Cost Engineering Module
Cost Engineering Module
Cost Engineering Module
University of Gondar
Institute of Technology
Department of Construction Technology and Management
Table of Contents
Chapter One 4
1. Fundamental Principles of Cost Engineering 4
1.1 Introduction 4
1.2 Definitions and Terminology to Cost Engineers 5
1.3 Project Planning 7
1.4 Cost Engineering Traits 10
1.5 The Function of Cost Engineering in Construction 12
1.6 Considerations in Costing 13
1.6.1 Project Size 13
1.6.2 Project Quality 14
1.6.3 Project Location 14
1.6.4 Construction Time 18
Chapter Two 20
2. Construction Pricing and Contracting 20
2.1 Tendering Policy and Procedure 20
2.1.1 Bidding Strategy 20
2.1.2 Tendering Procedure 24
2.1.3 Firm’s Mark-up target 25
2.1.4 General Overheads 26
2.2 Contract Provisions for Risk Allocation 27
2.3 Construction Contracts 29
2.3.1 Lump Sum Contract 29
2.3.2 Unit Price Contract 30
2.3.3 Cost plus Fixed Percentage Contract 31
2.3.4 Cost plus Fixed Fee Contract 31
2.3.5 Cost plus Variable Percentage Contract 31
2.3.6 Target Estimate Contract 31
2.3.7 Guaranteed Maximum Cost Contract 31
Chapter Three 33
3. Cost Estimating Approach 33
3.1 Types and Methods of Estimates 33
3.1.1 Approximate Estimate 33
3.1.2 Detailed Estimate 34
3
Chapter One
1. Fundamental Principles of Cost Engineering
1.1 Introduction
Before taking up any construction work for its execution, the owner or builder should have a thorough
knowledge about the volume of work that can be completed within the limits of his fund or the
probable cost that may be required to complete the contemplated work. It is therefore necessary to
prepare the probable cost or estimate for the intended work from its design plan and specifications.
Otherwise it may so happen that the work has to be stopped before its completion due to shortage of
funds and or materials.
There are many costs associated with construction projects. Some are not directly associated with the
construction itself but are important to quantify because they can be a significant factor in whether or
not the project goes forward and feasible. These include the initial capital cost and the subsequent
operation and maintenance costs. Each of these major cost categories consists of a number of cost
components:
Land acquisition, including assembly, Construction financing including
holding and improvement overhead costs
Planning and feasibility studies Insurance and taxes during construction
Architectural and engineering design Owner's general office overhead
Construction, including materials, Equipment and furnishings not
equipment and labor included in construction
Field supervision of construction Inspection and testing
The operation and maintenance cost in subsequent years over the project life cycle includes the
following expenses:
and takes more time. Cost estimating is critical in the development of the project because it informs the
owner of costs, which in turn guide design decisions.
Cost Engineers consider past projects while anticipating new factors. Some of these factors include:
All-in Material Rate: A rate which and the costs which arise directly from
includes the cost of material delivered to the employment of labor.
site, waste, unloading, handling, storage All-in Plant Rate: A compounded rate
and preparing for use. which includes the costs originating
Basic Material Price/Index: Unit price from the ownership or hire of plant
of the material including transportation, together with operating costs.
unloading, waste, handling, storage and Direct Costs: Costs directly rendered to
preparing for use. the production of the work. It includes,
All-in Labor Rate: A compounded rate all-in material costs, all-in labor costs
which includes payment to operatives and all-in plant costs.
Overhead Costs: Costs incurred not to the direct itemized works but indirectly to the overall
production and performance of the work. E.g.
Secretarial services, Utility provisions: energy, water,
Transportation facilities, communication, sanitation,
Administrative works,
The end result of the Cost Budgeting process is a Cost Baseline, which is a time-phased budget that
will be used to measure and monitor overall cost performance on the project—usually displayed in the
form of an S-curve. Additionally, the Cost Budgeting process will produce Project Funding
Requirements, including a management reserve amount that is included along with the cost baseline
to compensate for either early progress or cost overruns.
Briefly, let us consider an estimator pricing a brickwork item. What are the difficulties presented? They
are as follows:
There may be many or only a few work methods available. For instance, should the estimator assume
a three-man or a four-man crew, composed of two or three bricklayer with either one or two laborers?
Will there be central mortar mixing or individual mixers for each crew? How will the brickwork be
constructed? Will trestles or proper standing scaffolding be used? Where will work commence from?
What restrictions will the other trades impose on the masonry work? All possibilities must be
investigated, and the most economical possibility should be chosen.
9
Output of Crew:
The output chosen will be based on past performance, since the estimator will assume that this
performance will be repeated in the future. As will be explained later, recording and properly
documenting job site performance is helpful to the estimator when he or she considers future projects.
Manipulation of these historical data may occur; for example, decreasing output to allow for restricted
working condition. Whatever manipulation occurs, the estimator is faced with the difficulty of trying
to assess what output will be achieved.
Cost of Labor:
How much will the contractor be required to pay for labor? The estimator must predict this cost. The
labor cost will vary depending on job location, availability of skilled labor, contract wage regulations,
union or open shop labor requirements, general market conditions, and so on.
Cost of Material:
This can be predicted with a fair degree of accuracy if the material in question is in ready supply and
is frequently purchased. The quantity of material required must be accurately measured from the
drawing and is not dependent on the crew performance or work method adopted. Although the
estimator must not only consider the finished in -place quantity of material, but also must allow for a
wastage factor, this factor can vary dramatically and is highly dependent on the performance and work
procedures adopted by the crew.
This amount will depend on company policy, market condition, and many other variables that will be
discussed later. It is, as you can imagine, very important to incorporate overhead and profit into the
final estimate.
Variances between estimates and actual costs do occur. The estimator, unfortunately, always appears
to be incorrect, since an estimate is an “estimate”, which is a forecast of the anticipated future cost.
Many forces can in reality cause the actual cost to vary from the estimated cost. It sometimes appears
to owners and management that, when the estimate does not equal the actual costs, a mistake has been
made. Because it is an estimate, it should always be expected that the actual cost will vary somewhat
from the estimated cost. It is the job of the estimator to minimize the extent of variance between
estimate and actual cost. Any data collection system must be able to recognize that variances exist.
Variability of Estimates:
The following are where cost variances between one estimate and another can occur:
The total cost estimate is made up of numerous smaller cost estimates for each activity required to
complete the overall project. The estimating equation is therefore composed of a series of calculations,
the estimator has to assess and propose a monetary solution. The total cost estimate is the total of all
the minor monetary solutions. Each assessment the estimator performs is based on:
Previously recorded data (historical data) Previous experience of others.
The estimators own past experience. Hunches/intuition.
The final assessment is subjective. The estimator will decide what productivity to allow, or what birr
allowance or unit price to use. This subjective act is the main reason why estimates vary. If you give
identical drawings and specifications to 100 estimators, you will get 100 different cost estimates. Figure
below indicates the factors influencing variance in an estimate.
Basic reasons for variances being introduced into cost estimates – the subjective assessment.
Conflicting Issues of quality, size, performance and cost: As projects develop, there is continual
competition among issues of quality, size, performance and cost. Owners want to have the
biggest facility with the best finishes and systems that will perform over time with least possible
amount of money. With these criteria, it is likely that conflicts are bound to arise.
11
The design and construction team uses estimates to ensure that good cost information developed and
a feedback loop established so that these conflicts can be addressed as quickly as possible. As project
information becomes available, it is passed through a costing exercise. The owner can then decide to
proceed based on this information or ask for some alteration in the design. The designer can then devise
ways to meet the cost targets. Through this feedback loop, conflicting demands of cost versus
performance can be resolved.
Cost Engineering combines both science normal feature of the design process is that
and art: Cost estimates are a product of earlier stages of design are less precise than
information supplied by the designer, the later stages. Cost information provided at
owner and the suppliers. Experienced Cost schematic and preliminary design will by
Engineers use much judgment in nature be less accurate than the ones
interpreting and configuring this provided at design developments.
information. Cost estimate is based on previous
Cost Engineering does not offer guarantees estimates: A good, accurate estimate does
of costs: Used properly, however, can be not stand alone. It is the product of lessons
important tool in bringing a project under learned from previous estimates.
or at budget. The costs developed during Costing requires standard computing
design and even at the bidding stage are methodology and procedures: As the design
almost never the final and complete costs of proceeds, the level of details increases.
the project. Costing as a consequence becomes more
Costing can only be as accurate as the complex reflecting the many different
information upon which it is based: Cost factors that go into each unit of work.
accuracy depends on many factors. Calculations increase in number and the
Document completeness, data base potential to leave something out becomes
accuracy, the skill and judgment of the Cost greater. Only through adherence to strict
Engineer. methods and procedures that mistakes can
Cost estimate accuracy increases as the be minimize.
design becomes more precisely defined: A
12
Cost Engineering can also help to fix up Estimate is required to invite tenders and
completion period from the volume of prepare bills for payment.
works involved in the estimate. Cost Engineering helps for valuation of
Cost Engineering helps to justify existing property which itself is for a
investments from cost-benefit analysis. number of purposes.
1.6 Considerations in Costing
Project price is affected by the size of the project, the quality of the project, the location, construction
time, and other general market conditions. The accuracy of costing is directly affected by the ability of
the Cost Engineer to properly analyze these basic issues.
1.6.1 Project Size
The size of the project is a factor of the owner’s needs. At the conceptual stage, size is an issue of basic
capacity, such as apartment units for a real estate developer or kilometers of roadway for highway
engineering. As the project becomes better defined, its size begins to be quantified more accurately.
The principle of economy of scale is an important factor when addressing project size. Essentially as
projects get bigger, they get more expensive but at a less rapid rate. This occurs because the larger the
project, the more efficiently people and equipment can be used. Also as people repeat task, they get
better and faster, reducing the cost of labor. On large commercial building and heavy engineering
projects, worker productivity is plotted into learning curves. Cost Engineers treat project size by
establishing tables that recognize the typical size of a project and a respective price and then adjust up
or down from this norm.
As operations continue, crews learn so that the time required to complete the next like unit is less. In
general for buildings built to the same specification in the same locality, the larger building will have
the lower unit area cost. This is mainly to the decreasing contribution of the exterior walls plus the
economy of scale usually achievable in larger buildings. As an example, the area conversion scale
shown below will give a factor to convert costs for the typical size building to an adjusted cost for the
particular project.
14
Fig: Typical project size and method for modifying for economy of scale.
strength of the local bargaining unit. The cost of labor is also a factor the degree of sophistication and
level of training found at the project location. On some projects the numbers and the skill levels of
workers required are not available locally and must be imported. Understanding the need for such
importation adds significantly to the accuracy of an estimate.
Local conditions can influence the costs of the project. The need for citizen involvement, local taxes or
fees, and government requirements all can cost the project money. Extreme climatic conditions,
political instability, and earthquake zones all add to the cost in ways that may not be entirely obvious
without some investigation.
The cost of labor and material in different locations can be predicted by establishing location indices
for different cities and parts of the country. An index is created for a particular city by comparing the
cost of labor, equipment and material for that city to the national average. This allows an estimator
using national average costs to adjust the estimate to a particular location. Most design and
construction companies have developed an accurate record of location indices, which they use for their
pricing, or they buy this cost data from national pricing suppliers. To predict the costs of other local
factors, such as political instability, a company either uses its own experience in the locale or teams up
with a local partner who knows how the local atmosphere can affect project costs. Various locational
difficulties are described:
A remote construction site, for example, a project site located in valleys of Gibe River, poses a
contracting organization with a difficult set of problems to cope with.
contractor. Finally, the cost of hauling items of equipment to the job site increases as the distance
increases. Given these considerations, the requirement for management to make the correct
equipment selections becomes very important.
Increased Material Cost: Increased material cost is primarily due to increased transport charges
such as when distance for haulage from the depot to a remote job site is longer than the haulage
associated with other construction projects the estimator has previously worked on. Avery4
found that if the material was fragile or hazardous, then transport costs fluctuated widely
depending on distance. He also discovered that the bulk materials with low initial cost, such as
sand and gravel, tend to be the most adversely affected by distance and difficult transport
conditions. Ferry crossing or bridges with tolls increase the basic cost of materials.
Power and Water: Power and water are a necessity for building construction. Water is needed
for materials such as concrete, for cleaning the building, and for many other uses. Salt water is
not acceptable in most specifications for concrete or mortar mixing, so remote projects without
a convenient domestic water supply, even if the site has access to thousands of gallon of
seawater; require water to be trucked to the job site. The cost of water depends on the hauling
costs. In some instances wells can be dug to pump water to the surface; of course, the costs
involved must be considered in the estimate. If no power source is available, then power must
be provided by generators.
Confined Sites
The problems associated with confined sites generally take the form of congestion resulting in restricted
working areas resulting in low productivity from labor and equipment. These difficulties are generally
associated with downtown sites, but this need not always be the case.
In extreme cases, congestion can limit the choice of work methods, types of equipment used, and size
of crew to be employed. Careful investigation of the problems likely to be associated with each
particular site will allow a realistic assessment of factors such as productivity to be made. Project
startup requires a careful utilization of resources in order to provide production outputs that maximize
profits. Confined sites create logistical problems. Material movement should be minimized: each time
an item of material is moved, its cost to install in place increases. When materials are delivered to a
confined site, the material should be used immediately. If this is not possible, a storage area should be
available to receive the material, or, if possible, the material should be offloaded directly at its intended
utilization point.
The estimator needs to consider the unique logistical problems associated with each job site. These
problems, including restricted access, restricted material lay down area, restricted equipment storage
areas, and restricted location for site trailers, affect the type of equipment that can be used, the effective
management of the job, the worker productivity, and the amount of labor involved in handling
material. Since confined sites nearly always pose logistical problems, the unit prices used by the
estimator must account for the increased costs.
17
Labor Availability
Each location has varying amount of available skilled and unskilled labor, depending on the condition
of the local economy. If labor of any kind is not available locally (as may be the case in remote areas),
then labor must be imported from other location. In order to move labor from one area to another, a
financial incentive is usually required. The magnitude of this incentive will vary depending on the
state of the labor market. If labor is imported, accommodations may have to be provided. Labor camps
comprising full time kitchen staff, dormitories, leisure facilities, etc., have been set up on major
construction project to house the contractor’s labor force. The leisure facilities keep the labor force
relaxed and occupied during any rest periods. Living and working on a remote construction site can
be very demoralizing, after a while, and by keeping the morale level high, labor turnover is reduced.
Generally, the cost of importing labor will follow the laws of supply and demand.
Weather
Since the building process is highly weather dependent, extreme conditions can greatly affect
building costs. These extreme weather conditions include large amount of rain or snow, occurrences
of ice and frost, and high humidity and heat. Their effects on cost include the following situation.
Concrete pours in temperatures below 40 degrees Fahrenheit require special precaution. With cold
weather concreting, the cost of admixtures, insulation the formwork, removing ice from formwork,
and protecting the freshly placed concrete from dropping below the specified temperatures must be
taken in to account by the estimator. Not only does cold weather affect concrete, but hot weather
concreting has its associated problems as well. During periods when the temperature exceeds 80
degrees Fahrenheit, special precautions are required to reduce and maintain the concrete below this
temperature. For example, ingredients such as the water may be cooled or chopped ice can be
utilized. Another alternative is to use liquid nitrogen to cool the concrete. Admixtures and low heat
cement can be used to control the set and hardening times of the concrete to achieve the design
strength and quality. All these precautions and procedures increase the cost of pouring, placing, and
curing concrete.
Exposed sites may have problems associated with high winds, which affect crane and hoisting
operations, and the contractor’s dust control program. Additional temporary bracing to partly
completed structures may be required to prevent a collapse due to high wind gusts. In areas where
hurricanes occur, the estimator should consider the cost of temporary measures required to prevent
damage to a structure before, during, and after a hurricane. It would be prudent to allow for the costs
involved in bracing, tieing down structures providing sand banks, garaging equipment, and storing
particular materials such as doors and windows off the job site, unless safe, dry, and secure storage
exists on the project.
18
Labor productivity is also associated with the weather. During poor weather when it is cold, damp,
and windy, the morale of workers exposed to adverse elements, drops, which in turn results in a decline
of productivity. During days when it may be impossible to work, such as during a torrential rain, the
productivity is zero.
The location of a project has certain aspects that must be considered by a designer. For example, in
historic sites all designs must harmonize with the existing historical buildings (example around
Lalibela). Planning committees may dictate the material selections and configurations that designers
must abide by to suit certain local conditions.
These design considerations can create estimating problems in historic districts. The estimator must
know if the materials specified are, in fact, locally available of if local labor exists to carry out
complicated historical work, such as ornate plaster work; if not, a specialist will be required.
Traditional building techniques tended to be labor intensive. If the same techniques must be repeated,
then the estimator must be familiar with the procedures involved. If workers are required to use
traditional, building methods with which they are unfamiliar, then a learning curve cost needs to be
built into any unit price.
The local climate also dictates the designer’s choices in mechanical and electrical systems and in the
choice of materials and design of the building envelope. Material resources will fluctuate from location
to location throughout the country, and the designer must investigate what materials are locally and
economically available.
Finally, each locality tends to have its own construction trade practices, and the estimator should be
familiar with them.
Site integrity is an important problem in urban areas. Protective measures can be expensive, for
example, when 24-hour guard service and perimeter enclosures, are required. The level of security
will depend on the risk to the project from the surrounding neighborhood. The local police should be
consulted.
An estimator who accurately incorporates project size, project quality, location, and time has an
estimate that reflects the fair value for the project. In a normal market without any unusual
circumstances, this estimate should reflect the price that is paid.
Market conditions, however, shift; and owners, designers, and contractors all look at a given project
from different perspectives. In a market without much work, contractors may bid a project at cost or
with little profit to cover their overhead and keep their staff employed. On complicated projects,
contractors may bid the work low in hopes of making significant profit on future changes. Conversely,
they may bid a work high to cover the increased risks of a complex project. It is not unusual for
contractors to offer very competitive prices when they hope to enter a new market or establish a
relationship with a new owner. Such issues are very difficult to quantify but should be considered in
the preparation of the estimate. They are usually treated as a percentage applied at the end of the
estimate, included in either overhead or profit or in a final contingency.
ACTIVITY-1:
Chapter Two
2. Construction Pricing and Contracting
2.1 Tendering Policy and Procedure
Because of the unique nature of construction projects, it is almost imperative to have a separate price
for each. The construction contract price includes the direct project cost including field supervision
expenses which are often referred as site overhead costs plus the markup imposed by contractors for
general overhead expenses and profit. For any firm to operate its business in a satisfactory manner, it
is necessary for its policy directors to establish a clear objectives or a strategy. In construction pricing,
it is required for an organization to have a continual process of determining the missions and goals of
an organization within the context of its external environment that create opportunities and threats,
and its internal environment which are expressed as strengths and weaknesses. This strategy often
depends upon many factors which the management body of the contractor has to make a thorough
analysis of the situations at hand and take up appropriate competitive advantage. Among the factors
that one has to consider during construction pricing include:
Work at hand in reference to contractor’s The ultimate goal of the financial manager
assets deployed to the work, (profit maximization or wealth
The geographical areas in which the firm maximization),
will operate, Projected risks and uncertainties of the
Type of structure the organization seek to project,
control, Form of the bid: (open, short-listed, pre-
Type of services the organization is to qualification, etc) – please refer the diagram
deliver, in the next page.
Type of client the organization is to favor, (
private, local authority, community
services, )
It will then be the task of the executive management to make internal analysis of its strength and
weakness to hold the best advantage. Keep organization’s strength to exploit the opportunities and
minimize the weakness, say employing the available resources of the firm, to overcome external
threats.
2.1.1 Bidding Strategy
In a competitive tendering situation, the contracting firm is constantly facing a tradeoff of submitting
a high price for getting profit and the resulting shortage of work, with that of a low price for winning
the contracts, but allow little profit margin. A bidding strategy may be evolved for determining the
optimum bid, which will be the relationship between maximum profit and the probability of being the
lowest tenderer.
21
As the basis for this, it is necessary to analyze the bidding pattern of competitors, and apply statistics
rule for comparing the result with the firm’s own estimated costs over a number of contracts. A
competitor’s bid could be obtained from the list of tender results and a bidding pattern established.
In practice, because of contractor’s marketing policies, a contractor will find he is in competition with
a limited number of firms for any project in the locality. A bidding pattern could be worked out for his
major competitors.
If the contractor were able to identify the competition, an optimum bid could be ascertained by
combining the probability curves (the Z-distribution) and developing a bidding curve using a linear
regression line for this situation. The following steps shall be followed by a competing firm to assume
a bidding strategy.
least the winning price and the tender sum of the contractor under consideration have to be
recorded and put in a database file for further undertakings.
Example:
(Birr) (Birr)
1 500,000 450,000
2 750,000 750,000
3 1,000,000 800,000
4 625,000 600,000
5 850,000 800,000
6 250,000 250,000
7 400,000 350,000
8 1,200,000 1,000,000
9 900,000 875,000
10 1,100,000 950,000
ii) After having sufficient records of the respective bid prices, one could plot the information
on a scattered diagram.
For the example in (i), the scattered diagram looks the following:
23
1,200,000
1,000,000
800,000
600,000 Series1
Scattered Diagram
400,000
200,000
0
0 200,000 400,000 600,000 800,000 1,000,000 1,200,000 1,400,000
iii) Draw the most likely curve referred as a regression line. The simplest to draw is a linear
regression line that can be represented by:
Y = mX + b
m
n xy x y
b
y x x xy
2
n x 2 x
2
n x x
2 2
Furthermore, one has to determine the standard deviations, to define the probable region of winning
a tender.
24
n 1 2
VARIANCE
n2
s y m 2 sx2
iv) The final step is to decide the probability of winning a tender using the normal distribution.
The chance of winning the tender by offering the most likely price is 50%. A contractor can
increase or decrease the probability of winning the tender using the Z-normal distribution
theory of statistics.
Example: For the example in (i), suppose the contractor’s tender sum amounts to 675,000 Birr.
Determine the rebate to be improvised with 95 % probability of winning the tender.
The most likely winning price, Y = 0.813(675,000) + 66476.91 = Birr 615,251.91:- taken as the mean value
(µ) with a winning chance of 50%.
The Z-values of 95% probability, from the table = 1.645. The relation between Z, and probability in this
case is inverse. Higher probability is achieved by reducing the bid price and hence we need to use the
negative value of what we read from the table.
Yi
Z
Z= -1.645, µ = 615,251.91 and δ = 55509.2,
Yi = Birr 523,939.28
Rebate (R) = 100% -- (523,939.28/675,000) x100%
= 22.38 % (95% probability of wining)
= 8.9% (50% probability of winning)
2.1.2 Tendering Procedure
In order that the tendering policy of the firm be maintained it is necessary that a procedure for the
preparation of all tenders be established. This will vary with different contractors, depending on size
and personnel, but a basis could follow the stages set out by the Ministry of Infrastructure.
Decision to Tender:
25
A management decision based on the firm’s position at the time of invitation in relation to:
If management decides to tender for the project, the estimating staff should assemble information about
project costs. An accurate estimate can only be produced when each element is broken down into its
simplest terms and the cost estimated on factual information. Some of the factors required include:
Time scale for tendering with key dates as mentioned in the invitation to bid,
Examination of contract documents, with preliminaries attached with the tender,
Assessment of client and design team,
Enquiries to suppliers and sub-contractors with a time scale,
Site and locality visit,
Discussion with site management, plant and planning department,
Evaluation of alternatives
Preparation of detailed construction method statement and pre-tender program, developed to
include production outputs, gang sizes, plant details, etc.
Preparation of estimate:
Having assembled all the information, the next task of the estimating staff is to build the cost of the
unit rates. This requires the calculation of all-in rates for labor, plant, materials and extending these,
using the production details from the pre-tender programme. The cost of any on site administration
and services, known as project overheads is also calculated. These net production costs, together with
a project appraisal report are then submitted to management for adjudication.
The tender:
The management of the firm would consider the mark-up required on the estimated production costs,
to cover the firm’s overheads, profit and risk of the tender. These additional costs included, the tender
figure can then be determined and submitted.
Action with tender results:
An analysis of tenders and a comparison of results should be completed for each project to provide a
basis for future bidding strategy. With a successful tender, cost information during the progress of the
work and a final reconciliation of estimated and final account costs should be made.
established in tendering so that each project contributes to the firm. This will entail the setting up of a
mark-up target, over the production costs, for all contracts to be undertaken. To determine firm’s mark-
up, it is required establish:
i. Return on Capital Employed (ROCE), which is made to account the following costs:
Example:
The general overheads vary with individual firms, but a broad list may include:
For example:
If last year’s turnover was Birr 2,000,000 and the fixed costs Birr 160,000 then:
Standard forms for contracts can be obtained from numerous sources, such as the International
Conditions of Contract, FIDIC, Standard Conditions of Contract by Ministry of Works and Urban
Development. These standard forms may include risk and responsibility allocations which are
unacceptable to one or more of the contracting parties. In particular, standard forms may be biased to
reduce the risk and responsibility of the originating organization or group. Parties to a contract should
read and review all contract documents carefully.
All owners want quality construction with reasonable costs, but not all are willing to share risks and/or
provide incentives to enhance the quality of construction. In recent years, more owners recognize that
they do not get the best quality of construction by squeezing the last cash of profit from the contractor,
and they accept the concept of risk sharing/risk assignment in principle in letting construction
contracts. However, the implementation of such a concept in the past decade has received mixed
results.
Those public and private owners have found that while initial bid prices may have decreased
somewhat, claims and disputes on contracts are more frequent than before, and notably more so in
public than in privately funded construction. Some of these claims and disputes can no doubt be
avoided by improving the contract provisions.
Since most claims and disputes arise most frequently from lump sum and unit price contracts for both
public and private owners, the following factors are particularly noteworthy:
Unbalanced bids in unit prices on which periodic payment estimates are based.
Change orders subject to negotiated payments.
Changes in design or construction technology.
Incentives for early completion and penalties of damage for late completion.
Exceptional climatic condition or physical obstruction beyond the capacity of an experienced
contractor.
An unbalanced bid refers to raising the unit prices on items to be completed in the early stage of the
project and lowering the unit prices on items to be completed in the later stages. The purpose of this
practice on the part of the contractor is to ease its burden of construction financing. It is better for
owners to offer explicit incentives to aid construction financing in exchange for lower bid prices than
to allow the use of hidden unbalanced bids. Unbalanced bids may also occur if a contractor feels some
item of work was underestimated in amount, so that a high unit price on that item would increase
profits. Since lump sum contracts are awarded on the basis of low bids, it is difficult to challenge the
low bidders on the validity of their unit prices except for flagrant violations. Consequently remedies
should be sought by requesting the contractor to submit pertinent records of financial transactions to
substantiate the expenditures associated with its monthly billings for payments of work completed
during the period.
One of the most contentious issues in contract provisions concerns the payment for change orders. The
owner and its engineer should have an appreciation of the effects of changes for specific items of work
29
and negotiate with the contractor on the identifiable cost of such items. The owner should require the
contractor to submit the price quotation within a certain period of time after the issuance of a change
order and to assess whether the change order may cause delay damages. If the contract does not contain
specific provisions on cost disclosures for evaluating change order costs, it will be difficult to negotiate
payments for change orders and claim settlements later.
In some projects, the contract provisions may allow the contractor to provide alternative design and/or
construction technology. The owner may impose different mechanisms for pricing these changes. For
example, a contractor may suggest a design or construction method change that fulfills the
performance requirements. Savings due to such changes may accrue to the contractor or the owner, or
may be divided in some fashion between the two. The contract provisions must reflect the owner’s risk-
reward objectives in calling for alternate design and/or construction technology. While innovations
are often sought to save money and time, unsuccessful innovations may require additional money and
time to correct earlier misjudgment. At worse, a failure could have serious consequences.
In spite of admonitions and good intentions for better planning before initiating a construction project,
most owners want a facility to be in operation as soon as possible once a decision is made to proceed
with its construction. Many construction contracts contain provisions of penalties for late completion
beyond a specified deadline; however, unless such provisions are accompanied by similar incentives
for early completion, they may be ruled unenforceable in court. Early completion may result in
significant savings, particularly in rehabilitation projects in which the facility users are inconvenienced
by the loss of the facility and the disruption due to construction operations.
The table clearly shows the effect of inaccurate estimation in changing the ranking positions of
competitive contractors. Contractor B seems the lowest bidder in table 1 by taking the advantage of the
underestimated quantity of masonry work. As construction progresses, the risks of the
underestimation will be transferred to the owner which is contrary to the lump sum contract provision,
31
where the contractor will be responsible to absorb all risks associated with inaccurate estimation of
works.
ACTIVITY-2
Chapter Three
3. Cost Estimating Approach
3.1 Types and Methods of Estimates
3.1.1 Approximate Estimate
This is made to find out an approximate cost in a short time and thus enable the responsible authority
concerned to consider the financial aspect of the scheme for according sanction to the same. Such an
estimate is prepared adopting different methods for different types of works. During preparation of
the estimate detailed surveying, design, drawings etc., are not required. This estimate is prepared after
preliminary investigation, preliminary surveying and a line sketch of the drawing according to the
requirements. Rates are determined either from practical knowledge or from records of similar works.
The estimate is accompanied with a brief report stating the sources of proposal, necessity and demand,
provisions or accommodations made, viability, basis of the estimate, rates and how the expenditure
involved can be met. Beside the report the estimate is provided with a line plan, site or layout plan, soil
testing by trial boring etc…
Preliminary Estimates: Early in the planning stages, both building owners and designers must agree on
an anticipated cost of the project at bid award. Preliminary Estimates are employed in the early
planning phases of a proposed project to match an owner's needs, expressed as written programmatic
requirements, with budget constraints in order to establish its overall scope (size) and quality
expectations. Estimate comparisons at this stage are especially valuable in evaluating the feasibility of
strategic alternatives being considered to satisfy current and projected space requirements (e.g. new
construction versus renovation, or lease space). As the design is not fully developed at this stage, a
contingency is typically included in the order of 15%.
Intermediate Estimates: After proceeding with a preferred course of action, Intermediate Estimates are
employed at various stages of project design development to maintain accountability for initial budget
projections and as a means of evaluating competing alternative construction assemblies, systems, and
materials. On large projects it is common practice for an owner to employ a construction manager or
professional estimator to continually update project estimates and provide feedback on budget impacts
of decisions on major design elements. As the design progresses, the contingency can be.
Estimating Methods
There are four primary methods used to estimate construction costs. Those methods are known as:
Project Comparison Estimating or Assembly & System Estimating, and
Parametric Cost Estimating, Unit Price & Schedule Estimating
Area & Volume Estimating,
Each method of estimating offers a level of confidence that is directly related to the amount of time
required to prepare the estimate: fig A
35
Project Comparison Estimating or Parametric Cost Estimating is often used in early planning stages
when little information is known about the program other than overall project parameters. This method
is sometimes called a “preliminary “or "ballpark" estimate and has no better than 15% to 25% accuracy.
Project comparison estimating uses historical information on total costs from past projects of similar
building type. For example, the number of beds in a hospital, or number of spaces in a parking garage,
or number of courtrooms in a courthouse can form the basis of a project comparison estimate by
comparing them to similar scope projects recently done in the same geographic region.
This estimating method requires the assumption of an approximate gross area for the proposed work
and a sufficient historical record of similar building types. The greater the number of prior project
combinations for which scope and prices are known, the easier it is to perform Project Comparison
Estimating. Fig. B illustrates an example of regression analysis used to develop a project comparison
estimate. The scattered points in the figure show the combinations of overall project size and cost. The
line shown is the "best fit" of a linear relationship between size and construction cost and may serve to
predict a preliminary budget. The distances between the line and the points give a visual impression
of the statistical confidence of the estimate.
36
Line graph of the Range of Costs compared to the approximate gross area in thousands of square
meters for similar building types- graph begins roughly at a gross area of two thousand square
meters at a cost of under two million and increases at an incremental rate twenty thousand square
meters at a cost of ten million.
Square Foot & Cubic Foot Estimates are another method of developing both preliminary and
intermediate budgets based on historical data. This method is effective in preparing fairly accurate
estimates if the design is developed enough to allow measurement and calculation of floor areas and
volumes of the proposed spaces. There are several historical databases available to support this method
of estimating providing unit costs that are adjusted annually and many of the large estimating firms
maintain their own databases. More accurate estimates made with this method make adjustments and
additions for regional cost indices, local labor market rates, and interpolation between available cost
tables. Further adjustments may be made to account for other unique aspects of the design such as
special site conditions or design features being planned. In addition, the estimate can develop overall
"core and shell" costs along with build-out costs of different space types, allowing for relative ease of
determining the impact of changes to the program. Estimates made with this method can be expected
to be within 5% to 15% of accurate.
Assembly & Systems Estimates are intermediate level estimates performed when design drawings are
between 50% and 75% complete. Assemblies or systems group the work of several trades or disciplines
and/or work items into a single unit for estimating purposes. For example, a foundation usually
requires excavation, formwork, reinforcing, and concrete— including placement and finish— and
backfill. An Assembly & Systems estimate prices all of these elements together by applying values
available in assemblies cost data guides. Estimates made with this method can be expected to be within
10% of accurate.
37
Unit Price and Schedule Estimating, the work is divided into the smallest possible work increments,
and a "unit price" is established for each piece. That unit price is then multiplied by the required
quantity to find the cost for the increment of work. This calculation is often called "extending". Finally,
all costs are summed to obtain the total estimated cost. For example, the cost to erect a masonry wall
can be accurately determined by finding the number of bricks required and estimating all costs related
to delivering, storing, staging, cutting, installing, and cleaning the brick along with related units of
accessories such reinforcing ties, weep-holes, flashings and the like. This method of estimating
provides the most accurate means of projecting construction costs, beyond which accuracy is more
likely to be affected by supply and demand forces in the current market.
It is the task of the estimator to predict the cost of construction for the items of finished works presented
in the bill of quantities. An accurate cost prediction can only take place when each item has been
analyzed into its simplest element and the cost methodology estimated on the basis of factual
information.
The planning department of the firm does the analysis of the physical resources required for the project
and the deployment of these resources. Pre-tender program will be prepared after consultation with
other relevant departments and evaluation of alternate construction methods and sequences. The
program would be presented as a network or bar chart to show deployment of resources to
constructional elements on a time scale. The amount of detail developed would depend on the
complexity of the project and the time available for preparation. It should show the detailed labor and
plant requirements for each operation and the production outputs anticipated for these resources. A
schedule of labor and plant requirements is sometimes prepared to amplify the program.
The task of the estimator is to evaluate the cost of the resources from the program and to build up a
unit rate for each finished work item. A fundamental principle is that unit rates should be prepared
net. A unit rate prepared on this methodology will take into account methods of construction and all
circumstances which may affect the execution of work on the project. It will consist of a prediction of
the cost of the physical resources and mark-up by management. These physical resources are: Labor,
materials, and plant.
Disposition of the Cost Calculation
a. Material costs
The real challenge in pricing construction work is the computation of labor and equipment costs. These
are the categories of construction expense that are inherently variable and the most difficult to estimate
accurately because of human variance and external conditions. To do an acceptable job of establishing
these costs, the estimator must make a complete and thorough job analysis, maintain a comprehensive
library of costs and production rates from past projects (historical data), and obtain advance decisions
about how construction operation will be conducted.
Labor costs include:
Standard wages Social Service payments
Extra pay Supplements
Supplementary pay Other payments
c. Equipment costs:
All costs for commissioning /holding and operation of the equipment
Ownership of plant
Hire of plant
All items of mechanical plant should be estimated in terms of all-in rate and a production output. In
the case of hired plant, the standing costs will be comparable to the hire charge. The main factors in
building up a rate will be:
Standing Costs: includes capital sum based on purchase price and operating cost,
maintenance, tax and insurance
Operating Costs: operators cost, fuel, consumable stores
39
UNIT RATE
BUILD UPS
MATERIAL
COST
ON SITE
MATERIAL
COST
UNIT RATE
COST
PER UNIT OF
MEASURE
on time being obtained from the pre-tender program. Other project overheads are value related and
will not be able to be evaluated until after the adjudication process by management.
b) Labor Costs
All costs, which result from the building /construction works of the employees on site include:-
Standard wages
Extra and supplementary pay for:
Number and type of skilled and unskilled manpower for a particular type of work, (Crew)
Performance of crew per hour for a unit amount of work
Indexed hourly cost of the workman ship.
Utilization factor of the workmanship. Share of a particular personal per hour for the specified
work.
Example-1: Calculation of indexed hourly cost for carpenter
Over time
50 weekly working hours/44 weekly working hours/
6 overtime hours with 25% increment
Property- Creating performance
For 80% of the employees 0.25birr/hr
c) Equipment cost
Required information
i. With charges accounted for depreciation, interest return and monthly repair costs
ii. With monthly rental charges.
Example:
Calculation of equipment cost for m3 of concrete. Assume 8 working hours per day and 22 days per
month.
43
Mixer:
Original cost = 50.000 Birr
Useful life = 3yrs
Interest rate=6.5%
Monthly repair cost with supplies: - 700 Birr
Vibrator:
Original cost = 5.000 Birr
Useful life = 7yrs
Repair cost monthly = 50 Birr
Hourly equipment cost
i. For Mixer:
50,000
𝐷𝑒𝑝𝑟𝑒𝑐𝑖𝑎𝑡𝑖𝑜𝑛 (𝑑) =
3∗12∗(22∗8)=7.89 Birr/hr
1
𝐼𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑜𝑓 𝑟𝑒𝑡𝑢𝑟𝑛 (𝑖) = 3 ∗ (50,000 ∗ (1 + 0.0665)3 − 50,000) = 3465.83 Birr/yr
3465.88
𝐻𝑜𝑢𝑟𝑙𝑦 𝑐𝑜𝑠𝑡 = 12∗8∗22 = 1.641 Birr/hr
700
Hourly repair cost = 8∗22 = 3.98 Birr/hr
50
𝑅𝑒𝑝𝑎𝑖𝑟 𝑐𝑜𝑠𝑡 = = 0.284 𝐵𝑖𝑟𝑟/ℎ𝑟
8x22
Example.
Hourly cost:
Example
1m2 formwork for floor slab made of zigba: - 300 birr & number of possible uses 7
Unit prices
(Rate)
Bid Sum
The direct itemized cost will be established in accordance with the methods and approach illustrated
in the previous examples. However the indirect itemized cost will be a product of the corresponding
direct itemized cost with some fixed charge to be established by the individual contractors for the
particular project. In our country high-class contractors presume 30-40% of the direct itemized cost
as an indirect cost for the particular item of work. One can readily establish the corresponding unit
prices by just summing up the direct and indirect itemized costs. The summation of the price of the
whole item which results from the multiplication/unit price x quantity/ would give the bid sum to
the particular project.
Example: Establish the unit price of 1 m3 concrete considered for in the previous examples. Given that
the surcharge for the indirect cost is 35%.
In this approach, amounts for site overhead costs, general overhead costs, risk and profit are to be
ascertained separately for each project. Here from surcharges on direct itemized costs result with
different amount for each project. Four steps for this calculation method:
Given the following detail for the construction of 5Om long fence around a site.
1/ List of items quantities and direct itemized costs are as given in the table
Question: Establish bid sum and unit prices for the itemized works.
Step 2: Establish bid sum [production cost + General overhead cost + risk & profit]
22,417.58
𝑆𝑢𝑟𝑐ℎ𝑎𝑟𝑔𝑒 = = 𝟏. 𝟓𝟔
14,374
Unit
Item of work Unit Quantity Amount
price
Excavation m3 40 9.36 374.40
Masonry wall m3 25 288.53 7,213.25
Concrete m3 5 662.83 3,314.15
Dia. 4 bar kg 242 7.798 1,887.12
Dia. 8 bar kg 132 7.018 926.38
Formwork m2 20 70.18 1,403.60
HCB wall m2 90 81.099 7,298.91
Bid sum without VAT 22,417.80
Add 15 % VAT 3,362.67
Bid sum with VAT 25,780.47
The price of a unit of finished work will consist of the elements of labor, materials and a markup for
profit and on costs, which are not readily adjustable by simple proportionate methods. This may be
illustrated by the example that whilst a 40 mm screed will require double the quantity of material to
that of a 20mm screed, however the labor in laying will not be doubled, as there will be less surface to
work to a smooth finish per volume of material laid.
The major assumptions behind the concept is that: Material, equipment and indirect costs can readily be
determined or available from existing prices and predetermined charges and hence readily adjustable whilst
difficult to readily drive the labor cost component for existing rates and hence remain as uncertain factor.
There are three main methods of assessing pro-rata rates and some skill and thought is needed to
decide which is appropriate to the particular work at hand.
3.2.1 By Derivation
By derivation from two or more similar unit rates. This a simple and straight forward method of
obtaining a pro-rata rate but it may only correctly be used in certain circumstances, and to illustrate
this, two examples are quoted below.
Example-1:
Assuming a priced bill has rates for 20mm and 40mm thickness screeds for the same mix laid to a
similar specification: simple deduction of one rate from the other will give the additional value of the
material, mixing and profit for an increase in thickness of 20mm. As already stated, the value of
spreading in these circumstances would not be appreciably altered, therefore, to find the price of 25mm
thickness (an additional 5 mm) all that is needed is to add ¼ of the difference in price between 20mm
and 40mm thickness screed to the 20mm thickness.
Screed 20 mm: 20 Birr
Screed 40 mm: 30 Birr
The price of 25 mm screed is therefore Birr 22.5
Example-2:
The following items and prices appear in a bill of quantities prices by a contractor.
50 x 100 mm softwood joist Birr 31.5
50 x 125 mm softwood joist Birr 37.0
50 x 150 mm softwood joist Birr 42.5
be derived from the bill figure in the same way as they were priced- Birr 5.5 for each increase or
decrease in 25mm depth. Thus the rate becomes:
1st Step:
Break down a unit rate into its component to arrive fairly closely at the figures included by the
contractor as labor component.
2nd Step:
Apply the labor cost to arrive at a pro rata rate of a similar item.
Example:
Hollow Concrete Block wall for load bearing superstructure Class-A bonded in mortar 1: 6 =
Birr 150 / m3.
During construction, the engineer issued work order to change the HCB to class C wall with
1:3 mortar.
i) Deduct a reasonable rate for mark-up (Profit + Administrative Costs). 20% is assumed.
ACTIVITY-3
Chapter Four
4. Progress and Cost Control
4.1 Earned Value Overview
Traditional earned value analysis (EVA) is an established method for the evaluation and financial
analysis of projects throughout their life cycle’. Earned value management (EVM) is a fully integrated
project cost- and schedule control system which allows through trend analysis, the formation of ‘S’
curves and cost/schedule variances. The technique can be applied to the management of all capital
projects in any industry, while employing any contracting approach. EVM is superior to independent
schedule and cost control for evaluating work progress in order to identify potential schedule slippage
and areas of budget overruns. EVM involves calculating three key values for each activity in the WBS:
i. The planned value (PV): formerly known as the budgeted cost of work scheduled (BCWS) – that
portion of the approved cost estimate planned to be spent on the given activity during a given
period;
ii. The actual cost (AC): formerly known as the actual cost of work performed (ACWP) – the total of
costs incurred in accomplishing work on the activity in a given period. The actual cost must
correspond to whatever was budgeted for in the PV and earned value (EV) (e.g. all labor,
materials, construction equipment and indirect costs).
iii. The earned value (EV): formerly known as the budget cost of work performed (BCWP) – the value
of the work actually completed. These three values are combined to determine at that point in
time whether or not work is being accomplished as planned. The most commonly used measures
are the cost variance and the schedule variance: Cost variance (CV) = EV- AC
Similarly the cost of impact of schedule slippage, the schedule variance in terms of cost, may be
determined. Schedule variance (SV) = EV – PV The same data can be expressed as ratios that give an
indication of value for money. If work is proceeding to, or better than plan, these ratios will be equal
to or greater than 1.0. Conversely unfavorable variances will be less than 1.0.
1. How are we doing on money? We can measure our project cost performance using:
Cost performance index (CPI) = EV/AC
2. How well are we doing on time? We can measure our project time performance using:
Schedule performance index (SPI) = EV/PV
54
ACTIVITY 4.1
Given a project with the following characteristics:
You are the project manager of a project to build warehouses.
You are to build two warehouses a month for 12 months.
Each warehouse is planned to cost $100.
Your project is scheduled to last for 12 months.
It is the beginning of month 10.
You have built 20 warehouses and your CPI is .9091.
Based on the above data answer the following questions:
1. How is the project performing?
A. Over budget and ahead of schedule
B. Under budget and ahead of schedule
C. Over budget and behind schedule
D. Under budget and behind schedule.
2. What is the actual cost of the project right now?
A. $1800 B. $2000 C. $2200 D. $2400
3. Assuming that the COST variance experienced so far in the project will continue, how much
more money will it take to complete the project?
A. $400 B. $440 C. $2800 D. $2840
4. If the variance experienced so far were to stop, what is the project’s estimate at completion?
A. $2400 B. $2440 C. $2600 D. $2800
5. What is the project’s TCPI using the project’s budget at completion?
A. 5 B. 1 C. 1.5 D. 2
6. Senior management wants to the percentage of the project that is complete. What should you report?
A. 75% B. 83% C. 92% D. 95%
7. Imagine if instead of 10 months and costing $2200, the project was in month three and costing $4000. What
formula might you use for BAC?
A. [(BAC – EV) / (CPI * SPI)] + AC
B. new bottom-up estimate
C. AC + new ETC
D. AC + BAC – EV
55
The value of a component or system can be defined as its function plus quality divided by its life-cycle
cost.
𝐹𝑢𝑛𝑐𝑡𝑖𝑜𝑛 + 𝑄𝑢𝑎𝑙𝑖𝑡𝑦
𝑉𝑎𝑙𝑢𝑒 𝑜𝑓 𝑎 𝑐𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 = − 𝑊𝑜𝑟𝑡ℎ 𝑏𝑒𝑛𝑒𝑓𝑖𝑡
𝐿𝑖𝑓𝑒 𝐶𝑦𝑐𝑙𝑒 𝐶𝑜𝑠𝑡
𝑳𝒊𝒇𝒆 𝑪𝒚𝒄𝒍𝒆 𝑪𝒐𝒔𝒕 = 𝐼𝑛𝑖𝑡𝑖𝑎𝑙 𝑜𝑟 𝐶𝑜𝑛𝑠𝑡𝑟𝑢𝑐𝑡𝑖𝑜𝑛 𝐶𝑜𝑠𝑡 + 𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝐶𝑜𝑠𝑡 + 𝑀𝑎𝑖𝑛𝑡𝑒𝑛𝑎𝑛𝑐𝑒 𝐶𝑜𝑠𝑡 + 𝐷𝑒𝑝𝑟𝑒𝑐𝑖𝑎𝑡𝑖𝑜𝑛 𝐶𝑜𝑠𝑡 – 𝑎𝑛𝑦 𝑆𝑎𝑙𝑣𝑎𝑔𝑒 𝑉𝑎𝑙𝑢𝑒
Value Engineering seeks the highest value design components by Improving utility with same cost or
maintains same function with less cost. In general Value engineering:
The information gathering phase involves studying the design to identify potential components or
systems for detailed study. The essential functions of each component or system are studied to estimate
the potential for value improvement. The study team needs to understand the rationale used by the
designer in developing the plan and the assumptions made in establishing design criteria and selecting
materials and equipment.
56
The purpose of the speculation or creative phase is to identify alternative ways to accomplish
the essential functions of the items selected for the study. The intent is to develop a list of
alternative materials or components that might be used. No intent is made to evaluate the
identified alternatives, but rather to generate ideas that will be evaluated in the next step of the
study process.
iii. Evaluation through preliminary Life-Cycle Costing:
The evaluation phase involves determining the most promising alternatives from the set
identified in the speculation phase. Preliminary cost data is generated and functional
comparisons are made between the potential design components being studied. The intent is to
determine which alternatives will meet the owner’s functional requirements and provide more
value to the completed project.
iv. Development of Technical Solutions:
The development phase involves creating design concepts for the alternatives identified during
the evaluation phase. This involves developing detailed functional and economic data for each
alternative. Estimated Life-Cycle cost data is developed for each alternative and compared with
the estimated life-cycle cost of the components under study. The advantages and disadvantages
of each alternative are identified. Alternatives are compared, and the ones representing the best
value are selected for presentation to the designer and the owner.
v. Presentation of Alternative Options:
The final step is the preparation of the value engineering proposals, in which detailed technical
and cost data are developed to support the recommendations. The advantages and
disadvantages of each recommendation are described. The proposals are submitted to the
designer and the owner for proposal. If approved, the proposals are incorporated into the
design. If not approved, the design is not changed.
become of great value as the physical asset represent an important factor in the whole asset
management process. A physical asset is defined as an entity that is capable of creating, sustaining or
destroying value at any stage in its life-cycle.
The main principal objective of asset management is to enable an organization to meet its objectives
efficiently and effectively. Effective asset management could be achieved by ensuring that all
service potential of assets are appropriately used and maintained, In contrast with this, efficient AM
should always seek the continuous upgrade and improvement of asset utilization, performance and
feasibility in short term and long term basis. In addition, it can be addressed that managing asset in
an organization is mainly concerned by achieving organization’s goals at the lowest possible life
cycle cost.
Engineering asset management is generally refer to the management of the engineering assets such as:
Equipment,
Buildings,
Inventories, etc.
EAM becomes a vital part of business management for many organizations especially when capital
investment in plant equipment or infrastructure is significant and the productivity/sustainability of
the asset is crucial to the competitive capability of the business.
ACTIVITY 4.2