ISB ITPM Assignment 7.2 Keithdsouza

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

1.

Network diagram:

3 C 9
9 D 17
0 A 3 0 0
0 0 17 E 26
0 0 3 6 9
9 8 17 0 0
0 3 3
17 9 26

3 B 10 26 F 31

16 16 0 0 17 G 23

19 7 26 26 5 31 8 8

25 6 31

26 H 31

1 0
31 J 37
10 I 12
27 4 31
0 0
19 19
31 6 37
29 2 31

37 K 40

0 0

37 3 40

Legend
ES ID EF

Slack Slack

LS Duration LF
2. Critical Path

Task A Task C Task D Task E

Task K Task J Task F

3. Calculation for (Te) and Variance of all the tasks:

Weighted (Te) of
Best Most Worst Activity the Variance of
Case Likely case Critical Estimate critical the critical
ID Tasks (To) (Tm) (Tp) Activity (Te) Activities Variance activities
A Requirements 2 3 4 Yes 3 3 0 0
B Market assessment 4 7 10 No 7 1
C Design 5 6 9 Yes 6 6 0 0
D Development 6 7 16 Yes 8 8 3 3
E Testing 7 9 10 Yes 9 9 0 0
F Revising 4 5 6 Yes 5 5 0 0
G Documentation 3 6 10 No 6 1
H Quality Assurance 2 4 7 No 4 1
I Pricing 2 2 2 No 2 0
J Production 3 4 14 Yes 6 6 4 4
K Distribution 2 3 4 Yes 3 3 0 0
Total:7

std
TE=40 deviation=2.64

The estimated completion time is 40 weeks.


4. The probability that the project could be completed within the deadline of 35 weeks:

Ts= 35 weeks

Te=40 weeks

Std deviation= 2.6

Area under curve= z= 35-40/2.6 = -1.92

Probability = NORMSDIST(Z)= 0.02743