Building 230 (30b)
Building 230 (30b)
Building 230 (30b)
ACCOMMODATION
REGION
NEOM
KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES
FOR
SKELETON & FINISHING PACKAGE
FEB. 2024
REV.01
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
SKELETON & FINISHING PACKAGE
RECREATIONAL HUB AND GYM BUILDING - (230) - GENERAL CONTENTS
Div. DIVISION BOQ PAGES
FROM PAGE TO PAGE
GENERAL SUMMARY
00 GENERAL PROJECT REQUIREMENTS
01 GENERAL REQUIREMENTS
02 EXISTING CONDITIONS
03 CONCRETE 230/DIV.03/01 230/DIV.03/05
04 MASONRY 230/DIV.04/01 230/DIV.04/02
05 METALS - NON-STRUCTURE 230/DIV.05/01 230/DIV.05/04
06 METALS - STRUCTURE 230/DIV.05/01 230/DIV.05/04
06 WOOD, PLASTICS, AND COMPOSITES
07 THERMAL AND MOISTURE PROTECTION 230/DIV.07/01 230/DIV.07/05
08 OPENINGS 230/DIV.08/01 230/DIV.08/06
09 FINISHES 230/DIV.09/01 230/DIV.09/06
10 SPECIALTIES 230/DIV.10/01 230/DIV.10/03
11 EQUIPMENT
12 FURNISHINGS
13 SPECIAL CONSTRUCTION
14 CONVEYING EQUIPMENT
21 FIRE SUPPRESSION 230/DIV.21/01 230/DIV.21/03
22 PLUMBING 230/DIV.22/01 230/DIV.22/04
23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) 230/DIV.23/01 230/DIV.23/04
25 INTEGRATED AUTOMATIONS
26 ELECTRICAL 230/DIV.26/01 230/DIV.26/05
27 COMMUNICATIONS 230/DIV.27/01 230/DIV.27/04
28 ELECTRONIC SAFETY AND SECURITY 230/DIV.28/01 230/DIV.28/04
31 EARTHWORKS 230/DIV.31/01 230/DIV.31/03
32 EXTERIOR IMPROVEMENTS
33 UTILITIES
34 TRANSPORTATIONS
35 WATERWAY AND MARINE CONSTRUCTION
40 PROCESS INTEGRATION
41 MATERIAL PROCESSING AND HANDLING EQUIPMENT
42 PROCESS HEATING, COOLING, AND DRYING EQUIPMENT
PROCESS GAS AND LIQUID HANDLING, PURIFICATION, AND
43
STORAGE EQUIPMENT
44 POLLUTION AND WASTE CONTROL EQUIPMENT
45 INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT
46 WATER AND WASTEWATER EQUIPMENT
48 ELECTRICAL POWER GENERATION
Preambles:
The item unit rate shall include the followings:
The following requirements are
complementary to the mentioned items in
the B.O.Q;
A. Supply of materials and equipment.
Off loading and handling from trucks on
B. site to place of installation (including
carnage, unpacking, erecting in place).
On-site material protection and storage
C
before installation.
D Installation of materials and equipment
All civil works required and related to the
landscape works, such as: equipment,
tools, concrete bases and supports, cutting
and chasing through block and concrete
E walls and slabs for passage of conduits,
sleeves, trays, trunking and ladders,
excavation and back-fillings, riggings,
hoisting, waterproofing, cleaning &
protection
All labor, materials, tools, instruments,
electric power, water supply, fuel and
F
water required for work executions,
testing, and commissioning
Preparation of the shop-drawings and As-
G
built drawings
Preparation of the operation and
H
maintenance manuals
J Samples as required by the Engineer
Maintenance as per the Contract
K
Conditions
Coordination with other specialty
L contractors, such as special equipment
supplier(s) and subcontractor(s) etc.
****** *******
To Collection SAR
To Collection SAR
03 40 00 Precast Concrete
To Collection SAR
Preambles:
The item unit rate shall include the followings:
The following requirements are
complementary to the mentioned
items in the B.O.Q;
A. Supply of materials and equipment.
Off loading and handling from trucks
on site to place of installation
B.
(including carnage, unpacking,
erecting in place).
On-site material protection and
C
storage before installation.
D Installation of materials and equipment
All civil works required and related to
the landscape works, such as:
equipment, tools, concrete bases and
supports, cutting and chasing through
block and concrete walls and slabs
E
for passage of conduits, sleeves,
trays, trunking and ladders,
excavation and back-fillings, riggings,
hoisting, waterproofing, cleaning &
protection
All labor, materials, tools,
instruments, electric power, water
F supply, fuel and water required for
work executions, testing, and
commissioning
Preparation of the shop-drawings
G
and As-built drawings
Preparation of the operation and
H
maintenance manuals
J Samples as required by the Engineer
Maintenance as per the Contract
K
Conditions
Coordination with other specialty
contractors, such as special
L
equipment supplier(s) and
subcontractor(s) etc.
****** *******
SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 230/ DIV. 04/1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
DIVISION 4 - MASONRY WORKS
04 20 00 Unit Masonry
04 21 00 Clay Unit Masonry
Block Work
Hollow concrete blockwork in cement
and sand mortar (1:4) including but
not limited to all cutting, fire rated
gap at top level with mastic sealant,
bonding beams, control and
expansion joints, and bond beams,
complete as shown on drawings and
as per specifications
( By square meters )
Interior blockwork
A 100mm thick 35 M2
B Ditto; 60 Min. fire rating 60 M3
C 150mm thick 414 M2
D Ditto; 60 Min. fire rating 82 M2
E Ditto; 120 Min. fire rating 46 M2
2
F Ditto; 150 Min. fire rating 45 M
G 200mm thick 24 M2
H 250mm thick 15 M2
Preambles:
The item unit rate shall include the followings:
The following requirements are complementary to the
mentioned items in the B.O.Q;
A. Supply of materials and equipment.
****** *******
SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 230 / Div. 05 / 1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
METAL WORK
05 50 00 Metal Fabrications
Composite Aluminum Cladding
Quantity in SQM.
To facades, W4 - Wall Type-Exterior Aluminum cladding
A
(EALUM 002) - Light Grey Color 88 m2
Quantity in SQM.
To facades, W6 - Wall Type-Exterior Aluminum cladding
B
(EALUM 003) - Yellow Color 396 m2
Aluminium Coping
Detail (6) , DWG. STR. DRG. 822001
(By linear meters)
4mm ACP with non combustible mineral core, 450mm approx.
C
width 98 lm
05 51 00 - Metal Stairs
Stainless Steel cat ladder, comprising of side rail and rungs,
flat plate & support brackets, including welding, bolts, steel
angles, fixings, fittings, accessories and epoxy painting,
complete as shown on drawings & specifications
Quantity enumerated
D 6050mm high, safty cage steel ladder 1 No.
05 52 00 Metal Railings
Metal railings including but not limited to all necessary posts,
raking, brackets, support system, fittings, painting, complete as
shown on drawings and specifications
(by linear meters)
E 915mm high. to ramps (external) 36 LM
COLLECTION
CARRIED FROM PAGE #1 (PREAMBLES)
********
CARRIED FROM PAGE #2
Preambles:
The item unit rate shall include the followings:
The following requirements are
complementary to the mentioned items in
the B.O.Q;
Supply of materials and equipment.
Off loading and handling from trucks on
site to place of installation (including
carnage, unpacking, erecting in place).
On-site material protection and storage
before installation.
Installation of materials and equipment
All civil works required and related to the
landscape works, such as: equipment,
tools, concrete bases and supports, cutting
and chasing through block and concrete
walls and slabs for passage of conduits,
sleeves, trays, trunking and ladders,
excavation and back-fillings, riggings,
hoisting, waterproofing, cleaning &
protection
All labor, materials, tools, instruments,
electric power, water supply, fuel and
water required for work executions,
testing, and commissioning
Preparation of the shop-drawings and As-
built drawings
Preparation of the operation and
maintenance manuals
Samples as required by the Engineer
Maintenance as per the Contract Conditions
****** *******
To Collection SAR
(Quantity enumerated)
B OVERAL SIZE 2330 x 2970 mm 7 No.
C OVERAL SIZE 2330 x 2905 mm 3 No.
D OVERAL SIZE 3540 x 2945 mm 3 No.
E OVERAL SIZE 2430 x 2945 mm 1 No.
To Collection SAR
COLLECTION
(N/A)
Division 07
Thermal and Moisture Protection
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
DIVISION 07 - THERMAL & MOISTURE PROTECTION
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
Preambles:
The item unit rate shall include the followings:
The following requirements are
complementary to the mentioned items in
the B.O.Q;
A. Supply of materials and equipment.
Off loading and handling from trucks on
B. site to place of installation (including
carnage, unpacking, erecting in place).
On-site material protection and storage
C
before installation.
D Installation of materials and equipment
All civil works required and related to the
landscape works, such as: equipment,
tools, concrete bases and supports, cutting
and chasing through block and concrete
E walls and slabs for passage of conduits,
sleeves, trays, trunking and ladders,
excavation and back-fillings, riggings,
hoisting, waterproofing, cleaning &
protection
All labor, materials, tools, instruments,
electric power, water supply, fuel and
F
water required for work executions,
testing, and commissioning
Preparation of the shop-drawings and As-
G
built drawings
Preparation of the operation and
H
maintenance manuals
J Samples as required by the Engineer
Maintenance as per the Contract
K
Conditions
Coordination with other specialty
L contractors, such as special equipment
supplier(s) and subcontractor(s) etc.
****** *******
To Collection SAR
To Collection SAR
07 20 00 - Thermal Protection
Rock-wool thermal insulation, including
all necessary fixing, cuttings, and
accessories complete as shown on
drawings and as per Technical
Specifications.
(Refer to detailed drawing # 822001)
Quantities given by square meters
150mm thick, to building facades, vertically
A (EIFS), COVERED WITH
BREATHABLE FACER 485 M2
To Collection SAR
Preambles:
The item unit rate shall include the followings:
The following requirements are complementary to the
mentioned items in the B.O.Q;
A. Supply of materials and equipment.
****** *******
By Numbers
Single leaf Metal Doors - One way hinged
A S01 size 1000x 2200 mm high, H.M. PTD 1 No.
B S03 size 1000x 2200 mm high, H.M. PTD 1 No.
08 14 00 - Wood Doors
By Numbers
Single leaf Metal Doors - One way hinged
A W01 size VAR W. x 2200 mm high, S.W, PTD 16 No.
Quantity enumerated
A CO1, (W. 2400 x H 3000 mm) 11 No.
B CO2, (W. 3200 x H 3000 mm) 1 No.
C CO3, (W. 2400 x H 3000 mm), double leaf doors 2 No.
CO4, (W. 3600 x H 3000 mm), including single leaf door size
D
1200x2200 mm 1 No.
COLLECTION
Preambles:
The item unit rate shall include the followings:
The following requirements are complementary to the
mentioned items in the B.O.Q;
A Supply of materials and equipment.
****** *******
FINISHING WORK
09 20 00 - Plaster and Gypsum Board
09 24 00 Cement Plastering
09 96 00 High-Performance Coatings
09 96 56 Epoxy Coatings
Heavy duty anti slip high solid content Epoxy floor coating to
be applied on smoothed finished concrete screed, complete as
shown on drawings and as per specifications
09 63 00 Masonry Flooring
09 63 40.14 Marble Flooring
Marbel flooring tiles, including cement/sand mortar, cuttings,
grouting, jointing polishing and pointing, complete as shown in
drawings and as per specifications.
C 25mm thick marble threshold marfil marble to wet areas 8 lm
D 20mm thick marble threshold, generally 20 lm
09 70 00 Wall Finishes
09 72 00 Wall Coverings
Porcelain wall tiles, including adhesive material, cuttings,
grouting, jointing and pointing, complete as shown in drawings
and as per specifications
E ICT-001 to walls, light grey, size 300x600 mm 263 m2
(Ref. 03) glazed high-glossy impact & chimical resistance
F
ceramic wall tiles, size 400x400 mm 53 m2
TRAFFIC COATING
COLLECTION
CARRIED FROM PAGE #1 ********
CARRIED FROM PAGE #2
CARRIED FROM PAGE #3
CARRIED FROM PAGE #4
CARRIED FROM PAGE #5
CARRIED FROM PAGE #6
Preambles:
The item unit rate shall include the followings:
The following requirements are
complementary to the mentioned items in
the B.O.Q;
Supply of materials and equipment.
Off loading and handling from trucks on site
to place of installation (including carnage,
unpacking, erecting in place).
On-site material protection and storage
before installation.
Installation of materials and equipment
****** *******
SINDALAH NON MANAGERIAL 230 / DIV.10 / 1
STAFF ACCOMMODATION
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
JOD JOD
SPECIALTIES
10 21 00 Compartments and Cubicles
10 21 13 Toilet Compartments
Supply and install full package of toilet
cubicles, from TRESPA Panels or approved
equally, (13mm thick), consisting of high-
pressure laminated melamine surfaces
partitions, fixed on a moisture-resistant
particleboard core, with internal supporting
frames and pilasters, including side hinged
openable single leaf laminated doors in
proprietary toilet cubicles, swing type,
comprising hot pressed laminated on both
sides with hardwood lipping and timber jambs
frames, including all necessary fixings,
fittings, accessories, anti-fungus rubber
silicon, supporting system, heavy gauge
stainless steel hardware, stainless steel foot
support, stainless steel mortised lever-turn
indicator bolt with external emergency
released facility, and door closers, complete
as shown on drawings, specifications, and
Engineer's approval of samples
Complete package of Toilets Cubicles
partitions, including:
(By Numbers)
Front Partitions
Overall size 1000mm width x 1950 mm high,
A
Including (1) single leaf hinged door 2 No.
Overall size 2750mm width x 1950 mm high,
B
Including (1) single leaf hinged door 2 No.
Side partitions
C Size 1500mm width x 1950 mm high 2 No.
10 14 00 Interior Signage
Interior Signage shall be Good rigidity and
tensile strength. Resistant to chemicals and
corrosion and incorporates UV inhibitors to
reduce fading of colors, including fixing,
fittings, accessories, supporting and cleaning,
complete as shown on drawings and as per
specifications
Interior Signage
Quantity enumerated
D SR01 14 No.
E SR02 5 No.
F SR03 2 No.
COLLECTION
Preambles:
The item unit rate shall include the followings:
The following requirements are complementary to the
mentioned items in the B.O.Q;
The rates and prices for plant, equipment and installations are
to be all inclusive of supply, installation, testing,
commissioning and all associated builders work required for
A. the full operation of such plant, equipment and installations, to
comply in all respects with the Specifications, Drawings and to
the complete satisfaction of Municipality, Local Authorities and
the Engineer.
Builder’s Work shall include for all secondary steelwork
B. supports for plant, equipment, trunking and the like not
specifically shown or indicated on the drawings.
Rates for pipes and ducts generally are to include for all
cuttings, short lengths, back stops, couplers, wooden plugs
and retaining and alignment pegs required in laying and for the
C extra involved over normal trench excavating in hand packing
and tamping selected fine material around the lower half of
the pipes to buttress them against the side of the trench.
Rates are to include for leaving all pipes clean and clear.
Pipes are measured nett as laid and are to include for all
fittings on all types of pipes, extra joints of all types, cuttings,
D waste, fixing with approved holderbats or pipe clips, sleeves
through walls, thrust blocks, etc., for laying in trenches of any
depth, and building in to sides of inspection chambers.
The total cost for the services shall include for the detail
design, together with the preparation of all necessary
calculations and workshop drawings which, together with all
F manufacturing data shall be submitted to the Consultant for
approval before purchase, manufacture or installation.
Generally including spares for all Mechanical Installation item
as recommended by the manufacturer.
****** *******
21 12 00 Fire Extinguishers
K FE-1 6 No
L FE-2 2 No
21 11 19 Fire-Departments Connections
N SIAMESE CONNECTION 1 No
COLLECTION
CARRIED FROM PAGE #1 ********
CARRIED FROM PAGE #2
Pipes are measured nett as laid and are to include for all
fittings on all types of pipes, extra joints of all types, cuttings,
E waste, fixing with approved holderbats or pipe clips, sleeves
through walls, thrust blocks, etc., for laying in trenches of any
depth, and building in to sides of inspection chambers.
Rates for fittings on all types of drain pipes are to include for
F
extra joints of all types and cutting and waste on all pipes.
The rates for sanitary fittings and the like, unless otherwise
described, shall be deemed to include all accessories,
assembling component parts including suitable bedding
compounds, all necessary plugging and brass screwing, fixing
I accessories, joints to water services with straight or bent
proprietary connectors, joints to waste soils or drain pipes
with approved proprietary connectors, cleaning off all
protective wrappers and leaving ready for use and leaving taps
and valves greased, clean and in full working order.
****** *******
SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 230 / DIV. (22) / 1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR PLUMBING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
PLUMBING WORK
22 13 16 - Sanitary Soil, Waste, Vent, and CDP pipes
Above Ground Pipes
Waste Pipe
A 50mm dia 7 ml
B 82mm dia 3 ml
Soil Pipe
C 110mm dia 4 ml
Vent Pipe
D 50mm dia 62 ml
82mm dia 11 ml
Rain Pipe
E 82mm dia 37 ml
Condesate Drain Pipe
F 20mm dia 41 ml
G 32mm dia 15 ml
H 50mm dia 17 ml
22 14 26 - Roof Drains
Q Rain Water Outlet 4'' 4 No.
R Emergency Rain Water Outlet 4'' 4 No.
22 13 16 - Traps
T Floor Drain 3'' 13 No.
U Shower Drain 6 No.
22 13 19 - Sanitary Drains
V Funnel drain 1 No.
22 00 00 - Manholes
B 30-M-MH-01 (600x600mm) 2 No.
22 00 00 - Gully Trap
C Gully Trap 2 No.
22 11 23 - CIrculation Pumps
S 30-M-DHWCP-01 2 No.
COLLECTION
CARRIED FROM PAGE #1 ********
CARRIED FROM PAGE #2
Preambles:
The item unit rate shall include the followings:
The following requirements are complementary to the
mentioned items in the B.O.Q;
The rates and prices for plant, equipment and installations are
to be all inclusive of supply, installation, testing,
commissioning and all associated builders work required for
A. the full operation of such plant, equipment and installations, to
comply in all respects with the Specifications, Drawings and to
the complete satisfaction of Municipality, Local Authorities and
the Engineer.
Builder’s Work shall include for all secondary steelwork
B. supports for plant, equipment, trunking and the like not
specifically shown or indicated on the drawings.
Rates for pipes and ducts generally are to include for all
cuttings, short lengths, back stops, couplers, wooden plugs
and retaining and alignment pegs required in laying and for the
C extra involved over normal trench excavating in hand packing
and tamping selected fine material around the lower half of
the pipes to buttress them against the side of the trench.
Rates are to include for leaving all pipes clean and clear.
A Prices and rates for ductwork shall include for all bends,
hangers, vanes, Splitters, dampers, accessories flexible
D connections, joints, waste, seams, stiffeners, bracing, access
doors, sleeves, acoustic sleeves and all items include in the
sections of the specifications.
Prices and rates for insulation shall include for insulation to
E all fittings, flange boxes, valve boxes, etc and around all
supports.
The total cost for the services shall include for the detail
design, together with the preparation of all necessary
calculations and workshop drawings which, together with all
F manufacturing data shall be submitted to the Consultant for
approval before purchase, manufacture or installation.
Generally including spares for all Mechanical Installation item
as recommended by the manufacturer.
****** *******
23 62 00 - Condensing Unit
B 30-M-CU-01 1 No
23 07 13 Insulation ductwork
M Indoor insulation 123 m2
2
N Outdoor insulation 23 m
23 37 13 Air Outlets
Supply Diffuser
A 30-M-SD-01 (150x150) 3 No
B 30-M-SD-02 (300x300) 5 No
C 30-M-SD-03 (380x380) 8 No
Return Diffuser
D 30-M-RD-01 (150x150) 3 No
E 30-M-RD-02 (300x300) 5 No
F 30-M-RD-03 (380x380) 8 No
Exhaust Grille
G 30-M-EG-01 (150x150) 15 No
H 30-M-EG-02 (450x450) 1 No
Door Grille
J 30-M-DG-01 (300x250) 1 No
L 23 05 02 BMS LS LS
COLLECTION
CARRIED FROM PAGE #1 ********
CARRIED FROM PAGE #2
CARRIED FROM PAGE #3
26 27 26.20-Switch Points
E Switch Points 19 No.
26 27 26.30-Wiring Devices Elements
F 13A Single Switched Socket Outlet 25 No.
G 13A Single Switched Socket Outlet W/P 7 No.
H Floor box contains 1 number- 13A Double Switched Socket Outlet 2 No.
20A ceiling mounted industrial socket outlet 2P+E220V,IPA,60 HZ,IP44,
J 4 No.
plug
26 51 00-INTERIOR LIGHTING
26 51 19.10-Led Interior Lighting
A L2S 6 No.
B L3S 3 No.
C L5S 1 No.
D D1 12 No.
E D2 10 No.
F B3 9 No.
G B2 27 No.
H D9 6 No.
J L2SE 2 No.
K L3SE 1 No.
L L5SE 1 No.
M D1E 6 No.
N D2E 4 No.
P B3E 4 No.
Q B2E 6 No.
R D9E 2 No.
S 8w led, Ceiling mounted exit sign with indicates the escape direction 14 No.
T 8w led, Wall mounted exit sign with indicates the escape direction 2 No.
26 51 19.20-Wiring (Interior Lighting Points)
U Interior Lighting Points 74 No.
26 52 00-SAFTY LIGHTING
26 52 13-Emergency and Exit Signs
26 52 13.13.10-Wiring(Emergency Lighting Points)
V Emergency Lighting Points 26 No.
26 52 13.13.20-Wiring(Emergency Lighting Points)
Exit Lighting Points 16 No.
26 56 00-EXTERIOR LIGHTING
COLLECTION
CARRIED FROM PAGE #1 ********
CARRIED FROM PAGE #2
Telecommunications Outlets/Connectors
Horizontal Cross-connects:
IP Phones
GYM
G AV Rack 1 No.
COLLECTION
Controllers: (ACP’s);
Card readers
COLLECTION
CARRIED FROM PAGE #1 ********
CARRIED FROM PAGE #2
Preambles:
The item unit rate shall include the followings:
The following requirements are complementary to the
mentioned items in the B.O.Q;
A. Supply of materials and equipment.
****** *******
SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 230 / Div. 31 / 1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
EARTHWORK
31 23 16 Excavation
31 23 23 Fill
31 23 23.13 Backfill
GENERAL SUMMARY
00 GENERAL PROJECT REQUIREMENTS
01 GENERAL REQUIREMENTS
02 EXISTING CONDITIONS
03 CONCRETE
04 MASONRY
05 METALS
06 WOOD, PLASTICS, AND COMPOSITES
07 THERMAL AND MOISTURE PROTECTION
08 OPENINGS
09 FINISHES
10 SPECIALTIES
11 EQUIPMENT
12 FURNISHINGS
13 SPECIAL CONSTRUCTION
14 CONVEYING EQUIPMENT
21 FIRE SUPPRESSION
22 PLUMBING
23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
25 INTEGRATED AUTOMATIONS
26 ELECTRICAL
27 COMMUNICATIONS
28 ELECTRONIC SAFETY AND SECURITY
31 EARTHWORKS
32 EXTERIOR IMPROVEMENTS
33 UTILITIES
34 TRANSPORTATIONS
35 WATERWAY AND MARINE CONSTRUCTION
40 PROCESS INTEGRATION
41 MATERIAL PROCESSING AND HANDLING EQUIPMENT
42 PROCESS HEATING, COOLING, AND DRYING EQUIPMENT
43 PROCESS GAS AND LIQUID HANDLING, PURIFICATION, AND STORAGE EQUIPMENT
44 POLLUTION AND WASTE CONTROL EQUIPMENT
45 INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT
46 WATER AND WASTEWATER EQUIPMENT
48 ELECTRICAL POWER GENERATION