WRD 16 (15951) - P Draft - 13-07-2020
WRD 16 (15951) - P Draft - 13-07-2020
WRD 16 (15951) - P Draft - 13-07-2020
WRD 16(15951)P
July 2020
FOREWORD
(Formal clauses will be added later)
Surveillance of dams during their construction, reservoir filling, and operation is an essential
activity in a dam safety program. The level of surveillance should be appropriate to the
individual dam considering its type, foundation, design, construction, operational context,
consequences of failure, inherent condition, historical performance, characteristic behaviour
and potential failure modes. Surveillance plays a critical role in ensuring safety of existing
dams, whose failure can result in unacceptable loss of life and economic losses.
A robust surveillance process is the Owner’s ‘front line of defense’ for the safe operation of
their dams and reservoirs. Surveillance provides the cornerstone for effective management of
dam safety and operational risks and includes visual inspections, instrument monitoring
(including deformation surveys), data review and evaluation, and reporting on the safety of
the dam.
For the preparation of this standard, references have been drawn from ICOLD Bulletins, and
United States Army Corps of Engineers (USACE ) documents.
BUREAU OF INDIAN STANDARDS
Draft Indian Standard
1. SCOPE
The standard covers the general guidelines on surveillance and performance monitoring
of hydraulic structures.
2. TYPES OF INSPECTIONS
Four different types of dam safety inspections are carried out for all dams:
1. Informal inspections
2. Scheduled inspections (Pre & Post monsoon inspections & other scheduled inspections)
3. Special (unscheduled) inspections
4. Comprehensive evaluation inspections
Normally the dam owners, operators, maintenance crews, or other staff who are posted at
dam site will make informal inspections. These people are the “first line of defense” in
assuring safe dam conditions, and it is their responsibility to be familiar with all aspects of
the dam. Their vigilance in inspection/surveillance of the dam, checking the operating
equipment, and noting changes in conditions may prevent serious mishaps or even dam
failures.
Informal inspections are important and should be performed at every available opportunity.
These inspections may only cover one or two dam components as the occasion presents itself,
or they may cover the entire dam and its appurtenant structures. The informal inspections are
not as detailed as comprehensive evaluation, scheduled, and special inspections and will only
require that a formal report is submitted to the dam owner’s project files if a condition is
detected that might endanger the dam.
However, intensive inspection is required when there is a confirmed dam safety deficiency or
a developing dam safety threat. It is often round the clock, with experienced personal.
These inspections are performed to gather information on the current condition of the dam
and its appurtenant works. This information is then used to establish needed repairs and
repair schedules, and to assess the safety and operational adequacy of the dam. Scheduled
inspections are also performed to evaluate previous repairs.
The purpose of scheduled inspections is to keep the dam and its appurtenant structures in
good operating condition and to maintain a safe structure. As such, these inspections and
timely maintenance will minimize the long-term costs and will extend the life of the dam.
Scheduled inspections are performed more frequently than comprehensive evaluation
inspections to detect at an early stage any developments that may be detrimental to the dam.
These inspections involve assessing operational capability as well as structural stability and
detection of any problems and to correct them before the conditions worsen. The field
examinations should be made by the personnel assigned responsibility for monitoring the
safety of the dam. If the dam or appurtenant works have instrumentation, the individual
responsible for monitoring should analyze measurements as they are received and include an
evaluation of that data. Dam Inspection Report or an inspection brief should be prepared
following the field visit (Dam Inspection Report is recommended).
2.1.2.1 Scheduled inspections should include the following four components as a minimum:
a) Review of past inspection reports, monitoring data, photographs, maintenance records,
or other pertinent data as may be required;
b) Visual inspection of the dam and its appurtenant works;
c) Preparation of a report or inspection brief, with relevant documentation and
photographs.
d) Education and training if someone other than the owner is performing the inspection.
a) Visual inspection by competent and trained personnel is the most effective means of
dam surveillance. Visual observations of leakage/ seepage, deformations, cracking in
dam, slope failure, collapse of any component, functioning of gates and electrical
devices, hill slopes (upstream and downstream of the dam), roads etc.
b) It is very important that the developed checklist of each dam should not be so
prescriptive that the inspector is not encouraged to look at other areas and features
that may have a bearing on dam safety and this principle should be emphasized in the
inspector’s training. Photographs of general and specific features, from repeatable
locations provide an effective long term record of inspection observations.
Video recording of features or unusual events can also be particularly valuable.
c) Confirming any subsequent action to be taken.
2.1.3.4 Further the following activities are also recommended to minimize the adverse
impacts of an earthquake
a) Regular field drills at dam site to make the site officials aware of their roles and
responsibilities during and after an earthquake event and thereby to upgrade the
earthquake response system
b) Securing communication lines by having a redundancy in the system by way of
availability of different types of telecommunication systems (viz. mobile phone,
wireless, satellites, telephone etc.) at dam site.
c) Securing adequate fuel for at least 3 days (viz. petrol, diesel) for the emergency power
generators and other essential supplies like food, water, fire wood etc.
d) Installation of seismometers in a dam and development of a data sharing system.
2.1.4.1 General
For comprehensive dam safety evaluation for each dam an independent panel of experts
known as Dam Safety Review Panel (DSRP) needs to be constituted for determining the
condition of the dam and appurtenant works. The panel would undertake evaluation of each
dam once in 10 years or on occurrence of any extreme hydrological or seismic event or any
unusual condition of the dam or in the reservoir rim. The terms of reference of the
comprehensive dam safety evaluation shall include but not be limited to;
a) General assessment of hydrologic and hydraulic conditions, review of design flood,
flood routing for revised design flood and mitigation measures.
b) Review and analysis of available data of dam design including seismic safety,
construction, operation maintenance and performance of dam structure and
appurtenant works.
c) Evaluation of procedures for operation, maintenance and inspection of dam and to
suggest improvements / modifications.
d) Evaluation of any possible hazardous threat to the dam structure such as dam
abutment slope stability failure or slope failures along the reservoir periphery.
e) The surveillance process can be thought of as a ‘quality chain’ – a multi-linked chain
where each step in the process form sacritical link remarks.
The quality chain starts with the personnel undertaking surveillance activities in the
field, continues with regular review of the information by appropriate technical specialists,
and is completed with feedback to the field personnel (relative to the nature of continued
surveillance) and reporting to the owner on the safety of the dam and the need for specific
responses or required actions.
a) Dam
i. Upstream face
ii. Downstream face
iii. Top of dam
iv. Structural behavior as observed visually and as per evaluation of instrumentation
data (any visible cracking, deflections etc.)
v. Seepage assessment
vi. Condition of natural/excavated slopes in the abutments, both on u/s and d/s of the
dam.
vii. Any specific problems/ deficiencies
(b) Spillway
i. Civil structure
ii. Energy Dissipation Arrangements (EDA)
iii. Spill channel, drop structures etc. if any.
iv. Condition of EDA and its performance
v. Spillway Gates & Hoists
vi. Downstream safe carrying capacity of river / channel.
(c) River / Canal Outlets
i. Civil structures
ii. Outlet Gates, Hoists & Controls
iii. Conduits / Outlets through Embankment dams and sluices through Masonry /
Concrete dams (Condition, problems etc.)
iv. Trash racks, if any
v. Separate energy dissipation arrangements, if any.
(d) Review of Sedimentation of the Reservoir.
Assessment of sedimentation and its effect on flood routing, operation/ life of reservoir.
(e) Flood Hydrology
i. Extent & sufficiency of data available
ii. Method used for estimating the design flood.
iii. Design flood review study.
iv. Flood routing studies with the revised flood
v. Adequacy of free board available
(f) Miscellaneous services /facilities
i. Access Roads / Bridges / Culverts
ii. Elevators
iii. Stand by power arrangements
iv. Flood forecasting arrangements, if any
v. Communication facilities (Telephone, Satellite, Wireless, Mobile etc.)
(g) Hydraulic Model studies, if any new studies carried out.
(h) Earlier reports of experts / DSRP etc., if any, as annexures.
(i) Photographs of dam project showing problem areas.
3.1 Various options and layouts are considered while planning instrumentation in dams and
for monitoring their performance. Where possible, when determining what instruments are
required to monitor the performance of a dam throughout its operational lifetime, Owners and
Technical Advisers should adopt a ‘simple and targeted’ instrumentation philosophy. All dam
instrumentation should have a clear purpose that is linked to one or all of the following
objectives:
a) Improving the understanding of a dam or foundation’s characteristic behavior during
normal operation, and during unusual and extreme events.
b) Providing early indication of the onset of potential failure modes for a dam.
3.2 Instrumentation can assist with the identification of the trends or conditions that are
indicative of a potential failure mode that was not identified during earlier studies. For
example, uplift measurements in gravity dams can give an idea whether the uplift pressure
are more or less than the design values. It can also provide an idea regarding the condition of
foundation drainage holes viz. whether in working condition or choked. If choked then
cleaning / re-drilling of holes will be necessary from dam stability considerations.
3.3 Dam performance monitoring instruments should be robust, durable, require little
maintenance and able to be read easily and consistently, often by non-specialist personnel.
That is, it should measure as directly as possible a parameter, condition or quantity that
supports the aforementioned dam performance monitoring objectives. The operational
lifetime of a dam is typically tens of decades, and the surveillance instrumentation should be
selected so that either it has a similar lifespan, or that components with a shorter life can be
safely maintained and/or replaced. The instrumentation data should be graphed and reviewed
in a timely manner by a qualified engineer. Threshold and Action Levels should be
established on the graphs and the appropriate responses to be taken when these levels are
exceeded. Also, the instrumentation should be linked to a Potential Failure Mode.
3.4 The overall dam instrument layout / array should be resilient and should provide for
redundancy as appropriate. Redundancy is specifically important for dams where piezometric
(or uplift) information is measured using vibrating wire instruments, or where it is gathered
and reported using telemetry or other means of electronic transmittal that can be affected by
lightning strikes or power loss. In such cases backup manual measurements of embankment
piezometers or uplift pressures in concrete dams at key locations should be provided.
3.7 The need for and value of dam performance monitoring instrumentation will depend on
the requirements for the particular dam. Most instrumentation is selected during dam design
and installed during construction, and may have a primary purpose related to the monitoring
of construction-related parameters rather than those parameters required for the long- term
management of dam safety. Hence, it may be appropriate to consider additional instruments
to ensure dam performance monitoring needs are met or, where instruments are found to be
redundant, it may be appropriate to decommission instruments. Additional or different
instrumentation may also be installed when a potential dam safety deficiency is being
investigated and assessed.
3.8 Technological advances in instrumentation types and systems will occur over the life of
any dam. It is therefore likely that the original instrumentation will be augmented or replaced
by new systems over time. Where possible, a period of monitoring overlap should occur to
ensure that historical data can be correlated to information obtained from new systems.
The ability to measure rate of seepage and leakage through the embankment dam, its
foundation or abutment usually relies on directing the seepage or leakage, through
appropriate collection and drainage facilities, to a measurement point close to the dam’s toe
or at the location where the seepage or leakage emerges from the dam, foundation or
abutment.
Seepage and leakage flow is best measured volumetrically, either by measuring the time to
fill a container of known volume, or by installing a weir or flume with a theoretical (or
calibrated) rating that allows the measured head to be converted to flow rate. For the purpose
of ongoing monitoring and evaluation of a embankment dam’s performance the most
important aspect of seepage and leakage rate measurement is repeatability, rather than
absolute precision. Weirs should be sized for the anticipated flows and weir boxes should be
large enough to provide calm water surfaces behind the weir plates. In some cases baffles
may be needed to achieve this. V-notch weirs provide precision for the measurement of
seepage flows; however, for large flows, broad crested weirs or flumes will be necessary.
The observation of seepage and leakage flows via the use of weir also allows the detection of
any materials being transported by the seepage flows. The detection of turbid seepage or soil
particles in seepage flows is important as they may be an indicator that internal erosion
(backward erosion or piping or washing of the fines) is taking place within the dam, in its
abutments or in the foundation. In order to detect whether or not soil particles in a weir are
the results of internal erosion, the weir may have to be covered to protect it from windborne
material and periodically cleaned to enable the captured material to be examined and
weighed.
Also uplift pressure at or near the toe of embankment dams may also be relevant if a blowout
condition or potential piping condition exists.
Uplift pressures are also most relevant to concrete/masonry dams and their foundations, and
allow their stability to be evaluated.
Foundation drainage holes in concrete dams can be used for installing piezometers, either by
measuring the depth to the water level (if the water level is below the top of the drain) or by
installing a pressure gauge over the steel pipe at the top of foundation drainage holes (if water
is flowing from the drain). An appropriately experienced Technical Adviser or Technical
Specialist should be consulted in such cases. For correct evaluations of dam performance it is
important that the locations of piezometers in the body of a dam or foundation are accurately
known (position and level), that the instruments are correctly identified, that their precision
and accuracy are regularly assessed, and that they are appropriately maintained.
There are a vast range of other instruments and systems also available which are used for the
monitoring of dam performance and the monitoring of hazards. Some common examples
include, but are not limited to:
a) The use of cement plaster across cracks in concrete dams on the crest or within galleries to
monitor relative movements. Two or three dimensional crack monitoring devices can also be
attached to the dam for greater accuracy. An easy crack monitor is to have inspectors at the
site mark the end of a crack with a perpendicular line and date. This provides a visual log of
the crack progression with time.
b) Dye tests for determining seepage and leakage origins/paths.
c) Turbidity meters (indicators of internal erosion).
d) Video cameras for real-time visual observations, including the internal inspection of conduits
(drains and outlet tunnels) both above and under water.
e) Thermometers for recording temperature and temperature gradients in concrete dams (for
thermal studies).
f) Trip wire systems (e.g. displacement/rupture of an active fault, or a dam itself).
g) Post-tensioned cable anchor load testing (to confirm anchor tensions).
h) Temperature sensing systems for the identification of seepage in dams or foundations (e.g.
distributed temperature sensing and resistance temperature devices). Temperature sensors can
provide valuable data on the flow time and flow source of seepage water, particularly when
complemented by other measured parameters such as piezometric pressure, seepage flow
rate, and the temperature of the reservoir and other potential sources (such as ambient
groundwater or tail water).
i) Early warning upstream rainfall collection and catchment modelling systems for predicting
the size of incoming floods or extreme weather conditions (an important aspect for
surveillance and emergency preparedness).
j) Rainfall measurement to assist with the interpretation of seepage observations, and the
evaluation or correlation of landslide and abutment slope movements.
k) A seismic monitoring network for detecting and notifying the location and strength of
earthquakes (an important aspect for emergency response). The India Meteorological
Department (IMD) Seismic network is available
i. Strong motion seismic sensors for the measurement of ground motions. These may be helpful
where the IMD network coverage is limited and/or where measurement of ground motions at
the dam site is required. The locations for installation of strong motion recorders should be
based on the site conditions and preferred locations. In order of usefulness the preferred
location are the base of the dam to record the peak ground acceleration, the abutments to
record topographic amplification of the peak ground acceleration and the dam crest to record
the amplification of the peak ground acceleration.
Instruments and systems as indicated above may be built into or near a dam at the time of its
construction or added during the life of a dam to supplement or enhance existing
instrumented monitoring, to address a specific potential failure mode, or to investigate a
potential or confirmed dam safety deficiency.
5 VARIOUS PARAMETERS MEASURED AND THE SUGGESTED FREQUENCY OF
MEASUREMENTS
Various parameters to be measured in dams & suggested frequency of readings for specified
instruments as prescribed in other guidelines viz. Instrumentation for dam & O&M for dam
are given at Tables 1 & 2 for reference. All instruments should be read immediately after
seismic activity or historic reservoir levels.
Many of the instruments in Tables should be read daily during initial filling or anytime the
reservoir goes above the historic maximum; weekly is too infrequent. First filling is a critical
timeframe for a dam. Also, the dam should have continual visual monitoring during initial
filling or any time the reservoir goes above the historic maximum. A Potential Failure Mode
workshop can help establish the need for certain instruments and the reading frequency. As a
minimum, instrument readings at a concrete dam should include reservoir levels, dam
deflections, seepage through the dam, and uplift pressures under the dam. It is suggested that
some instruments be read weekly for the first year and some monthly to develop a detailed
plot of data. Then the frequency of readings can be reduced as indicated in the Table.
Preferably, instruments should be read at the same time of the dam and the same day of the
month.
While reviewing the safety of existing dams it is desirable to include the following aspects in
the structural behavior reports:
a) Comments on the actual structure behavior based on: an understanding of the dam’s
characteristic behavior – how the dam and its foundation should typically behave under
various loading conditions, comparison of the actual parameters measured with the
design assumptions/parameters.
b) The potential failure modes of the dam, key performance indicators and condition of the
dam. Potential failure modes are an extremely important concept for engineers, owners,
and maintenance personnel.
c) Established two alert thresholds (acceptable performance limits) for key performance
indicators coupled with action items. For instance, a reservoir level that starts a
preparedness level, beginning actions, and then possible evacuations. Other terms for this
is the Ready, Set, Go levels. Also, every Every concrete dam should have “safe” water
levels determined for the key reservoir levels that indicate the dam is within criteria,
starts developing tension at the heel, and starts overturning.
Table -1: Parameters to be monitored at Dams Hydraulic Structure
(Clause 5)
Water quality
Seepage flows
measurement
measurement
measurement
measurement
Temperature
Stress-strain
Water levels
observation
Movements
Feature
pressure
Seismic
Visual
Upstream slope ✓ ✓ ✓ ✓ ─ ─ ─ ─ ✓ ─
Downstream slope ✓ ✓ ✓ ─ ✓ ✓ ✓ ✓ ✓ ─
Embankment Dams
Abutments ✓ ✓ ✓ ─ ✓ ✓ ✓ ─ ✓ ─
Crest (Dam Top) ✓ ✓ ✓ ─ ─ ─ ─ ✓ ✓ ─
Internal drainage ✓ ✓ ✓
─ ─ ─ ✓ ─ ─ ─
system
D/s Toe Drains ✓ ✓ ✓
✓ ─ ─ ─ ─ ─ ─
Relief Drain
U/s Riprap and D/s ✓
─ ─ ─ ─ ─ ─ ─ ─ ─
slope protection
Upstream slope ✓ ✓ ─ ✓ ─ ─ ✓ ✓ ✓ ✓
Concrete and Masonry Dams
Downstream slope ✓ ✓ ✓ ─ ─ ─ ✓ ✓ ✓ ✓
Abutments ✓ ✓ ✓ ─ ✓ ✓ ─ ─ ✓ ✓
Crest (Dam Top) ✓ ✓ ✓ ─ ─ ─ ✓ ✓ ✓ ✓
Internal drainage ✓ ✓
system in Dam ─ ─ ─ ─ ─ ✓ ─ ─
Body
Foundation drains ✓ ─ ✓ ─ ✓ ─ ─ ─ ─ ─
Galleries ✓ ✓ ─ ─ ─ ─ ─ ✓ ✓ ✓
Sluices / controls ✓ ─ ─ ✓ ─ ─ ─ ─ ─ ─
Approach channel ✓ ✓ ─ ✓ ─ ─ ─ ─ ─ ─
Control structure ✓ ✓ ✓ ✓ ✓ ─ ─ ✓ ✓ ─
Stilling basin / any ✓ ✓
─ ─ ─ ─ ─ ✓ ─ ─
other EDA
Spillways
Discharge ✓ ✓
─ ✓ ─ ─ ─ ─ ─ ─
conduit/channel
Gate controls ✓ ─ ─ ─ ─ ─ ─ ─ ─ ─
Erosion protection ✓
─ ─ ─ ─ ─ ─ ─ ─ ─
on d/s of EDA
Side slopes ✓ ✓ ✓ ─ ✓ ─ ─ ─ ─ ─
Control Structure ✓ ✓ ✓ ✓ ─ ─ ─ ✓ ✓ ─
Outlets
Water quality
Seepage flows
measurement
measurement
measurement
measurement
Temperature
Stress-strain
Water levels
observation
Movements
Feature
pressure
Seismic
Visual
Discharge ✓ ✓ ✓ ✓
─ ─ ─ ✓ ─ ─
conduit/channel
Trash rack/debris ✓
─ ─ ─ ─ ─ ─ ─ ─ ─
controls
Reservoir surface ✓ ─ ─ ─ ─ ✓ ─ ─ ─ ─
Mechanical/ ✓
─ ─ ✓ ─ ─ ─ ─ ─
electrical systems
General Areas
Reservoir Periphery ✓ ─ ─ ─ ─ ✓ ─ ─ ─ ─
Upstream watershed ✓ ─ ─ ─ ─ ✓ ─ ─ ─ ─
Downstream ✓ ✓
─ ─ ─ ✓ ─ ─ ─ ─
channel
Emergency ✓ ─
─ ─ ─ ─ ─ ─ ─ ─
Warning System
NOTE 3 -- Shutdown is that period during construction when the works remained suspended / stopped, due to any
reason.