Audit Action Plan

CAP ON THE NOTICE UNDER SECTION 24 FOR THE VIOLATION OF SECTION 14 OF BALOCHISTAN ENVIROMANTAL ACT, 2012
Serial Recommendation or Continual Company Action Plan
number Improvement Area (Corrective Action)
1. The underground drain Lines were found to As this is an operational chemical plant, the ongoing processing reveals sediments
be highly contaminated. rather than contaminants, which are subsequently removed at the conclusion of
the process.
2. Leakages of chemically treated water from To stop the leakages, we will retitled the flange joints.
boiler systems and different pipe nozzles
were observed during this visit.
3. Presence of Polluted soil on the site due to The soil should not be classified as contaminated. However, there were previous
fuel spill and leakage. fuel leaks that were subsequently addressed and cleaned up, but some traces still
exist which are unable to be removed by normal cleaning hence it will further be
removed through floor scraping.
4. Chemical substances and hazardous solutes The chemical substance observed was a red-oxide primer, which had previously
detected across the soil surface. been applied to the pipes. It will now undergo a recoating process using synthetic
enamel.
5. Unavailability off PPEs(mainly gloves) in the Basic Personal protective equipment (PPE) were found to be available additionally
boilers section. rubber gloves, has been provided to the workers in the boiler section for chemical
handling.
6. Submission of Environmental monthly The environmental monthly reports, which include boiler emission testing reports,
monitoring report along with wastewater test reports, and drinking water test reports, were presented during
 Details of Gaseous emissions this audit visit. Additionally, the EPA receiving letter and the NOC were also shown
produced. to them.
 Details of noise pollution created The details of waste disposal as per our SOP includes.
 Details of waste material  We record the information and the quantity of final waste disposition on
discharged. the waste Disposal.
 Details of disposal mechanism of  The waste material is stored in storage containers and bags and then
waste shifted to the designated location before the waste is dispatched outside
the facility after its been classified as hazardous and nonhazardous .
7. Below are the attachments that was
verified by Bahria University.
1. Boiler Stack Gaseous Emission
Monitoring report
Boiler Stack
Geseous Emmission monitoring.pdf

2. Generator Stack Gaseous Emissions


Monitoring Report
Generator Stack
Gaaseous Emission Monitoring Report.pdf

3. Forkliftor Exhaust Emission


Monitoring Report
Forkliftor Exhaust
Emission Monitoring Report.pdf

4. Clarifier Tank (ETP Treated Effluent)


Sample
Clarifier Tank(ETP Remaining
treated Effluent) sample.pdf parameters of Clarifier Tank.pdf

5. Drinking water (Canteen Sample)


Report
Drinking Water(
Canteen sample )report.pdf

6. Monthly Waste Disposal report


(August waste Disposal data)
waste disposal
statement of August 2023.pdf