SECTION 02220 April 2023

EARTHWORK, DAMS

INDEX

SECTION 02220 - EARTHWORK, DAMS

PART 1 - GENERAL

1.1 DESCRIPTION
1.2 QUALITY ASSURANCE
1.3 JOB CONDITIONS
1.4 PERMITS AND FEES
1.5 SUBMITTALS

PART 2 - PRODUCTS

2.1 FILL MATERIALS


2.2 FILTER SAND
2.3 DAM OUTLET STRUCTURES
2.4 SELECT BORROW

PART 3 - EXECUTION

3.1 SURFACE CONDITIONS


3.2 ELEVATIONS AND LINES
3.3 MAINTENANCE
3.4 WATER CONTROL
3.5 SUBGRADE PREPARATION
3.6 CORE TRENCH
3.7 IMPERVIOUS FILL PLACEMENT - DAM
3.8 IMPERVIOUS FILL PLACEMENT – POND LINER
3.9 CONTROLLED GENERAL FILL PLACEMENT
3.10 INTERNAL DRAINS
3.11 OUTLET STRUCTURES
3.12 SELECT COVER PLACEMENT
3.13 TESTING
3.14 MEASUREMENT AND PAYMENT

02220 - 1
SECTION 02220 April 2023
EARTHWORK, DAMS

PART 1 - GENERAL

1.1 DESCRIPTION

A. Work Included:

Work under this SECTION covers requirements for materials, tools, equipment and services
necessary to complete the Earth Dams for this project. The work shall include, but is not
necessarily limited to, completion of the following work:

1. Field engineering
2. Excavation
3. Dewatering of excavations prior to filling as may be required
4. Conveyance, placement, and compaction of excavated materials
5. Chemical/mechanical soil stabilization as may be required
6. Implementation of Storm Water Pollution Prevention Plan (SWPPP)

1.2 QUALITY ASSURANCE

A. Use adequate numbers of skilled workmen who are thoroughly trained and experienced in the
necessary crafts and who are completely familiar with the specified requirements and the
methods needed for proper performance of the work of this SECTION.

B. Use equipment adequate in size, capacity, and numbers to accomplish the work in a timely
manner.

C. In addition to complying with requirements of governmental agencies having jurisdiction, comply


with the directives of Engineer and Division.

D. References

1. ASTM D1556: Density of Soil-in-Place by Sand-Cone Method or other equivalent


method with Engineers approval.

2. ASTM D698: Moisture-Density Relations of Soils and Soil-Aggregate Mixtures – Standard


Proctor Test.

3. ASTM D2922: Density of Soil and Soil Aggregate In-Place by Nuclear Methods.

4. ASTM D3017: Standard Test Method for Water Content of Soil and Rock In-place by
Nuclear Methods.

5. ASTM D2487: Unified Soil Classification System (USCS).

6. ASTM D4253: Maximum Index and Unit Weight of Soils Using a Vibratory Table.

7. ASTM D4254: Minimum Index Density and Unit Weight of Soils and Calculation of
Relative Density.

8. ASTM D558: Moisture-Density Relations of Soil-Cement Mixtures.

9. ASTM D422: Particle-Size Analysis of Soils.

10. ASTM D4318: Liquid Limit, Plastic Limit and Plasticity Index of Soils.

02220 - 2
SECTION 02220 April 2023
EARTHWORK, DAMS

11. Iowa Department of Transportation Standard Specifications for Highway and Bridge
Construction (IDOT).

E. The Division/Engineer will retain the services of a Geotechnical Engineer to provide inspection of
the core trench, material evaluation and approval, and compaction testing of fill where required.
Contractor shall be responsible for coordinating and providing advance notice of any operations
involving these components to allow adequate time for scheduling and testing.

1.3 JOB CONDITIONS

A. Nature of Work Site

1. Materials to be handled under this Contract include quantities of spoil, gob, and coal
refuse which may be toxic and/or acidic in nature.

2. The Project site is situated in an area where underground coal mining could have been
conducted. There is a possibility that mine drifts or shaft openings are present on site.
Contractor shall exercise reasonable caution in recognition of this potential hazard, and
shall notify Engineer immediately upon discovery of any openings. Sealing of openings
will be incorporated into this Contract through issuance of change orders, as required.
Additional specifications will be provided by Division as needed.

3. During excavation in existing spoil piles, Contractor shall recognize possible existence of
cavities or smoldering fires and, if encountered, shall notify Engineer promptly.
Contractor shall exercise caution and be prepared to take appropriate actions since
accelerated combustion may occur. Burning materials shall be extinguished before
being covered or incorporated as fill. Contractor shall notify Division and Engineer if
smoldering fires are encountered.

4. Spoil material used to construct fills is subject to significant increase in pore water
pressure, particularly during rapid construction, with a corresponding decrease in shear
strength, and thus slope stability. Contractor shall exercise caution and notify Engineer
and Division promptly should signs of slope instability appear.

1.4 PERMITS AND FEES

A. Division has obtained any required permits from the Iowa Department of Natural Resources
(IDNR) as required for construction of the dam(s) on this Project. All requirements of the
permit(s) have been incorporated into the Construction Specifications and Plans.

1.5 SUBMITTALS

A. Contractor shall submit or assist with obtaining samples of all on-site or off-site materials
intended to be used to complete the work included in this SECTION. The samples shall be
obtained by or submitted to the designated Geotechnical Engineer at least ten (10) working days
in advance of its intended use. All samples shall be marked with its source and intended use.

B. The Geotechnical Engineer shall make appropriate examinations, classifications, and perform
necessary tests to determine the suitability of the material for its intended use. Engineer will
notify Contractor of the suitability of the submitted samples. Any submitted samples deemed
unsuitable shall not be used as intended and new samples must be submitted to or obtained by
the Geotechnical Engineer.

02220 - 3
SECTION 02220 April 2023
EARTHWORK, DAMS

C. Contractor shall schedule and coordinate all construction activities requiring observation and
testing with Engineer and/or Construction Observer and the designated Geotechnical Engineer.

D. Copies of all laboratory and field tests will be provided to Contractor, Engineer and Division.

PART 2 - PRODUCTS

2.1 FILL MATERIAL

A. Impervious Fill Material: Material used as impervious fill in areas designated on the Plans shall
be obtained from the area(s) indicated on the Plans as Impervious Fill Material, or in areas as
approved by Engineer and Division. Impervious Fill Material shall consist of clay or weathered
shale materials that do not have less than sixty percent (60%) by dry weight passing a Standard
No. 200 U.S. Sieve. Impervious fill shall be sorted to remove all material having any dimension
greater than four (4) inches. All impervious fill shall be classified as CL, CH, or CL-CH in
accordance with Unified Soil Classification System (USCS). All impervious fill shall be free from
debris, roots, organic matter, frozen material, and coal refuse. Any layers or pockets of granular
materials encountered within impervious fill borrow shall not be incorporated as impervious fill.

B. General Fill Material: General fill materials consist of spoil piles, coal refuse materials, gob and
all other soil material from required cut operations. All boulders, large rocks, organic matter,
frozen material, and miscellaneous debris shall be sorted out and not used within the footprint of
the dam.

2.2 FILTER SAND

A. Material used to construct the filter blanket and the toe drain backfill shall conform to one of the
following IDOT gradations. Fine aggregate shall not be of calcareous (limestone) nature. Submit
material certifications to Engineer.

SECTION 4112, PCC Intermediate, Gradation No. 2.


SECTION 4117 (Class V), PCC FA & CA, Gradation No. 7
SECTION 4131, Porous Backfill, Gradation No. 29
SECTION 4134 (Natural Sand), Floodable Backfill, Gradation No. 36

2.3 DAM OUTLET STRUCTURES

A. Refer to SECTION 02310 - DRAINAGE STRUCTURES, DAMS

2.4 SELECT BORROW

A. Refer to SECTION 02250 - EARTHWORK, SELECT BORROW

PART 3 - EXECUTION

3.1 SURFACE CONDITIONS

A. Examine the areas and conditions under which work of this SECTION will be performed. Correct
conditions detrimental to timely and proper completion of the work. Do not proceed until
unsatisfactory conditions are corrected.

3.2 ELEVATIONS AND LINES

A. Contractor shall stake the alignment and grades of earth dams in the field as shown on the Plans.

02220 - 4
SECTION 02220 April 2023
EARTHWORK, DAMS

B. Rough grading shall be to within three-tenths (0.3) feet of lines and grades as shown on the
Plans.

C. The crest of the dam at its midpoint shall be overbuilt as indicated on the Plans to accommodate
anticipated future settlement. The overbuilt crest of the dam shall taper from its mid-point to
zero (0) inches at both abutments.

3.3 MAINTENANCE

A. Protection of newly graded areas.

1. Protect newly graded areas from traffic and erosion, and keep free from trash and weeds.

2. Repair and reestablish grades in settled, eroded, and rutted areas to specified tolerances.

B. Contractor shall scarify the surface, reshape, and compact (if necessary) any areas where grading
is completed that becomes disturbed by subsequent construction operations or adverse
weather, prior to further construction.

C. Contractor shall maintain new and existing drainage ways free from detrimental quantities of
sediment, leaves, sticks, trash and other debris during execution of the work.

D. Contractor shall maintain access to adjacent areas at all times.

E. Contractor shall implement the approved SWPPP for this Project and conduct all excavation and
select borrow placement activities to minimize losses due to erosion and sedimentation of
adjacent areas.

3.4 WATER CONTROL

A. Contractor shall furnish, install, operate, and maintain all necessary and sufficient equipment and
methods for controlling surface water and groundwater during construction of the earthen dam.

B. Cofferdams may be used to divert water or collect water for pumping to protect the earth dam
during construction. Cofferdams should be located beyond the limits of the proposed earth dam.
The cofferdam(s) shall be removed after completion of the dam unless other arrangements are
made with Engineer and Division.

C. All excavations required for construction of the earth dam and drainage structures shall be
dewatered as necessary to prevent excessive disturbance of exposed subgrade and allow for fill
placement and compaction. Dewatering should be accomplished using pumps, drains, or other
suitable methods.

3.5 SUBGRADE PREPARATION

A. Contractor shall remove all vegetation, topsoil, soft, or otherwise unsuitable material from the
footprint of the dam as shown on the plans. Excavate further as needed to the subgrade
elevation lines shown on the plans.

B. The exposed subgrade shall be proofrolled with heavy equipment such as a loaded scaper or
tandem-axle dump truck in the presence of the Geotechnical Engineer, and Engineer or Division.
Soft or disturbed areas shall be improved by disking, drying, and compacting with a sheep’s foot
roller or by overexcavating and replacing with suitable, properly compacted, impervious fill. The

02220 - 5
SECTION 02220 April 2023
EARTHWORK, DAMS

area and depth of the overexcavation as approved by Division and Engineer shall be jointly
measured by Engineer and Contractor for payment quantities prior to backfilling.

3.6 CORE TRENCH

A. The core trench shall be excavated in the location shown on the plans after the dam footprint
has been has been stripped, proofrolled, and corrected as needed. The core trench shall extend
to the minimum width and depth as shown on the plans, unless bedrock is encountered or
conditions warrant additional excavation as determined by the Geotechnical Engineer.

B. The Geotechnical Engineer and Engineer shall observe the core trench prior to backfilling. If
additional excavation is required due to the site conditions, the Division shall be informed
immediately and this additional excavation shall be measured for payment. If additional
excavation is required due to inadequate water control measures or construction techniques
used by Contractor, this additional excavation and backfilling shall be completed at no additional
cost to Division.

C. The final core trench dimensions shall be measured jointly by Contractor and Engineer prior to
backfilling. Only the amount of excavation approved by Engineer and Division shall be computed
for payment. Additional excavated areas extending beyond the amount approved shall be
properly backfilled at no additional cost to Division. Any survey information obtained by
Contractor shall be provided to Engineer.

D. The core trench shall be backfilled with impervious fill after receiving approval by Engineer. The
impervious fill shall be placed and compacted in accordance with the requirements of this
Section.

E. The core trench shall be dewatered when necessary to allow for observations by Engineer and
during fill placement. Subgrade and fill materials that become disturbed or too wet for proper
compaction shall be removed and replaced at no additional cost to Division.

3.7 IMPERVIOUS FILL PLACEMENT - DAM

A. Impervious fill, as approved by the Geotechnical Engineer, shall be placed in the core trench and
within the designated areas of the embankment. Impervious fill shall also be placed as the pond
liner where indicated on the Plans.

B. Impervious fill shall be placed in horizontal lifts for the core trench and dam. Vertical benches
shall be cut into adjacent slopes as needed to allow for horizontal placement.

C. Impervious fill shall be placed and spread in horizontal, loose lifts of no more than nine (9) inches
and compacted to at least ninety-five percent (95%) of the material’s maximum standard Proctor
dry density.

D. The moisture content of the impervious fill shall be adjusted as needed by disking and drying or
wetting the material to be within the range of minus two percent (-2%) to plus four percent
(+4%) of the material’s optimum moisture content as determined by the standard Proctor test.

E. Compaction of impervious fill and general fill within the footprint of the dam and for the pond
liner shall be accomplished with a sheep’s foot roller meeting IDOT Section 2001.05A, Tamping-
type rollers. Manual compaction equipment shall be used as required to prevent damage to
structures and shall meet the same compaction requirements. No other types of compaction
equipment will be allowed for placement of impervious fill, unless written approval is obtained
from Division or Engineer.

02220 - 6
SECTION 02220 April 2023
EARTHWORK, DAMS

F. The exposed surface shall be properly prepared prior to placement of each subsequent lift. If the
exposed surface becomes too smooth to bond to the next layer, the existing layer shall be
scarified. If the exposed surface becomes excessively dry or moist, the surface shall be scarified
and moisture conditioned as necessary before placing subsequent fill layers.

G. Impervious fill shall not be placed during periods of freezing weather or over frozen materials.
Frozen material shall not be used as impervious fill.

3.8 IMPERVIOUS FILL PLACEMENT- POND LINER

A. The subgrade in pond areas to receive impervious fill shall be established to allow the design
thickness of impervious material to be placed.

B. The exposed subgrade shall be disked to a depth of at least six (6) inches and observed by the
Geotechnical Engineer. Areas with sandy or otherwise unsuitable materials will be
overexcavated and replaced with impervious fill. The overexcavation will extend so that at least
two (2) feet of compacted and impervious material is present over sandy material. The exposed
subgrade shall be moisture conditioned as necessary to be within minus two percent (-2%) to
plus four percent (+4%) of the standard Proctor optimum moisture content. The disked subgrade
material shall be compacted to at least ninety percent (90%) of the material’s standard Proctor
maximum dry density.

C. Impervious fill for the pond liner shall be placed in loose lift thicknesses or no more than eight (8)
inches and compacted to at least ninety percent (90%) of the material’s maximum standard
Proctor dry density at a moisture content between minus two percent (-2%) and plus four
percent (+4%) of the material’s maximum standard Proctor moisture content.

3.9 CONTROLLED GENERAL FILL PLACEMENT

A. Controlled general fill materials shall be placed in the portions of the dam as shown on the plans
adjacent to the impervious fill areas to the rough grade shown on the plans. General fill shall be
placed concurrently with impervious fill.

B. Controlled general fill placed within the footprint area of the dam shall be placed in horizontal
lifts not to exceed twelve (12) inches in loose thickness. Each lift shall be compacted to at least
ninety percent (90%) of the material’s maximum standard Proctor dry density. The moisture
content of the general fill placed adjacent to the impervious fill within the footprint of the dam
shall be adjusted as needed by disking and drying or wetting to be within minus two percent (-
2%) to plus four percent (+4%) of the material’s optimum moisture content as determined by the
standard Proctor test.

C. Compaction of controlled general fill within the footprint area of the dam shall be accomplished
with a sheep’s foot roller meeting IDOT Section 2001.05A, soil compaction rollers. Manual
compaction equipment shall be used as required to prevent damage to structures and shall meet
the same compaction requirements. No other compaction equipment will be allowed for
placement of impervious fill, unless written approval is obtained from Division.

D. Controlled general fill shall not contain frozen materials, be placed over frozen material, or be
placed during a period of freezing weather.

02220 - 7
SECTION 02220 April 2023
EARTHWORK, DAMS

3.10 INTERNAL DRAINS

A. The dam construction may include installation of internal drains such as a downstream drainage
blanket, chimney drain, and/or toe drain. Placement of impervious and general fill shall be
completed in a manner that insures these drains function properly.

B. Refer to SECTION 02310 – DRAINAGE STRUCTURES – DAMS and to the Plans for further details.

3.11 OUTLET STRUCTURES

A. The dam construction may include installation of both primary and emergency spillways. Refer
to SECTION 02310 – DRAINAGE STRUCTURES – DAMS and to the Plans for further details.

3.12 SELECT COVER PLACEMENT

A. When select cover material is required, this material shall be placed after completion of
construction of the earthen dam at the locations and with the thickness shown on the Plans.
Refer to SECTION 02250 – EARTHWORK, SELECT BORROW.

3.13 TESTING

A. Division shall pay all field and laboratory soil tests to ensure that proper compaction and
moisture control are being achieved. All test data shall be regularly submitted by the selected
Geotechnical Engineer to Engineer, Division, and Contractor.

B. A minimum of one (1) standard Proctor test shall be performed on each cohesive material type
used to construct the dam. Additional laboratory tests will be performed as needed to
determine the material’s suitability for its intended use.

C. In-place field density tests shall be performed in sufficient number and locations to ensure that
the impervious fill is being placed and compacted in accordance with the Construction
Specifications. As a minimum, one (1) test shall be performed for every two (2) feet of loose fill
thickness placed and at a maximum spacing of one-hundred (100) feet along the length of the
dam both within the impervious fill and general fill sections. Tests performed for the pond liner
shall be taken as needed to insure proper compaction and no less than on a one-hundred (100)
foot grid for each lift, including the subgrade.

D. All areas with failing tests shall be reworked by Contractor and retested by the Geotechnical
Engineer until the required compaction and the proper moisture content is achieved.

E. Additional or supplemental field or laboratory tests requested by or conducted for the


convenience of Contractor shall be completed at no additional cost to Division.

3.14 MEASUREMENT AND PAYMENT

The construction cost of all work included in this SECTION of the Construction Specifications shall be
included in Contractor's unit prices set forth in the Proposal and Schedule of Prices (Document C) for the
work items described below. The unit price for each of these items shall include its pro rata share of
overhead so that the sum of the products obtained by multiplying the unit prices so set forth by the
amount of the work actually constructed, measured as described herein, shall constitute full payment to
Contractor for performance of the work included in this SECTION.

02220 - 8
SECTION 02220 April 2023
EARTHWORK, DAMS

Measurement and payment for each work item in this SECTION shall be in accordance with the following:

A. Undercut Excavation, Earth Dam: The unit price for this item shall include all equipment,
materials, and labor to remove material below the footprint of the dam as discussed in the
Subgrade Preparation and Core Trench portions of this SECTION. Said unit price shall constitute
full payment for undercut excavation, and all incidental work pertaining thereto. Excavations for
dewatering and cofferdams, if needed, are incidental to construction of the embankment and
will not be included in the undercut quantity. Excavation for toe drains, filter sand, and outlet
works conduit, if needed, will not be measured for payment and this associated cost should be
included in the unit prices for each of these items.

Contractor will be paid for the undercut excavation based on conditions encountered during
construction. The undercut area will be jointly measured by Contractor and Engineer. The
backfill required for any overexcavation will be paid for as impervious fill. Any undercut
excavation and associated backfill not approved by Engineer and Construction Observer will not
be measured for payment.

Contractor shall be paid at the unit price for "Undercut Excavation" for each cubic yard as
measured above. The quantity of cubic yards for the undercut excavation included in the bid
items have been separated out of the overall excavation required for rough grading.

B. Impervious Fill, Earth Dam and Pond Liners: The unit price for this item shall include all
equipment, materials, and labor required to properly place approved material in the core trench,
undercut excavation, and within the designated area of the dam and pond liner as shown on the
on the plans. Said unit price shall constitute full payment for dewatering, moisture adjustment
and compaction, and all incidental work pertaining thereto.

Contractor will be paid for the bid quantity of impervious fill for the earth dam provided in the
specifications unless additional undercut excavation was required or other changes were needed
based on conditions encountered during construction. If additional undercut excavation was
required, the approved quantity will be added to the bid quantity for impervious fill. If other
areas of impervious fill were required by Engineer that are not shown on the plans or were not
measured as part of the undercut, these areas will be jointly measured by Contractor and
Engineer/Construction Observer. Any impervious or general fill placed in undercut excavations
not approved by Engineer will not be measured for payment.

Contractor shall be paid at the unit price for "Impervious Fill" for each cubic yard compacted in
place and as measured above. The quantity of cubic yards for the impervious fill included in the
bid items have been separated out of the overall excavation required for rough grading and has
been adjusted for the shrinkage rate indicated in the Supplemental Specifications or Plans.

C. Controlled General Fill, Earth Dam: The unit price for this item shall include all equipment,
materials, and labor required to properly place approved material within the designated area of
the dam as shown on the on the plans. Said unit price shall constitute full payment for
dewatering, moisture adjustment and compaction, and all incidental work pertaining thereto.

Contractor will be paid for the bid quantity of controlled general fill for the earth dam as shown
on the plans and in any other areas requested by Division and Engineer. Any controlled general
fill placed in areas not approved by Engineer or Division will not be measured for payment. The
quantity of cubic yards for the controlled general fill included in the bid items have been
separated out of the overall excavation required for rough grading and has been adjusted for the
shrinkage rate indicated in the Supplemental Specifications or Plans.

02220 - 9
SECTION 02220 April 2023
EARTHWORK, DAMS

D. Summary: Proposal Bid Items applicable to work covered by this SECTION are as follows:

Description Unit

Undercut Excavation, Earth Dam Cu. Yd.


Impervious Fill, Earth Dam Cu. Yd.
Impervious Fill, Pond Liner Cu. Yd.
Controlled General Fill, Earth Dam Cu. Yd.

END OF SECTION 02220