR)
BUS PT
BUS PT
3
HT Fuses
3 VCB VCB VCB HT Fuses
VCB
3
Bus Voltage Transformer 3 Bus Voltage Transformer
M.F. METER M.F. METER M.F. METER M.F. METER V, 30VA
V, 30VA
1 A,KW,KVA,PF,KWH 1 A,KW,KVA,PF,KWH 1 A,KW,KVA,PF,KWH 1 A,KW,KVA,PF,KWH
Metering 3 3 3
3 3 3 3
MFM 1 3 1 V W VAR PF kWh F
R 50/51 R 50/51 R 50/51 R 50/51
Protection 3 3 3 3
Out-going -09
Out-going -01 Out-going -02
Out-going -03 (Sunday Market Feeder)
(RBP - I) (Trade Industry)
(SAARC Feeder) CTR - 300-150/1-1A
CTR - 300-150/1-1A CTR - 300-150/1-1A
CTR - 300-150/1-1A
Note:
THIS SCHEMATIC IS NOT MEANT TO BE A DETAILED
SPECIFICATION OF THE SUBSTATION. IT IS FOR
ILLUSTRATION PURPOSE ONLY.
Electricity Services Division Bhutan Power Corporation Limited Distribution Construction Department
THIMPHU
LEGEND
SYMBOLS
FIG. INDICATES NO. OF CTs/VTs
VOLTAGE TRANSFORMER
R-RELAYING
CURRENT TRANSFORMER I-INSTRUMENTATION
INSOLATOR
LIGHTNING ARRESTER
33kV Incomer - 1 33kV Incomer - 2 FUSE (THICK LINE INDICATES SUPPLY SIDE)
3
R 50/51 R 50/51 INSTRUMENTATION
Protection Protection A AMMETER
3 3 V VOLT METER
M.F. METER M.F. METER W WATT METER
VAR VAR METER
1 A,KW,KVA,PF,KWH 1 A,KW,KVA,PF,KWH
Metering 3 Metering 3 VS VOLT METER SELESTOR SWITCH
F FREQUENCY METER
PF POWER FACTOR METER
33KV BUS -I 33KV BUS -II kWh ENERGY METER
MFM MULTI FUNCTION METER
BUS PT
BUS PT
3 3 HT Fuses
HT Fuses
33kV VCB 33kV VCB
Bus Voltage Transformer 3 3 Bus Voltage Transformer
3 3
R 87, 50, 51 ... R 87, 50, 51 ...
V, 30VA Protection V, 30VA
33 kV Transformer Protection
3 3
3 Feeder 3
MFM 1 1 A W kWh 1 A W kWh 1 V W VAR PF kWh F
Metering 3 (CTR - 300-150/1-1-1A Metering 3
PS
R 86/87 R 86/87
3 PS
3
TRANSFORMER TRANSFORMER
2.5 MVA 5 MVA
33/11KV 33/11KV Note:
1 1 THIS SCHEMATIC IS NOT MEANT TO BE A DETAILED
51N SPECIFICATION OF THE SUBSTATION. IT IS FOR
51N ILLUSTRATION PURPOSE ONLY.
Electricity Services Division Bhutan Power Corporation Limited Distribution Construction Department
THIMPHU